CAPITAL IMPROVEMENTS COMMITTEE
Regular MeetingMilwaukee, WI · February 28, 2013
Minutes
200 E. Wells Street
City of Milwaukee Milwaukee, Wisconsin
53202
Meeting Minutes
CAPITAL IMPROVEMENTS COMMITTEE
ALD. NIK KOVAC, CHAIR
Ald. Robert Bauman, Ald. Michael Murphy, Ghassan Korban,
Martin Matson, Mark Nicolini, and Mariano Schifalacqua
Staff Assistant: Linda Elmer, 286-2231
Fax: 286-3456, lelmer@milwaukee.gov
Fiscal Planning Specialist: Kathleen Brengosz, 286-3926,
kbreng@milwaukee.gov
Thursday, February 28, 2013 9:00 AM Room 301-B, City Hall
Meeting called to order at 9:11 a.m.
1. Review and approval of the February 6th meeting minutes.
Minutes were approved as written.
2. Presentation of Underground Conduit & Communications Condition Report.
Individuals appearing:
David Henke, Department of Administration
Bryan Pawlak, Department of Public Works
Bob Bryson, Department of Public Works
Karen Rogney, Department of Public Works
Jeff Polenske, City Engineer
Mr. Henke presented a PowerPoint regarding the Communications system (please
see the attachment "Public Safety Communications Program PowerPoint" to Council
file 121406).
Mr. Henke and Mr. Pawlak discussed the condition of city-owned communication
cabling and public safety infrastructure. Mr. Henke began by discussing the 2013
reorganization that moved the oversight of the communications infrastructure out of
the Department of Public Works (DPW) and into the Department of Administration –
Information and Technology Management Division (ITMD).
He said that telecommunications for the City is divided into four different areas; the
data network, the phone system, the physical cable plant and the communications
conduit. ITMD is responsible for the design, installation, records, operation and
maintenance of all of the hardware that comprises the City’s data network. ITMD is
responsible for the design, records and operation of the phone system. The physical
installation and maintenance of the phone system is done by DPW. For the cable
City of Milwaukee Page 1
CAPITAL IMPROVEMENTS Meeting Minutes February 28, 2013
COMMITTEE
plant, ITMD does the design and maintains the records and DPW does the
installation and maintenance.
Mr. Henke said the City leases conduit space to 3rd party providers who install their
own cabling. ITMD manages those leases. He said that the revenue from 3rd party
leases is approximately $750,000 annually and it has been growing slowly but
steadily for several years.
Mr. Henke said that copper cable is used primarily for small, remote facility
connections such as sewer pump cabinets or traffic count stations, locations which
have low bandwidth communications needs for small specific items. Mr. Henke said
that fiber optic cable is used for the majority of the City’s network, which connects all
of the City’s major facilities.
He said that in future years, capital funding will be used to extend the network to
other facilities such as the Housing Authority, libraries, water booster stations and
smaller city buildings. Mr. Henke said that the system by design has redundant
connections for critical facilities to ensure service.
Mr. Henke said that the city phone network is comprised of two main phone systems.
One system is dedicated to the Police and Fire Departments. It serves the 911
system and all of the administrative phones for the Police and Fire Departments.
ITMD performs some administrative functions for that system on behalf of the Fire
Department. The other phone system serves the rest of the City’s facilities. Funding
is used to maintain and upgrade the phone system and the network hardware. A
major upgrade of the phone system, which began in 2012, is essentially complete.
The project included software upgrades for the phone system as well as
improvements and upgrades for the Call Center.
Mr. Henke said there are multiple construction projects planned for 27th Street; one
between St. Paul and Highland and another from the KK River to Howard Avenue.
The City will be relocating facilities in advance of those construction projects.
Installation of new cabling will also be done in 2013 in conjunction with the Zoo
Interchange project. Facilities will be restored on Capitol Drive and Morgan Avenue
following the reconstruction projects in 2012.
