Capital Improvements Commission
Regular MeetingGlen Ellyn, IL · November 12, 2025
Minutes
Village of Glen Ellyn
Meeting Minutes
Village of Glen Ellyn
Capital Improvements Commission
November 12, 2025
7:00 PM
Glen Ellyn Civic Center Room 301
Board or Commission: Capital Improvements Date: November 12, 2025
Meeting: Regular Called to Order: 7:00 p.m.
Quorum: Yes Adjourned: 8:28 p.m.
Member Attendance:
Rocco Zucchero Chair Present
Joel Baldin Commissioner Present
Tom Drapinski Commissioner Absent
Orion Galey Commissioner Absent
John MacDonald Commissioner Present
Adil Saeed Commissioner Present
David Warnick Commissioner Present
Jill Ziegler Commissioner Present
Donna Jean Simon Trustee Liaison Present
Richard Daubert Staff Liaison/Professional Engineer Present
Also Present:
John Hubsky Public Works Director
Glenbard West Students
A. CALL TO ORDER
The November 12, 2025 meeting of the Capital Improvements Commission was called to order by
Chair Zucchero at 7:00 p.m. at the Glen Ellyn Civic Center.
B. PUBLIC COMMENT – Chair Zucchero noted that we have some audience members in attendance
and asked if they could introduce themselves. Students from Glenbard West noted they were in
attendance for a Governance Class. Trustee Simon asked Engineer Daubert if he could give the
students an overview on the Capital Improvements Commission and its role for the community.
Engineer Daubert informed the students accordingly noting that the Village is responsible for
maintaining and improving a variety of infrastructure and that it relies upon the Commission to
Capital Improvement
November 12, 2025
Meeting Minutes | 2
provide staff with guidance on certain matters such as the Capital Improvement Plan, Budget, Street
Condition, Sidewalk Improvements, Etcetera. The Commission will provide recommendations which
are sometimes presented to the Village Board to assist the Board in making certain decisions.
Daubert noted that the CIC is an advisory Commission, but the Village Board does heavily weigh
their recommendations in making decisions.
C. APPROVAL OF MINUTES
APPROVAL OF SEPTEMBER 10, 2025 CAPITAL IMPROVEMENTS COMMISSION
MEETING MINUTES
MOTION TO APPROVE THE SEPTEMBER 10, 2025 CAPITAL IMPROVEMENTS
COMMISSION MEETING MINUTES
MOTION BY: Commissioner Saeed
SECOND BY: Commissioner MacDonald
AYES: Zucchero, Baldin, MacDonald, Saeed, Warnick, Ziegler
RESULT: APPROVAL
D. CURRENT BUSINESS
1. ADA Transition Plan Review and Approval Process
Engineer Daubert overviewed that CMAP and Oates are still working on the development of the
Village’s ADA Transition Plan but that a draft of the plan is anticipated within the next month.
Staff will review the draft and provide comments to allow the plan to be finalized for the public
comment period. The public comment period will be open for 30 days. Public comments will be
compiled and addressed/responded to. Capital Improvements Commission feedback will be
sought with staff ultimately looking for a recommendation from the CIC on the adoption of the
plan. The CIC recommendation to adopt the plan will be presented to the Village Board for
consideration of adoption of the plan.
Daubert elaborated that staff has been y focused in its discussions with Oates and CMAP on the
prioritization of the various items that challenge accessibility. For example, a high priority seems
to be curb ramps, trip hazards, and sidewalk gaps. Cross slope is still a challenge but may not be
seen as high of a challenge as the other factors. There’s also been discussions about the location
defects/items that challenge accessibility. For example, Roosevelt Road is an important corridor
from Engineer Daubert’s perspective but there’s not as much foot traffic as in the downtown or
around schools. Hence, there could be differing opinions on the priority of Roosevelt Road. In the
context of these factors as well as the recently secured grant for engineering sidewalk and street
lighting improvements the Oates/CMAP/Staff team feels that Roosevelt Road should be a separate
priority.
Commissioner MacDonald noted he feels Roosevelt Road should be a priority. He also shared his
positive experience with the Village recently improving the curb ramp near his home.
Capital Improvement
November 12, 2025
Meeting Minutes | 3
Commissioner Baldin inquired if we should prioritize higher liability items. Engineer Daubert
noted that this would reinforce prioritizing the trip hazards and curb ramps.
Commissioners were asked if they were overall supportive of the review and approval process.
Chair Zucchero noted that perhaps staff could provide the Commissioners with the draft report
once it is received. Engineer Daubert noted he would provide the draft report once received to
allow Commissioners time to review it and provide comments to staff. The members of the
Capital Improvements Commission in attendance expressed their support for this approach.
E. TRUSTEE’S REPORT – Trustee Simon noted that the Village Board has a new Trustee Robert
Duncan whose current term is for 2 years. The first reading of the budget was completed with the
second reading occurring next month. As part of the budget process, many infrastructure needs have
been identified including with facilities such as Fire Station 62.
F. OTHER BUSINESS – None
G. PUBLIC WORKS REPORT – Public Works Director Hubsky provided several updates, noting that
the Department is working on filling a number of openings including the Facilities Superintendent
and Public Works Management Analyst. He elaborated that the prior Facilities Superintendent was
promoted to the Assistant Public Works Director position. Hubsky noted that we had the first snow
event which allowed us to test some new operations which will likely be much quicker. We have a
new contract for snow removal in the downtown which should relieve staff. Hubsky discussed that
related to the Roosevelt Road hotel property (west side of Exmoor), we found out that the
environmental review was approved and demolition can proceed. We also heard that the State has
approved demolition to continue for the hotel property on the east side of Exmoor. With respect to
the study of Fire Station 62, we are continuing to do public outreach to get feedback on that project.
H. PROJECT REPORT – Engineer Daubert gave updates on the Crescent Glenwood Parking lot
project noting that it is complete minus the installation of lighting units which are anticipated in
December, temp lighting removal, curb work, and planting of perennials which will be in the spring.
Daubert briefly noted that CBD Streetscape concrete repair punch list items and the alley south of
Duane/west of Main are well underway and hopefully wrapping up soon. The Village’s more
significant roadway projects are substantially completed and anticipated to close out below the
contract award values. Engineer Daubert also discussed that staff recently met with DuPage County
and CBBEL to discuss the East Branch Trail Project. Daubert discussed the bid results for the Riford
and Lambert Federal Aid Resurfacing Projects which were overall favorable and staff has accordingly
directed the State to award the contracts. With respect to the Metra Station Project, Daubert noted that
the Project Development Report update was completed and is in the State’s hands for review. Land
Acquisition is underway for the project but can only advance so far until we have approval of the
Project Development Report. Finally, Daubert overviewed the recently secured State grant for
sidewalk and street lighting improvements on Roosevelt Road.
I. ADJOURNMENT – Commissioner MacDonald motioned and Commissioner Warnick seconded to
adjourn the meeting. The motion is unanimously approved, and meeting adjourned at 8:28 p.m.
Submitted and Reviewed by: Richard Daubert, Professional Engineer
Agenda
Agenda
Village of Glen Ellyn
Capital Improvements Commission Meeting
Wednesday, November 12, 2025
7:00 PM
Glen Ellyn Civic Center, Room 301
Any individual with a disability requiring a reasonable accommodation in order to participate in a meeting should
contact The Village of Glen Ellyn ADA Coordinator, 630-469-5000, at least five (5) business days in advance of
the next scheduled meeting. All matters on the Agenda may be discussed, amended, and acted upon.
