Rock Quarry Road Scenic Roadway Stakeholder Advisory Group
Regular MeetingColumbia, MO · June 8, 2016
Minutes
City of Columbia, Missouri
Meeting Minutes
Rock Quarry Road Scenic Roadway Stakeholder Advisory Group
Wednesday, June 8, 2016 Meeting Room 1C, 701
6:30 PM E. Broadway
I. CALL TO ORDER
by Vicky Riback Wilson at 6:35pm.
Staff Present: Richard Stone, Public Works; John Ogan, Public Works
Present: 8- Janet Hammen, Dan Harder, Barbara Hoppe, Bev Peterson, Jan Pritchard, Victoria
Wilson, Julie Youmans and Betsy Peters
Absent: 3- Tony Davis, Meredith Donaldson and Anthony Stanton
II. Read and approve minutes from April 13, 2016
Ms. Hoppe moves to approve minutes from April 2016. By voice vote, minutes
unanimously approved.
III. Timeline - a brief consideration of our timeline and work during the month to finalize
details on Preamble, Enforcement, other
IV. Powerpoint version of report
V. Clarification of 3 under IV - Enforcement
VI. Inventory
VII. Latest version of committee report on recommendations - revisions and
enforcement
Since the May 2016 meeting, Ms. Hoppe and Ms. Youmans have met and reviewed
the many revisions/comments that were shared. Ms. Youmans would like to have
all photos captioned with information pertaining to points the committee is making
in the report. Julie Youmans brings up consistency with how we refer to ourselves
in the report. Richard Stone advises the group they are officially an Advisory Group
- Scenic Rock Quarry Road Advisory Group.
Ms. Youmans asks if there is any larger issue or topic that may have been missed?
Ms. Pritchard asks “the intent is to preserve….” Whose intent? The intent of the
Advisory Group or the report? Discussion followed and Ms. Pritchard agrees it is a
good idea to say what the Advisory Group wants to accomplish but we need to
determine whose intent it is. Amended language might include: The
recommendations presented herein are intended to preserve the previously
designated Scenic Rock Quarry Road corridor. Nothing in these recommendations
City of Columbia, Missouri Page 1 Printed on 7/20/2016
Rock Quarry Road Scenic Roadway Meeting Minutes June 8, 2016
Stakeholder Advisory Group
however should preclude consideration of new ideas provided they meet the
presented guidelines. Discussion continues about language in section IV relating to
a possible pedway along Rock Quarry Road. Vicky suggests changing section VI to
Enforcement and section V to Maintenance and Development because we
recognize the whole report is only a recommendation. While reviewing the
introduction Jan suggests further defining “Rock Quarry Assets” by formatting the
introduction similar to the way statutes are written. Draft report discussion
continues. Vicky would like to add alternating one way traffic morning & evening in
place of rumble strips. Vicky recognizes this has been previously discussed. Julie
suggests adding “Consider and explore innovative options and solutions used by
other cities consistent with recommendations of this report ”. This will be added as
#12 in lieu of Vicky’s suggestion of alternating one way traffic. Insertion of a colon
following topic headings was discussed. Several group members did not feel
insertion of a colon was necessary. Discussion review moved to section V -
Vegetative Buffer.
Discussion continued about existing development agreements adjacent to Rock
Quarry Road. While making recommendations it would be a good idea to point out
certain things that have been ordinance violation and include in the enforcement
section of the report. Janet suggests that should another development plan come
into existence it be added to this report, under enforcement. Janet would like
something that links this report to all other development plans so the SRQR
Advisory Group report does not get lost. All revisions discussed this meeting will
be incorporated into revision #8 which will be available for the SRQR Advisory
Group July 13, 2016 meeting.
Since the May 2016 meeting, Ms. Hoppe and Ms. Youmans have met and reviewed
the many revisions/comments that were shared. Ms. Youmans would like to have
all photos captioned with information pertaining to points the committee is making
in the report. Julie Youmans brings up consistency with how we refer to ourselves
in the report. Richard Stone advises the group they are officially an Advisory Group
- Scenic Rock Quarry Road Advisory Group.
Ms. Youmans asks if there is any larger issue or topic that may have been missed?
