Committee of the Whole
Regular MeetingGeneva, IL · September 8, 2015
Minutes
SPECIAL COMMITTEE OF THE WHOLE MINUTES
Tuesday, September 8, 2015 at 7pm
1. Call to Order
Mayor Burns called the meeting to order at 7pm.
Present: Bruno, Burghart, Kilburg, Maladra, Marks, Radecki, Seno, Simonian
Absent: Cummings, Singer
Also Present: Radovich, McKittrick, Dawkins, Babica, DeGroot, Schiber
2. Items of Business
a. Recommend Resolution No. 2015-94 Authorizing Contract for South Fourth Street Parking Lot
Construction to Abbey Paving and Sealcoat Company Inc. in the Amount of $430,484.36 for a
Concrete Parking Lot with $113,734.36 of Said Funds Derived from City’s Non-Home Rule Sale Tax
Fund.
Moved by Ald. Maladra, second by Ald. Marks
Several aldermen had routine questions seeking clarification.
Roll Call: Ayes: 8 Nays: 0 Absent: 2 Motion carried.
3. New Business None
4. Adjournment
On a motion by Ald. Bruno, second by Ald. Marks, the meeting was adjourned by unanimous voice
vote at 7:09pm.
Agenda
1
AGENDA
SPECIAL COMMITTEE OF THE WHOLE MEETING
Tuesday, September 8, 2015 at 7pm
City Hall Council Chambers
109 James Street
Geneva, IL 60134
1. Call to Order
2. Items of Business
a. Recommend Resolution No. 2015-94 Authorizing Contract for South Fourth
Street Parking Lot Construction to Abbey Paving and Sealcoat Company Inc. in
the Amount of $430,484.36 for a Concrete Parking Lot with $113,734.36 of Said
Funds Derived from City’s Non-Home Rule Sale Tax Fund.
3. New Business
4. Adjournment
2
AGENDA ITEM EXECUTIVE SUMMARY
Agenda Item: South Fourth Street Parking Lot
Brian Schiber
Presenter & Title:
City Engineer/Assistant Director of Public Works
Date: August 26, 2015
Please Check Appropriate Box:
Committee of the Whole Meeting X Special Committee of the Whole Meeting
X City Council Meeting Special City Council Meeting
Public Hearing Other -
X YES
Estimated Cost: $340,000.00* Budgeted?
X NO
If NO, please explain how the item will be funded: The construction bids came in higher
than the budgeted amount. Staff is recommending the use of ICPF funds to cover the
difference.
Executive Summary:
The construction of a downtown public parking lot on the City acquired property at the
corner of South Fourth Street/Crescent Place has been a high priority in the City’s Capital
Improvement Program for several years and the City has budgeted $340,000.00 for this
construction. In April of this year the Council approved an engineering design contract
with Baxter & Woodman for $23,250 to prepare the final engineering/specifications
necessary to bid this project. Public Works staff will do the daily inspections and
construction management on this project.
Eight (8) bids were received for the South Fourth Street Parking Lot construction project
and these were publicly opened/read on August 20, 2015. The bids were set up with a
base bid to get the site ready for the parking lot construction, and then we requested
alternate bids for both a concrete and an asphalt (HMA) parking lot. See the attached bid
tabulations.
The low bidder for an asphalt (HMA hot mix asphalt) parking lot @$400,338.05 is
Copenhaver Construction out of Gilberts, Illinois. The low bidder for a concrete parking
lot @$430,484.36 is Abbey Paving & Sealcoat Company out of Aurora, Illinois. Both
companies are prequalified by IDOT to perform the work involved in this contract, but
only Abbey has done work in Geneva previously. We have found their work to be
acceptable.
HMA is cheaper to maintain and it has ice/snow melting benefits when it’s exposed to the
sun. The HMA plants typically close in November of each year due to cold
weather/snow, but with the proper cold weather protective measures, concrete can be
3
placed almost year round. However, concrete has about 10-15 more years of useful life
than HMA. The Public Works staff is of the opinion that the ~$30,000 extra cost for a
concrete parking lot is worth it over the useful life of the parking lot.
The Public Works staff has discussed the difference between the budgeted amount and
the bid amounts (max. of ~$114,000) with Tom Dahl and he has reported that the Non-
Home Rule Sales Tax fund (ICPF) ended last fiscal year with a $823,000 balance and the
City budgeted the use of $500,000 of this balance for this fiscal year. That leaves a
balance for the City of approximately $323,000.
