Plat and Subdivision Committee
Regular MeetingArlington Heights, IL · March 22, 2017
Agenda
Village of Arlington Heights
Plat and Subdivision Committee
Community Room, 3rd Floor
Arlington Heights Village Hall
33 S. Arlington Heights Road
Arlington Heights, IL 60005
March 22, 2017
7:00 PM
I. CALL TO ORDER
II. ROLL CALL
III. APPROVAL OF MINUTES
IV. REPORTS
V. OLD BUSINESS
VI. NEW BUSINESS
A. Industrial Development - 702-723 W. Algonquin Rd. - T1581
Preliminary PUD, Plat of Subdivision to Consolidate Lots
VII. OTHER BUSINESS
VIII.ADJOURNMENT
Persons with disabilities requiring auxiliary aids or services, such as an
American Sign Language interpreter or written materials in accessible
formats, should contact David Robb, Disability Services Coordinator, at 33 S.
Arlington Heights Road, Arlington Heights, Illinois 60005, (847)368-5793
(Voice), (847)368-5980 (Fax) or drobb@vah.com.
Item: Industrial Development - 702-723 W. Algonquin Rd. - T1581
Department: Planning & Community Development
REQUESTED ACTION
1. Preliminary Planned Unit Development.
2. Plat of Subdivision to Consolidate the Lots.
VARIATIONS REQUIRED
1. None identified at this time.
RECOMMENDATION
The Staff Development Committee is generally supportive of the proposed PUD
and lot consolidation, however, further details from the petitioner are needed
before a formal recommendation can be rendered. The petitioner should address
the following items in their formal application to the Plan Commission.
1. Engineering plans and details, including a fire-truck auto turn exhibit, shall be
required as part of the formal review process.
2. A market assessment shall be required, which must analyze the need for this type
and size development at this location.
3. Design Commission review shall be required prior to a formal hearing of the Plan
Commission.
4. Driveway modifications along Algonquin Road shall be subject to IDOT approval.
5. An REA shall be required along the western property line (where appropriate) if
sufficient easements do not already exist relative to the neighboring development to
the west.
6. Provide a detailed Traffic and Parking Study from a Certified Traffic Engineer. This
study will need to assess access, on-site circulation, parking, trip generation, trip
distribution, and impacts to local streets.
7. A code compliant Landscape and Tree Preservation Plan shall be required. The
applicant shall provide an appropriate landscape screen along the southern (rear)
property boundary and shall evaluate if additional greenspace can be added to the
southwest corner of the development.
8. These are preliminary comments only and should not be relied upon as
identification of the only major concerns. The Staff Development Committee reserves
the right to change its position on issues upon submittal of a formal application and
detailed review.
ATTACHMENTS:
Description Type
Staff Report Board or Commission Report
Aerial Exhibits
Narrative Correspondence
Site Plan - Phase I Exhibits
Site Plan - Phase II Exhibits
VILLAGE OF ARLINGTON HEIGHTS Temp File Number: T1581
Project Title: 703-723 W Algonquin Ind. Redev.
Address: 703-723 W. Algonquin Rd.
PIN: Multiple PIN’s
To: Plat and Subdivision Committee
Prepared By: Sam Hubbard
Meeting Date: March 22, 2017
Date prepared: March 17, 2017
Petitioner: Mike Wauterlek
Address: Hamilton Partners Real Estate
300 Park Blvd. – Suite 201
Itasca, IL 60143
Existing Zoning: M-2, Limited Heavy
Manufacturing District
SURROUNDING LAND USES
Direction Existing Existing Use Comprehensive Plan
Zoning
North M-2 Multi-tenant office/light industrial building R&D, Mfg, Warehousing
South Elk Grove Village
East M-2 Self-Storage facility, 2 light industrial/office R&D, Mfg, Warehousing
buildings
West M-2 Light industrial/office building (Weber R&D, Mfg, Warehousing
Packaging Solutions)
Requested Action:
1. Preliminary Planned Unit Development.
2. Plat of Subdivision to Consolidate the Lots.
Variations Required:
1. None identified at this time
Page 1 of 4
Project Background:
The subject property is a composed of multiple lots of record comprising a total of 15.4 acres in area. The site is occupied by two
light industrial/office building, one on the northern half of the site and one on the southern half of the site. There are two driveway
entrances along Meijer Drive and one full access driveway along W. Algonquin Rd. The intersection of Meijer Drive and W.