Ms. Pritchard asks “the intent is to preserve….” Whose intent? The intent of the
Advisory Group or the report? Discussion followed and Ms. Pritchard agrees it is a
good idea to say what the Advisory Group wants to accomplish but we need to
determine whose intent it is. Amended language might include: The
recommendations presented herein are intended to preserve the previously
designated Scenic Rock Quarry Road corridor. Nothing in these recommendations
however should preclude consideration of new ideas provided they meet the
presented guidelines. Discussion continues about language in section IV relating to
a possible pedway along Rock Quarry Road. Vicky suggests changing section VI to
Enforcement and section V to Maintenance and Development because we
City of Columbia, Missouri Page 2 Printed on 7/20/2016
Rock Quarry Road Scenic Roadway Meeting Minutes June 8, 2016
Stakeholder Advisory Group
recognize the whole report is only a recommendation. While reviewing the
introduction Jan suggests further defining “Rock Quarry Assets” by formatting the
introduction similar to the way statutes are written. Draft report discussion
continues. Vicky would like to add alternating one way traffic morning & evening in
place of rumble strips. Vicky recognizes this has been previously discussed. Julie
suggests adding “Consider and explore innovative options and solutions used by
other cities consistent with recommendations of this report ”. This will be added as
#12 in lieu of Vicky’s suggestion of alternating one way traffic. Insertion of a colon
following topic headings was discussed. Several group members did not feel
insertion of a colon was necessary. Discussion review moved to section V -
Vegetative Buffer.
Discussion continued about existing development agreements adjacent to Rock
Quarry Road. While making recommendations it would be a good idea to point out
certain things that have been ordinance violation and include in the enforcement
section of the report. Janet suggests that should another development plan come
into existence it be added to this report, under enforcement. Janet would like
something that links this report to all other development plans so the SRQR
Advisory Group report does not get lost. All revisions discussed this meeting will
be incorporated into revision #8 which will be available for the SRQR Advisory
Group July 13, 2016 meeting.
A motion was made by Vicky Riback-Wilson to dissolve the Wordsmithing
Committee and changes agreed upon this evening be incorporated into a draft
document by volunteers. The motion was seconded and approved unanimously by
voice vote.
A motion was made by Vicky Riback-Wilson to table remaining agenda items until
subsequent meeting. Motion was seconded and unanimously approved by voice
vote.
The SRQR Advisory Group has contacted Steve MacIntyre in Community
Development who has expressed interest in reviewing our draft report. Roxy
Campbell with Rock Bridge State Park contacted Barbara Hoppe and requested a
draft copy of SRQR Advisory Group report.
VIII. ADJOURNMENT
Meeting adjourned at 8:00pm.
Minutes Respectfully Submitted,
Brenda Broxton
City of Columbia, Public Works
City of Columbia, Missouri Page 3 Printed on 7/20/2016
Rock Quarry Road Scenic Roadway Meeting Minutes June 8, 2016
Stakeholder Advisory Group
Members of the public may attend any open meeting. For requests for accommodations related to
disability, please call 573-874-7214. In order to assist staff in making the appropriate arrangements for
your accommodation, please make your request as far in advance of the posted meeting date as
possible.
City of Columbia, Missouri Page 4 Printed on 7/20/2016
Agenda
City of Columbia, Missouri
Meeting Agenda
Rock Quarry Road Scenic Roadway Stakeholder Advisory Group
Wednesday, June 8, 2016 Meeting Room 1C, 701 E.
6:30 PM Broadway
I. CALL TO ORDER
II. Read and approve minutes from April 13, 2016
III. Timeline - a brief consideration of our timeline and work during the
month to finalize details on Preamble, Enforcement, other
IV. Powerpoint version of report
V. Clarification of 3 under IV - Enforcement
VI. Inventory
VII. Latest version of committee report on recommendations - revisions and
enforcement
VIII. ADJOURNMENT
Members of the public may attend any open meeting. For requests for
accommodations related to disability, please call 573-874-7214. In order to assist staff
in making the appropriate arrangements for your accommodation, please make your
request as far in advance of the posted meeting date as possible.