Planning & Zoning Commission
Regular MeetingDeKalb, IL · April 8, 2020
Minutes
Planning and Zoning Commission
April 8, 2020
Page 1 of 4
MINUTES
CITY OF DEKALB
PLANNING AND ZONING COMMISSION
April 8, 2020
The Planning and Zoning Commission held a Meeting on April 8, 2020, at the City of
DeKalb Municipal Building, 200 South Fourth Street, DeKalb, Illinois. Chair Max Maxwell
called the meeting to order at 6:05 PM.
Chair Maxwell stated he wanted to thank everyone for being here tonight, including
Commission members who are attending remotely and for those who are watching
on Channel 14 or streaming live. He referenced the Governor’s Executive Order in
March that allows Commission members to participate remotely. He said member
Chris Doe will be joining the meeting remotely by calling in and mentioned for those
attending the meeting the room has been set up to meet the CDC recommended
distancing guidelines and the Executive Order from the Governor.
A. ROLL CALL
Recording Secretary Aaron Walker called the roll. Planning and Zoning
Commission members present were: Chair Max Maxwell, Steve Becker, Ron Klein,
and Trixy O’Flaherty. Vice Chair Christina Doe attended the meeting remotely by
an audio conference call. Commissioners Jerry Wright and Vicki Buckley were
absent. Principal Planner Dan Olson was present representing the City.
B. APPROVAL OF THE AGENDA (Additions/Deletions)
Chair Maxwell requested a motion to approve the April 8, 2020, agenda as
presented. Mr. Klein motioned to approve the agenda as presented. Ms. O’Flaherty
seconded the motion, and the motion was approved by unanimous voice vote.
C. APPROVAL OF MINUTES
1. March 4, 2020 – Chair Maxwell requested a motion to approve the March 4,
2020 minutes as presented. Vice Chair Doe noted two corrections on pages
one and three regarding the incorrect referencing of Chair Maxwell which
should have been Vice-Chair Doe. Mr. Becker motioned to approve the minutes
with the corrections noted. Mr. Klein seconded the motion, and the motion was
approved by unanimous voice vote.
D. PUBLIC PARTICIPATION (Open Floor to Anyone Wishing to Speak on Record)
None
E. NEW BUSINESS
Planning and Zoning Commission
April 8, 2020
Page 2 of 4
1. Public Hearing – Petition by Ventus Tech Services LLC for the annexation,
rezoning, and conceptual site plan approval for approximately 505 acres of
property generally located east of State Route 23 and south of Gurler Road.
Chair Maxwell noted the public hearing for the Petition by Ventus Tech Services
LLC would be continued until April 22, 2020, to ensure all relevant plans and
plats would be included with the petition. He said If there is anyone in the
audience from the public who wants to speak, we can take their comments.
There was none. He asked the Commission for a motion to continue the
hearing.
Mr. Klein moved the Planning and Zoning Commission continue the public
hearing for Ventus Tech Services, LLC to Wednesday, April 22, 2020 at
6:00PM in the City Council Chambers in the DeKalb Municipal Building located
at 200 S. Fourth Street, DeKalb, IL.
Mr. Becker seconded the motion.
A roll call vote was taken. Mr. Becker – yes, Mr. Klein – yes, Ms. Doe – yes,
Ms. O’Flaherty – yes, Chair Maxwell – yes. Motion was passed 5-0-2. Ms.
Buckley and Mr. Wright were absent.
2. Public Hearing – Petition by B33 Northland Plaza LLC for approval of
amendments to Ordinance 2019-004 and to waive provisions from Articles 5,
9, 10, and 12 of the UDO regarding building and parking setbacks, maximum
site coverage, lots having to front on a public street, and to permit existing utility
connections and other approvals as required in association of approval of the
Final Plat of Northland Plaza Third Resubdivision located within the address
range of 2420-2572 Sycamore Road.
Kevin Buick, attorney representing B33 Northland Plaza, LLC, advised Bridge
33 Capital is a Seattle based commercial firm that has owned the subject
property for some time. He advised in January of 2019, B33 Northland Plaza
LLC had petitioned for a second resubdivision, which created an additional lot
within the shopping center to allow for a new tenant, Planet Fitness. He stated
Planet Fitness requires ownership of the property they are operating in. Mr.
Buick said Northland Plaza is currently a two-lot subdivision and are proposing
to create a total of 8 lots.
Mr. Buick noted Lot 1 would include the large building on the east side of the
shopping center, Lot 2 would be Planet Fitness, Lot 3 would include the Egg
Haven building, Lot 4 would include the Panera Bread building, Lot 5 would be
the detention pond, Lot 6 would include the Panda Express building, Lot 7
Planning and Zoning Commission
April 8, 2020
Page 3 of 4
would include the Buffalo Wild Wings Building, and Lot 8 would include the
building at the southwest corner of the shopping center.
Mr. Buick stated the shopping center would continue to operate as a cohesive
body. He advised the resubdivision would allow the buildings to be sold
separately if required and noted this is the most common arrangement for
shopping centers.
Mr. Buick advised the amendments to the Planned Development will
accommodate the requested provisions. He noted the Planned Development
has restrictions on setbacks, which would be impossible to meet with the
proposed resubdivision because the buildings are already in place. He advised
Article 9 of the UDO requires lots to front a public street. He noted Lot 2 and 7
would not meet this requirement with the resubdivision, however, they would
still be accessible to a public street through the shopping center’s reciprocal
easement agreement (REA). Mr. Buick also mentioned there are waivers to
Article 10 regarding utility extension and Article 12 regarding parking setbacks
that are needed. Mr. Buick stated no new tenants are proposed with this
petition, but it will set up the shopping center for future investments.
Principal Planner Dan Olson went through the staff report dated April 3, 2020.
Mr. Olson advised the exterior setbacks of the shopping center will be
maintained. He stated only the internal setbacks within the shopping center will
have to be amended. He noted maintenance of the shopping center will still be
maintained through the REA, even if the lots are divided and sold to various
investors.
Mr. Olson advised staff recommended approval of the petition and Exhibit A
and described the proposed amendments.
Chair Maxwell gave the Commission members the opportunity to speak.
Chair Maxwell gave the public a chance to speak. There was none.
Mr. Klein moved that the Planning and Zoning Commission forward its findings
of fact and recommend to the City Council approval of amendments to
Ordinance 2019-004 and to waive provisions of the Unified Development
Ordinance and approval of the Final Plat of Northland Plaza Third
Resubdivision dated April 2, 2020, located along Sycamore Road subject to the
amendments, waivers and conditions as indicated on Exhibit A in the staff
report.
Ms. O’Flaherty seconded the motion.
Planning and Zoning Commission
April 8, 2020
Page 4 of 4
A roll call vote was taken. Mr. Becker – yes, Mr. Klein – yes, Ms. Doe – yes,
Ms. O’Flaherty – yes, Chair Maxwell – yes. Motion was passed 5-0-2. Ms.
Buckley and Mr. Wright were absent.
F. REPORTS
Mr. Olson advised the next Commission meeting will be on April 22, 2020 and
will include the continued petition by Ventus Tech Services LLC, a petition for
a proposed cannabis dispensary to be located at 818 W Lincoln Hwy, and a
text amendment to add data centers to the UDO.
G. ADJOURNMENT
Ms. O’Flaherty motioned to adjourn, Mr. Becker seconded the motion, and the
motion was approved by unanimous voice vote. The Planning and Zoning
Commission adjourned at 6:19PM.
Agenda
DeKalb Municipal Building
City Council Chambers
200 S. Fourth St., 2nd Floor
DeKalb, IL 60115
AGENDA
Planning and Zoning Commission
April 8, 2020
6:00 PM
Please Note: On March 16, 2020, Illinois Governor JB Pritzker issued executive order 2020-07 which
declared that during the duration of the Gubernatorial Disaster Proclamation pertaining to the coronavirus
outbreak, “the provisions of the Open Meetings Act, 5 ILCS, requiring or relating to in-person attendance
by members of a public body are suspended. Specifically, (1) the requirement in 5 ILCS 120/2.01 that
‘members of a public body must be physically present’ is suspended; and (2) the conditions in 5 ILCS
120/7 limiting when remote participation is permitted are suspended.” The executive order further states
that when a public meeting is considered necessary by the governing body, “public bodies are
encouraged to provide video, audio, and/or telephonic access to meetings to ensure members of the
public may monitor the meeting, and to update their websites and social media feeds to keep the public
fully apprised of any modifications to their meeting schedules or the format of their meetings due to
COVID-19, as well as their activities relating to COVID-19.” The City of DeKalb has taken prudent steps to
assure that Planning and Zoning Commission member remote participation and public access are
available and will be provided within the provisions of the Governor’s executive order.