A. Call to Order
B. Public Comment
C. Approval of Minutes
1) Motion to approve the September 10, 2025 Capital Improvements Commission
Meeting Minutes
D. Current Business
1) ADA Transition Plan Review and Approval Process
E. Trustee Liaison's Report
F. Other Business
G. Public Works Report
H. Project Report
1) Engineering Division Project Activity Report November 7, 2025
I. Adjourn
Civility Pledge - In the interest of civility, I pledge to promote civility by listening, being respectful of others,
acknowledging that we are striving to support and improve our community, and understanding that we each may have
different ideas for achieving that objective.
Packet
Agenda
Village of Glen Ellyn
Capital Improvements Commission Meeting
Wednesday, November 12, 2025
7:00 PM
Glen Ellyn Civic Center, Room 301
Any individual with a disability requiring a reasonable accommodation in order to participate in a meeting should
contact The Village of Glen Ellyn ADA Coordinator, 630-469-5000, at least five (5) business days in advance of
the next scheduled meeting. All matters on the Agenda may be discussed, amended, and acted upon.
A. Call to Order
B. Public Comment
C. Approval of Minutes
1) Motion to approve the September 10, 2025 Capital Improvements Commission
Meeting Minutes
D. Current Business
1) ADA Transition Plan Review and Approval Process
E. Trustee Liaison's Report
F. Other Business
G. Public Works Report
H. Project Report
1) Engineering Division Project Activity Report November 7, 2025
I. Adjourn
Civility Pledge - In the interest of civility, I pledge to promote civility by listening, being respectful of others,
acknowledging that we are striving to support and improve our community, and understanding that we each may have
different ideas for achieving that objective.
Page 1 of 25
Village of Glen Ellyn
Meeting Minutes
Village of Glen Ellyn
Capital Improvements Commission
September 10, 2025
7:00 PM
Glen Ellyn Civic Center Room 301
Board or Commission: Capital Improvements Date: September 10, 2025
Meeting: Regular Called to Order: 7:00 p.m.
Quorum: Yes Adjourned: 9:32 p.m.
Member Attendance:
Rocco Zucchero Chair Present
Joel Baldin Commissioner Present
Tom Drapinski Commissioner Present
Orion Galey Commissioner Present
John MacDonald Commissioner Present
Adil Saeed Commissioner Absent
David Warnick Commissioner Present
Jill Ziegler Commissioner Present
Donna Jean Simon Trustee Liaison Present
Richard Daubert Staff Liaison/Professional Engineer Present
Also Present:
John Hubsky Public Works Director
Derek Peebles Assistant Village Engineer
A. CALL TO ORDER
The September 10, 2025 meeting of the Capital Improvements Commission was called to order by
Chairman Zucchero at 7:00 p.m. at the Glen Ellyn Civic Center.
B. PUBLIC COMMENT – None
Page 2 of 25
Capital Improvement
September 10, 2025
Meeting Minutes | 2
C. APPROVAL OF MINUTES
APPROVAL OF AUGUST 13, 2025 CAPITAL IMPROVEMENTS COMMISSION
MEETING MINUTES
MOTION TO APPROVE THE AUGUST 13, 2025 CAPITAL IMPROVEMENTS
COMMISSION MEETING MINUTES
MOTION BY: Commissioner Ziegler
SECOND BY: Commissioner Warnick
AYES: Zucchero, Baldin, Drapinski, Galey, MacDonald, Warnick, Ziegler
RESULT: APPROVAL
D. CURRENT BUSINESS
1. 2026-2030 Capital Improvement Plan and 2026 Capital Improvements Budget
Engineer Daubert reviewed the CIP and 2026 Capital Improvements Budget
presentation with the CIC, noting that the plan spans 2026 through 2030 and totals
$140 million in expenditures. Of this amount, $98 million is designated for capital
improvements, primarily roadway projects, $15 million is allocated for debt service
payouts, and $27 million is for water and sewer fund projects. Trustee Simon asked
what is included in the debt service, and Daubert explained that it covers the Civic
Center Remodeling, the Civic Center Parking Garage, the Central Business District Streetscape
and Utility Improvements, and the Metra/Phase 4 Streetscape and Utility Improvements.
Daubert further explained that the plan assumes approximately $38.5 million in grants,
including $33.9 million for the Metra Station, Underpass, and Crescent Boulevard
improvements and $4.6 million for the Street Rehabilitation Program. The plan also
includes an additional $9 million in general obligation bonds, structured to remain
under $10 million in order to secure a better interest rate. Daubert noted that this level
of bonding will be scrutinized by staff and the board. Projections show that even with the
$9 million in bonds, the fund balance is expected to be $330,000 in the red by 2029,
although the fund does recover over time. He added that additional revenue could come
from TIF funds or other village resources and that many project costs have historically
come in below the original estimates.
Daubert reported that major contributors to the 2025–2029 Capital Fund balance
include the Metra Station/Streetscape Phase 4 at approximately $47 million with $34
million in outside funding, the Street Program including construction and engineering at
approximately $35 million with $3.4 million in outside funding, the Traffic Signal
Modernization at approximately $2.6 million, and the Roosevelt Road Streetlight Fixture
Replacement and Streetscape Design at approximately $3.4 million. He also reviewed
the major contributors to the Water and Sewer Fund balance, which include water main
replacement and rehabilitation at approximately $14 million and the lead service line
replacement mandate at approximately $5 million.
Page 3 of 25
Capital Improvement
September 10, 2025
Meeting Minutes | 3
Daubert emphasized that the board has been primed on these issues and that
discussions will continue over the next year. He added that the village will continue to
explore grant opportunities, PCI surveys to guide street rehabilitation timelines, water
and sewer system improvements, future bond financing, project engineering, and
revenue reviews, particularly with regard to water and sewer rates.
Next, Engineer Daubert reviewed the 2026 Capital Project Budget, which includes $15.1
million in capital projects, $4.8 million in water projects, and $2.5 million in sewer
projects. He also provided an update on the 2025 major roadway, water, sewer, and
engineering design projects. Daubert then highlighted the 2026 miscellaneous initiatives
and expenditures, which include the Stormwater Drainage Program at approximately
$10,000, street lighting replacement at approximately $116,000, professional services
such as traffic counts and topographic surveys at approximately $10,000, engineering
software at approximately $6,500, and a speed limit adjustment study and associated
signage, each budgeted at $35,000.
Daubert noted that the speed limit items reflect ongoing discussions at the board level
regarding the possibility of lowering residential speed limits. While there appears to be
interest from the board, it is not yet clear what direction will ultimately be taken. The
budget anticipates the cost of a study, as well as the signage that would be required if
speed limits are reduced. He added that any change would also require consideration of
enforcement measures. Trustee Simon commented that pending state legislation could
mandate reducing residential speed limits to 20 MPH, and the board should consider
this possibility before committing to spending. Daubert confirmed that staff has been
asked to issue an RFP for a speed study and stated that the CIC would be included in
that process.
