Public Works and Utilities Committee
Regular MeetingCharleston, SC · October 27, 2015
Agenda
City of Charleston
JOSEPH P. RILEY, JR. South Carolina LAURA S. CABINESS, P.E.
Mayor Director
Department of Public Service
PUBLIC WORKS AND UTILITIES COMMITTEE
AGENDA
There will be a meeting of the Public Works and Utilities Committee on Tuesday, October 27,
2015 to begin at 4:00 p.m. at 1st Floor Conference Room, 80 Broad Street. The following items
will be heard:
A. Invocation
B. Approval of Public Works and Utilities Committee Minutes
September 21, 2015 – DEFERRED
October 13, 2015 – DEFERRED
C. Request to Set a Public Hearing
None
D. Acceptance and Dedication of Rights-of-Way and Easements
1. Fenwick Hills Phase 2 – abandonment of existing 16-foot drainage easement.
a. Abandonment of Easement
b. Plat
c. Letter
E. Requests for Permanent Encroachments
None
F. Temporary Encroachments Approved By The Department of Public Service (For
information only)
1. 1655 Pierce Street – installing irrigation encroaching into right-of-way. This
encroachment is temporary. Approved 10/14, 2015.
2. 1831 Village Crossing Drive – installing irrigation encroaching into right-of-way.
This encroachment is temporary. Approved 10/14, 2015.
75 Calhoun Street, 3rd Floor, Charleston, SC 29401-3506 · Phone (843) 724-3754 · Fax (843) 973-7261
3. 1904 Village Crossing Drive – installing irrigation encroaching into right-of-way.
This encroachment is temporary. Approved 10/14, 2015.
4. 1908 Village Crossing Drive – installing irrigation encroaching into right-of-way.
This encroachment is temporary. Approved 10/14, 2015.
5. 2544 Daniel Island Drive – installing irrigation encroaching into right-of-way.
This encroachment is temporary. Approved 10/14, 2015.
6. 2545 Daniel Island Drive – installing irrigation encroaching into right-of-way.
This encroachment is temporary. Approved 10/14, 2015.
7. 439 Lesesne Street – installing salt-finish concrete driveway apron and irrigation
encroaching into right-of-way. This encroachment is temporary. Approved 10/14,
2015.
8. 1622 Sparkleberry Lane – installing 4-foot wooden fence with 5-foot posts
encroaching into drainage easement. This encroachment is temporary.
Approved 10/14, 2015.
9. 1540 Seabago Drive – installing 5-foot wood fence encroaching into drainage
easement. This encroachment is temporary. Approved 10/14, 2015.
10. 2877 Ortega Drive – installing 6-foot wooden privacy fence encroaching into
drainage easement. This encroachment is temporary. Approved 10/14, 2015.
11. 343 King Street – installing 15.42-ft x 3.5-ft awning encroaching into right-of-
way. This encroachment is temporary. Approved 10/14, 2015.
12. 38 Broad Street – installing 27” x 14” right angle sign encroaching into right-of-
way. This encroachment is temporary. Approved 10/14, 2015.
13. 1251 Adela Hills Drive – transfer of encroachment from contractor – irrigation
encroaching into right-of-way. This encroachment is temporary. Approved 10/14,
2015.
14. 1501 Creek Side Way – installing irrigation encroaching into right-of-way. This
encroachment is temporary. Approved 10/14, 2015.
15. 77 Wentworth Street – installing 32” diameter right angle sign encroaching into
right-of-way. This encroachment is temporary. Approved 10/14, 2015.
16. 1215 Adela Hills Drive – transfer of encroachment from contractor - irrigation
encroaching into right-of-way. This encroachment is temporary. Approved 10/14,
2015.
17. 1110 John McEnery Road – transfer of encroachment from contractor -
irrigation encroaching into right-of-way. This encroachment is temporary.
Approved 10/14, 2015.
18. 1255 Adela Hills Drive – transfer of encroachment from contractor - irrigation
encroaching into right-of-way. This encroachment is temporary. Approved 10/14,
2015.