Mr. Henke said that the City has a large number of copper cables which are costly to
maintain. The department wants to migrate off of the copper and onto fiber optic as
much as possible to increase capacity and reduce maintenance costs. Mr. Henke
said that there are approximately 500 active repair tickets for the copper plant. 137,
112, and 79 repair tickets were added in 2010, 2011 and 2012, respectively. He said
that the department does not repair all of the reported troubles and that because the
cable plant has excess capacity, service can sometimes be moved to alternate pairs
within a cable. Over time, if the backlog of repairs continues to grow, the City will use
up the buffer provided by the excess capacity. Mr. Henke said that fiber optic cables
were damaged four times last year and three are still in need of repair. He said that
most fiber optic damage incidents are caused by contractors excavating and that his
office anticipates a couple every year.
Mr. Schifalacqua asked which department will apply for capital funding now that the
responsibility has been split between DPW and ITMD. Mr. Henke said that he would
verify which department should apply. Mr. Nicolini said that he believed ITMD would
submit the capital request. Mr. Schifalacqua said that in the past the Water
Department had a similar split of responsibilities. He said it was not very efficient and
all the functions were combined in one department.
City of Milwaukee Page 2
CAPITAL IMPROVEMENTS Meeting Minutes February 28, 2013
COMMITTEE
Mr. Bryson discussed the conduit system and the communications and electrical
conduit manholes and presented a PowerPoint regarding the underground conduit
and manholes (please see the attachment "Communications and Electrical Conduit
and Manholes PowerPoint" to Council file 121406).
He said that the conduit and manhole system provides the infrastructure that is
needed to support the communication system as well as the street lighting system
and the traffic signal system. He noted that communication cables have to remain
separate from the power lines that are used for various purposes.
Mr. Bryson said that much of the program for replacing conduit is driven by paving
projects. He said that on connecting highway projects, the cost of installing conduit is
100% federally funded. Mr. Bryson said the City has 565 miles of conduit, 9% of
which is iron pipe installed between 1888 and 1905. He said that clay tile was
installed in the early part of the 20th century and fiber was used from 1938 to 1980.
Currently the city uses PVC. Mr. Bryson said that 43% of the City’s communications
manholes are brick installed between 1888 and 1950. Block manholes were installed
between 1950 and 1980. The City switched from block to precast concrete because
of the failure rate of the block manholes, most of which were constructed without
reinforcement.
Mr. Bryson said that the City currently does not have a program to do regular
inspection of communications manholes. He said an inspection record database was
created in 1988. Currently, over half of the City’s manhole inspection reports are at
least 20 years old. Based on those records, 400 manholes need repair and 200 need
to be replaced. He said that approximately 2000 manholes are older than 75 years.
Mr. Bryson clarified that the 600 manholes that need work needed work at the time of
the inspection and there may be more manholes today that need repair or
replacement.
Mr. Bryson said that manholes are inspected prior to street reconstruction projects.
He said that 322 communications manholes were inspected last year in conjunction
with paving activities. Mr. Bryson said that conduit has an estimated life of 75 years.
He said the City would have to repair or replace roughly 100 manholes a year to keep
up with a 75-year replacement cycle.
Mr. Schifalacqua said that this committee has been interested in getting good existing
data. He asked if there was a plan for updating the condition data. Mr. Bryson said
yes. He said that Sewers currently has a program to inspect manholes on a five- to
ten-year cycle. He said the department will work jointly with Sewers to include the
inspection of communications manholes as part of their annual sewer manhole
inspection contract. Mr. Schifalacqua asked if funds would be requested for the 2014
budget to do the survey. Mr. Bryson replied that the goal was to begin the inspection
in 2013. Mr. Polenske said that the current sewer contract has some inspection of
communications manholes. He said that partnering with Sewers would give an area
wide component to the inspection program in addition to the project specific focus
currently being used.
Ald. Kovac asked how often communications manholes collapse. Ms. Rogney replied
that there were eight manholes that were replaced last year. Mr. Bryson said that the
department has been functioning on a reactive basis. He said that updating the
condition of the entire manhole system would allow them to be proactive. Ald. Kovac
asked how closely the inspection reports from 1988 identified manholes that
ultimately failed. Mr. Bryson said that he didn’t know. Ald. Kovac asked if it was
possible to find out. Mr. Bryson said yes.
City of Milwaukee Page 3
CAPITAL IMPROVEMENTS Meeting Minutes February 28, 2013
COMMITTEE
Mr. Bryson showed a picture of an old fiber duct. Ald. Kovac asked about its shape
and condition. Ms. Rogney said that when fiber duct gets wet, it’s like cardboard. It
deforms and can actually cause more problems than the older clay tile. Mr.
