Public Works Committee Minutes December 13, 2011
1.0 Call to Order and Pledge of Allegiance
Meeting was called to order by Chairperson Ware at 7:03 PM.
2.0 Roll Call
Present 1 - Ken Blakeslee
3.0 Public Participation
4.0 Approval of Minutes
A motion was made by Mike Kuderna, seconded by Arthur Kuehl, that this be
approved . The motion passed by an unanimous vote.
5.0 Unfinished Business
6.0 New Business
110722 First Draft: FY 2012b-FY 2021 Capital Improvement Program
Ware: explained to the committee that the Village is changing to a calendar
year from a fiscal year. First item is FY2012b and second is FY2013.
Dratnol: reviewed memo for 110722 – FY2012B. Asked committee to hold their
questions until he completed review. Discussion ensued regarding the Salt
Dome and GIS Development project. Ware: would like to see the North
Garfield improvements in FY2012b if possible. Committee was in agreement.
Dratnol continued to review CIP memo. Further discussion took place
regarding the Train Station Underpass, Yorktown Watermain and IL Route 53
Stormwater Pump Station. Ware: would like to see a lot more information
about IL Route 53 Stormwater project – bring to the next meeting with the
second draft of CIP. Committee would like to see the final plans for the
Underpass. Ware inquired if the Route 53 project was continued in the FY2013
CIP. Dratnol responded yes. Kaforski: Terrace View pond – who is
maintaining this? Will final approved project come to this committee?
Bachner: believes that the underground utilities will be maintained by the
Village – none of the pond, the banks, etc. should be maintained by the Village.
Ware: would like to know what the responsibilities of the Village are in project.
Asked staff to bring to next meeting. Kaforski: do not see the point of
spending 100K for study (Philips Court). Why do we have to do this I & I
study? Dratnol: it is required. Ware: asked staff to provide further info on
this in the second draft. Dratnol: remember that there are 2 separate projects
here.
Kaforski: not part of the CIP, but wanted to bring to the attention staff and
committee members that there is a new chemical out there for treatment of the
Ash trees. Could staff check with Forestry Dept. about this to see if this could
be cost effective? Asked staff to bring to next meeting.
110723 First Draft: FY 2013-FY 2022 Capital Improvement Program
Village of Lombard Page 1
Public Works Committee Minutes December 13, 2011
Dratnol: reviewed memo for 110723 – FY2013. Will only be reviewing the items
that were not covered in the FY2012b memo. Kuehl: thought that the Madison
St. improvements were completed last year. Ware: not all of it. Madison is
really bad. Dratnol continued to review the projects and improvements.
Kuehl: Madison and Rte. 53 signal improvements – is that even in Lombard?
Dratnol: no but there already is an intergovernmental agreement in place.
Kuehl: s/light at the corner of Madison and Finley goes on and off.
8.0 Ratification of Item
110651 Lincoln-St. Charles Road Crosswalk, Final Balancing Change
Order No. 1
Authorizing an increase to the contract with Lorusso Cement
Contractors in the amount of $2,085.00. (DISTRICT #1)
A motion was made by Arthur Kuehl, seconded by David Arnold, that this
Resolution be recommended to the Board of Trustees for approval . The
motion passed by an unanimous vote.
9.0 Information Only
Arnold: questioning new Weight Limit signs on Grace St. just north of North
Ave. and also on Grace St. going s/b. Is there a difference between a load limit
sign posted on a bridge and a sign on a road? There is no bailout there.
Trucks going w/b on North Ave. want to make a right hand turn onto Grace –
still can’t make that turn. Asked staff to find out about these signs and bring to
next meeting or e-mail group about them. Also, s/b on Grace St. at North Ave.
after the North Ave. construction project there were changes made to the lane
markings. Asked staff to check the lane markings and signage. Is this
something that we take care of or IDOT?
Kaforski: regarding crack sealing - in both budgets there is money for this
project. My street was just done. What they are grinding out ends up shooting
on to the parkway, sidewalks and driveway aprons. Is there some sort of guard
that can be put on this machine? Also, at the s/w corner of Hickory and
Lombard – sidewalk was replaced through the sidewalk program this year.
There were some of the corners that were vandalized – and they look horrible.
Please check them and get back to committee about status.
970045 Project Status Report
980212 Change Order Report
10. Adjournment
0
Village of Lombard Page 2
Public Works Committee Minutes December 13, 2011
Ware: thanked committee members for coming out tonight right before the
holiday. Wished everyone a happy holiday.
A motion was made by John Kaforski, seconded by Arthur Kuehl to adjourn the
meeting at 8:32 PM. The motion passed by an unanimous vote.
Village of Lombard Page 3