ORIGINAL BUDGETED AMOUNT…………………………$340,000.00
Baxter & Woodman design contract…………………………….$23,250.00
Abbey Paving bid for concrete parking lot…………………….$430,484.36
TOTAL COST…………………………………………………$453,734.36
DIFFERENCE (from ICPF)…………………………………...$113,734.36
If the Council is receptive to using $113,734.36 of the ICPF $323,000 to cover the
difference between the budgeted amount and the bid amounts, the Public Works staff
recommends the City Council accept the bid for the concrete parking lot for $430,484.36
from Abbey Paving.
The budget will be rectified with a future budget amendment.
Attachments: (please list)
• Resolution
• Bid Tabulation
Recommendation / Suggested Action: (briefly explain)
Recommend award of the contract for the South Fourth Street Parking Lot at the next
scheduled Council meeting, to Abbey Paving and Sealcoat Company, Inc. of Aurora,
Illinois for the amount of $430,484.36 for a concrete parking lot; and using $113,734.36
from the ICPF in addition to the budgeted amount of $340,000.
4
RESOLUTION NO. 2015-94
RESOLUTION AUTHORIZING EXECUTION OF
Contract with Copenhaver Construction for the “South Fourth Street Parking Lot”
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF GENEVA, KANE
COUNTY, ILLINOIS, as follows:
SECTION 1: That the City Administrator is hereby authorized to execute, on behalf of the
City of Geneva, a Construction Contract with Copenhaver Construction in the form attached hereto
as Exhibit “A”, relating to the construction of a public concrete parking lot in the City of Geneva, IL.
SECTION 2: That the City will use $113,734.36 from the ICPF in addition to the budgeted
amount of $340,000 for the construction of the public concrete parking lot.
SECTION 3: This Resolution shall become effective from and after its passage as in
accordance with law.
PASSED by the City Council of the City of Geneva, Kane County, Illinois, this 8th day of
September, 2015
AYES: __ NAYS: __ ABSENT: __ ABSTAINING: __ HOLDING OFFICE:
__ Approved by me this 8th day of September, 2015.
Mayor
ATTEST:
City Clerk
5
FOURTH STREET PARKING LOT
TABULATION OF BIDS OPEN: AUGUST 20, 2015 @ 10:00 AM
ENGINEER'S ESTIMATE Copenhaver Construction Abbey Paving & Sealcoat. Co., Inc. Aliance Contractors, Inc A Lamp Concrete Contractors, Inc Martam Construction, Inc. Landmark Contractors, Inc. Geneva Construction Co. Eliot & Wood, Inc.