Schifalacqua asked if there was program to replace the fiber duct. Mr. Polenske said
no. Ald. Kovac asked why the City used fiber. Ms. Rogney replied that it was the
industry standard at the time. Mr. Pawlak said that fiber duct becomes problematic
when a cable gets damaged and has to be removed. The deformed fiber makes it
difficult to pull cable through the ducts. He said that the City does use some
Roto-Rooter type service to remove fiber from the inside of the casing. He said that
replacing the entire conduit system would have significant impacts on service and
would require a great deal of coordination. Replacement of fiber should be
considered when the opportunity presents itself, such as with paving programs. Ald.
Kovac if most of the cable troubles were caused by excavation or by natural
deterioration of the system. Mr. Pawlak said he believed it was excavation.
Mr. Froh suggested increasing external revenues to fund the repair and maintenance
of the conduit and communications manhole system. He said that it seems difficult to
get a comprehensive understanding of what is actually in the City’s ducts. He said
that 3rd party lessees weren’t very clear or forthcoming about what they had in our
system. He suggested reviewing and raising the lease rates to provide additional
funding. Mr. Pawlak noted that lease revenue does not go to DPW. Mr. Froh replied
that as long as the City received the revenue it would be a good thing.
3. Presentation of the Department of Public Works Buildings Condition Report.
Individuals appearing:
Paul Fredrich, Department of Public Works
Sean Schutten, Department of Public Works
Mr. Fredrich and Mr. Schutten presented a PowerPoint on the Facilities Condition
Assessment Program (please see the attachement "FCAP PowerPoint 2013" to
Council file 121406).
Mr. Fredrich and Mr. Schutten discussed the City buildings that are maintained by
DPW and the Facilities Condition Assessment Program (FCAP) that is used to
evaluate the condition of the buildings and forecast capital expenditures. Mr.
Fredrich said that the FCAP program involves a very comprehensive inspection of
each facility’s interior, exterior, mechanicals and site. The results of the inspection
are compiled into a database that is used to predict future capital needs.
Mr. Fredrich said that DPW is responsible for 72 buildings and 18 vacant properties.
The current replacement value is $347 million plus $10 million for the vacant
properties. The department uses information from the City Attorney’s Office relative
to the insurance on the buildings. He said that it is the State that actually establishes
the values for the buildings.
Mr. Schutten said that 30 buildings have complete FCAP reports and 29 buildings
have been inspected and are currently being processed. Thirteen buildings are
planned for 2013 and eight are planned for 2014. He said that the ten remaining
properties, some of which are vacant properties, will be scheduled when the other
buildings are complete.
Mr. Schutten said that the FCAP complies with the recommendations of various
governing agencies for different metrics that the City is using. He said the building
City of Milwaukee Page 4
CAPITAL IMPROVEMENTS Meeting Minutes February 28, 2013
COMMITTEE
inspections follow the facilities audit format of the Association of Higher Education
Facilities Officers and the National Research Council standardized inspection
process. Cost estimates are made following the recommendations of International
Facilities Management Association (IFMA). The department also uses the key
performance measure of the U.S. Department of the Interior, the Facilities Condition
Index (FCI). He said that the entire process is tied into the American Public Works
Association (APWA) recommendations for capital improvement planning and
strategizing.
Mr. Schutten said that each facility is broken down into its components; the envelope,
building interior components and building control components. He said that
maintenance is scheduled for 20 years, which is well beyond the six years that is
generally standard for capital planning. Mr. Schutten said the key performance
measure is the FCI which is an indication of what percentage of the building is
deficient. From zero to 5% deficiency is considered good, 5.1% to 9.9 % is fair and
anything greater than 10% would be considered a poor facility condition index.
Mr. Schutten said that buildings can be looked at individually, but they can also be
combined to determine the average condition of the City’s building portfolio. Mr.
Schutten presented a summary table with all the buildings that have been inspected
so far. He noted that just because a building has a good FCI it doesn’t mean no
funding will be required at that facility. Ald. Kovac asked if this was a new system.