A. ROLL CALL
B. APPROVAL OF AGENDA (Additions or Deletions)
C. APPROVAL OF MINUTES
1. March 4, 2020
D. PUBLIC PARTICIPATION (Open Floor to Anyone Wishing to Speak on Record)
E. NEW BUSINESS
1. Public Hearing – Petition by Ventus Tech Services, LLC for approval of the
annexation, rezoning, and conceptual plan for a data center on approximately 505
acres of property generally located east of State Rt. 23 and south of Gurler Road.
The public hearing for Ventus Tech Services, LLC will be continued to April
22, 2020.
2. Public Hearing – Petition by B33 Northland Plaza, LLC for approval of
amendments to Ordinance 2019-004 and to waive provisions from Articles 5, 9, 10
and 12 of the UDO regarding building and parking setbacks, maximum site
coverage, lots having to front on a public street, and to permit existing utility
connections and other approvals as required in association of approval of the Final
Plat of Northland Plaza Third Resubdivision located within the address range of
2420-2572 Sycamore Road.
F. REPORTS
G. ADJOURNMENT
MINUTES
CITY OF DEKALB
PLANNING AND ZONING COMMISSION
March 4, 2020
The Planning and Zoning Commission held a Meeting on March 4, 2020, at the City of
DeKalb Municipal Building, 200 South Fourth Street, DeKalb, Illinois. Vice Chair Christina
Doe called the meeting to order at 6:00 PM.
A. ROLL CALL
Recording Secretary Aaron Walker called the roll. Planning and Zoning
Commission members present were: Christina Doe, Steve Becker, Ron Klein,
Jerry Wright, and Trixy O’Flaherty. Chair Max Maxwell and Commissioner Vicki
Buckley were absent. Principal Planner Dan Olson and City Attorney Matthew
Rose were present representing the City.
B. APPROVAL OF THE AGENDA (Additions/Deletions)
Vice Chair Doe requested a motion to approve the March 4, 2020, agenda as
presented. Mr. Klein motioned to approve the agenda as presented. Mr. Wright
seconded the motion, and the motion was approved by unanimous voice vote.
C. APPROVAL OF MINUTES
1. February 19, 2020 – Vice Chair Maxwell requested a motion to approve the
February 19, 2020 minutes as presented. Mr. Wright motioned to approve the
minutes as presented. Ms. O’Flaherty seconded the motion, and the motion
was approved by unanimous voice vote.
D. PUBLIC PARTICIPATION (Open Floor to Anyone Wishing to Speak on Record)
Bessie Chronopoulos, of 423 Gayle Ave, thanked the Commission for their hard
work and welcomed Ms. O’Flaherty to the Commission. She stated the
Commission should meet on a more frequent basis to review the comprehensive
plan, to conduct training sessions, and to review the City Code. She stated the
Commission has the greatest impact on the community, second to the City Council.
E. NEW BUSINESS
1. Public Hearing – Petition by J&S Tri-State Recovery and Towing for approval
of a special use permit for a vehicle tow facility and storage yard to be located
at 110 Industrial Dr.
Adrian Roscelli, of 1516 Hulmes Dr, and Andrew Bjornson, of 114 Laurel St in
Batavia, were present representing J&S Tri-State Recovery and Towing.
Mr. Roscelli stated they were looking to open a new towing facility and start
relocations and towing for the DeKalb Police and County Sheriff’s Department
at 110 Industrial Dr. Mr. Roscelli advised the new site plan includes new
signage and striping for the parking lot and the installation of a 10-foot high
privacy fence.
Principal Planner Dan Olson went through the staff report dated February 28,
2020. He stated J&S Recovery and Towing is proposing to establish a vehicle
tow facility and storage yard at 110 Industrial Dr. He advised the zoning is “HI”
Heavy Industrial and vehicle tow facilities and storage yards are designated as
a special use in that zoning district. Mr. Olson noted the UDO requires storage
yards to have their activities within an enclosed building or surrounded by a
solid sight-proof fence not less than ten (10) feet in height.
Mr. Olson stated the applicant submitted a site plan showing the proposed
vehicle storage area, which will be mainly south of the existing building. He
advised parking will be provided for five vehicles in front of the building,
including a handicap space. A total of four parking spaces are required per the
UDO based on the number of employees on the maximum shift. The parking
spaces will have to be striped and a handicap space added with appropriate
signage prior to final occupancy of the towing operation.
Mr. Olson noted the City approval of a special use permit in 2015 for a vehicle
tow and storage yard located at 1888 State Street, which included several
conditions. He also noted the past special use permit for Lovett’s Towing at
along E. Lincoln Highway. He stated the conditions included those special uses
included no stacking of vehicles, no crushing of vehicles, no storage of vehicles
used in operation of the business being parked outside the fenced area, and
several other conditions. Mr. Olson advised the Commission staff is
recommending the petitioner be required to operate under the same conditions.
Mr. Olson advised the subject site has been zoned Heavy Industrial for
decades and there are several other motor vehicle related commercial and
industrial businesses along Industrial Drive. He noted the nearest residential
property is approximately 270 feet away, along the north side of East Lincoln
Hwy.
Mr. Olson advised a Citizen Response Form was received from the current
property owner, Stephanie Hankes of 383 Quinlan Ave, indicating her support
for petition.
Vice Chair Doe then invited attendees in the audience to speak.
Shannon Lovett, of 1837 East Lincoln Hwy (Lovett’s Towing) questioned
whether the setback for the proposed fence was within regulations. Mr. Olson
advised the proposed 10-foot fence can extend to the front yard for this type of
use and there are no setback requirements currently. Mr. Lovett advised his
business was required to have a 10-foot setback for a fence from property lines
when his petition was approved in 1990. Mr. Olson reiterated there are no
current fence setback requirements for the screening of s towing storage yard.
Vice Chair Doe gave the Commission members the opportunity to speak.
Mr. Wright questioned why the petitioner decided to establish a tow company
in DeKalb. Mr. Roscelli stated he worked for another tow company in the City
and understands the demand for towing services in DeKalb. Mr. Wright
inquired what the size of the proposed lot would be. Mr. Bjornson advised the
lot is 100 feet by 175 feet.
Mr. Becker questioned whether the business would also be involved in vehicle
or vehicle part sales. Mr. Roscelli advised the business would not be involved
in vehicle or vehicle part sales.
Vice Chair Doe inquired where the dumpster will be located on the property.
Mr. Roscelli said it would be in the fenced in area. Vice Chair Doe asked what
happens to a vehicle if it has been stored on the property longer than 90 days.
Mr. Bjornson advised the Commission of a state statute that allows a vehicle
tow facility to take ownership of a stored vehicle if the owner of the vehicle does
not retrieve it within 15 days of being notified that the tow facility is current in
possession of the vehicle.
City Attorney Matthew Rose questioned what security measures will be taken
around the exterior of the property. Mr. Roscelli advised there will be high
definition security cameras throughout the property, as well as multiple flood
lights.
Mr. Becker questioned if they will be doing any repossession of vehicles. Mr.
Bjornson stated they will not.
Chair Maxwell gave the public one more opportunity to speak. There was none.
Mr. Becker moved the Planning and Zoning Commission forward its findings of
fact and recommend to the City Council approval of a Special Use Permit for
a vehicle tow facility and storage yard located at 110 Industrial Dr. per the site
plan received on 2-25-20 and labeled as Exhibit A and per the conditions listed
in Exhibit B.
Mr. Klein seconded the motion.
A roll call vote was taken. Mr. Becker – yes, Mr. Klein – yes, Mr. Wright – yes,
Ms. O’Flaherty – yes, Vice Chair Doe – yes. Motion was passed 5-0-2. Ms.
Buckley and Chair Maxwell were absent.
2. Public Hearing – Petition by 2411 Sycamore LLC for approval of a special use
permit for a drive-through restaurant with an outdoor seating area and approval
of a Final Plan for a proposed Raising Cane’s Chicken Fingers Restaurant to
be located at 2411 Sycamore Rd.
Jeff Gould, of ADA Architects, advised his client, 2411 Sycamore LLC, is
proposing the construction of a new Raising Canes Chicken Fingers restaurant
to be located at 2441 Sycamore Road. He advised plans to demolish the
current Applebee’s building and rebuild Raising Canes at the same location.
He advised the access points and parking lot will be similar to the current
Applebee’s site, with the addition of a two-lane drive through.
Mr. Gould advised the building will be approximately 3357 square feet and will
be able to seat 121 customers, with 26 of the seats being in the outdoor area.
He noted some of the current landscaping will be removed and replaced.