Commissioner MacDonald expressed concern about spending $70,000 if safety is not
clearly an issue with respect to speed, noting that other factors, such as rolling stops or
drivers ignoring stop signs can also contribute to hazards. He cautioned against being
shortsighted and suggested that enforcement may be a more effective solution. Daubert
responded that a more productive outcome would be for the CIC to recommend
broadening the scope beyond speed alone, by reviewing high-incident areas and
determining whether speed or other factors are the primary cause. Trustee Simon added
that residents have already brought safety concerns to the board, which is why a study
has been requested to gather data on the root causes. Chairman Zucchero noted there
is value in looking at the data, adding that many streets could potentially qualify for
reduced speed limits. He explained that while a speed study would not be a heavy lift, a
broader safety study may be, in light of all the projects already underway. Engineer
Peebles added that funding opportunities, such as Safe Routes to School funds, may
help support the initiative, and although staffing is limited, it remains an important
priority.
Engineer Daubert asked the commission if there were any comments or concerns
regarding the 2026–2030 Capital Improvement Plan or the 2026 Capital Improvements
Budget. Chairman Zucchero stated that he was comfortable with the plan as presented.
Commissioner Galey suggested exploring project contingencies to address the projected
$330,000 shortfall.
Page 4 of 25
Capital Improvement
September 10, 2025
Meeting Minutes | 4
Commissioner Baldin motioned to approve the 2026-2030 Capital Improvement Plan and 2026
Capital Improvements Budget; Commissioner MacDonald seconded the motion. The motion
unanimously passed.
MOTION TO RECOMMEND TO THE GLEN ELLYN VILLAGE BOARD THE APPROVAL
OF THE 2026-2030 CAPITAL IMPROVEMENT PLAN AND 2026 CAPITAL BUDGET
ITEMS
MOTION BY: Commissioner Baldin
SECOND BY: Commissioner MacDonald
AYES: Zucchero, Baldin, Drapinski, Galey, MacDonald, Warnick, Ziegler
RESULT: APPROVAL
2. Metra Station Warming Shelter Followup
Engineer Daubert provided a follow-up on the Metra station warming shelter project, noting he
had received updated cost information from CDM Smith the previous Friday. To help reduce
overall project costs, the current plans are being reconsidered. The original design called for two
elaborate brick and mortar warming shelters, but the inbound shelter is now proposed for
elimination. Passengers would still have access to a covered area at the end of the depot, along
with on-demand heating mechanisms.
On the outbound side, the question remains whether to maintain the originally proposed ornate
brick and mortar structure or to simplify it with a prefabricated structure would result in further
cost savings. Daubert presented an image of the revised shelter concept, explaining it would be a
prefabricated structure with lighting and on-demand heat, but not fully enclosed. Two cost-saving
alternatives were reviewed: Alternate 1 would eliminate the inbound shelter while keeping the
ornate brick and mortar outbound shelter for a cost of $650,000, a savings of $361,000 over two
ornate brick and mortar warming shelters. Alternate 2 would provide a prefabricated outbound
shelter with on-demand heat only, at a cost of $350,000, while still maintaining a heated covered
area on the inbound side.
Commissioner MacDonald questioned the need for an outbound shelter given that none currently
exists. Daubert clarified that Metra requires a shelter for when the depot is closed with the loggia
at the end of the depot serving as the inbound shelter if it has on-demand heat. On the outbound
side, the prefabricated or brick and mortar structure would serve the shelter requirement.
Discussions advanced relative to whether or not a wind screen should be provided for the inbound
shelter area under the station loggia. Commissioner Baldin suggested evaluating the area under
the soffit on the south side of the depot for meeting the inbound shelter requirement. After further
discussion, Commissioners Galey, Baldin, Ziegler, Drapinski, Warnick, and Chairman Zucchero
expressed preference for Alternate 2, which would include the prefabricated shelter on the
outbound (south) side of the tracks and eliminate the warming shelter on the inbound (north) side
of the tracks but use the roof overhand area with on-demand heat and no windscreen. Among
other factors, the wind screen was of concern for aesthetic and functional reasons. Commissioner
MacDonald, however, preferred eliminating warming shelters entirely, relying instead on existing
covered roof areas without heat or wind protection.
Page 5 of 25
Capital Improvement
September 10, 2025
Meeting Minutes | 5
E. TRUSTEE’S REPORT – Trustee Simon provided several updates, noting that the Village is
currently in the budget process, with meetings planned through November. The Board recently
approved funding for lead service line replacements. Additionally, the Village is in the process of
filling the Trustee vacancy on the Village Board. To date, 11 applications have been received, and
several candidates have been interviewed. The appointment is at the discretion of the Village
President, with the Board able to provide input.
F. OTHER BUSINESS – None
G. PUBLIC WORKS REPORT – Public Works Director Hubsky provided several updates, noting that
the Village is still seeking to fill an Assistant Public Works Director position. In the meantime, the
team has been covering those responsibilities, and the goal is to have someone hired soon.
Preparations for winter are underway, including reviewing brine supplies, and equipment with some
new equipment expected to arrive in January. A major focus for the department is assessing space
needs at Village facilities. Staff is reviewing how neighboring communities manage access to their
yards and facilities and are conducting a facilities study to determine the village’s requirements.
H. PROJECT REPORT – Engineer Peebles provided several updates. Work on the
Crescent/Glenwood station parking lot is progressing ahead of schedule and is expected to be
completed by November 7. Full demolition is underway, and once resurfacing begins, the lot will be
fully closed. Drivers will be directed to nearby parking lots during this phase.
For the CBD Streetscape project, the team continues to press Alamp on tree replacement and concrete
brick punch list items. The 2025 Reconstruction project is also moving forward, with much of the
street resurfacing already completed.
Engineer Daubert added that progress continues on the Roosevelt Road bridge work near Baker Hill
Drive, with completion targeted for November. He also noted that the ADA transition plan is
advancing, with a consultant next scheduled to host public outreach on October 4 at 10:00 a.m. at the
fire station downtown.
I. ADJOURNMENT – Commissioner Drapinski motioned and Commissioner Galey seconded to
adjourn the meeting. The motion is unanimously approved, and meeting adjourned at 9:32 p.m.
Submitted by Elisa Pollina, Recording Secretary
Reviewed by: Richard Daubert, Professional Engineer
Page 6 of 25
Glen Ellyn Capital Meeting 11/12/2025 7:00 PM
Improvements Commission Department: Public Works - Internal Services
535 Duane Street Department Head: John Hubsky
Glen Ellyn, IL 60137 Category: Discussion Item
Prepared By: Richard Daubert
AGENDA ITEM (ID DOC ID: 2025-963
# 2025-963)
ADA Transition Plan Review and Approval Process
Statement of the Issue:
Staff is looking to consult the Capital Improvements Commission on its engagement plan for the
approval of the Village's ADA Transition Plan.
As a refresher, information on the Village's ADA Transition Plan is available
at: https://engage.cmap.illinois.gov/glen-ellyn-ada
Analysis:
CMAP and its consultant, Oates Associates, are looking to complete the Village's ADA Transition
Plan and submit it to Village staff for review within the next month. Upon staff review and
refinement, the plan will be released for public comment for a 30-day period.
As every community is handling the review and approval process slightly differently, staff is
proposing the following general process:
1. Village Staff reviews the ADA Transition Plan and works with Oates Associates/CMAP to
finalize it for the public comment period.
2. The public comment period opens with the public to review and provide input on the plan.
Concurrent with the opening of the public comment period, a short presentation is given to
the Village Board as another mechanism to communicate that the plan is open for public
comment.
3. Public comments are received, responded to, and summarized.
4. The Capital Improvements Commission offers any feedback/input on the plan, in the
context of the public comments. Ultimately, staff would be looking for a recommendation
from the Commission for the Village Board to adopt the plan.