Mr. Fredrich said that it is about 2 ½ years old. He said that three years ago, the
department made an initial attempt and then refined the process over the last 2 years
utilizing more nationally recognized standards and trying to make the system as
efficient as possible. He said that there is a team of four or five people who inspect
the buildings and process the information. He added that those employees have
other duties as well. Mr. Gupta said that the first cycle will be the most time
consuming. Once one cycle is complete the department intends to inspect 20% of
the facilities each year for a 5-year inspection cycle. Mr. Nicolini said that the FCAP
is a helpful planning tool but that it was important to look at the probability of asset
failure, how well the asset is performing and the consequences of failure. He also
said that 10% of asset replacement value qualifying as poor seems to be a fairly
rigorous standard.
Ald. Kovac asked if DPW was working with the Office of Environmental Sustainability.
Mr. Gupta said yes. He added that the Mayor’s initiative called for a 15% energy
savings by 2012. He said that DPW has reached that goal and has committed to an
additional reduction of 5%.
Mr. Fredrich said that DPW is working with other departments such as the Police
Department, the Port of Milwaukee and the Health Department. Mr. Schifalacqua
asked if DPW was working with the Fire Department. Mr. Fredrich said that DPW
has had some preliminary discussions with the Fire Department.
4. Presentation of Recreation Facilities Condition Report.
Individual appearing:
Paul Fredrich, Department of Public Works
Mr. Fredrich presented a PowerPoint presentation on the city's recreational facilities
(please see the attachment "FCAP Rec Facilities PowerPoint" to Council file 121406).
Mr. Fredrich discussed the City’s recreational facilities. He said that the City has 62
City of Milwaukee Page 5
CAPITAL IMPROVEMENTS Meeting Minutes February 28, 2013
COMMITTEE
sites on 77 acres with a current replacement value of almost $ 20 million, including 46
play structures, 21 basketball courts and 4 tennis courts. He said that Milwaukee
Public Schools has 36 sites on 259 acres with a current replacement value of almost
$75 million. He added that the City is responsible for the reconstruction of all 98 sites
and that DPW has completed facility condition assessments of all the City’s 62 sites.
Mr. Fredrich said that the criteria by which DPW establishes its budget requests are
driven by ADA compliance. He said that 75% of our sites are ADA compliant.
Ald. Kovac asked if it was a moral hazard for MPS to maintain sites that the City is
responsible for replacing. Mr. Fredrich replied that MPS does have its challenges but
he believes that MPS does a fairly good job of maintaining the sites. He said it has
been several years since MPS has contacted the City regarding a site that needed
replacement. Ald. Kovac asked if MPS had their own system for evaluating the
condition of the sites. Mr. Fredrich said it was likely that they did.
Mr. Fredrich described the process for evaluating recreational sites. He said there
was a field form for each site. The field form itemizes the equipment and includes
information like age, current replacement value, overall condition rating and whether
the site is ADA compliant. Information from the field form is put into the condition
assessment form, which is used to develop the six year plan. He said the rec
facilities use the same FCI scale as the buildings. Overall in 2014, the FCI is 0.02 for
all recreational sites.
Ald. Kovac asked how much of the funding for recreational facilities is coming from
the ADA account. Mr. Fredrich said that normally the department will request funding
for one or two sites each year to address the ADA deficiencies on that site. Ald.
Kovac asked if there was a separate recreational facilities line in the capital budget.
Ms. Brengosz said that prior to the 2012 budget there was a separate capital account
for recreational facilities. Beginning in the 2012 budget, that account was no longer
funded. The funding that would have gone into the recreational facilities account was
put in the ADA account to address the ADA issues at the rec facilities. She said a
portion was also put into the municipal garages and outlying facilities account to
address issues that were not ADA related at other rec facilities. Mr. Fredrich said
that following the Dept. of Justice’s evaluation of the City, it seemed best to address
the ADA deficiencies at recreational facilities through a dedicated ADA program. Ald.
Kovac asked if funding would return to the recreational facilities account once all the
sites were ADA compliant. Mr. Fredrich said that it was possible.
5. Set next agenda.
The next agenda includes a discussion of debt targets and a discussion of the 2014
Capital Requests.
Meeting adjourned at 10:22 a.m.
Staff Assistant Tobie Black
This meeting can be viewed in its entirety through the City's Legislative Research Center
at http://milwaukee.legistar.com/calendar.
City of Milwaukee Page 6