Mr. Gould noted the petitioner has requested a waiver to the current parking
requirements. He advised based off the current UDO regulations, 76 parking
spaces are required, and the petitioner is proposing 46 parking spaces. He
stated their waiver request is based off data collected from several other
Raising Canes sites that are similar to the proposed site in DeKalb. He advised
the DeKalb site will have more parking than any of the other nearby (Batavia
and Naperville) and comparable Raising Cane sites.
Mr. Gould advised the main entrance would be from the north and the drive-
through pick up area would be facing Sycamore Road. He noted the exterior
finish of the building would be typical of other Raising Cane’s buildings.
Principal Planner Dan Olson went through the staff report dates February 28,
2020. Mr. Olson advised Raising Cane’s Chicken Fingers is a fast-food
restaurant chain specializing in chicken fingers that is based out of Baton
Rouge, Louisiana. He noted the company has approximately 450 restaurants
in 27 states, with approximately 10 locations in the Chicago area.
Mr. Olson mentioned the Applebee’s on the site has been closed since June
2018 and has remained vacant. He stated this lot is in the Oakland Place
Planned Development, which requires a Final Plan to be approved by the
Commission and City Council prior to issuance of any building permit.
Mr. Olson noted there will be access points to the northeast, northwest, and
southwest portions of the site, but there will be some access restrictions due to
the drive-through. He advised the drive-through will have two lanes for ordering
and will narrow down to one lane at the pick-up window. He noted the UDO
requires five stacking spaces for drive-throughs and the proposed layout will
accommodate the required stacking without interfering with the non-drive
through traffic.
Mr. Olson stated there is a cross access agreement with the shopping center
to the west that allows for parking within the shopping center. He reiterated
the petitioner is requesting a waiver to the parking requirements. He advised
the applicant provided a traffic and parking analysis, which indicated the
parking demand at a comparable Raising Cane’s location in Oak Lawn
showed a peak demand of 26 parking spaces, even though the restaurant
had 41 spaces. He also noted parking data was also provided by the
petitioner for their Batavia and Naperville locations, which show there is
enough parking for the subject site.
Vice Chair Doe then invited attendees in the audience to speak. There were
none.
Vice Chair Doe gave the Commission members the opportunity to speak.
Mr. Becker questioned what the expected completion date for the project
would be. Jason Cooper, of 1001 Warrenville Road in Lisle, advised the intent
is to open the restaurant by the end of 2020.
Mr. Klein stated his concern for the amount of parking. He stated if half of the
121 potential seats were filled by customers, 46 parking spots wouldn’t be
enough. Mr. Cooper advised they studied peak lunch hours and evening
hours at several of their other locations in the Chicago area. He noted during
peak hours, only 26 parking spots were occupied. Mr. Cooper reiterated the
cross-parking agreement throughout the shopping center. Mr. Cooper noted
there would have to be approximately 20 vehicles stacked in the drive-
through before it effected parking on the site.
Mr. Klein questioned how many employees would be on site at peak hours.
Mr. Cooper advised the maximum would be 15, but on average it would be
closer to 8 employees.
Mr. Wright questioned if there was any use for the existing Applebee’s
building. Mr. Cooper advised Raising Canes prefers a clean slate with clean
facilities, a new building, and to have their brand on the building itself.
Vice Chair Doe questioned where the overflow would go if there were 20
vehicles stack in the drive-through. Mr. Cooper advised they conducted a
traffic study and the maximum queue was approximately 9 vehicles. Vice
Chair Doe also questioned what signage would be included in the plans to
prevent customers from accessing the parking lot from the wrong direction.
Mr. Cooper stated there will be two do not enter signs on each side of the
access point. He noted the parking lot will also be 28 ft wide on each side of
the building, giving more than enough room in case someone accidently
enters the lot from the wrong direction.
Vice Chair Doe questioned why they specifically chose this site for the project
and what the operating hours would be. Mr. Cooper stated he did not know
the exact reason for this site location, but the real estate team does intensive
studies and surveys before choosing a site. He also noted typical operating
hours would be 10:00AM to 11:00PM. Vice Chair Doe noted she would prefer
another wall sign on the south elevation so there is visibility of the restaurant
from traffic going north along Sycamore Road.
Vice Chair Doe gave the public one more opportunity to speak. There was
none.
Mr. Klein moved that the Planning and Zoning Commission forward its findings
of fact and recommend to the City Council approval of a Special Use Permit for
a drive-through and outdoor eating area and approval of a Final Plan for a
Raising Cane’s Chicken Fingers Restaurant to be located at 2411 Sycamore
Road, per the Final Plan dated 1-24-20 and Exterior Elevations dated 2-11-20
labeled as Exhibit A and per the conditions listed in Exhibit B being addressed
per City Staff’s satisfaction prior to final City Council action.
Mr. Wright Seconded the motion.
A roll call vote was taken. Mr. Becker – yes, Mr. Klein – yes, Mr. Wright – yes,
Ms. O’Flaherty – yes, Vice Chair Doe – yes. Motion was passed 5-0-2. Ms.
Buckley and Chair Maxwell were absent.
3. Public Hearing – Petition by the City of DeKalb for text amendments to Article
13 “Signs” and Article 18 “Appeals and Variances” of the Unified Development
Ordinance.
Mr. Olson advised a preliminary discussion with the Planning and Zoning
Commission regarding sign regulations occurred on December 5, 2018. He
stated the City Council had a follow-up discussion on March 25, 2019 during a
Committee of the Whole meeting. Mr. Olson advised the review of the City’s
sign code was prompted by the need to bring the codes in line with a Supreme
Court ruling (Reed v. Town of Gilbert, 2015) that held content-based sign
restrictions were unconstitutional. He added on February 10, 2020 the City
Council Committee of the Whole discussed the proposed amendments that are
included in the Commission’s packet. He said the Council agreed with the
proposed changes and there was a consensus to forward the amendments to
the Planning and Zoning Commission and conduct a public hearing.
Mr. Olson advised staff prepared the amendments based upon the Supreme
Court case, experiences administering DeKalb’s sign code, and reviewing
other communities’ ordinances. He noted the proposed amendments will make
the sign regulations easier to understand, promote economic development, and
become more business friendly while still ensuring public safety and
maintaining aesthetic standards.
Mr. Olson stated the amendments will make regulations content neutral, so
they are in line with the Supreme Court ruling. He advised it will also increase
the allowable wall signage size from one times the frontage of a building/tenant
space to one and a half times the frontage. He noted this will allow increased
visibility for businesses that may be substantially setback from a roadway.
Mr. Olson advised electronic changeable copy signs are currently prohibited,
except with the approval of a special use permit. He stated staff is proposing
electronic changeable copy signs be removed from the prohibited sign list and
allowed with a sign permit within all zoning districts except “CBD” Central
Business District and any residential zoning district with certain conditions
being met. He noted one of the conditions would include a display time
minimum on changing messages of no longer than 5 seconds. He advised staff
looked at other communities, which had minimum display times ranging from 2
to 10 seconds. Mr. Olson stated the amendment would also prevent electronic
changeable copy signs from taking up more than 50% of the sign or 40 square
feet, whichever is less. He noted there would be other operational standards
added to include limits on how messages can change, light intensity, and
advertising restrictions.
Mr. Olson mentioned the current temporary signs regulations require permits
from the City prior to display. He noted the maximum size allowed is 40 square
feet per sign and a limit of 14 days per permit, and six permits per year. He
stated staff is proposing temporary non-commercial ground or wall signs not
exceeding 16 feet in residentially zoned properties and 40 square feet in
commercial/industrial zoned properties be exempt from a sign permit as long
as they meet size, height and display standards. He advised these signs would
not be displayed for more than 90 days in a calendar year and be removed no
more than 7 days after the event they are advertising. Mr. Olson noted
temporary commercial signs would still require a permit and be restricted to
being located only on the property the business is located. He stated the
number of days the signs can be displayed will be increased from 84 to 90 days
and the restriction of requiring a new permit every 14 days would be removed.
Mr. Olson advised the amendment would also clarify the calculation of area for
signs, as make the window signage regulations consistent.
Mr. Olson noted staff is proposing variances for signs be allowed to be applied
for and would be reviewed under the current variance procedures in Article 18
of the UDO in lieu of a special use permit or planned development ordinance.
He stated in conjunction with this amendment, staff is proposing to add
language to Article 18 “Variances” by allowing applicants to vary sign height,
size, and location. He noted, per the UDO, a public hearing in front of the
Planning and Zoning Commission is required for any variance with final
determination laying with the Commission.
Vice Chair Doe then invited attendees in the audience to speak. There were
none.
Vice Chair Doe gave the Commission members the opportunity to speak.
Mrs. O’Flaherty had concerns with sign regulations that have been addressed
with the proposed amendments. She stated she appreciates the clarification
throughout the report and proposed amendments.