5. The Capital Improvements Commission Recommendation is presented to the Village Board
for consideration of adoption of the plan.
Budget Impact:
Page 7 of 25
Contribution to Strategic Plan
Action Requested:
Staff is ultimately looking for any input or thoughts the Commission may have on its plan for
securing CIC recommendation for, and Village Board adoption of the Village of Glen Ellyn's ADA
Transition Plan.
Attachments:
Page 8 of 25
Glen Ellyn Capital Meeting 11/12/2025 7:00 PM
Improvements Commission Department: Public Works - Internal Services
535 Duane Street Department Head: John Hubsky
Glen Ellyn, IL 60137 Category: Report
Prepared By: Richard Daubert
AGENDA ITEM (ID # 2025- DOC ID: 2025-957
957)
Engineering Division Project Activity Report November 7, 2025
Statement of the Issue:
The November 7, 2025 Engineering Division Project Activity Report is attached for review by the
Capital Improvements Commission.
Analysis:
Budget Impact:
Contribution to Strategic Plan
Action Requested:
Attachments:
1. Engineering Project Report 11-7-25
Page 9 of 25
November 7, 2025
ENGINEERING DIVISION PROJECT ACTIVITY REPORT
CONSTRUCTION PROJECTS IN PROGRESS
CRESCENT-GLENWOOD PARKING LOT AND MEDIAN REHABILITATION –
Contractor: Abbey Construction (Value of Construction Contract = $1,208,252.93)
This project involves the resurfacing and modest reconfiguration of the parking lot along with
reconstruction of the north side median with addition of new trees and other plantings, and the
addition of new parking lot lighting.
The parking lot project is nearing completion. The median and sidewalk reconstruction is largely
complete, the 25 new trees have been planted, brick pavers have been installed, and the parking
lot has been resurfaced with new pavement markings applied. The remaining work items include
installation of the irrigation spray heads, minor remaining concrete items, installation of new
decorative street lighting, and installation of the perennial plantings. The delivery of the light
poles will likely be the last item to be completed this year due to delays with fabrication and
shipping. Current estimates for delivery range from November 21 to the first week in December.
Staff has continued to push for, and is anticipating, confirmation of the anticipated delivery date
within the next few days. The perennial plantings are planned to occur in the spring.
Parking lot just after resurfacing and application of new pavement markings
Page 1 of 16
Page 10 of 25
2025 MFT/Rebuild Illinois Street Resurfacing Project – Contractor: A Lamp Concrete
Contractors
(Project No. 25001; Value of Construction Contract = $3,052,075.77)
This project involves utility and roadway were generally at or slightly under the award
improvements along approximately 2.4 amount however, base patching and sodding
centerline miles of streets shown in the were far under the award amount and
location map to the right. The project was compromise approximately $200,000 of the
awarded to A Lamp Concrete Contractors at savings.
the February 24 Village Board Meeting.
Substantial completion is required by August
29th
The contractor has divided the project area
into three phases, with the Anthony-Cottage-
Newton plus Evergreen area being phase 1,
the Hillside-Montclair-Annandale area
streets being phase 2, and the Arlington-
Regent area being phase 3.
Asphalt surface was paved on Evergreen
Avenue the week of June 9th and sodded in
early July. Asphalt surface paving work was
completed in the Phase 2 & 3 areas the week
of August 18th, prior to school activities. The
project was substantially completed,
including sodding, in September and is now
proceeding to closeout. The contract is
anticipated to be closed out approximately
$438,700 under the awarded amount.
Providing some context, many pay items
2025 UTILITY AND ROADWAY IMPROVEMENTS PROJECT DESIGN – Contractor: John
Neri Construction Company
(Project No. 25002; Value of Construction Contract = $4,568,404.95)
The contractor substantially completed all utility, concrete curb and flatwork, parkway restoration,
and street paving work within the Grandview/May/Revere/Lowell/Valley area of the project in
September. Underground work was completed on Traver in early October, with roadway building
being completed throughout October. Melrose and Traver were then paved by the week of October
27th and sodding was completed by October 31st. Punchlist work is now underway, so that the
project can be wrapped up well before the end of the construction season. The project is projected
to be closed out below the contract amount, with the exact amount depending on agreements to
final quantities and force account items.
Page 2 of 16
Page 11 of 25
CBD STREETSCAPE AND UTILITY IMPROVEMENTS – Phase 1 – Contractor: A Lamp
Concrete Contractors
(Project No. 15006; Value of Construction Contract = $5,704,293)
Minor remaining items in the Phase 1 area include: completion of a remaining electrical item at
504 Hillside (in coordination with ComEd and Nicor), and replacement of concrete around the
trench drain behind Fire & Wine. These items are targeted to be completed this year as part of
final closeout of the Phase 1 project.
The other big item in the Phase 1 area is the sanitary sewer replacement, storm sewer work, and
pavement reconstruction in the Main Street alley (west of Main, south of Duane). As per previous
communication, this alley work was not part of the original Phase 1 construction contract, but was
an add-on item in response to the inability to line the alley sanitary sewer as part of the Phase 1
work. At their September 8th meeting, the Village Board approved awarding of the construction
contract to the low bidder, R.W. Dunteman Company ($269,403.93).
Construction on the alley started the week of October 6th with sawcutting, removal of the existing
concrete pavement, and beginning of the underground excavation. While the underground work
was anticipated to be completed within 2-3 weeks, there have been complications with the planned
installation of new storm sewer. During design there were several attempts at televising the
existing sanitary main by the Village and two different contractors, using various equipment.
However, due to small six-inch pipe size and various alignment changes it was not possible to
televise various segments. In addition, surface location of the underground lines was complicated
by the overhead power lines interfering with the sewer location equipment signal. As a result, the
final sewer and sewer service locating had to be left to the construction phase, with potholing.
However, the potholing itself proved insufficient due to the discovered proximity of the existing
lines to the ComEd utility poles. Even with bracing, ComEd would not allow excavation within
proximity of the poles due to the depth of the existing sewer line and concerns about the long term
stability of the poles. As a secondary plan, multiple cleanouts were installed in the existing sanitary
sewer to allow for full televising of the existing line for condition and identification of all laterals.
This final round of televising was completed this week and results are being reviewed. The intent
is for underground storm sewer work to commence next week and for the new alley concrete
surface construction to follow the week after.
CBD STREETSCAPE AND UTILITY IMPROVEMENTS – Phase 2-3 – Contractor: A Lamp
Concrete Contractors
(Project No. 15006; Value of Construction Contract = $16,298,499
Staff is continuing work with the contractor to complete the remaining punchlist items for full
project closure this year. Updates on the remaining larger items are below.
• Plants – The Phase 2-3 re-plantings were completed September 12th. The irrigation
settings were tweaked multiple times and supplemental waterings performed during the
dry heat wave that followed the plantings. In addition the irrigation system were kept
running longer this year than in year’s past to help the plants get established. The plants
appear to be doing well and irrigation systems are finally being shut down and winterized
this week.
Given the variable moisture conditions that have been observed within irrigation subzones
and even within individual planters, with the ongoing assistance from Christy Truitt of the
Page 3 of 16
Page 12 of 25
Environmental Commission, the Village is also looking to coordinate with the College of
DuPage horticultural program on a student research project to collect data on the moisture
levels within individual planters to allow for refinement of the irrigation settings through
the dozens of subzones within the downtown. If successful, this data collection would
occur in the spring when the irrigation systems are reactivated.