G. Miscellaneous or Other New Business
1. Building Inspections Third Party Inspection Policy
Councilmember Perry K. Waring
Chairperson
CITY OF CHARLESTON BUILDING INSPECTIONS
DIVISON
Third Party Inspection Program Policy
September 2015
I. Purpose
The purpose of the City of Charleston Building Inspections Division (BID) Third Party
Inspection Program (hereafter TPIP) is to establish:
• When third party inspections (hereafter TPI) can be utilized;
• The minimum criteria to become a pre-qualified third party inspector;
• The minimum criteria to maintain pre-qualification as a third party inspector;
• The processes of conducting TPI including obtaining approval for a specific inspection,
scheduling and reviewing previous inspection;
• The process of submitting TPI reports;
• Disciplinary and revocation procedures; and
• TPI Acknowledgement Form.
II. Basis for Third Party Inspections
TPI are not allowed by right. TPI are intended to augment inspections mandated by 2012
International Building Code (hereafter IBC) §104.4 and §110.3 performed by building official or
designee. IBC §104.4 and §110.4 authorizes the building official to accept reports by
preapproved inspection agencies. The building official recognizes the use of TPI as a means to
augment the demand on daily City inspection services as a means to maintain services delivery
and reduces potential construction projects delays, such as the need for inspection services
outside of normal City working hours and City holidays.
IBC 104.4 Inspections. The building official shall make all of the required inspections, or the building official shall
have the authority to accept reports of inspection by approved agencies or individuals. Reports of such inspections
shall be in writing and be certified by a responsible officer of such approved agency or by the responsible
individual. The building official is authorized to engage such expert opinion as deemed necessary to report upon
unusual technical issues that arise, subject to the approval of the appointing authority.
IBC §110.3 Required inspections. The building official, upon notification, shall make the inspections set forth in
§110.3.1 through §110.3.10.
IBC §110.4 Inspection agencies. The building official is authorized to accept reports of approved inspection
agencies, provided such agencies satisfy the requirements as to qua lifications and reliability.
III. Use of Third Party Inspections
In all instances, TPI shall be by an agency or individual that has met the City’s minimum
qualifications, experience and preapproved by the building official in advance of the inspection
request(s). Prior to commencement of work, the permit holder shall request, in writing to the
City of Charleston building official, to use TPIs for the project.
Page 1 of 9
IV. Third Party Inspection Limitations
TPI will not routinely replace City inspections conducted during the normal course of a business
day. TPI may be utilized only as authorized and approved by the building official. Due to the
many special requirements found in various City of Charleston ordinances/procedures and as a
final measure of quality assurance, TPI will only be authorized as listed below.
Inspection Responsibility
Temporary Power Pole TPI
Clearing, Grading & Sediment control City
Foundation - including applicable Electrical, Mechanical, Fuel-gas and
TPI
Plumbing
Sheathing & Strapping TPI
Trade Rough-in - Electrical, Mechanical, Fuel-gas and Plumbing TPI
Framing TPI
Quality Assurance Prior to Concealment City
Insulation TPI
Temporary Power - Fuel-gas or Electric TPI
Final Trade - Electrical, Mechanical, Fuel-gas and Plumbing TPI
Final Building City
Certificate of Construction Completion City
Certificate of Occupancy City
V. Third Party Inspector Qualifications
Third party inspectors (hereafter Inspector) must demonstrate the knowledge, skills and abilities
to perform inspections in their area of expertise. Not only must they demonstrate a technical
knowledge of the code and trade they inspect, they must also demonstrate that they have
applicable knowledge of City ordinances and regulations. Third party inspectors must provide
the following for evaluation and approval purposes to the building official. Approval of a third
party inspector shall be in writing from the building official.
A. Registration and Certification
The following shall serve as minimum qualifications for all inspectors:
• South Carolina Department of Labor, Licensing & Regulation (LLR) registration as an
inspector in the specific area(s) of inspections performed; and
• International Code Council (ICC) certification(s) as an inspector in the specific area(s) of
inspections performed; or
• A South Carolina Registered Design Professional (RDP) practicing within their area of
competency as related to the area of inspection; or
• Individuals or firms approved to perform special inspections as specified in 2012 IBC
§110.3.9 within their area of qualification, competency and operating under the direction
of a South Carolina RDP.
Page 2 of 9
B. Experience
The Inspector shall demonstrate knowledge of the applicable codes, South Carolina
modifications, City ordinances and other applicable City regulations by demonstrating the
following minimum experience:
• A minimum of five years of experience conducting inspections within the specific area of
expertise as regulated by IBC and LLR; or
• Applicants may also submit for consideration additional qualifications to substantiate
equivalent experience. This may include engineers-in-training that include a college
degree in subject area augmented with field inspection experience and supervision of a
South Carolina RDP; or
• Applicants may substitute two years of field construction supervision experience for each
one year of field inspection experience if it is relevant to the area of inspections being
sought for approval. Field construction supervision experience may replace up to three of
the five years of inspection experience.