Mr. Becker stated he believes signs can be overwhelming and unsightly. He
noted, however, his appreciation for the consistency, clarity, and ease of
access the proposed amendments add.
Vice Chair Doe gave the public one more opportunity to speak. There was
none.
Mrs. O’Flaherty moved that the Planning and Zoning Commission recommend
to the City Council approval of amendments to Article 13 “Signs” and Article 18
“Appeals and Variances” of the Unified Development Ordinance per Exhibit A
in the staff report.
A roll call vote was taken. Mr. Becker – yes, Mr. Klein – yes, Mr. Wright – yes,
Ms. O’Flaherty – yes, Vice Chair Doe – yes. Motion was passed 5-0-2. Ms.
Buckley and Chair Maxwell were absent.
F. REPORTS
Mr. Olson advised the next Commission meeting on March 18, 2020 would be
cancelled, as no hearings have been scheduled. He noted Planning and Zoning
Commission meetings will continue to be held at City Hall at least through April.
He stated during the last City Council Meeting, the special use permit for the
Verizon antenna co-location at 1500 S 7th St was approved.
G. ADJOURNMENT
Ms. O’Flaherty motioned to adjourn, Mr. Wright seconded the motion, and the
motion was approved by unanimous voice vote. The Planning and Zoning
Commission adjourned at 7:23PM.
STAFF REPORT
April 3, 2020
TO: Planning and Zoning Commission
FROM: Dan Olson, Principal Planner
RE: Annexation, rezoning and conceptual site plan approval for approximately
505 acres of property generally located east of State Rt. 23 and south of
Gurler Road for a data center (Ventus Tech Services, LLC)
I. GENERAL INFORMATION
A. Purpose To accommodate a data center and
accessory uses in an approximately
970,000 sq. ft. facility with an option to
expand.
B. Owner/Applicant Ventus Tech Services, LLC
C. Location and Size East of Rt. 23, south of Gurler
Road/approximately 505 acres
D. Existing Zoning and Land Use “A-1” (unincorporated DeKalb County);
agriculture
E. Proposed Zoning and Land Use “PD-I”; data center and accessory uses
F. Surrounding Zoning and Land Use North– PD-I, PD-C and A1; food
distribution center – under
construction, agriculture
South – A-1 (unincorporated);
agriculture
East – A-1 (unincorporated);
agriculture
West – PD-R & A-1 (unincorporated);
agriculture and single-family
residential
G. Comprehensive Plan Designation Office/Research Park, Commercial &
Light Industrial
The legal notice for the April 8th Planning and Zoning Commission public hearing
referenced approval of a “Conceptual” Site Plan along with the rezoning of the site,
upon annexation, to the “PD-I” Planned Development Industrial District to
accommodate a proposed data center. Since the legal notice was published, the
applicant is completing more detailed plans which will be ready for the
Commission’s review on April 22. These plans will serve as the preliminary and
final development plans, which will more closely conform to the Unified
Development Ordinance’s reference to a Preliminary and Final Development Plan
and Subdivision Plat, typically approved with any Planned Development. A Plat of
Subdivision has been already submitted by the applicant and is provided in the
Commission’s packet.
The City wants to be precise and transparent and ensure all relevant plans and
plats were included in the notice, so staff is recommending the Planning and
Zoning Commission open and then continue the public hearing to the April 22nd
meeting. A new hearing notice was sent out to surrounding property owners on
April 3rd noting the new hearing date and the requested approval of a Preliminary
and Final Development Plan and Plat of Subdivision in conjunction with annexation
and rezoning of the site. On April 8th the Commission can open the hearing and
note it will be continued to April 22nd for the reasons noted. If anybody from the
public attends the hearing on April 8th, it is recommended the Commission take
their comments and questions and note the continuation of the hearing.
Staff is providing a report below that provides a background and analysis of the
plan and request, draft of the findings of fact and development standards.
I. BACKGROUND AND ANALYSIS
The petitioner, Ventus Tech Services, LLC, is requesting approval of the annexation and
rezoning of approximately 505 acres of property generally located east of State Rt. 23
and south of Gurler Road to accommodate a data center and accessory uses in an
approximately 970,000 sq. ft. facility with an option to expand. Ventus Tech Service is
representing the data center company and has been working with the City through the
pre-application process. The requested rezoning would change the zoning of the subject
site, after annexation, from the “SFR1” Single-Family Residential District to the “PD-I”
Planned Development Industrial District. The petitioner also seeks approval of a
Conceptual Site Plan, Landscape Plan, and Building Elevations which are part of the
petition, along with the approval of associated development standards for the subject site.
The applicant has indicated that more detailed plans will be provided in the next few
weeks that will qualify as the Preliminary and Final Development Plan. A Plat of
Subdivision has been submitted by the applicant and is provided in the Commission’s
packet.
Page 2 of 8
On March 9, 2020 the DeKalb City Council unanimously approved a Pre-Development
Agreement with Ventus Tech Services, LLC which established the City’s intent to
appropriately annex and rezone the subject site. The agreement also established the
intent to extend financial incentives including a property tax abatement program through
the DeKalb County Enterprise Zone program that is tied to job creation and retention
goals, minimum square footage goals, and project wage levels. To accommodate the
incentives, the City Council approved an extension to the DeKalb County Enterprise Zone
map on January 13, 2020 to include the subject property, and included new property tax
incentives for high impact knowledge-based companies or data centers with a minimum
of $800 million of investment and a minimum of 900,000 square feet of development area.
On April 2, 2020 the DeKalb County Enterprise Zone approved a Memorandum of
Understanding (MOU) to deliver these benefits to Ventus Tech Services, LLC. within the
reciprocal obligations defined by the Enterprise Zone program.
The petitioner is proposing an initial investment of more than $800 million to construct an
approximately 970,000 square foot date center facility, with the option to expand
thereafter in additional phases. The skilled workforce will consist of high wage technology
professionals and would include about 50 initial jobs with an average starting wage of
$38.50 an hour. The proposed rezoning request and plan approval will allow the
development of a data center that will generate new business opportunities and support
existing commerce in the surrounding area, while spurring increased property values and
other development opportunities. Over the next 20 years the proposed data center is
projected to yield tax revenue for the participating taxing bodies (even with the tax
abatements) that is comparable to the five largest existing industrial companies in the
City, combined.
Conceptual Site Plan/Plat of Subdivision and Development Standards
The Overall Site Plan sheet shows an approximate 970,000 sq. ft. data center building on
the far eastern portion of the site and an electrical substation to the southwest of the
building. The main access to the site will be provided by Peace Road, which will be extend
into the site and security controlled. Access will also be provided along Gurler Road, at
Crego Road (gated and controlled) and other possible locations along Gurler as the site
is built out. Crego Road is currently under the jurisdiction of Afton Township and the right-
of-way will be vacated as a public roadway from Gurler Road to the southern boundary
of the site and made into a private road for the data center. Access to the data center
from Crego Road at the southern end of the property will be through a gate also. Public
access will not be allowed at this location, with a proposed cul-de-sac providing an
adequate turnaround.
The building footprint shown for the approximate 970,000 sq. ft. data center building is
general and will also include parking for the facility and landscape areas. A mechanical
yard is proposed around two sides of the building. Internal private drives will connect the
data center building with the three proposed access points and the proposed substation,
which will be partially owned by the data center and ComEd. Security fencing will surround
the site. Sample building elevations were provided indicating precast concrete wall panels
Page 3 of 8
on the lower half of the building and metal wall panels on the upper half. The final
architectural plans will indicate the amount of precast concrete wall panels and metal wall
panels. The majority of the building will be 54 feet in height and just under 57 feet at the
highest point. The maximum height in the “LI” Light Industrial and “HI” Heavy Industrial
Districts is 75 feet.
The landscape details sheet show landscaping around the perimeter of the initial phase
of the development that is intended to meet the UDO requirements. The plan also has
landscaping along the Rt 23 that exceeds the UDO requirements by 30 trees and will
include a berm to match what is proposed for the Chicago West Business Center to the
north. The plantings and berm along the Rt. 23 frontage will be installed in a future phase
of the project when development of the site moves to the west.
The proposed conceptual site plan, building elevations and landscape plan for the subject
site are in compliance with UDO standards and the recommended draft development
standards at the end of the report. The standards were based upon the regulations in the
“LI” and “HI” Districts and the standards for the Chicago West Business Center (Ferrara
Site) to the north.
A Plat of Subdivision has been submitted indicating the creation of one lot for the entire
site. The Plat also includes the dedication of 50 feet of right-of-way along Gurler Road for
roadway improvements and the establishment of a 20-foot easement along Rt. 23 for the
Kishwaukee Water Reclamation District to extend a future sanitary sewer.