Algonquin Road is a full access lighted intersection. On the southern end, the subject property abuts the I-90 Toll Road.
The applicant has proposed to purchase the site and redevelop the subject property in two phases. Phase I would involve the
demolition of the north building and the redevelopment of an approximately 131,750 square foot distribution facility with 28 loading
spaces and 187 parking spaces. Phase II would involve the demolition of the southern building and a 167,250 square foot addition
to the Phase I building, for a total of 299,000 square feet for distribution/warehousing. The total amount of on-site parking provided
would increase to 363 parking spaces.
The subject property would be built on speculation and no anchor tenant has signed on to lease space. The building would be
designed to allow the interior to be demised into 40,000 square foot spaces. The petitioner believes that proximity to I-90 and
Algonquin Road will make the site attractive to distribution and logistics companies, and are estimating approximately 350
employees to work out of the facility once both phases are complete. The property would operate on a 24-hour around the clock
schedule.
Zoning and Comprehensive Plan
Warehousing and distribution facilities are allowed as a permitted uses within the M-2 District and therefore no special use permit is
required for the proposed development. However, if tenants other than warehouse/distribution businesses are located for the
building, a special use permit may be required in the future depending on the proposed use of the tenant. Additionally, all
developments on property over 4 acres in size and within the M-2 District are required to obtain Planned Unit Development (PUD)
approval. The petitioner will be required to submit a zoning application, including all required plans and studies, in order to initiate
the Plan Commission process.
The Comprehensive Plan designates the subject property as appropriate for “Research & Development, Manufacturing, and
Warehousing.” The proposed use and PUD is consistent with this designation.
As the phased development approach involves a building that will cross multiple lot lines, a Plat of Subdivision will be required to
consolidate the lots. Since the project will proceed with zoning approvals for both Phase I and Phase II at the same time, approval
of the lot consolidation will be required as part of the PUD process.
All developments within the M-2 District are required to conform to the Industrial Performance Standards as identified within Section
5.1-18.2 of Chapter 28, which does mostly with odor, noise, vibrations, and other physical impacts that an industrial development
can have on neighboring properties. Although a distribution facility will not likely have issues conforming to these standards, the
petitioner should be aware of the standards to ensure that the proposed development can conform.
In order to demonstrate the sufficient demand for this particular development, the petitioner shall provide a market study that
discusses the market supply and demand for distribution facilities within this submarket.
When more detailed plans are received, additional Variations may be identified.
Site & Building
Preliminary analysis shows that the both phases of development will conform to all setback and bulk standards within the M-2
District, with exception to the rear parking row within Phase II which appears to be setback only 5’ from the rear property line where
all parking and storage must be setback a minimum of 15’ from the rear property line. Although there are no height, building
coverage, and impervious surface coverage regulations within the M-2 District, the petitioner should provide data on these aspects
of the development to allow staff to understand the overall impact of the building on the site.
The existing site appears to share an access drive along the western property line that provides access to the property to the west.
As part of the PUD process, the applicant must identify any Reciprocal Easement Agreements (REA) that provide for this access,
and if this access is not formally granted, it shall be required as part of the PUD process. Additionally, truck turning exhibits will be
required for both phases of the development, which should exhibits should also show how a Village fire truck will be able to
navigate the site.
Page 2 of 4
The applicant should examine the southwestern corner of the site and provide additional green space in this area. Currently, this
area is shown as impervious surface and it does not appear that paving will be necessary here to allow for truck movements.
Additionally, the proposed development must comply with all Village and MWRD regulations regarding detention, and additional
stormwater detention facilities may be needed. Finally, a code compliant photometric plan will be required as part of any formal
PUD application, and a Design Commission application will be required for the proposed development.