• Concrete sidewalk/driveways – As mentioned previously, there are some areas where the
concrete surface has signs scaling and/or spalling. These are concentrated along the north
side of Pennsylvania Ave (Main to Prospect) and the west side of Main Street (Anthony to
Crescent). The bulk of the concrete replacements were completed the first two weeks of
October. There is a final round of locations to be completed; however, the Village is still
working with the contractor on dates.
• Brick pavers – As mentioned previously, there are select bricks throughout the project
area that are showing signs of deterioration. While most of the bricks are fine, some are
visibly deteriorating. After further investigation and multiple field walks with the paver
brick supplier and contractor, we have now identified select furniture zone bricks for
replacement. Due to the mixing of brick batches, the bricks for replacement are scattered
throughout the various furniture zone fields rather than being concentrated in one area like
the concrete. In some fields there are just a few bricks slated for replacement whereas in a
few concentrated areas (east side of Fire Station) most of the soldier course bricks are
proposed for replacement. The brick paver replacement is anticipated to start next week
and be completed within a week.
2024 UTILITY AND ROADWAY IMPROVEMENTS – Contractor: John Neri Construction
(Value of Construction Contract = $13,148,961)
Construction was largely completed last November. As part of the punchlist, portions of Forest
Avenue and High Avenue were re-paved at the Contractor’s expense to address some deficiencies
the week of August 11th. A handful of remaining work items including isolated sod placement,
landscaping installation, and culvert epoxy injection at Glen Crest creek were completed this
spring. Various landscaping items were completed this month, with a deadline being set for
November 14th.
OTHER AGENCY PROJECTS
Butterfield Road Reconstruction (IDOT)
The State continues to advance its project to reconstruct Butterfield Road from 700 feet west of
Arboretum Drive to I-355. The project involves complete reconstruction of IL-56 with the end
deliverable being 3 through travel lanes in each direction from Route 53 to IL-355. The
intersection of IL-56 and IL-53 will also be improved with all approaches to the intersection to
have dual left- turn lanes and exclusive right-turn lanes. The intersection improvements will
extend north and south along IL-53 with the State continuing to work through the design process
for future reconstruction of IL-53 down to Park Boulevard.
The project will also include the construction of a 10-foot-wide shared use bicycle path on the
north side of IL-56 between Arboretum Drive and Lloyd Avenue. As part of the shared use path
Page 4 of 16
Page 13 of 25
construction, a new pedestrian bridge will be constructed over the East Branch of the DuPage
River. New sidewalks will also be constructed along the west side of IL-53 from the southern
Walmart entrance to Pinegrove Court and along the south side of IL-56 from the Abbington to
IL-53.
The Contractor has been working on widening the north side of Butterfield Road with temporary
pavement which will allow staging of future traffic to the outside lanes of Butterfield Road.
Utility relocations continue to be a controlling item in advancing the roadway reconstruction
work. However, the construction team is hopeful that work will be able to be started on the
bridge over the East Branch in the coming months.
Roosevelt Road Bridge Repair (Over IL-53/West of Baker Hill Drive (IDOT)
This IDOT project involves reconstructing the joints at each end of the bridge, partial and full
depth bridge deck and abutment repairs, overlaying the bridge with a latex modified concrete,
asphalt overlay of ~40’ of the concrete pavement approaching the bridge, sidewalk replacement,
railing/fencing replacement, guardrail replacement, and other various items of work.
Per the original project schedule, there was generally anticipated to be approximately two weeks
work on the south side of the bridge (Stage 1), then two weeks in the middle (Stage 2), and two
weeks on the north side of the bridge (Stage 3), with traffic diverted around the work zone in
each stage. With project completion in mid to late July.
However, during Stage 1 removals, an issue was identified with the bridge joint that required
evaluation and re-design through various divisions of IDOT. As a result, the project was stuck in
Stage 1 (south side work zone). A resolution was finally approved through IDOT at the end of
July, which allowed the project to again move forward. The project moved into Stage 2 (middle
lanes work zone) on August 28th and Stage 3 on September 17th. Stage 3 work is now nearly
complete and there will be a series of individualized lane closures for remaining work. The
latest anticipated project completion date offered by IDOT is the week of November 17th.
Route 53 Resurfacing from Bemis Road to ~ 400’ south of Pershing Avenue (IDOT)
This IDOT project consists of pavement patching, milling of the asphalt surface, placing new
binder and surface course, replacing aggregate shoulders with asphalt shoulders, drainage
structures adjustment and cleaning, placement of pavement markings, sidewalk ADA
improvements, detector loops replacement, and incidental and collateral work necessary to
complete the improvement.
IDOT let the project on June 13, 2025 with award of the project to R.W. Dunteman Company. A
pre-construction meeting was conducted on August 19th. The project is underway with
substantial completion anticipated in advance of the Thanksgiving holiday.
Page 5 of 16
Page 14 of 25
Route 53 Resurfacing from Baker Hill Drive to just south of Saint Charles Road
This IDOT project consists of pavement patching, milling of the asphalt surface, placing new
binder and surface course, replacing aggregate shoulders with asphalt shoulders, drainage
structures adjustment and cleaning, placement of pavement markings, sidewalk ADA
improvements, detector loops replacement, and incidental and collateral work necessary to
complete the improvement.
IDOT submitted final plans for this project to Village staff on October 4, requesting that the
Village review said plans for utility conflicts and other applicable feedback. Staff provided
comments back to IDOT on October 30th. The project is scheduled to be competitively bid by
the State in January with construction planned for 2026. However, staff did comment to the
State that they should consider coordinating this project with the Route 53/Spring Traffic Signal
Installation project noted below.
Route 53/Spring Avenue Traffic Signal Installation and APS Pushbuttons at IL-38/Nicoll
(IDOT)
IDOT was working through the design of a project involving the replacement of the temporary
cable hung (trombone) traffic signal equipment at Route 53 and Spring Avenue, along with the
replacement of the the pedestrian pushbuttons at IL-38 and Nicoll Way/Ave with Accessible
Pedestrian Signal (APS) pushbuttons. However, the two elements of the project were split into
two separate projects.
The Route 53/Spring Avenue project is still in design. The project proposes to install all new
permanent traffic signal equipment including a new controller cabinet and electrical service, post
and mast arm mounted signal heads, accessible pedestrian signals, and sidewalk ADA
improvements. The State is reviewing Village staff’s request that the project be communicated
to residents within a logical vicinity of the intersection of 53/Spring. Staff provided sample
notification letters to IDOT along with a phone conversation as to outline communication
expectations.
Meanwhile, the IL-38/Nicoll Way/Ave APS project was folded into another traffic signal
modernization contract with four other intersections around the region and is scheduled for a
September 19th bid opening. APS pushbuttons provide non-visual walk and don’t walk
indications (audible and vibrotactile) for visually impaired individuals. IDOT let the signals
contract on September 19th. Based upon conversation with the IDOT project manager, the
lowest bid was higher than the estimated cost, but IDOT is planning to award the bid. Work is
anticipated to begin in Spring of 2026 with 95 working days. However, since much of the work
is signal related and not involving surface or underground excavation, it is possible that the
contractor could get an early season start on the project. Village staff have asked to be included
in the pre-construction meeting once it is scheduled.