75 Koppie Dr Gilberts, Illinois 1949 Countyline Rd Aurora, IL 16 Lake Av Woodstock, Illinois 1900 Wright Boulevard 1200 Gasket Dr, Elgin IL 11916 W Main St Huntly, Illinois PO Box 998 Aurora IL 210 Industrial Dr Sycamore, IL
ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST
1 TREE REMOVAL (6 TO 15 UNITS DIAMETER) UNITS 210.00 $ 30.00 $ 6,300.00 $ 21.00 $ 4,410.00 $ 13.99 $ 2,937.90 $ 15.00 $ 3,150.00 $ 15.00 $ 3,150.00 $28.00 $ 5,880.00 $ 14.50 $ 3,045.00 $22.00 $ 4,620.00 $ 20.21 $ 4,244.10
2 TREE REMOVAL (OVER 15 UNITS DIAMETER) UNITS 51.00 $ 36.00 $ 1,836.00 $ 23.00 $ 1,173.00 $ 116.95 $ 5,964.45 $ 25.00 $ 1,275.00 $ 20.00 $ 1,020.00 $47.00 $ 2,397.00 $ 17.50 $ 892.50 $23.00 $ 1,173.00 $ 25.26 $ 1,288.26
3 EARTH EXCAVATION CU YD 2,400.00 $ 30.00 $ 72,000.00 $ 28.00 $ 67,200.00 $ 31.45 $ 75,480.00 $ 52.25 $ 125,400.00 $ 38.00 $ 91,200.00 $47.00 $ 112,800.00 $ 43.80 $ 105,120.00 $36.88 $ 88,512.00 $ 105.00 $ 252,000.00
4 FENCE REMOVAL FOOT 110.00 $ 10.00 $ 1,100.00 $ 8.00 $ 880.00 $ 4.00 $ 440.00 $ 9.51 $ 1,046.10 $ 15.00 $ 1,650.00 $8.00 $ 880.00 $ 13.63 $ 1,499.30 $4.80 $ 528.00 $ 5.00 $ 550.00
5 TRENCH BACKFILL CU YD 5.00 $ 100.00 $ 500.00 $ 65.00 $ 325.00 $ 52.50 $ 262.50 $ 50.00 $ 250.00 $ 50.00 $ 250.00 $57.00 $ 285.00 $ 60.00 $ 300.00 $60.00 $ 300.00 $ 30.00 $ 150.00
6 SUBBASE GRANULAR MATERIAL, TYPE B, 6 INCH CU YD 400.00 $ 50.00 $ 20,000.00 $ 37.00 $ 14,800.00 $ 45.10 $ 18,040.00 $ 40.00 $ 16,000.00 $ 20.00 $ 8,000.00 $1.00 $ 400.00 $ 41.00 $ 16,400.00 $42.00 $ 16,800.00 $ 17.96 $ 7,184.00
7 AGGREGATE BASE COURSE, TYPE B, 4 INCH CU YD 2,605.00 $ 36.00 $ 93,780.00 $ 0.01 $ 26.05 $ 45.10 $ 117,485.50 $ 0.40 $ 1,042.00 $ 20.00 $ 52,100.00 $1.00 $ 2,605.00 $ 8.20 $ 21,361.00 $38.00 $ 98,990.00 $ 17.96 $ 46,785.80
8 PORTLAND CEMENT CONCRETE SIDEWALK 5 INCH SQ FT 1,850.00 $ 7.00 $ 12,950.00 $ 7.00 $ 12,950.00 $ 7.27 $ 13,449.50 $ 6.50 $ 12,025.00 $ 7.00 $ 12,950.00 $8.00 $ 14,800.00 $ 5.60 $ 10,360.00 $8.00 $ 14,800.00 $ 10.00 $ 18,500.00
9 DETECTABLE WARNINGS SQ FT 6.00 $ 50.00 $ 300.00 $ 70.00 $ 420.00 $ 2.10 $ 12.60 $ 25.00 $ 150.00 $ 45.00 $ 270.00 $33.00 $ 198.00 $ 18.00 $ 108.00 $27.00 $ 162.00 $ 41.80 $ 250.80
10 DRIVEWAY PAVEMENT REMOVAL SQ YD 24.00 $ 15.00 $ 360.00 $ 16.00 $ 384.00 $ 13.40 $ 321.60 $ 30.00 $ 720.00 $ 15.00 $ 360.00 $16.00 $ 384.00 $ 13.00 $ 312.00 $24.00 $ 576.00 $ 40.00 $ 960.00
11 CURB REMOVAL FOOT 432.00 $ 10.50 $ 4,536.00 $ 7.00 $ 3,024.00 $ 3.75 $ 1,620.00 $ 30.00 $ 12,960.00 $ 4.00 $ 1,728.00 $15.00 $ 6,480.00 $ 8.70 $ 3,758.40 $9.00 $ 3,888.00 $ 10.00 $ 4,320.00