Roadway Improvements
Several roadway improvements are planned for the project and in conjunction with the
Ferrara Candy Company development across Gurler Road. The existing T-intersection of
Peace Road and Gurler Road will be reconstructed and made into a roundabout. Gurler
Road will be upgraded to a three-lane section, similar to Fairview Drive, capable of
accommodating year-round truck traffic. Intersection traffic control improvements are
necessary at both ends of Gurler Road adjacent to the project site. State Rt. 23 and
Gurler Road will receive a signalized intersection with appropriate turns lanes to
accommodate demand with State Rt. 23 through traffic remaining the dominant
movement. The proposed roundabout at Peace Road and Gurler Road will accommodate
free-flowing traffic to avoid delays from conflicting dominant movements from both Project
Ventus and the Ferrara sites as those trips enter/exit the I-88 interchange.
Although Crego Road is planned to be vacated between Gurler Road and the southern
limits of the subject site with the proposed development, there are plans to construct a
new north-south roadway just to the east of the site between Gurler Road and Keslinger
Road. The City will be using monies dedicated by State Representatives Tom Demmer
and Jeff Keicher from the State's 2019 Capital Projects Fund of $500,000 to help pay for
the new one-mile roadway which will include a 66-foot-wide right-of-way and two 12-foot
driving lanes. This new roadway will allow for a new means of access from Peace Road
and Gurler Road to areas south of the subject site. (see attached map).
Page 4 of 8
Utilities/Stormwater Drainage
The existing overhead electrical line along the east side of the site is 138kv will serve the
initial building and a 34 kv line further west will service future facilities. An electrical
substation will be construed to the southwest of the initial building and owned by the data
center company and ComEd.
A 16" watermain will be looped to the south side of Gurler Road between stubs under I-
88 at State Rt. 23 and Crego Road (near the DeKalb Oasis). Additionally, the stub on
Gurler Road near Corporate Drive will be drawn east to tie into the loop as well. The loop
will have an eastern extension which will terminate just east of Peace Road serving as
the final connection point for the Ventus site. Two 12” water meter connections are
proposed to extend into the subject site in the initial phase. A separate water agreement
will be provided that will ensure that adequate and reliable water will be provided to the
site.
The Kishwaukee Water Reclamation District has been working with the developer, Jerry
Krusinski, on the sanitary sewer layout which will serve the Ferrara and Ventus sites. The
sanitary sewer will be extended from a point near Harvester Dr. and Rt. 23, down the east
side of Rt. 23 and then east along the north side of Gurler Road to the site at Crego Road.
Four stormwater retention ponds are initially proposed on the site and will accommodate
the initial phase of development. Its anticipated that site development and mass grading
would commence in the next few months, once the project is approved by the City.
III. FINDINGS OF FACT - REZONING
1. The proposed rezoning conforms to the Comprehensive Plan, or conditions
have changed to warrant the need for different types of land uses in that area. The
proposed rezoning is appropriate considering the length of time the property has
been vacant, as originally zoned, and taking into account the surrounding areas
trend in development.
The 2005 Comprehensive Plan recommends Office/Research, Light Industrial and
Commercial uses for the subject site. An approximately 1,222,400 sq. ft. food distribution
center is under construction just to the north of the subject site along Gurler Road and will
also include a future 466,560 sq. ft. packaging center. Additional acreage for future
manufacturing, distribution, office/research and technology uses are available in the
areas to the north of the site. The rezoning of the subject site to the “PD-I” Planned
Development – Industrial District and the approval of a data center meets the intent of the
City’s Comprehensive Plan and is compatible with the trend of development in the area.
2. The proposed rezoning conforms to the intent and purpose of the Unified
Development Ordinance.
Re-zoning of the subject site to the “PD-I” Planned Development District and the
Page 5 of 8
development of a data center will allow the project to comply with the regulations of the
UDO and per the development standards made part of the annexation and development
agreement. The PD-I” zoning classification, as provided under the City’s Unified
Development Ordinance, is the most appropriate zoning classification for the subject site
and provides the opportunity for the City to more directly shape the development, use and
appearance of the subject property. In addition, the Planned Development zoning allows
the applicant flexibility in integrating public capital facilities, construction schedules and
phasing of the development.
3. The proposed rezoning will not have a significantly detrimental effect on the
long-range development of adjacent properties or adjacent land uses.
The property to the north of the site along Gurler Road, between Rt. 23 and Crego Road
is being developed with an approximately 1,222,400 sq. ft. food distribution center and
future 466,560 sq. ft. packaging center. Areas to the east, south and west are agricultural
uses with some single-family homes to the west of the site along Rt. 23. The proposed
zoning and data center are consistent with and compatible with the surrounding area and
the City’s Comprehensive Plan. The proposed rezoning to “PD-I” Planned Development
Industrial District and the development of a data center will not have a detrimental effect
on the adjacent properties or land uses. In fact, the extension of utilities and upgrading of
roadways will appreciably increase the value of adjacent farm parcels for future
development.
Although Crego Road is planned to be vacated between Gurler Road and the southern
limits of the subject site with the proposed development, there are plans to construct a
new north-south roadway just to the east of the site between Gurler Road and Keslinger
Road. The City will be using monies from the State's 2019 Capital Projects Fund of
$500,000 to help pay for the new one-mile roadway which will include a 66-foot-wide right-
of-way and two 12-foot driving lanes. This new roadway will allow for a new means of
access from Peace Road and Gurler Road to areas south of the subject site.
4. The proposed rezoning constitutes an expansion of an existing zoning district
that, due to the lack of undeveloped land, can no longer meet the demand for the
intended land uses.
The subject property is proposed for “PD-I” Planned Development – Industrial zoning.
The “PD-I” district designation and development of a data center will allow the site will be
compatible with the surrounding area. In addition, the data center will allow for the
continuation of an area with high quality development under the “PD-I” classification and
which is consistent with the Comprehensive Plan recommendations.
5. Adequate public facilities and services exist or can be provided.
Gurler Road, Rt. 23 and Peace Road will be improved to accommodate the proposed
development and provide for efficient means of access for the data center. Sanitary sewer
and watermain will be extended to the site along the north side of Gurler Road in
Page 6 of 8
conjunction with the development of the Ferrara Candy Company site to the north and
will provide connections to the subject property. A separate water agreement will be
provided that will ensure that adequate and reliable water will be provided to the site.
Stormwater management will be provided on the subject property per the requirements
of the Unified Development Ordinance. Electrical power is readily available and more than
adequate to provide the needs for the proposed data center.
V. Citizen Comments
The City has received correspondence from Joseph Gormley who represents 240 acres
of property just south of the subject site (see attached map). Mr. Gormley had concerns
about future access to the property, the vacation of Crego Road and the value of the
property. After discussions, it has been agreed that a future north-south roadway will be
located just to the east of the site between Gurler Road and Keslinger Road (see attached
map). The City will be using monies from the State's 2019 Capital Projects Fund of
$500,000 to help pay for the new one-mile roadway which will include a 66-foot-wide right-
of-way and two 12-foot driving lanes. This new roadway will allow for a new means of
access from Peace Road and Gurler Road to areas south of the subject site. The
proposed location of the new road is acceptable to Mr. Gormley.
VI. CONCLUSIONS AND RECOMMENDATION
As noted at the beginning of the report, the staff wants to make sure all relevant plans
and plats were included in the public hearing notice, so staff is recommending the
Planning and Zoning Commission continue the public hearing to the April 22nd meeting.
A sample motion is provided below.
Sample Motion:
I move that the Planning and Zoning Commission continue the public hearing for Ventus
Tech Services, LLC to Wednesday, April 22, 2020 at 6:00 PM in the City Council
Chambers in the DeKalb Municipal Building located at 200 S. 4th St., DeKalb, IL.
Page 7 of 8
Draft Development Standards
Amendments, Standards and Conditions
Permitted Uses: Data center and accessory uses. A data center is defined as buildings
or structures specifically designed or modified to house networked computers and data
and transaction processing equipment and related infrastructure support equipment,
including, without limitation, power and cooling equipment, used primarily to provide, as
a service to persons other than the company operating the data center, data and
transaction processing services, outsource information technology services and
computer equipment colocation services, or, used primarily to provide, to a single user,
including the user's affiliates, customers, lessees, vendors and other persons authorized
by the user, data and transaction processing services, along with ancillary warehouse,
administrative office, and storage buildings.