Page 6 of 16
Page 15 of 25
East Branch DuPage River Trail (DuPage County)
DuPage County is leading this exciting project involving the construction of a regional north
south bike-ped trail with Christopher B. Burke Engineering Limited (CBBEL) completing the
preliminary engineering work for the project. Information on the project can be found at
www.ebdrt.com. Staff from DuPage County, Glen Ellyn, Glenbard Wastewater Authority
(GWA), Lombard, DuPage County, and CBBEL recently met to discuss the project status as well
as to review specific technical aspects of project.
ENGINEERING PROJECTS
2026 UTILITY AND ROADWAY IMPROVEMENTS PROJECTS – Engineer: AECOM
This project involves the rehabilitation of approximately 4.6 centerline miles of Village Streets.
The scope of work varies from resurfacing to complete street reconstruction including the full
gamut of underground sewer and water infrastructure. Preliminary plans, specifications, and cost
estimates are under review by staff.
LAMBERT ROAD FEDERAL AID PROJECT – Engineer: AECOM
This project involves the rehabilitation of approximately 1.5 miles of Lambert Road between the
southern Village Limit (Near Woodcroft Drive) and Lambert Road. The scope of work generally
includes spot sidewalk replacement, spot curb replacement, driveway approach replacement,
milling and resurfacing of the roadway, line striping, installation of recessed pavement reflectors,
and parkway lawn restoration. The Village has secured $1,201,306 in Federal Funding for
Construction and Construction Engineering Services for the project. Construction Engineering
Services were procured through a Qualification Based Selection Process with Primera Engineers
retained for the assignment in an amount not-to-exceed $126,244.
IDOT conducted the bid opening for the project on November 7, 2025 with the apparent low bid
being submitted by K-Five Construction Corporation of Westmont, Illinois in the amount of
$1,759,308.62. Bid results are summarized as follows:
Lambert Road Bid Opening 11/7/2025
Contractor Bid Amount
K-Five Construction Corporation $1,759,308.62
Schroeder Asphalt Services, Inc. $1,932,776.35
Everlast Blacktop, Inc. $1,938,381.94
R.W. Dunteman Company $1,940,500.00
Plote Construction, Inc. $1,991,036.21
A Lamp Concrete Contractors, Inc. $2,114,907.00
At the time the joint funding agreement was presented to the Village Board (September 22, 2025),
staff estimated the project bid would be $2,100,000 ($2,226,244 with construction engineering).
Page 7 of 16
Page 16 of 25
The total of the Construction Contract Bid of $1,759,308.62 and the Construction Engineering
Agreement of $126,244 is $1,885,552.62. While the Village’s grant for Lambert Road is
$1,201,306 the grant cannot exceed 60% of the cost for construction and construction engineering;
hence the grant is effectively reduced to $1,131,331.57. This means the Village’s share for
construction and construction engineering as bid will be $754,221.05. The as-constructed contract
value and Village share will deviate as they are based on the actual work performed in the field.
At the time the joint funding agreement was presented to the Village Board, it was estimated that
the Village’s share for the project would be $1,024,938 (i.e. as bid amount is ~$270,717 lower).
Staff accordingly deems the bid acceptable and consistent with the joint funding/engineering
agreement memo and board presentation, staff will direct the State to award the contract to K-Five
as the bid was not objectionable.
RIFORD ROAD FEDERAL AID PROJECT – Engineer: AECOM
This project involves the rehabilitation of approximately 0.5 miles of Riford Road between
Crescent Boulevard and St. Charles Road. The scope of work generally includes spot sidewalk
replacement, spot curb replacement, spot driveway approach replacement, milling and resurfacing
of the roadway, line striping, and parkway lawn restoration. The Village has secured $338,788 in
Federal Funding for Construction and Construction Engineering Services for the project.
Construction Engineering Services were procured through a Qualification Based Selection Process
with Primera Engineers retained for the assignment in an amount not-to-exceed $81,700.
IDOT conducted the bid opening for the project on November 7, 2025 with the apparent low bid
being submitted by Schroeder Asphalt Services of Huntley, Illinois in the amount of $603,175.13.
Bid results are summarized as follows:
Riford Road Bid Opening 11/7/2025
Contractor Bid Amount
Schroeder Asphalt Services, Inc. $603,175.13
Everlast Blacktop Inc. $611,004.07
R.W. Dunteman Company $622,700
K-Five Construction Corporation $643,460.20
A Lamp Concrete Contractors, Inc. $668,977.13
Plote Construction, Inc. $767,227.19
At the time the joint funding agreement was presented to the Village Board (September 22, 2025),
staff estimated the project bid would be $600,000 ($681,700 with construction engineering).
The total of the Construction Contract Bid of $603,175.13 and the Construction Engineering
Agreement of $81,700 is $684,875.13. Subtracting the grant amount of $338,788, the Village
share for the project as bid, including engineering, is $346,087.13. The as-constructed contract
value and Village share will deviate as they are based on the actual work performed in the field.
At the time the joint funding agreement was presented to the Village Board, staff estimated that
the Village’s share for the project would be $342,912 (i.e. as bid amount is ~$3,175 higher). Staff
accordingly deems the bid acceptable and consistent with the joint funding/engineering agreement
memo and board presentation, staff will direct the State to award the contract to Schroeder Asphalt
as the bid was not objectionable. Having said this, staff has had a conversation with DuPage
Page 8 of 16
Page 17 of 25
Mayors and Manager’s Conference about potentially securing additional Surface Transportation
Program Funding for the project. With the bid amount now affirmed, staff will submit a formal
request for additional ~$72,000 in funding for the project.
HILL AVENUE UTILITY IMPROVEMENTS – Engineer: Walter E. Deuchler Associates
(Project No. 00511)
This project involves the construction of sanitary sewer and water distribution system
improvements on Hill Avenue between Golf Avenue and the East Branch of the DuPage River.
The improvements will ultimately result in the Village’s water main being continuous and looped
along both Hill Avenue and Crescent Boulevard. Also, this will allow the Village to serve the
fronting properties on Hill Avenue with potable water service.
Easement documentation was prepared for the Elliot Construction property with the documents
signed by the respective party. A similar easement is needed on the north side of Hill Avenue;
staff has met with the property owner to review draft easement documents. Most recently, staff
evaluated an alternative corridor that the property owner requested and a follow up meeting was
held with the property owner and his attorney to discuss the complications of an alternative
alignment for the utilities. Having said that, staff was able to identify and opportunity to reduce
the footprint of the easement which was of interest to the property owner. Next step is to revise
the design plans to align with the revised easement. Other various comments will also need to be
addressed by the Engineer. This will allow the project design to ultimately be finalized, easements
secured, permits amended or refreshed, and project to be competitively bid.
TRAIN STATION / PEDESTRIAN TUNNEL – Engineer: CDM Smith/KMI Architects
(Project No. 16016)
The Phase 1 Engineering Project Development Report (PDR) has been amended to update the
project environmental clearances, incorporate the Section 106/4(f) approvals, incorporate the most
recent crash data, incorporate and execute the required design exceptions, etcetera. The assembled
PDR was transmitted to IDOT on 10/24 with a hard copy delivered to District 1 on 10/27.
With the PDR Submitted to IDOT, staff also transmitted the Phase 2 Engineering 90% plans to
IDOT for their review.
Land Acquisition is underway with most recent work including a questionnaire and informational
meeting with the next stop coffee shop owner. Development of plats and legals for the project
components on UP property will be the next focus.