12 SIDEWALK REMOVAL SQ FT 885.00 $ 3.50 $ 3,097.50 $ 2.00 $ 1,770.00 $ 2.60 $ 2,301.00 $ 3.00 $ 2,655.00 $ 2.00 $ 1,770.00 $2.00 $ 1,770.00 $ 1.65 $ 1,460.25 $1.75 $ 1,548.75 $ 1.00 $ 885.00
PRECAST REINFORCED CONCRETE FLARED END SECTIONS, 15 $ 750.00 $ 750.00 $ 600.00 $ 600.00 $ 1,605.00 $ 1,605.00 $ 500.00 $ 500.00 $ 1,500.00 $ 1,500.00
13 EACH 1.00 $950.00 $ 950.00 $ 1,800.00 $ 1,800.00 $3,000.00 $ 3,000.00 $ 1,405.03 $ 1,405.03
INCH
14 STORM SEWERS, CLASS A, TYPE 2, 12" FOOT 10.00 $ 40.00 $ 400.00 $ 97.00 $ 970.00 $ 37.45 $ 374.50 $ 148.00 $ 1,480.00 $ 65.00 $ 650.00 $86.00 $ 860.00 $ 80.00 $ 800.00 $60.00 $ 600.00 $ 143.58 $ 1,435.80
15 STORM SEWERS, CLASS A, TYPE 2, 15" FOOT 30.00 $ 60.00 $ 1,800.00 $ 86.00 $ 2,580.00 $ 42.80 $ 1,284.00 $ 154.00 $ 4,620.00 $ 75.00 $ 2,250.00 $94.00 $ 2,820.00 $ 82.00 $ 2,460.00 $70.00 $ 2,100.00 $ 121.34 $ 3,640.20
16 DOMESTIC WATER SERVICE BOXES TO BE REMOVED EACH 1.00 $ 250.00 $ 250.00 $ 300.00 $ 300.00 $ 1,605.00 $ 1,605.00 $ 250.00 $ 250.00 $ 250.00 $ 250.00 $200.00 $ 200.00 $ 300.00 $ 300.00 $3,000.00 $ 3,000.00 $ 750.50 $ 750.50
17 CATCH BASINS, TYPE A, 4' DIAMETER, TYPE 11 FRAME AND GRATE EACH 1.00 $ 3,000.00 $ 3,000.00 $ 3,200.00 $ 3,200.00 $ 4,015.00 $ 4,015.00 $ 6,100.00 $ 6,100.00 $ 2,500.00 $ 2,500.00 $4,400.00 $ 4,400.00 $ 3,900.00 $ 3,900.00 $12,000.00 $ 12,000.00 $ 4,531.64 $ 4,531.64
18 INLETS, TYPE A, TYPE 1 FRAME AND OPEN LID EACH 1.00 $ 2,000.00 $ 2,000.00 $ 1,400.00 $ 1,400.00 $ 1,285.00 $ 1,285.00 $ 2,100.00 $ 2,100.00 $ 2,000.00 $ 2,000.00 $1,500.00 $ 1,500.00 $ 2,000.00 $ 2,000.00 $2,600.00 $ 2,600.00 $ 3,062.72 $ 3,062.72
19 INLETS, TYPE A, TYPE 11 FRAME AND GRATE EACH 1.00 $ 2,000.00 $ 2,000.00 $ 1,400.00 $ 1,400.00 $ 1,340.00 $ 1,340.00 $ 2,100.00 $ 2,100.00 $ 2,000.00 $ 2,000.00 $1,650.00 $ 1,650.00 $ 1,400.00 $ 1,400.00 $3,000.00 $ 3,000.00 $ 2,233.66 $ 2,233.66
20 REMOVING INLETS EACH 1.00 $ 350.00 $ 350.00 $ 300.00 $ 300.00 $ 535.00 $ 535.00 $ 250.00 $ 250.00 $ 200.00 $ 200.00 $100.00 $ 100.00 $ 320.00 $ 320.00 $600.00 $ 600.00 $ 829.88 $ 829.88
21 COMBINATION CONCRETE CURB AND GUTTER, TYPE B-6.12 FOOT 805.00 $ 30.00 $ 24,150.00 $ 21.00 $ 16,905.00 $ 22.22 $ 17,887.10 $ 41.00 $ 33,005.00 $ 20.00 $ 16,100.00 $28.00 $ 22,540.00 $ 31.70 $ 25,518.50 $22.00 $ 17,710.00 $ 45.00 $ 36,225.00
22 GUARDRAIL REMOVAL FOOT 15.00 $ 50.00 $ 750.00 $ 12.00 $ 180.00 $ 15.00 $ 225.00 $ 38.04 $ 570.60 $ 10.00 $ 150.00 $21.00 $ 315.00 $ 40.00 $ 600.00 $8.00 $ 120.00 $ 131.05 $ 1,965.75