Landscaping
A code compliant landscape plan shall be required as part of the formal review process. According to code, a nine foot wide
landscape island with a four inch caliper shade trees are required at the end of each row of parking and after every 20 parking
stalls. In addition, a three foot high continuous row of shrubs is required to screen the parking lot from the public rights of way
(Algonquin Road and I-90). Additional landscaping is recommended along the rear of the property to provide a buffer from the
highway and to present an attractive development as viewed from this heavily travelled corridor
In conjunction with the landscape plan, a tree preservation plan shall be required. This plan needs to identify all existing trees that
have a trunk caliper size of 3-inches or greater. In addition, each tree must be identified by common and botanical name, size,
condition (good, fair, poor), disposition (remove, relocate, preserve), and its replacement value. As part of the formal review
process, staff will work with the Petitioner to try and save and/or relocate as many of the existing trees as possible.
Traffic and Parking
According to Chapter 28, Section 6.12, Traffic Engineering Approval, any Planned Unit Development larger than 5,000 square feet
in size that requires Plan Commission review is required to provide a traffic and parking study from a Certified Traffic Engineer. This
study needs to assess access (location, design, and Level of Service), on-site circulation, trip generation and distribution, parking,
and impacts to public streets. The traffic study should be sure to evaluate the impact of increased truck traffic and deliveries along
Meijer Drive and at the intersection of Meijer Drive and W. Algonquin Road. The petitioner should be aware that Algonquin Road is
under IDOT jurisdiction, and any modifications to the driveway along Algonquin Road will require IDOT approval.
Both phases of the development conform to parking requirements, however, the petitioner should note that parking requirements for
a warehouse facility are based on the number of employees at peak shift, plus the number of vehicles that will be used in the
conduct of the premises (i.e. one space per loading bay). Since the development is being constructed without any known tenants
and interior buildout plans, the number of employees is unknown, the total square footage of all office spaces is unknown, and the
74 loading bays are only a conceptual design. Therefore, the total amount of code required parking is unknown. The petitioner
should be mindful to design the parking to accommodate one parking space for every two employees, plus one parking space per
loading bay, plus one parking space per every 300 square feet of office areas in order to conform to code requirements. Given the
estimate of 350 employees, 74 loading spaces, and 26,000 square feet of office space, 336 parking spaces would be required and
363 parking spaces have been proposed. Finally, staff notes that Phase I appears to have a handicap parking stall that shares an
access aisle with a neighboring handicap stall, which is not allowed by code and should be revised.
RECOMMENDATION
The Staff Development Committee is generally supportive of the proposed PUD and lot consolidation, however, further details from
the petitioner are needed before a formal recommendation can be rendered. The petitioner should address the following items in
their formal application to the Plan Commission.
1. Engineering plans and details, including a fire-truck auto turn exhibit, shall be required as part of the formal review process.
2. A market assessment shall be required, which must analyze the need for this type and size development at this location.
3. Design Commission review shall be required prior to a formal hearing of the Plan Commission.
4. Driveway modifications along Algonquin Road shall be subject to IDOT approval.
5. An REA shall be required along the western property line (where appropriate) if sufficient easements do not already exist
relative to the neighboring development to the west.
6. Provide a detailed Traffic and Parking Study from a Certified Traffic Engineer. This study will need to assess access, on-site
circulation, parking, trip generation, trip distribution, and impacts to local streets.
7. A code compliant Landscape and Tree Preservation Plan shall be required. The applicant shall provide an appropriate
landscape screen along the southern (rear) property boundary and shall evaluate if additional greenspace can be added to the
southwest corner of the development.
Page 3 of 4
8. These are preliminary comments only and should not be relied upon as identification of the only major concerns. The Staff
Development Committee reserves the right to change its position on issues upon submittal of a formal application and detailed
review.
