Land Use
Regular MeetingEdwardsville, IL · August 23, 2018
Minutes
1
LAND USE COMMITTEE
EDWARDSVILLE PLAN COMMISSION
August 23, 2018
7:00 PM
PRESENT ABSENT
John McDole John Mullane, Chairman
Mark Rabe Dorothy Hummel
Emily Fultz, Staff Veronica Armouti, PC Chairman
Cheryl Porter, Staff
Ryan Zwijack, Staff
Walt Williams, Staff
Lisa Schneck, Staff
Chris Schneider
Tyler Unterbrink, Korte Construction
David Oates, Oates Associates
Kevin Shepard, Oates Associates
Bill Eck, Anderson Hospital
At the regular meeting of the Plan Commission's Land Use Committee, the following items were
discussed:
A. Case 2018-29: Edwardsville Marketplace
Preliminary Plat
Developer: SM Properties
Engineer: Oates Associates
Staff gave a quick overview of the proposed Preliminary Plat. The developer is taking what
was originally outlots and converting them to buildable lots. Staff has been working with the
developer and engineer to make sure there was enough frontage along Troy Road for Lots B
and D and also working with them for the stormwater detention. There is a request for a
variance for sidewalks. There are no sidewalks existing along that side of Troy Road.
There were also a few comments related to easements. There are currently two detention
areas, one on each lot. Those will be vacated with the exception of a 60 foot easement at the
southern end of Lot D and 20-foot easement at the southern side of Lot C. Staff is currently
in review of the stormwater report and is comfortable with the easement sizes proposed.
For Lot C the retained drainage easement area along the southern property line is clear of the
buildable area. However when taking into account the 16.5 foot fiber optic easement along
the northern property line and the adjacent 10 foot drainage easement shown on the north
side of this lot, it appears the buildable area shown on the north side of the lot overlaps the 10
foot drainage easement by 1.5-foot. The labeled buildable area requires appropriate labeling
to clear the 26.5 feet of obligated easements on the north side of the lot. Currently, those
easements will contain underground storage. The amount of storage needed will be figured
for the existing and added for the proposed development also. What is being submitted is
based on the worse case scenario.
On Lot D the drainage easement area that will remain along the southern property line
2
overlaps 35 feet with the buildable area on the south side of the lot. This also will require the
appropriate labeling of the buildable area to clear the obligated easement area. Building
setback will need to be 60 feet.
Discussion regarding the sidewalk requirement for this development. This area is not a
walkable area. But on the other hand, if two more businesses are added, it may be. There is
a ribbon area to the North which was put in by the City. Sidewalks could be placed within
the right of way near the property lines to leave room for a future center turn lane but there is
no connectivity in this area. There are intermittent sidewalks along State Route 157.
Examples were given of McAllister’s and Edison’s which leads to nowhere. The only thing
is that this area still has undeveloped lots. The proposed lots are the only vacant lots within
the development. The only way sidewalks will be installed on the existing developments is if
the City would install them when and if it is warranted for a pedestrian corridor. It was
suggested to have a more thorough discussion with more members present at the Plan
Commission meeting.
The Preliminary Plat is forwarded to Plan Commission without a recommendation due to the
lack of a quorum.
B. Case 2018-31: Anderson Goshen Campus - PUD
Development Plan
Developer: The Korte Company
Engineer: Oates Associates
Staff gave a brief outline of the proposed PUD. The proposed development is a 10 acre site.
It will be a four phase development. This is zoned “Town Center” within the I-55 Corridor
area. Staff has been paying close attention to the code requirements for this area. The
developer has done a great job of identifying those areas where the plan does not comply
with the I-55 development. They are requesting a parking variance. The required parking
for this development is 490 spaces and 503 total spaces with the future ambulatory addition
and they are proposing 441 spaces. This is a 10% variance or 12½ % after the addition.
Staff can grant a 10% variance. It really only comes into play when the addition will be
constructed.
New water and sewer mains will be constructed through the site. The building materials are
primarily brick and glass which are required by the I-55 Corridor development code. There
is a variation for the amount of glazing on the building. Many of the variations requested
from the I-55 Corridor development code are because of the height of the buildings. Because
these buildings are a medical center, there are certain requirements by the state; it is a
challenge to meet those requirements. They have tried to meet as many requirements as
possible. They did design a front corridor in the building to get as much glazing as possible.
Because of all of the walking paths and detention pond within the development, they have
exceeded the requirements for greenspace.
They have moved the entrance to line up with the YMCA. They made sure the dedication for
Gusewelle and for the proposed road to the North were adequate. They also made sure there
were adequate sidewalks and added some bicycle parking per ordinance. They will also
improve that section of Goshen Road. At some point there will be a crosswalk at District
Drive which will eventually be signalized.
Sanitary sewer will run to the North corner. The water line will be extended to the North but
3
capped in anticipation of future development. There is currently a drainage way through the
site. Their intent is connecting to the drainage way and bypassing the basin.
The construction during Phase 1 will consist of enough of the access road, the pond, and the
parking lot and water for the first building. The only thing that will be complete is the
sanitary sewer. They are not sure if the entire site will be graded at once. The road profile
will match with the existing grade as much as possible.
The developers did their own parking study with other facilities with this type of use. Their
submittal is in line with their study. It seems that 4 spaces per 1000 square feet of office
space is an adequate for the estimate. The biggest amount of traffic generated in this area is
during school hours. They will have a better idea of the parking situation once the first two
buildings are built as to how much is actually being used and what will be available.
The PUD – Development Plan for this development is forwarded to Plan Commission
without a recommendation due to the lack of a quorum.
REMINDER:
PLAN COMMISSION MEETING: Monday, September 17, 2018 at 7:00 p.m. at City Hall, City
Council Chambers, 118 Hillsboro Avenue.
Agenda
LAND USE COMMITTEE
AGENDA
MEETING DATE: Thursday, August 23, 2018
TIME: 7:00 P.M.
PLACE: City Hall Committee Meeting Room
LAND USE CASES:
A. Case 2018-29: Edwardsville Marketplace
Preliminary Plat
Developer: SM Properties
Engineer: Oates Associates
B. Case 2018-31: Anderson Goshen Campus - PUD
Development Plan
Developer: The Korte Company
Engineer: Oates Associates
INFORMATION:
PLAN COMMISSION MEETING: Monday, September 17, 2018 at 7:00 p.m. in City Hall
Council Chambers, 118 Hillsboro Avenue.