23 TRAFFIC CONTROL AND PROTECTION, STANDARD 701501 L SUM 1.00 $ 5,000.00 $ 5,000.00 $ 66,000.00 $ 66,000.00 $ 1,850.00 $ 1,850.00 $ 6,916.00 $ 6,916.00 $ 45,000.00 $ 45,000.00 $4,500.00 $ 4,500.00 $ 45,524.00 $ 45,524.00 $28,381.00 $ 28,381.00 $ 4,217.75 $ 4,217.75
24 TRAFFIC CONTROL AND PROTECTION, STANDARD 701801 L SUM 1.00 $ 100.00 $ 100.00 $ 700.00 $ 700.00 $ 1,850.00 $ 1,850.00 $ 1.00 $ 1.00 $ 6,500.00 $ 6,500.00 $31,000.00 $ 31,000.00 $ 1.00 $ 1.00 $100.00 $ 100.00 $ 106.10 $ 106.10
25 JOINT & CRACK FILLING FOOT 1,000.00 $ 2.50 $ 2,500.00 $ 2.00 $ 2,000.00 $ 1.60 $ 1,600.00 $ 2.00 $ 2,000.00 $ 1.00 $ 1,000.00 $3.00 $ 3,000.00 $ 1.00 $ 1,000.00 $1.60 $ 1,600.00 $ 0.76 $ 760.00
26 PARKING BUMPER REMOVAL EACH 20.00 $ 50.00 $ 1,000.00 $ 40.00 $ 800.00 $ 35.00 $ 700.00 $ 25.00 $ 500.00 $ 45.00 $ 900.00 $25.00 $ 500.00 $ 45.00 $ 900.00 $28.00 $ 560.00 $ 10.11 $ 202.20
27 SEALCOATING SQ YD 820.00 $ 4.00 $ 3,280.00 $ 2.00 $ 1,640.00 $ 1.45 $ 1,189.00 $ 3.00 $ 2,460.00 $ 3.50 $ 2,870.00 $3.00 $ 2,460.00 $ 4.00 $ 3,280.00 $1.60 $ 1,312.00 $ 4.16 $ 3,411.20
28 REMOVAL AND SALVAGING TRAFFIC SIGNS EACH 8.00 $ 150.00 $ 1,200.00 $ 250.00 $ 2,000.00 $ 100.00 $ 800.00 $ 300.00 $ 2,400.00 $ 500.00 $ 4,000.00 $25.00 $ 200.00 $ 175.00 $ 1,400.00 $295.00 $ 2,360.00 $ 151.58 $ 1,212.64
29 PAVEMENT MARKING REMOVAL SQ FT 380.00 $ 1.50 $ 570.00 $ 3.00 $ 1,140.00 $ 1.00 $ 380.00 $ 2.00 $ 760.00 $ 5.00 $ 1,900.00 $3.00 $ 1,140.00 $ 3.00 $ 1,140.00 $3.00 $ 1,140.00 $ 3.03 $ 1,151.40
30 URETHANE PAVEMENT MARKING - LETTERS AND SYMBOLS SQ FT 75.00 $ 6.00 $ 450.00 $ 8.00 $ 600.00 $ 15.00 $ 1,125.00 $ 5.95 $ 446.25 $ 22.00 $ 1,650.00 $8.00 $ 600.00 $ 20.00 $ 1,500.00 $20.00 $ 1,500.00 $ 21.22 $ 1,591.50
31 URETHANE PAVEMENT MARKING - LINE 4" FOOT 3,600.00 $ 2.00 $ 7,200.00 $ 2.00 $ 7,200.00 $ 1.50 $ 5,400.00 $ 1.82 $ 6,552.00 $ 2.00 $ 7,200.00 $2.20 $ 7,920.00 $ 1.00 $ 3,600.00 $1.00 $ 3,600.00 $ 1.06 $ 3,816.00
32 URETHANE PAVEMENT MARKING - LINE 6" FOOT 75.00 $ 3.00 $ 225.00 $ 5.00 $ 375.00 $ 2.25 $ 168.75 $ 2.85 $ 213.75 $ 4.00 $ 300.00 $3.60 $ 270.00 $ 2.00 $ 150.00 $2.00 $ 150.00 $ 2.12 $ 159.00
33 URETHANE PAVEMENT MARKING - LINE 12" FOOT 110.00 $ 6.00 $ 660.00 $ 7.00 $ 770.00 $ 4.50 $ 495.00 $ 5.70 $ 627.00 $ 15.00 $ 1,650.00 $7.00 $ 770.00 $ 10.00 $ 1,100.00 $10.00 $ 1,100.00 $ 10.61 $ 1,167.10
34 UNDERGROUND CONDUIT, GALVANIZED STEEL, 3" DIA FOOT 182.00 $ 35.00 $ 6,370.00 $ 33.00 $ 6,006.00 $ 19.26 $ 3,504.96 $ 30.00 $ 5,460.00 $ 33.00 $ 6,006.00 $36.00 $ 6,552.00 $ 30.00 $ 5,460.00 $34.90 $ 6,351.80 $ 37.03 $ 6,739.46
