JOINT COMMITTEE ON DOWNTOWN STREETCAR IMPLEMENTATION
Regular MeetingMilwaukee, WI · June 12, 2015
Minutes
200 E. Wells Street
City of Milwaukee Milwaukee, Wisconsin
53202
Meeting Minutes
JOINT COMMITTEE ON DOWNTOWN
STREETCAR IMPLEMENTATION
Ghassan Korban, Chair
Ald. Robert Bauman, Vice Chair
Mayor Tom Barrett, Common Council President Michael
Murphy, Ald. Nik Kovac, Comptroller Martin Matson, Dan
Boehme, Rocky Marcoux, and Jeff Polenske
Staff Assistant: Chris Lee, 286-2232, Fax: 286-3456,
clee@milwaukee.gov
Friday, June 12, 2015 9:00 AM Room 301-B, Third Floor, City Hall
1. Call to Order
Meeting called to order at 9:04 a.m.
2. Roll Call
Present 8 - Korban, Murphy, Polenske, Gonda, Kovac, Matson, Marcoux and Boehme
Excused 1 - Bauman
Individuals also present:
Timothy Clancy, The Concord Group
Ashley Booth, HNTB Corporation
Mr. Clancy and Booth gave a PowerPoint presentation regarding items 3 through 7,
which can be found within CCFN 141879.
3. Project Status
Mr. Clancy and Booth gave updates on the project status.
-30 Day Look Back
Vehicle RFP clarifications and questions were received, reviewed, and addressed
with an addendum number 3. The Tiger Grant application was submitted. The
alternate alignment was developed for review with affected utilities. An environment
analysis update associated with the alternative alignment was prepared and will be
submitted to Federal Transit Administration (FTA) by next week. Pending final review
with private utilities, stakeholders, and FTA approval of the environmental
re-evaluation, the alignment will be locked. Additional survey for the phase 1 route
was completed, and the survey for the lakefront line was started. The permitting
process for the remaining soil borings was finalized. Utility coordination is continuing
and design issues for the Operations and Maintenance Facility (OMF) building are
City of Milwaukee Page 1
JOINT COMMITTEE ON Meeting Minutes June 12, 2015
DOWNTOWN STREETCAR
IMPLEMENTATION
being evaluated.
-90 Day Look Ahead
Approval of the environmental re-evaluation is expected by mid July 2015. Receipt of
vehicle proposals is anticipated by July 2, 2015. The federal grant agreement will be
amended. Private and public utility coordination are ongoing. Final design will
progress including public utilities. The baseline project schedule will be finalized.
-Overall Phase 1 Project Schedule
The project schedule for some public utilities has been pushed out about a month
due to the alignment change, environmental re-evaluation, and We Energies
coordination associated with the route change. Design completion is now July 2015
and the awarding of contracts is August 2015. Construction is still anticipated be
begin September 2015 and finish in August 2016.
The project schedule for the OMF building remains unchanged with design
completion in October 2015, awarding of contracts in January 2016, and a one year
construction period beginning in March 2016.
The project schedule for the mainline (roadway, trackwork, systems / overhead
contact system) is similar to the OMF building schedule. Design is to complete by
November 2015, contracts awarded in January 2016, construction to begin in April
2016, construction to finish in February 2018.
Revenue service is to begin in July 2018.
-Budget Status
An additional $300,000 has been spent in professional services over the last month.
Total expenses through May 2015 are $6.4 million.
4. Alignment Change
Mr. Clancy and Booth gave an update on alignment change. The team has identified
the best path and analyzed public and private utility impacts. Originally proposed
was for the alignment to go north on Van Buren Street and south on Jackson Street
and operate on Wells Street. The current proposal is for the track to go north and
south on Jackson Street and operate on Kilbourn Avenue rather than Wells Street.
The route adjustments are expected to produce significant cost savings associated
with public and private utilities. The team has met with We Energies many times and
will continue to work with them to finalize the alignment and confirm and projected
cost savings. The team has met and will continue to work with Eastown Association
and other stakeholders to minimize impacts on special event operations. The new
alignment allows for a new signature stop at Kilbourn Avenue and Jefferson Street.
The stop will include a central platform in the median, and can serve the Cathedral
Square area.
Commissioner Korban asked when the cost benefits of the route change can be
finalized or quantified. Mr. Booth replied that the team will continue to work with We
Energies to finalize the new alignment and quantify the cost savings.
Mr. Booth replied within four weeks. Confirmation is needed from We Energies.
City of Milwaukee Page 2
JOINT COMMITTEE ON Meeting Minutes June 12, 2015
DOWNTOWN STREETCAR
IMPLEMENTATION
5. Utility Coordination
Mr. Clancy said that there has been progress over the last month. Negotiations of
the design agreement with We Energies are continuing, and meetings with the
company are ongoing. There was a meeting on May 20, 2015. Another meeting with
the company will be next Thursday to review the alignment changes and overall
project. Another draft agreement will be sent to We Energies from the Department of
Public Works (DPW) by early next week.
6. Tiger Grant Application
Mr. Booth gave an update on the Tiger Grant application. Notice of Funding
Availability was announced in April 2015 with pre application due in May 2015. An
application was submitted on June 5, 2015 to request $14.2 million from the federal
government with $14.2 million in local matching funds. The overall project is $28.4
million. The Common Council approved the local funding and the 50 percent federal
government match on February 10, 2015.