Staff will begin drafting the ICC petition for the pedestrian underpass component of the project
and work with the State to advance the petition process.
TRAFFIC SIGNAL MODERNIZATION PROJECT – Engineer: AECOM
(Project No. 23006)
Work is underway on design of the improvements to the six Village-owned traffic signals,
consistent with the 2024 Recommendations Report created by AECOM. While work on the six
Village-owned traffic signals is to be spread over three years (2026-2028), initial design on all six
Page 9 of 16
Page 18 of 25
signals is being conducted this year. The target intersections for each construction year will be
part of each year’s budget discussions.
The AECOM contract also provides for optimization of the Village intersections in 2025. Traffic
counts, using video detection technology, were conducted the week of May 12th, before schools
let out for the year. AECOM is now using these counts to model the intersection operations and
determine optimal timings for each location.
On Thursday, July 24th, the traffic signal cabinet at the Lambert/Fawell intersection sustained
damage from a lightning strike. As a result, the signals are currently operating in a pretimed pattern
that is less efficient than the former actuated, traffic responsive mode. The intersections of
Lambert/Tallgrass and Lambert/College, while not damaged by the lighting, are part of an
interconnect with Lambert/Fawell and are therefore also affected to a degree.
The surge damaged much of the equipment in the cabinet. Temporary equipment is currently in
place allowing for basic signal operation. However, given the age of the cabinet and equipment,
replacements for some of the equipment are not readily available and new equipment is not
compatible with some of the older systems.
Given the state of the existing equipment along the corridor, and in light of the lightning damage,
the Lambert corridor signal modernization work is being proposed for the first round of signal
improvements, to be completed in 2026. In addition, the Village is working with Meade Electric
on the potential advance replacement of the Lambert/Fawell cabinet which is currently operating
with some loaned equipment and there are concerns about reliability of existing lightning exposed
equipment.
ADA PUBLIC RIGHT-OF-WAY TRANSITION PLAN – CMAP TECHNICAL ASSISTANCE
– Project Partner: Chicago Metropolitan Agency for Planning (CMAP)
In March of 2024, Public Works applied to CMAP for assistance with creation of its federally-
required ADA Transition Plan, as part of CMAP’s 2024 Technical Assistance Call for Projects.
Out of a competitive process (122 applications submitted, 30 awarded), the Village was selected
to receive assistance.
Since the last update, Village staff met with the consultant and were given a preview of the lidar
survey data of the sidewalks in the Village. The data dashboard allows for weighting of curb ramp,
cross-slope, running slope, and vertical displacement deficiencies in order to develop priority areas
for sidewalk improvements. The consultant recently secured direct access to the data dashboard
for Village staff to perform additional review.
As part of the public outreach, the Village, CMAP, and the project consultant staffed a table at the
October 4th Fire Open House, to publicize the planning effort and solicit additional feedback from
residents. Given the popularity of the Fire Open House, a lot of people were reached by having the
table set up. In addition, CMAP provided sticker and hang tag reflectors as a giveaway to help
raise awareness of the importance of pedestrian visibility at night as part of the overall safety
equation.
Page 10 of 16
Page 19 of 25
The next Steering Committee meeting is being held on November 7th and will include revisiting
of the prioritization discussion started at the last Steering Committee meeting.
Next step will be to marry the locational priority and defect priority schemes to arrive at an overall
priority for various sidewalk accessibility improvements throughout the Village. The consultant
will also be establishing rough costs for addressing defects identified through the sidewalk survey
and working with the Village on defining a program for addressing the deficiencies in future years.
The overall plan is to be wrapped up by February of 2026.
WATER DISTRIBUTION SYSTEM STUDY – Engineer: Christopher B. Burke Engineering
Limited (CBBEL)
This project involves the development of a model of the Village’s water distribution system which
will be used to optimize operation of the system as well as identify and confirm needed capital
improvements. The model and a technical report will be the ultimate deliverables of the
assignment. Through a competitive RFP Process, staff identified CBBEL as the best firm for the
completion of the assignment. The Village Board approved an agreement with CBBEL on January
27 th.
The consultant has completed the initial modeling of the Village’s pipe network and water
facilities. Hydrant flow testing, conducted at eleven locations the week of May 5th, was used to
help calibrate the model. Public Works staff met with CBBEL on July 1st to review preliminary
results. There was significant discussion around the areas of four-inch watermain in the Village
that result in reduced fire-flow volumes, and are a likely first priority for replacement. The
consultant has been focusing on updating the model to incorporate the Village’s most current GIS
data on the water distribution system along with recently completed upgrades to the water
distribution system. A draft report for the study is anticipated from CBBEL by November 13th.
CONSTRUCTION MAINTENANCE PROGRAMS
Public Works seeks the best vendor prices for various annual municipal and utility maintenance
and operations activities. This effort includes local bidding of projects or joint purchasing
initiatives, including the Municipal Partnering Initiative (MPI), a consortium of DuPage County
communities.
2025
Project Estimated Status
VGE Cost*
The project scope includes roadway patching throughout the Village.
Locations were determined by staff utilizing both the Village’s 2024
Pavement Management System Data and field inspections. This program had
2025 Asphalt a February 26th bid opening and R.W. Dunteman provided the low bid of
$202,000
Roadway Patching $188,630. R.W. Dunteman was awarded the contract at the March 10th Board
Meeting for the full bid amount. Work was completed on October 20th. Major
areas that were addressed were Duane Terrace, Buena Vista, and the Derby
Glen neighborhood.
Page 11 of 16
Page 20 of 25
2025
Project Estimated Status
VGE Cost*
The 2025 Crack Sealing program targets candidate locations using Pavement
Condition Index (PCI) Study data and visual inspections. The 2025 budget
for the program is $45,000. Bids were opened on February 12th with Denler,
2025 Crack Sealing $39,237 Inc. providing the low, responsible, and responsive bid of $33,700. Denler,
Inc. was awarded the contract at the March 10th Board meeting in the not-to-
exceed amount of $40,000, which resulted in $5,000 in savings in the Capital
Projects Fund. Denler completed the crack fill work on 9/16.
This annual program includes repairs to deteriorated or damaged sidewalk
and concrete roadway infrastructure and the installation of new sidewalk
throughout the Village. The low bidder, Schroeder and Schroeder (S&S),
was awarded the contract at the March 10th Board Meeting in the not-to-
exceed amount of $398,620. The brick crosswalk removals at Main Street &
St. Charles and Main St. & Elm St. were completed over the weekend of
October 17th. Crews put in place a large detour so they could excavate the
2025 Sidewalk and roadway on Friday evening and return on Saturday morning to pour concrete.
$400,000
Concrete Street PW was appreciative of the coordination efforts made by the County,
Repairs Schroeder, Meade, Gewalt Hamilton, the Police Dept., the Streets Division,
and the area residents and businesses. Schroeder is currently working in the
Village and will complete the last phase of the program by November 14 th.
Major intersection improvements were made at Lorraine & Kenilworth and
Lenox & Oak, in addition to a large number of concrete street repairs on
Fawell, and numerous sidewalk and curb replacement throughout the
Village. Modified urethane pavement markings will be installed during the
3rd week of November.