LUMINAR SODIUM VAPOR, HORIZONTAL MOUNT, PHOTO CELL $ 400.00 $ 2,000.00 $ 600.00 $ 3,000.00 $ 3.47 $ 17.35 $ 550.00 $ 2,750.00 $ 589.00 $ 2,945.00
35 EACH 5.00 $650.00 $ 3,250.00 $ 550.00 $ 2,750.00 $385.00 $ 1,925.00 $ 408.51 $ 2,042.55
CONTROL, 150 WATT
36 LIGHT POLE FOUNDATION, 24" DIA FOOT 45.00 $ 250.00 $ 11,250.00 $ 220.00 $ 9,900.00 $ 215.00 $ 9,675.00 $ 180.00 $ 8,100.00 $ 193.00 $ 8,685.00 $225.00 $ 10,125.00 $ 180.00 $ 8,100.00 $182.00 $ 8,190.00 $ 193.11 $ 8,689.95
37 MODIFY EXISTING CONTROLLER EACH 1.00 $ 800.00 $ 800.00 $ 550.00 $ 550.00 $ 802.50 $ 802.50 $ 500.00 $ 500.00 $ 535.00 $ 535.00 $600.00 $ 600.00 $ 500.00 $ 500.00 $1,880.00 $ 1,880.00 $ 1,994.81 $ 1,994.81
UNIT DUCT, 600V, 2-1C NO.10,1/C NO.10 GROUND, (XLP-TYPE USE), 1" $ 4.75 $ 2,346.50 $ 20.00 $ 9,880.00 $ 10.70 $ 5,285.80 $ 16.00 $ 7,904.00 $ 17.50 $ 8,645.00
38 FOOT 494.00 $20.00 $ 9,880.00 $ 16.00 $ 7,904.00 $8.90 $ 4,396.60 $ 9.44 $ 4,663.36
DIA POLYETHYLENE
39 LIGHT POLE, ALUMINUM, 25 FT. M.H., 5 FT. ARM EACH 5.00 $ 5,000.00 $ 25,000.00 $ 7,100.00 $ 35,500.00 $ 1,442.00 $ 7,210.00 $ 6,500.00 $ 32,500.00 $ 6,955.00 $ 34,775.00 $7,800.00 $ 39,000.00 $ 6,500.00 $ 32,500.00 $7,420.00 $ 37,100.00 $ 7,873.12 $ 39,365.60
40 6 FT. PRIVACY FENCE FOOT 180.00 $ 30.00 $ 5,400.00 $ 41.00 $ 7,380.00 $ 59.00 $ 10,620.00 $ 142.92 $ 25,725.60 $ 30.00 $ 5,400.00 $51.00 $ 9,180.00 $ 44.34 $ 7,981.20 $152.00 $ 27,360.00 $ 190.62 $ 34,311.60
SEGMENTAL BLOCK RETAINING WALL, (3' OR LESS EXPOSED $ 100.00 $ 28,500.00 $ 44.00 $ 12,540.00 $ 90.00 $ 25,650.00 $ 45.00 $ 12,825.00 $ 42.00 $ 11,970.00
41 FOOT 285.00 $161.00 $ 45,885.00 $ 201.00 $ 57,285.00 $156.25 $ 44,531.25 $ 206.91 $ 58,969.35
HEIGHT)
42 WILSON HOLLY - "LLEX WILSONI" @ 3" CAL. EACH 8.00 $ 250.00 $ 2,000.00 $ 40.00 $ 320.00 $ 455.00 $ 3,640.00 $ 100.00 $ 800.00 $ 426.00 $ 3,408.00 $1,050.00 $ 8,400.00 $ 675.00 $ 5,400.00 $450.00 $ 3,600.00 $ 716.22 $ 5,729.76
43 JAPANESE MAPLE - "ACER PALATUM" @ 3" CAL EACH 3.00 $ 250.00 $ 750.00 $ 750.00 $ 2,250.00 $ 486.00 $ 1,458.00 $ 650.00 $ 1,950.00 $ 433.00 $ 1,299.00 $1,225.00 $ 3,675.00 $ 675.00 $ 2,025.00 $450.00 $ 1,350.00 $ 716.22 $ 2,148.66
44 NORWAY MAPLE - "ACER PLATANOIDES" - ALMIRA @ 3" CAL. EACH 2.00 $ 650.00 $ 1,300.00 $ 760.00 $ 1,520.00 $ 455.00 $ 910.00 $ 650.00 $ 1,300.00 $ 428.00 $ 856.00 $880.00 $ 1,760.00 $ 575.00 $ 1,150.00 $450.00 $ 900.00 $ 610.11 $ 1,220.22