Minimum Building Setbacks:
Rt. 23 – 150’
Gurler Road - 100’
East and South Property Lines – 150’
Minimum Parking/Paving Setbacks (except points of access and turnarounds):
Rt. 23 – 100’
Gurler Road – 50’
East and South Property Lines – 50’
Maximum Site Coverage (area covered by buildings, paving): None
Maximum Building Height: 75’
Landscaping: Per the Unified Development Ordinance and City Manager’s approval.
Lighting: Per the Unified Development Ordinance.
Parking: Per the Unified Development Ordinance. Parking formula (number of spaces
required) shall be determined in consultation with the Owner and City Staff based upon
the owner’s needs and parking demand at a similar facility.
Page 8 of 8
LEGEND:
PROPERTY LINE
200 Clinton Avenue // Suite 800 // Huntsville, Alabama 35801
POTENTIAL WATER FEATURE
EXISTING OVERHEAD POWER
DEKALB OASIS RONALD REAGAN MEMORIAL TOLLWAY/I-88
TRAVEL PLAZA PROPOSED WATER LINE
PHONE (256) 533-1561 // FAX (256) 533-1564
PROPOSED SANITARY LINE
MECHANICAL YARD
PROPOSED DRIVEWAY
NOTE:
NET AREA OF TRACT: ±504 acres
PURPOSES ONLY
EXHIBIT FOR
ZONING: A-1
DILIGENCE
OFF-STREET PARKING PROVIDED: 220 Spaces
CREGO RD PEACE RD
PROPOSED 12" WATER METER CONNECTION PROPOSED ACCESS POINT
PROPOSED ACCESS POINT
PROPOSED 12" WATER
METER CONNECTION
GURLER RD PROPOSED 12" SANITARY CONNECTION
SD SD SD SD SD SD SD SD SD SD
SD
PROPOSED
SD RETENTION POND
EXISTING OVERHEAD ELECTRIC PROPOSED
OVERALL SITE PLAN
RETENTION POND
PROJECT VENTUS
DEKALB, ILLINOIS 60115
SD
SD
EXISTING OVERHEAD ELECTRIC
PROPOSED BUILDING
±971,282 SF
SD
SD
SAMPLE EW SITE CROSS SECTION
SEE SHEET C1.02
PROPOSED SD SD
SUBSTATION
PROPOSED
RETENTION POND
SD
S 4TH ST/SR 23
SD PROPOSED
SD SD SD SD SD SD SD SD RETENTION POND
PROPOSED ACCESS POINT
SAMPLED NS SITE CROSS SECTION
SEE SHEET C1.02
FILE:S:\37\37144\3714401\04_CAD\CIVL\Exhibit\PD Submittal\Exhibits\PDS_Site Plan_rev1.dwg
CREGO RD
REVISION INFORMATION
DATE DESCRIPTION
CHK.
DR.
REV.
400' 200' 0' 400' 800'
SCALE: 1 INCH = 400 FEET
C1.01
3/27/2020 FILE NO. 37144-01
Copyright 2019, Barge Design Solutions, Inc. ALL RIGHTS RESERVED
FILE:S:\37\37144\3714401\04_CAD\CIVL\Exhibit\PD Submittal\Exhibits\PDS_ELEVATIONS_mwf.dwg
SCALE: N.T.S. SCALE: N.T.S. SCALE: N.T.S.
SCALE: N.T.S. SCALE: N.T.S.
SEE A1.02 ELEVATIONS
SEE A1.02 ELEVATIONS SEE A1.02 ELEVATIONS
3/27/2020
REVISION INFORMATION
REV. DR. CHK. DATE DESCRIPTION
SAMPLE BUILDING ELEVATIONS
EXHIBIT FOR
FILE NO.
DILIGENCE
PURPOSES ONLY
37144-01
A1.01 PROJECT VENTUS 200 Clinton Avenue // Suite 800 // Huntsville, Alabama 35801
DEKALB, ILLINOIS 60115 PHONE (256) 533-1561 // FAX (256) 533-1564
Copyright 2019, Barge Design Solutions, Inc. ALL RIGHTS RESERVED
FILE:S:\37\37144\3714401\04_CAD\CIVL\Exhibit\PD Submittal\Exhibits\PDS_ELEVATIONS_mwf.dwg
SCALE: N.T.S.
SCALE: N.T.S. SCALE: N.T.S.
SCALE: N.T.S. SCALE: N.T.S.
SCALE: N.T.S.
SEE A1.02
A1.01
3/27/2020
REVISION INFORMATION
REV. DR. CHK. DATE DESCRIPTION
SAMPLE BUILDING ELEVATIONS
EXHIBIT FOR
FILE NO.
DILIGENCE
PURPOSES ONLY
37144-01
A1.02 PROJECT VENTUS 200 Clinton Avenue // Suite 800 // Huntsville, Alabama 35801
DEKALB, ILLINOIS 60115 PHONE (256) 533-1561 // FAX (256) 533-1564
Copyright 2019, Barge Design Solutions, Inc. ALL RIGHTS RESERVED
SYMBOL LEGEND
CONCEPTUAL PLANT SCHEDULE
# KEY BOTANICAL NAME COMMON NAME
200 Clinton Avenue // Suite 800 // Huntsville, Alabama 35801
PINE OAK
234 AL Tilia americana American Linden
101 BS Picea mariana Black Spruce
133 BW Juglans nigra Black Walnut
27 GB Betula populifolia Gray Birch
97 HT Crataegus Hawthorn
BLACK WALNUT 102 PO Quercus palustris Pin Oak
89 YB Betula alleghaniensis Yellow Birch
PHONE (256) 533-1561 // FAX (256) 533-1564
783
YELLOW BIRCH
HAWTHORN
AMERICAN LINDEN
BLACK SPRUCE EXHIBIT FOR
DILIGENCE
PURPOSES ONLY
LANDSCAPE DETAILS PROJECT VENTUS
DEKALB, ILLINOIS 60115
LOCAL GRID
REVISION INFORMATION
TRANSFORMATION
IL STATE PLAN IL83-EF
DATE DESCRIPTION
CHK.
DR.
REV.
3/27/2020 A1.05
FILE NO. 37144-01
C Copyright 2019, Barge Design Solutions, Inc. ALL RIGHTS RESERVED
FILE:S:\37\37144\3714401\04_CAD\CIVL\Exhibit\PD Submittal\Exhibits\PDS_ELEVATIONS.dwg
REVISION INFORMATION
REV. DR. CHK. DATE DESCRIPTION
ARCHITECTURAL PERSPECTIVES
EXHIBIT FOR
FILE NO.
DILIGENCE
PURPOSES ONLY
37144-01
A1.03 PROJECT VENTUS 200 Clinton Avenue // Suite 800 // Huntsville, Alabama 35801
DEKALB, ILLINOIS 60115 PHONE (256) 533-1561 // FAX (256) 533-1564
Copyright 2019, Barge Design Solutions, Inc. ALL RIGHTS RESERVED
COMMUNITY DEVELOPMENT DEPARTMENT
STAFF REPORT
April 3, 2020
TO: DeKalb Planning and Zoning Commission
FROM: Dan Olson, Principal Planner
RE: Amendments to Ordinance 2019-004 to modify setbacks and other provisions and
to approve a Final Plat of Resubdivision for the Northland Plaza Shopping Center
– Sycamore Road (B33 Northland Plaza, LLC)
I. GENERAL INFORMATION
A. Purpose Create separate lots around the existing five
smaller outbuildings within the shopping center
B. Location/Size NE Quadrant of Sycamore Road and Barber
Greene Road – Northland Plaza Shopping Center
/approx. 38 acres
C. Petitioner B33 Northland Plaza, LLC
D. Existing Zoning “PD-C” Planned Development Commercial
E. Existing Land Use Commercial
F. Proposed Land Use Commercial
G. Surrounding Zoning and Land Use North: Unincorporated; Agriculture
South: PD-C; Various Commercial Uses
East: Unincorporated; Agriculture
West: GC & PD-C; Various Commercial Uses
H. Comprehensive Plan Designation Commercial
II. BACKGROUND AND ANALYSIS
The applicant, B33 Northland Plaza, LLC, is requesting approval of a resubdivision the Northland
Plaza Shopping Center in order to create separate lots around the existing five smaller buildings
within the shopping center. There is no construction planned or new tenants proposed with this
petition. The intent of the resubdivision is to help retain and attract quality tenants. The applicant
believes that proposed resubdivision will facilitate better organization of the property through the
separation of the lots and allow businesses to own their own buildings and lot. The reason that
Planet Fitness located in the shopping center in 2019 was their ability to own (rather than rent)
their lot.