Page 12 of 16
Page 21 of 25
2025
Project Estimated Status
VGE Cost*
Staff proposed using Safe Step to evaluate sidewalks for trip hazards in three
areas (the Derby Glen neighborhood, the Surrey/Briar neighborhood, and
Revere Rd between Main and Park Blvd.) based on the defect identification
criteria that Safe Step and the Village developed together. Safe Step’s
patented process uses waterless saws, which eliminates slurry and water
runoff contamination, and a dust-abatement system designed to capture fine
dust. Safe Step makes sawcut repairs tapered to a 1:12 slope ratio with a
smooth, uniform finish and are ADA-compliant. Safe Step was awarded a
contract at the April 14th Board Meeting. In May, Safe Step surveyed three
Sidewalk Sawing areas and provided a report with locations, descriptions, suggested repair
$35,842
Repair Program types, and photos of each identified defect. The Village reviewed the data
and gave the go-ahead to Safe Step to make 393 sawcut repairs. Several
locations with more severe defects were recorded by Safe Step and added to
the Village’s sidewalk removal and replacement list. The sidewalk
sawcutting work was completed in mid-July. The Village received positive
feedback via email from a resident in the Surrey neighborhood who
complimented the construction workers on their professionalism and
neatness and thanked the Village for making repairs in the area.
This program allows Public Works to use one contractor to restore Village
right-of-way following in-house utility repairs instead of relying on the
availability and coordination of the Village’s separate concrete and asphalt
contractors. The program requires the contractor to make up to three
mobilizations throughout the construction season. The contractor must be
2025 Utility capable of doing full-depth concrete and asphalt pavement patches, and
Pavement $74,557.33 concrete sidewalk, driveway, and curb and gutter repairs. Bids were opened
Restoration on February 26, 2025, with the low bid being provided by G.A. Paving, of
Bellwood, IL, in the amount of $58,340, which was just under the 2025
budget of $60,000. G.A. Paving was awarded the contract at the March 10th
Board Meeting. As of June 20th, approximately $74,000 worth of right-of-
way restorations were needed so the Village Manager approved a change
order increasing the amount of the contract by $16,500. The increased
number of water main breaks last winter, which was experienced by
Page 13 of 16
Page 22 of 25
2025
Project Estimated Status
VGE Cost*
municipalities across the Chicagoland area, and numerous 50/50 sewer cost
share projects and lead service investigations accounted for the need for
more right-of-way restorations than were originally estimated. Last year,
G.A. Paving completed eight restorations for the Village. In 2025, G.A.
Paving made twenty-seven utility restorations by mid-July.
For the last fifteen years, the Village has utilized local purchasing cooperatives to
obtain competitive pricing for pavement marking work. In 2024, the Village joined
the Suburban Purchasing Cooperative’s contract and entered an agreement with the
low bidder, Superior Road Striping (SRS), to refresh pavement markings in Glen
Ellyn. SRS was overwhelmed with work demands around the region and was
unable to complete their work in Glen Ellyn before temperatures dropped too low
to meet the specifications for pavement marking installation. SRS will hold their
unit prices and complete the balance of the 2024 work this spring. After last year’s
experience with scheduling delays, staff decided to bid out this project locally in
order to have more control over project completion dates and to be higher on the
contractor’s priority list.
The bid opening was held on February 26th; Precision Pavement Marking was
the lowest bidder out of four with a bid proposal of $101,908, which was
slightly over the $100,000 budget. Precision Pavement Marking agreed to
reduced quantities to allow the Village to stay under budget; however, the total
price still came at a significant premium compared to historic cooperative
pricing. DuPage County (DPC) awarded a contract to Precision on April 8th.
Suburban Purchasing Cooperative (SPC) negotiated 2025 prices as part of a
2024 contract extension with Superior Road Striping and these unit prices
provided the most value to the Village. On April 28 th, the Board formally
rejected all of the bids from the February 26th bid opening and awarded a
contract to Superior Road Striping based on the Village’s membership in the
SPC. SRS began working on the 2025 contract on June 30 th. SRS had
2025 Pavement additional work to complete in the Village, but could not schedule their crews
$84,676 to complete the work before the end of the season so Engineering made the
Markings
decision to postpone the work in the CBD (Phase 1 area) until spring. The final
invoice to SRS will be considerably less than what the contract was approved
for.
Page 14 of 16
Page 23 of 25
2025
Project Estimated Status
VGE Cost*
Taylor pedestrian tunnel.
The annual line striping contract was awarded to Superior Road Striping
(SRS), the low bidder of both the DuPage County and Suburban Purchasing
Cooperative contracts, on April 22, 2024, in the not-to-exceed amount of
$100,000. SRS began pavement marking in October 2024, but could not
complete the Village’s worklist due to weather delays and SRS’workload.
They finished installing modified urethane pavement markings in early June
2024 Pavement and completed the 2024 thermoplastic work on June 30th.
$81,842*
Markings
The Streets Division refreshed pavement markings using paint in various
locations, including the handicap symbols in all of the Village-owned parking
lots. The Streets Division’s 2024 budget for paint materials was $5,000.
*The Village paid Superior Road Striping $17,912.39 for work completed in
2024; the P.O. was carried over and Superior was paid an additional
$63,929.16 for work completed in 2025.
Candidate locations include streets that have been resurfaced one to three
2025 Asphalt
years prior. On August 25th, 2025, the Board awarded a contract to single
Surface $90,000
source vendor Corrective Asphalt Materials (CAM), who extended MPI joint
Rejuvenation
bid unit prices to the Village. Work was completed on October 23rd.
The 2025 program will provide for sanitary sewer lining and repairs
2025 Sanitary Sewer
$200,000 throughout the Village including within the Street Improvements Project
Lining and Repairs
Areas. The proposed budget for this program is $200,000.
*All costs are rounded to nearest dollar.
OTHER ENGINEERING ITEMS
Successful Grant Pursuit
In May of 2025, staff applied for IDOT’s 2024 Local Project Notice of Funding Opportunity
(NOFO). The NOFO specified that $400,000,000 in State Funding was available for local
transportation initiatives including highway, bike/ped, transit, passenger rail, and other
transportation projects which align with the State’s transportation priorities for improving local
assets, enhancing complete streets, and improving safety. This is a reimbursement grant with no
matching funds required.
Staff submitted five applications for:
1. Lambert Road Resurfacing with request of $500,000 for Construction/Construction
Engineering
2. Riford Road Resurfacing with request of $200,000 for Construction/Construction
Engineering
3. Illinois Route 38 Sidewalk and Street Lighting Improvements with request of $400,000 for
Preliminary and Final Engineering
Page 15 of 16
Page 24 of 25
4. Sheehan Avenue Utility and Roadway Improvements with request of $1,250,000 for
Construction/Construction Engineering
5. Metra Station and Multimodal Access Improvements with request of $10,000,000 for
Construction/Construction Engineering
Over 1,900 applications were submitted with 223 applications being selected for funding. The
Village received notice that its Illinois Route 38 (Roosevelt Road) Sidewalk and Street Lighting
Improvement Engineering Project was selected with $400,000 to be provided (reimbursed) for
Preliminary and Final Engineering. Staff has met with the State to discuss the program
requirements. To receive the reimbursement funding, the Village Board will ultimately need to
review and approve funding and engineering agreements for the assignment. The timing of this
grant is ideal in that staff was looking to advance the design of the street lighting improvements
in 2026 with sidewalk/streetscape improvement design planned to start in 2027 per the latest
CIP.
X:\Public Works\ENGINEER\Monthly Construction Reports\Engineering Project Report 11-7-25.docx
Page 16 of 16
Page 25 of 25