However, the building official reserves the right to require more than the above minimum
requirements in specific situations, at his/her sole discretion.
C. Independence
Inspectors must be able to demonstrate and maintain independence from any person or firm
responsible for construction of work they will inspect. The Inspector shall have no financial
or personal relationship with the property owners, designers, permit holders, contractors or
sub-contractors being inspected. Inspectors shall not have:
• Accepted monies or any other item of value other than remuneration for third party
inspection services; or
• Performed services or other work other than third party inspections for the property
owners, designers, permit holders, contractors or sub-contractors being inspected for a
period of 2 years prior to performing such inspection.
The Inspector must always maintain a high degree professionalism, neutrality and autonomy
necessary to secure the health, safety and welfare provisions of the IBC. Although paid by
the permit holder, the Inspector is ultimately responsible to the City of Charleston building
official. If the Inspector discovers any attempts by the responsible party to cover or conceal
discrepancies or rejected work, the Inspector shall immediately contact the building official.
The Inspector shall not perform any further TPIs on the project until approval is obtained
from building official.
The Inspector is required to complete the attached “Affidavit of Independence” and submit it
to the City of Charleston building official prior to approval as a TPI.
Page 3 of 9
VI. Third Party Inspector Insurance Requirements
The Inspector or agency must submit proof of general liability insurance and professional errors
and omissions insurance with a minimum $1,000,000 limit for each occurrence. The insurance
company must state that they will provide a thirty day cancellation notice to the City. The
Inspector or agency shall provide proof of insurance prior to approval as a TPI.
VII. Independent Contractor
The relationship of the TPI to the City, and its employees and agents, is that of an independent
contractor and not an employee. TPI acknowledges that the true nature of its relationship is that
of an independent contractor in that TPI may use any appropriate method of conducting its
services based on its knowledge, skill, judgment, means and methods.
VIII. Indemnification
TPI shall be solely responsible for any and all of its actions, errors and/or omission, and agree to
indemnify and hold harmless the City, its agents and employees, against any and all claims for
injury, liability or damage, whether to person, property or business, that may arise as a result of
TPI actions.
IX. Business License
The Inspector or agency performing TPIs shall provide documentation of an appropriate business
and LLR license(s) as required by the City of Charleston. If a license is required, a copy of the
license shall be provided before approval as a TPI.
X. Training & Meetings
Inspectors maintaining an approval status or who are providing continuous inspection services
shall have at least one qualified company representative attend designated City TPI meetings as
necessary. All qualified inspectors shall attend all the following training to maintain their
approval:
• Any South Carolina Building Code Council (BCC) code update or mandated training; and
• Any required training to maintain a professional license or certification.
XI. Annual Renewal of Third Party Inspector Qualification
To maintain approval to conduct third party inspections in The City of Charleston, the Inspector
shall submit, one month before their approval anniversary date, all the following:
• Proof of attendance of any mandatory training to maintain LLR registration or professional
qualifications;
• Proof of the required insurance; and
• Proof of business license.
Page 4 of 9
Failure to submit the above documentation will result in suspension status and suspension of
inspection privileges. The Inspector or agency will be required to be re-approved before being
authorized to perform inspections.
XII. Inspection Scheduling
Third Party Inspections shall be scheduled by the established procedures below:
Inspection requests shall be scheduled directly by the general contractor. The process will be
reviewed and a procedure approved at a mandatory TPI pre-permit meeting conducted by the
City. Unless otherwise directed, inspections must be requested by using the automated
scheduling system and documented as any other BID performed inspection. An inspection code
shall be provided to the permit holder and/or the TPI so that the inspection request can be
identified by BID. It shall be the responsibility of the pre-qualified Third Party Inspector to
contact BID before conducting an inspection as noted in this policy. If the agent performing the
inspection is pre-qualified, the building official or designee may approve the TPI. The
inspection shall not be authorized if BID can perform the inspection within two working days
and during normal working hours. No TPI shall be performed without pre-inspection approval.
XIII. Inspection and Inspection Reports
TPI reports conducted by approved inspectors or agencies shall be in writing and shall indicate if
compliance was achieved based on the applicable codes and City ordinances and regulations.
The report shall be certified by the individual inspector or responsible agency representative.
The Inspector or agency is not authorized to approve any construction field changes and must
make sure that the approved plans are strictly followed.