There will be a total of eight (8) lots and include the existing Planet Fitness lot and a lot for the
stormwater detention pond (Lot 5). The original subdivision for the property was approved in 1965
and the First Resubdivision was approved in 2003. The Northland Plaza Resubdivision No. 2 was
approved in 2019 when Planet Fitness located in the shopping center and created a separate lot for
their tenant space and part of the parking lot. Up until the plat for Planet Fitness was approved, the
entire shopping center was covered by one lot, except for the stormwater detention pond along
Sycamore Road. The proposed resubdivision does include the lot created with the resubdivision
plat approved for Planet Fitness in 2019. The lot boundaries will remain for that lot; however, the
lot number will change. The applicant’s petition also includes amending the Ordinance approved
in 2019 (#2019-004) by waiving certain provisions of the UDO to accommodate the proposed
resubdivision.
The proposed amendments to Ordinance 2019-004 include the following:
Amending Article 5.08 “GC-General Commercial District” regarding building setbacks and
maximum site coverage. By creating lots around the five existing outbuildings, some building
setbacks will not be able to be met and will create non-conforming lots. The applicant is proposing
the building setbacks and maximum site coverage restrictions be waived to accommodate the Plat.
The proposal is to waive any interior building setbacks, however maintaining the building setbacks
along Sycamore Road and Barber Green Road that were established by the previous subdivision
plats. Those setbacks include a 135-foot building setback from the centerline of Sycamore Road
and a 25-foot building setback from the Barber Green Road right-of-way. The maximum site
coverage (impervious site coverage) in the existing Planned Development Ordinance is 90%. With
the establishment of lots around each of the outbuildings, a few lots may exceed the 90%
maximum. It’s recommended the 90% maximum for individual lots be waived, however the
maximum site coverage (impervious site coverage) for the entire subdivision should remain at
90%.
Article 9 “Streets, Sidewalks and Subdivision Design” regarding lots having to front on a public
street With the proposed Lot 2 (Planet Fitness) and Lot 7 (Buffalo Wild Wings/Kay Jewelers) not
fronting on a public street, a waiver to this UDO requirement is requested.
Page 2 of 4
Article 10 “Utilities” to permit existing utility connections The subdivision regulations in the UDO
require utility connections to newly created lots. Since the proposed lots already have buildings
located on them with utility connections, a waiver is needed for this requirement.
Article 12 “Off-Street Parking, Loading and Storage Requirements” regarding parking setbacks.
As with the building setbacks, the creation of lots around the five outbuildings results in some
parking setbacks that will be violated. The minimum parking setback in the UDO is 10 feet for
lots along a public roadway and 5 feet for interior lots. Maintaining a 10-foot parking setback from
the right-of-way of Sycamore Road and Barber Green Road is recommended. It should be noted
the Declaration of Easements, Covenants and Restrictions for the shopping center has provisions
for cross parking and access easements for all the lots. The Covenants also have provisions for the
maintenance of the common areas by the owner, B33 Northland Plaza, LLC, that will ensure the
private drives and parking areas are properly maintained.
III. RECOMMENDATION
Sample Motion:
Based upon the submitted petition and testimony presented, I move the Planning and Zoning
Commission recommend to the City Council approval of amendments to Ordinance 2019-004
and to waive provisions of the Unified Development Ordinance and approval of the Final Plat of
Northland Plaza Third Resubdivision dated 4-2-20 located along Sycamore Road subject to the
amendments, waivers and conditions as indicated on Exhibit A.
Page 3 of 4
Exhibit A
1. The following items shall be addressed on the Final Plat prior to recording:
a) Include all the existing easements and setbacks as shown on the Final P.U.D. and Plat
of Resubdivision of Northland Plaza Resubdivision recorded as Document No.
2003008143 including the 10-foot building setback along the City right-of-way along
the south side of the site.
2. Approval of amendments to Ordinance 2019-004 as follows:
a) Article 5.08 “GC-General Commercial District” regarding building setbacks and
maximum site coverage by waiving any interior building setbacks, however
maintaining the building setbacks along Sycamore Road and Barber Green Road that
were established by the previous subdivision plats. Waive the 90% maximum site
coverage (impervious site coverage) for individual lots, however, maintain the 90%
maximum site coverage (impervious site coverage) for the entire subdivision.
b) Waiver to Article 9 “Streets, Sidewalks and Subdivision Design” regarding lots
having to front on a public street.
c) Waiver to Article 10 “Utilities” to permit the existing utility connections for the
proposed lots in the resubdivision.
d) Article 12 “Off-Street Parking, Loading and Storage Requirements” regarding parking
setbacks to waive any interior parking setbacks, however maintaining the parking
setbacks along Sycamore Road and Barber Green Road that were established by the
previous subdivision plats or as required by the UDO.
Page 4 of 4
PARCEL 1
PPAAR
RCCEELL 12
SURVEY PREPARED FOR:
Bridge33 Capital
4001 S. Decatur Blvd., Suite 6
Las Vegas, NV 89103
PHONE: 702.463.4603
T:\FINISHED PROJECTS\2019_PROJECTS\19-821-100\dwg\19-821-100.dwg, 4/2/2020 1:25:49 PM,
UTILITY EASEMENT PROVISIONS
CITY COUNCIL CERTIFICATE
ALL EASEMENTS FOR SERVING THE SUBDIVISION AND OTHER PROPERTY
STATE OF ILLINOIS)
INDICATED AS EASEMENTS, UTILITY EASEMENTS OR COMBINED DRAINAGE AND
) S.S.
UTILITY EASEMENTS ON THIS PLAT ARE HEREBY RESERVED FOR, AND GRANTED TO
COUNTY OF DEKALB )
THE CITY OF DEKALB, COUNTY OF DEKALB, AND TO UTILITY COMPANIES INCLUDING,
BUT NOT LIMITED TO; ILLINOIS BELL TELEPHONE COMPANY, NORTHERN ILLINOIS
GAS COMPANY, COMMONWEALTH EDISON COMPANY, AND THEIR RESPECTIVE
THIS IS TO CERTIFY THAT THE ATTACHED PLAT WAS APPROVED BY THE MAYOR AND CITY
SUCCESSORS AND ASSIGNS JOINTLY AND SEVERALLY, TO INSTALL, OPERATE,
COUNCIL OF THE CITY OF DEKALB, ILLINOIS
MAINTAIN, RENEW, RELOCATE AND REMOVE, FROM TIME TO TIME, FACILITIES USED
IN CONNECTION WITH OVERHEAD AND UNDERGROUND TRANSMISSION AND
ON THIS ___ DAY OF ______________________________, 2020.
DISTRIBUTION OF GAS, WATER, ELECTRICITY AND SOUNDS AND SIGNALS,
TOGETHER WITH STORMWATER, SANITARY SEWER AND ANY OTHER FACILITIES
USED IN THE TRANSMISSION, DISTRIBUTION OR TRANSPORTATION OF ANY
_______________________________________ ____________________________________
COMMODITY IN A LIQUID OR GASEOUS STATE IN, OVER, UNDER, ACROSS, ALONG
MAYOR (SIGNATURE) PRINT NAME
AND UPON THE SURFACE OF THE PROPERTY SHOWN WITHIN DOTTED LINES ON
THE PLAT MARKED EASEMENT, AND THE PROPERTY DESIGNATED ON THE PLAT
FOR STREETS AND ALLEYS, TOGETHER WITH THE RIGHT TO INSTALL REQUIRED
_______________________________________________________ __________________________________________________ SERVICE CONNECTIONS OVER OR UNDER THE SURFACE OF EACH LOT TO SERVE
CITY CLERK (SIGNATURE) PRINT NAME IMPROVEMENTS THEREON, OR ON ADJACENT LOTS, THE RIGHT TO CUT, TRIM OR
REMOVE TREES, BUSHES AND ROOTS AS MAY BE REASONABLY REQUIRED
INCIDENT TO THE RIGHTS HEREIN GIVEN, AND THE RIGHT TO ENTER UPON THE
SUBDIVIDED PROPERTY FOR ALL SUCH PURPOSES. OBSTRUCTIONS SHALL NOT BE
PLACED OVER GRANTEE'S FACILITIES OR IN, UPON OR OVER THE PROPERTY
WITHIN THE DOTTED LINES MARKED EASEMENT WITHOUT THE PRIOR WRITTEN
CONSENT OF GRANTEES. AFTER INSTALLATION OF ANY SUCH FACILITIES, THE
GRADE OF THE SUBDIVIDED PROPERTY SHALL NOT BE ALTERED IN A MANNER SO
AS TO INTERFERE WITH THE PROPER OPERATION AND MAINTENANCE THEREOF.
PLANNING AND ZONING COMMISSION CERTIFICATE
STATE OF ILLINOIS)
) S.S.