45 COLODADO SPRUCE - "PICEA PUNGENS" EACH 1.00 $ 650.00 $ 650.00 $ 800.00 $ 800.00 $ 375.00 $ 375.00 $ 800.00 $ 800.00 $ 420.00 $ 420.00 $750.00 $ 750.00 $ 475.00 $ 475.00 $450.00 $ 450.00 $ 504.01 $ 504.01
46 COMMON BOXWOOD - "BOXUS SEMPER VIRENS" @ 6' HT. EACH 2.00 $ 100.00 $ 200.00 $ 500.00 $ 1,000.00 $ 455.00 $ 910.00 $ 600.00 $ 1,200.00 $ 258.00 $ 516.00 $750.00 $ 1,500.00 $ 475.00 $ 950.00 $250.00 $ 500.00 $ 504.01 $ 1,008.02
47 GROUND COVER AND MULCH SQ YD 435.00 $ 15.00 $ 6,525.00 $ 10.00 $ 4,350.00 $ 11.21 $ 4,876.35 $ 6.00 $ 2,610.00 $ 56.00 $ 24,360.00 $21.00 $ 9,135.00 $ 5.20 $ 2,262.00 $8.50 $ 3,697.50 $ 5.52 $ 2,401.20
48 NATIVE GRASS AND STRAW MAT SQ YD 530.00 $ 6.50 $ 3,445.00 $ 4.00 $ 2,120.00 $ 7.50 $ 3,975.00 $ 7.00 $ 3,710.00 $ 7.00 $ 3,710.00 $8.00 $ 4,240.00 $ 2.70 $ 1,431.00 $8.50 $ 4,505.00 $ 2.86 $ 1,515.80
49 DRAINAGE AND UTILITY STRUCTURES TO BE ADJUSTED EACH 1.00 $ 500.00 $ 500.00 $ 480.00 $ 480.00 $ 375.00 $ 375.00 $ 500.00 $ 500.00 $ 400.00 $ 400.00 $560.00 $ 560.00 $ 375.00 $ 375.00 $977.10 $ 977.10 $ 752.31 $ 752.31
50
$371,431.00 $ 316,018.05 $ 363,313.36 $ 359,159.30 $ 388,948.00 $ 391,066.00 $ 399,858.15 $ 466,145.00 $ 583,049.69
ALTERNATE A - HMA PAVEMENT
SUBBASE GRANULAR MATERIAL, TYPE B, 6 INCH SQ YD 2,000.00 $ 12.00 $ 24,000.00 $ 12.00 $ 24,000.00 $ 5.00 $ 10,000.00 1.00 2,000.00 11.00 22,000.00 $ 6.00 $ 12,000.00 $ 8.20 $ 16,400.00 $ 7.00 $ 14,000.00 $ 15.00 $ 30,000.00
A1
HOT - MIX ASPHALT BINDER COURSE, IL-19.0, N30 TON 475.00 $ 80.00 $ 38,000.00 $ 81.00 $ 38,475.00 $ 76.00 $ 36,100.00 80.00 38,000.00 90.00 42,750.00 $ 126.00 $ 59,850.00 $ 80.00 $ 38,000.00 $ 84.00 $ 39,900.00 $ 89.66 $ 42,588.50
A2
HOT - MIX ASPHALT SURFACE COURSE, MIX "C", N30 TON 205.00 $ 100.00 $ 20,500.00 $ 89.00 $ 18,245.00 $ 82.00 $ 16,810.00 100.00 20,500.00 95.00 19,475.00 $ 144.00 $ 29,520.00 $ 100.00 $ 20,500.00 $ 104.00 $ 21,320.00 $ 99.21 $ 20,338.05
A3
BITUMINOUS MATERIAL (PRIME COAT) GAL 1,200.00 $ 2.00 $ 2,400.00 $ 3.00 $ 3,600.00 $ 0.10 $ 120.00 0.01 12.00 1.00 1,200.00 $ 5.00 $ 6,000.00 $ 0.01 $ 12.00 $ 0.01 $ 12.00 $ 0.11 $ 132.00
A4
HMA PAVEMENT TOTAL $ 84,900.00 $ 84,320.00 $ 63,030.00 $ 60,512.00 $ 85,425.00 $ 107,370.00 $ 74,912.00 $ 75,232.00 $ 93,058.55
6
ENGINEER'S ESTIMATE Copenhaver Construction Abbey Paving & Sealcoat. Co., Inc. Aliance Contractors, Inc A Lamp Concrete Contractors, Inc Martam Construction, Inc. Landmark Contractors, Inc. Geneva Construction Co. Eliot & Wood, Inc.