Note: Photographs, videos or other sources of pertinent data or information may be considered
as constituting such reports and tests.
A. TPI Reports Shall Be Legible and Include:
• The Inspector's name, address, phone number and E-mail
• The name of the approved agent if different from above
• The applicable permit number(s)
• Project street address
• Inspection type
• Date and time of the inspection
• City approved permit plans were available on site for inspection
• The inspection results with deficiencies properly identified
• Verification that previous inspection discrepancies were known, reviewed and approved
or need correction where applicable
• A statement that reads, "This inspection report is subject to review and approval by the
City of Charleston Building Inspections Division. Construction is not to proceed until
inspection validation is assured."
Page 5 of 9
B. Recording TPI Reports
All inspection reports shall be submitted through the City’s designated electronic permitting
system by close of business on the day the inspection was performed.
Any inspection deficiencies must be identified with sufficient detail and applicable code
sections cited and provided, in writing, to the permit holder on the day the inspection was
performed. The written notice shall provide the reason for the rejection, any concerns raised
through the inspection process and the terms to achieve compliance and remedy the
rejection.
The City reserves the right to perform quality assurance (QA) inspections without prior
notice to evaluate the performance of the Inspector or agency. The interval shall be
determined by the City, but shall be conducted at least weekly.
Code deficiencies subsequently found by the City, which may have been missed by the
Inspector or agency, shall be corrected prior to concealment.
It will be the responsibility of the Inspector or agency to verify all required inspections have
been completed and passed before sequential inspections may be performed.
XIV. Third Party Inspector Revocation
The building official may suspend or revoke inspection privileges of an approved inspector or
agency for just cause. Any decision rendered by the building official may be appealed to the
City of Charleston Board of Appeals (BOA). Failure to strictly comply with all of the below
terms may result in inspection reports being rejected and suspension or termination of approval
to conduct TPI.
• Failure to maintain required certifications or licenses
• Failure to maintain the minimum required insurance
• Failure to adhere to the requirements for inspection scheduling or reporting
• Failure to perform proper inspections in accordance with the code and City ordinances,
policies and the TPI program
• Failure to attend training or meetings that are required by TPI program
• Failure to follow the written City directives when unacceptable inspection practices or results
are identified
• Evidence of misrepresentation of fact that led to approval by the City
• Failure to maintain independence from the individuals or firms responsible for the project
construction being inspected
• Failure to have City approved inspectors performing inspections
• Falsification of any reports
• Any act or omission that is deemed by the City to violate the letter or intent of the TPI
program or any laws or ordinances of the Federal Government, State of South Carolina or
City of Charleston.
Page 6 of 9
XV. Third Party Inspection Costs
The permit holder is responsible for all costs associated with TPIs. In addition to paying the TPI
services, the permit holder shall be responsible for all normal City permit fees.
Page 7 of 9
City of Charleston, SC
Third Party Inspection Program Policy - Acknowledgement Form
Please read the City of Charleston’s Third Party Inspection Program Policy carefully to ensure
that you understand the policy before signing this acknowledgement.
I have read and understand the City of Charleston’s Third Party Inspections Program Policy.
I have received a copy of the policy and agree to abide by the policy guidelines as a condition to
use third party inspection for my permitted project.
Project Address
Master Building Permit(s)
Permit Holder’s or Authorized Designee’s Signature:
Permit Holder’s or Authorized Designee’s Printed Name:
Date:
Page 8 of 9
THIRD PARTY INSPECTOR
AFFIDAVIT OF INDEPENDENCE
PERSONALLY, appeared before me the undersigned who, being duly sworn, deposes and says:
My name is .
I currently am employed as a with .
I understand that as a Third Party Inspector for the City of Charleston (“TPI”), I am required to
demonstrate and maintain independence from any person or entity responsible in any way for the
work I am inspecting.
I have no financial or personal relationship with the property owners, designers, permit holders
or sub-contractors associated with the [“the Project”].
I understand that as the TPI, I cannot accept money or any other item of value other than
remuneration for my third party inspection services related to this Project.
I further understand that as the TPI, I cannot have performed services or other work other than
third party inspections for the property owners, designers, permit holders, contractors or sub-
contractors for the Project being inspected for a period of TWO (2) years prior to performing
such inspections.
Further your deponent saith not.
Signed and sworn to before me this day of , 20 .
_______________________________
Notary Public
My Commission Expires: __________
Page 9 of 9