The grant is for .4 miles of new route on the lakefront line, .8 miles of track alignment
on Michigan Street and Clybourn Avenue, an additional vehicle for the system,
additional track on St. Paul Avenue, and additional improvements to the OMF
building. The improvements to the OMF building will provide additional flexibility for
phase 1 and the lakefront line to accommodate both systems at the same time. The
team is still determining the best operational scenario for the lakefront line. The
application is strengthened with about 50 letters of support from political individuals,
trade groups, construction trade entities, businesses, local supporters, and
stakeholders.
Compared to past submittals, this application has several advantages. There is
Common Council authorization to construct and commit 50 percent to match in local
funding. There is a conceptual agreement on private utility costs. The project is
defined as a transformative project for the lakefront and City as a whole with potential
developments along the alignment, such as projects for the Couture, Northwestern
Mutual, and Milwaukee Art Museum. The grant application supports the USDOT
Ladders of Opportunity initiative by providing local employment in construction jobs
and Work Force Development programs.
7. Vehicle Procurement Status
Mr. Clancy gave an update on the vehicle procurement schedule. Receipt of
proposals from car builders is expected by July 2, 2015. An update can be given to
the joint committee concerning the quantity of proposals at the joint committee’s July
10, 2015 meeting. Interviews will be conducted in August 2015. The vehicle
specification may be refined in conjunction with a Best and Final Offer process
potentially including another round of evaluations and interviews. A car builder will be
selected in September 2015. A pre award audit and issuance of a notice to proceed
are anticipated by the end of September 2015. A recommendation should be brought
to the joint committee at its September 2015 meeting.
The team has started to form a proposal evaluation and review committee consisting
of four subcommittees: technical, budget, qualifications, and aesthetics. The
technical subcommittee will be comprised of DPW, Owner’s Rep vehicle specialists
City of Milwaukee Page 3
JOINT COMMITTEE ON Meeting Minutes June 12, 2015
DOWNTOWN STREETCAR
IMPLEMENTATION
(LTK), final designer (HNTB), and Milwaukee County Transit System (MCTS). The
budget subcommittee will be comprised of DPW, Owner’s Rep (The Concord Group
and LTK), and the City’s budget office. The qualifications subcommittee will be
comprised of DPW, OR (LTK), final designer (HNTB), SEWRPC, and MCTS. The
Aesthetics subcommittee will be composed of DPW, Department of City
Development (DCD), and two community members to be determined.
Commissioner Korban questioned the pre award Buy America audit process.
Mr. Clancy replied that an audit will be done to verify that the recommended vendor
will be able to meet FTA requirements and deliver the project under those
requirements prior to signing a contract.
After discussion, Commissioner Korban said that there will be an August meeting of
the joint committee unless many of the members have attendance conflicts.
Ald. Kovac joined the committee at 9:15 a.m. Ald. Murphy joined the committee at
9:18 a.m.
Ald. Murphy asked about a response time regarding the Tiger Grant submittal?
Mr. Booth said that a response is typically from three to four months. Awarding of the
grant should occur in September or October 2015.
Meeting adjourned at 9:25 a.m.
Chris Lee, Staff Assistant
Detailed information regarding materials presented at this meeting can be found within
Common Council File Number 141879.
City of Milwaukee Page 4
Agenda
200 E. Wells Street
City of Milwaukee Milwaukee, Wisconsin
53202
Meeting Agenda
JOINT COMMITTEE ON DOWNTOWN STREETCAR
IMPLEMENTATION
Ghassan Korban, Chair
Ald. Robert Bauman, Vice Chair
Mayor Tom Barrett, Common Council President Michael
Murphy, Ald. Nik Kovac, Comptroller Martin Matson, Dan
Boehme, Rocky Marcoux, and Jeff Polenske
Staff Assistant: Chris Lee, 286-2232, Fax: 286-3456,
clee@milwaukee.gov
Friday, June 12, 2015 9:00 AM Room 301-B, Third Floor, City Hall
1. Call to Order
2. Roll Call
3. Project Status
-30 Day Look Back
-90 Day Look Ahead
-Overall Project Schedule
-Budget Status
4. Alignment Change
5. Utility Coordination
6. Tiger Grant Application
7. Vehicle Procurement Status
Detailed information regarding materials presented at this meeting can be found within Common
Council File Number 141879.
Members of the Common Council and its standing committees who are not members of this committee
may attend this meeting to participate or to gather information. Notice is given that this meeting may
constitute a meeting of the Common Council or any of its standing committees, although they will not
take any formal action at this meeting.
Upon reasonable notice, efforts will be made to accommodate the needs of persons with disabilities
through sign language interpreters or auxiliary aids. For additional information or to request this
service, contact the City Clerk's Office ADA Coordinator at 286-2998, (FAX)286-3456,
(TDD)286-2025 or by writing to the Coordinator at Room 205, City Hall, 200 E. Wells Street,
Milwaukee, WI 53202.
City of Milwaukee Page 1 Printed on 6/10/2015
JOINT COMMITTEE ON Meeting Agenda June 12, 2015
DOWNTOWN STREETCAR
IMPLEMENTATION
Limited parking for persons attending meetings in City Hall is available at reduced rates (5 hour limit)
at the Milwaukee Center on the southwest corner of East Kilbourn and North Water Street. Parking
tickets must be validated in the first floor Information Booth in City Hall.
Persons engaged in lobbying as defined in s. 305-43-4 of the Milwaukee Code of Ordinances are
required to register with the City Clerk's Office License Division. Registered lobbyists appearing
before a Common Council committee are required to identify themselves as such. More information is
available at http://city.milwaukee.gov/Lobbying.
City of Milwaukee Page 2 Printed on 6/10/2015