________________________________________ March 17, 2017
Bill Enright, Deputy Director of Planning and Community Development
Cc: Randy Recklaus, Village Manager
All Department Heads
Temp File 1581
Page 4 of 4
703-723 W. Algonquin Rd - Aerial
March 17, 2017 1:4,514
0 0.0375 0.075 0.15 mi
0 0.05 0.1 0.2 km
Village of Arlington Heights GIS
Copyright 2013
March 9th, 2017
RE: 15.40 acres located at the northeast corner of Algonquin Road and Meijer Drive Arlington Heights,
Illinois
To Whom It May Concern:
Hamilton Partners was formed in 1987 after a core group of partners separated from Trammell Crow’s Midwest
operations. Hamilton Partners has since grown to be one of the largest privately held real estate development firms
in the central US with a total portfolio of over 25 million square feet and a conservative market value in excess of
$2 billion. Our portfolio consists of office, industrial, apartment and retail with projects in Chicago, Salt Lake City,
Denver, Milwaukee and Raleigh Durham.
The property at Algonquin Road and Meijer Drive gives us an opportunity to expand upon an existing local
portfolio of distribution buildings totaling in excess of 15,000,000 square feet. The proposed state of the art facility
will be the most functional industrial property in the area totaling approximately 299,000 square feet, with the
ability to be demised to approximately 40,000 square foot suites. The initial phase of the project will be
approximately 131,750 square feet. The construction of the first phase of the facility will begin immediately upon
receipt of a building permit. The duration of the construction will last approximately 6 months. The expansion of
the building will occur once the existing southern facility becomes vacant. The proposed facility will offer 32’ clear
heights, high efficiency lighting, a 130’ truck court, and the highest car parking ratio in the submarket for similar
properties with a total of 363 auto stalls.
Our target customers for the property will be light distribution companies and companies desiring image or a
showroom given the exposure off of I-90 and Algonquin Road. We also believe the facility will be attractive to
logistics companies given the properties’ proximity to access on both I-90 and Highway 53. The property will offer
24 hour access and use to prospective tenants. Based upon similar properties, the property will be occupied by
tenants employing approximately 350 employees.
Hamilton Partners’ business model has been to construct quality properties with an infinite hold period. We look
forward to partnering with the Village of Arlington Heights on this project and others over the years to come.
Mike Wauterlek
Hamilton Partners Real Estate
300 Park Boulevard, Suite 201
Itasca, Illinois 60143
L
AD
TO DAM
90
LL S
W ME
AY MO
I-9
0 RIA
E
JA
N
ME
EXI IJE
STIN R
DR
GB '
131
71'
TO UILD
REM ING
AIN '
250 IND 527
' 60' 24'
40'
59'
UST
FOO
TPR
R IAL 60'
INT
: 131
B LDG
CLR ,750 50'
OFF .HG SF
ICE T: 3 TYP
2'
40'
52'
TYP
OFF 24
ICE '
60'
RD
I N
U
NQ
O
ALG
W
This conceptual design is based upon a preliminary review of 1" =60'
entitlement requirements and on unverified and possibly
incomplete site and/or building information, and is intended
merely to assist in exploring how the project might be developed.
0 30 60 150 300 NORTH
scheme: 05
W Algonquin Road CHI16-0313-00 SHEET
Arlington Heights, Illinois 03.08.2017
1
L
AD
TO DAM
90
LL S
W ME
AY MO
I-9
0 RIA
E
JA
N
EXISTING LOT LINE
250
'
ME
OFFICE 119 IJE
6' R
DR
' 71'
131
OFFICE
INDUSTRIAL BLDG 60' 24'
FOOTPRINT: 299,000 SF
CLR.HGT: 32' 60'
OFFICE
50'
TYP
40' 52'
OFFICE
TYP
OFFICE 24
'
60'
RD
I N
U
NQ
O
ALG
W
This conceptual design is based upon a preliminary review of 1" =60'
entitlement requirements and on unverified and possibly
incomplete site and/or building information, and is intended
merely to assist in exploring how the project might be developed.
0 30 60 150 300 NORTH
scheme: 03
W Algonquin Road CHI16-0313-00 SHEET
Arlington Heights, Illinois 01.04.2017
1