75 Koppie Dr Gilberts, Illinois 1949 Countyline Rd Aurora, IL 16 Lake Av Woodstock, Illinois 1900 Wright Boulevard 1200 Gasket Dr, Elgin IL 11916 W Main St Huntly, Illinois PO Box 998 Aurora IL 210 Industrial Dr Sycamore, IL
ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST UNIT PRICE COST
BASR BID + HMA PAVEMENT $ 456,331.00 $ 400,338.05 $ 426,343.36 $ 419,671.30 $ 474,373.00 $ 498,436.00 $ 474,770.15 $ 541,377.00 $ 676,108.24
PCC PAVEMENT
PORTLAND CEMENT CONCRETE PAVEMENT, 6 INCH SQ YD 1,970.00 $ 50.00 $ 98,500.00 $ 54.00 $ 106,380.00 $ 29.10 $ 57,327.00 52.00 102,440.00 50.00 $ 98,500.00 $ 47.50 $ 93,575.00 $ 60.35 $ 118,889.50 $ 67.00 $ 131,990.00 $ 50.00 $ 98,500.00
B1
PROTECTIVE COAT SQ YD 1,970.00 $ 5.00 $ 9,850.00 $ 2.00 $ 3,940.00 $ 0.25 $ 492.50 0.01 19.70 1.00 $ 1,970.00 $ 1.00 $ 1,970.00 $ 1.50 $ 2,955.00 $ 1.00 $ 1,970.00 $ 1.75 $ 3,447.50
B2
HOT -MIX ASPHALT BINDER COURSE, IL-19.0, N30 TON 85.00 $ 100.00 $ 8,500.00 $ 130.00 $ 11,050.00 $ 76.00 $ 6,460.00 114.00 9,690.00 100.00 $ 8,500.00 $ 126.00 $ 10,710.00 $ 114.00 $ 9,690.00 $ 114.00 $ 9,690.00 $ 127.86 $ 10,868.10
B3
HOT -MIX ASPHALT SURFACE COURSE, MIX "C", N30 TON 35.00 $ 120.00 $ 4,200.00 $ 135.00 $ 4,725.00 $ 82.00 $ 2,870.00 124.00 4,340.00 125.00 $ 4,375.00 $ 144.00 $ 5,040.00 $ 124.00 $ 4,340.00 $ 124.00 $ 4,340.00 $ 130.51 $ 4,567.85
B4
BITUMINOUS MATERIAL (PRIME COAT) GAL 215.00 $ 2.50 $ 537.50 $ 2.00 $ 430.00 $ 0.10 $ 21.50 2.75 591.25 1.00 $ 215.00 $ 5.00 $ 1,075.00 $ 2.75 $ 591.25 $ 0.01 $ 2.15 $ 0.11 $ 23.65
B5
PCC PAVEMENT TOTAL $ 121,587.50 $ 126,525.00 $ 67,171.00 $ 117,080.95 $ 113,560.00 $ 112,370.00 $ 136,465.75 $ 147,992.15 $ 117,407.10
BAASE BID + PCC PAVEMENT TOTAL
$ 493,018.50 $ 442,543.05 $ 430,484.36 $ 476,240.25 $ 502,508.00 $ 503,436.00 $ 536,323.90 $ 614,137.15 $ 700,456.79
Note: Rose colored shading represents minor math errors corrected by PW Staff