COUNTY OF DEKALB ) CROSS ACCESS EASEMENT PROVISIONS
THIS IS TO CERTIFY THAT THE ATTACHED PLAT WAS APPROVED BY THE PLANNING AND ZONING
COMMISSION OF THE CITY OF DEKALB, ILLINOIS
ON THIS ___ DAY OF ____________________________, 2020.
_______________________________________ __________________________________
CHAIRMAN (SIGNATURE) CHAIRMAN (PRINT NAME)
PARKING EASEMENT PROVISIONS
SURVEYOR'S CERTIFICATE
STATE OF ILLINOIS )
) SS
COUNTY OF WILL )
THIS IS TO CERTIFY THAT I, JAMES L. HARPOLE, AN ILLINOIS REGISTERED LAND
SURVEYOR, HAVE SURVEYED THE FOLLOWING DESCRIBED PROPERTY:
OWNER'S CERTIFICATE OWNER'S CERTIFICATE
STATE OF ILLINOIS ) STATE OF ILLINOIS )
) SS ) SS
COUNTY OF _________ ) COUNTY OF _________ )
THIS IS TO CERTIFY THAT THE UNDERSIGNED, DKIL6, LLC, IS THE LEGAL OWNER OF THIS IS TO CERTIFY THAT THE UNDERSIGNED, 833 NORTHLAND PLAZA, LLC, IS THE
LOT 2 OF THE LAND DESCRIBED ON THE ATTACHED PLAT, AND HAS CAUSED THE LEGAL OWNER OF LOT 1 AND LOTS 3 THROUGH 8 OF THE LAND DESCRIBED ON THE
SAME TO BE SURVEYED AND SUBDIVIDED AS INDICATED THEREON FOR THE USES ATTACHED PLAT, AND HAS CAUSED THE SAME TO BE SURVEYED AND SUBDIVIDED
AND PURPOSES THEREIN SET FORTH. AS INDICATED THEREON FOR THE USES AND PURPOSES THEREIN SET FORTH.
DATED AT ______________, ILLINOIS, THIS ______ DAY OF _____________, A.D., 2020. DATED AT ______________, ILLINOIS, THIS ______ DAY OF _____________, A.D., 2020.
CITY DATE MONTH CITY DATE MONTH
BY: ____________________________ TITLE: ___________________________ BY: ____________________________ TITLE: ___________________________
SIGNATURE PRINT TITLE SIGNATURE PRINT TITLE
ATTEST: __________________________ TITLE:__________________________ ATTEST: __________________________ TITLE:__________________________
SIGNATURE PRINT TITLE SIGNATURE PRINT TITLE
NOTARY'S CERTIFICATE NOTARY'S CERTIFICATE
STATE OF ____________ ) STATE OF ____________ )
) SS ) SS
COUNTY OF ___________ ) COUNTY OF ___________ )
I, _____________________________, A NOTARY PUBLIC IN AND FOR THE SAID COUNTY I, _____________________________, A NOTARY PUBLIC IN AND FOR THE SAID COUNTY
PRINT NAME PRINT NAME
IN THE STATE AFORESAID, DO HEREBY CERTIFY THAT __________________________, IN THE STATE AFORESAID, DO HEREBY CERTIFY THAT __________________________,
PRINT NAME PRINT NAME
_________________, AND _________________________________, _________________, _________________, AND _________________________________, _________________,
TITLE PRINT NAME TITLE TITLE PRINT NAME TITLE I FURTHER CERTIFY THAT BASED UPON AN EXAMINATION OF THE FEDERAL
EMERGENCY MANAGEMENT AGENCY (F.E.M.A.) FLOOD INSURANCE RATE MAP
OF SAID OWNER, WHO ARE PERSONALLY KNOWN TO ME TO BE THE SAME PERSONS OF SAID OWNER, WHO ARE PERSONALLY KNOWN TO ME TO BE THE SAME PERSONS
COMMUNITY-PANEL NO. 17037C0253E SHOWS THAT THE PROPERTY SURVEYED
WHOSE NAMES ARE SUBSCRIBED TO THE FORGOING INSTRUMENT AS SUCH WHOSE NAMES ARE SUBSCRIBED TO THE FORGOING INSTRUMENT AS SUCH
HEREON IS NOT SUBJECT TO FLOOD RISK AND THAT SAID PROPERTY FALLS WITHIN
___________________ AND _____________________ RESPECTFULLY, APPEARED ___________________ AND _____________________ RESPECTFULLY, APPEARED ZONE X.
TITLE TITLE TITLE TITLE
I FURTHER CERTIFY THAT IRON PIPE SURVEY STAKES OR THE CONCRETE
BEFORE ME THIS DAY IN PERSON AND JOINTLY AND SEVERALLY ACKNOWLEDGED BEFORE ME THIS DAY IN PERSON AND JOINTLY AND SEVERALLY ACKNOWLEDGED MONUMENTS AS SHOWN ON THE PLAT HEREON DRAWN, HAVE BEEN ESTABLISHED
THAT THEY SIGNED AND DELIVERED THE SAID INSTRUMENT AS THEIR OWN FREE THAT THEY SIGNED AND DELIVERED THE SAID INSTRUMENT AS THEIR OWN FREE AT THE LOT CORNERS.
AND VOLUNTARY ACT AND AS THE FREE AND VOLUNTARY ACT OF SAID OWNER FOR AND VOLUNTARY ACT AND AS THE FREE AND VOLUNTARY ACT OF SAID OWNER FOR
THE USES AND PURPOSES THEREIN SET FORTH. THE USES AND PURPOSES THEREIN SET FORTH.
DATED AT SHOREWOOD, ILLINOIS, THIS ______ OF _______________________, 2020.
GIVEN UNDER MY HAND AND NOTARIAL SEAL GIVEN UNDER MY HAND AND NOTARIAL SEAL
THIS ________ DAY OF _____________, A.D., 2020. THIS ________ DAY OF _____________, A.D., 2020.
DATE MONTH DATE MONTH
_________________________________________ _________________________________________
NOTARY PUBLIC SIGNATURE NOTARY PUBLIC SIGNATURE ______________________________________________________
SURVEYOR SIGNATURE
_________________________________________ _________________________________________
PRINT NAME PRINT NAME
JAMES L. HARPOLE
MY COMMISSION EXPIRES ON _____________________ _________, A.D., 2020. MY COMMISSION EXPIRES ON _____________________ _________, A.D., 2020. ILLINOIS PROFESSIONAL LAND SURVEYOR # 3190
MONTH DATE MONTH DATE REGISTRATION / EXPIRATION RENEWAL DATE NOVEMBER 30, A.D., 2020.
T:\FINISHED PROJECTS\2019_PROJECTS\19-821-100\dwg\19-821-100.dwg, 4/2/2020 1:25:49 PM,
T:\FINISHED PROJECTS\2019_PROJECTS\19-821-100\dwg\19-821-100.dwg, 4/2/2020 1:25:51 PM,
PARCEL 1
PPAAR
RCCEELL 12
LEGAL NOTICE
NOTICE is hereby given that a public hearing will be held before the DeKalb Planning and Zoning
Commission at its regular meeting on Wednesday, April 8, 2020, at 6:00 p.m. in the DeKalb
Municipal Building, 200 South Fourth Street, DeKalb, Illinois, on the petition by B33 Northland
Plaza, LLC for approval of amendments to Ordinance 2019-004 and to waive the provisions of
Article 5.08 “GC-General Commercial District” regarding building setbacks and maximum site
coverage; Article 9 “Streets, Sidewalks and Subdivision Design” regarding lots having to front on
a public street; Article 10 “Utilities” to permit existing utility connections and to Article 12 “Off-
Street Parking, Loading and Storage Requirements” regarding parking setbacks of the Unified
Development Ordinance and other approvals as required in association of approval of the Final
Plat of Northland Plaza Third Resubdivision. The subject property is generally located at the
northeast quadrant of Sycamore Road and Barber Greene Road with an address range of 2420-
2572 Sycamore Road, with PIN’s 08-12-451-004, 08-12-451-006, 08-12-451-015, 08-12-451-016,
08-12-451-017 and 08-12-451-018, and is commonly known as the Northland Plaza Shopping
Center. The intent is to create separate lots around the existing five smaller buildings within the
shopping center.
All interested persons are invited to appear and be heard at the time and place listed above.
Interested persons are also encouraged to submit written comments on the proposal to the City of
DeKalb, Community Development Department, 200 South Fourth Street, DeKalb, Illinois, 60115
by 5:00 p.m. on Wednesday, April 8, 2020 or by e-mail to dan.olson@cityofdekalb.com. Further
information regarding the petition is available from the Community Development Department at
(815) 748-2070 or on the City of DeKalb’s web page at
https://www.cityofdekalb.com/1103/Public-Hearings.
Max Maxwell, Chair
DeKalb Planning and Zoning Commission