JOINT COMMITTEE ON DOWNTOWN STREETCAR IMPLEMENTATION
Regular MeetingMilwaukee, WI · July 10, 2015
Minutes
200 E. Wells Street
City of Milwaukee Milwaukee, Wisconsin
53202
Meeting Minutes
JOINT COMMITTEE ON DOWNTOWN
STREETCAR IMPLEMENTATION
Ghassan Korban, Chair
Ald. Robert Bauman, Vice Chair
Mayor Tom Barrett, Common Council President Michael
Murphy, Ald. Nik Kovac, Comptroller Martin Matson, Dan
Boehme, Rocky Marcoux, and Jeff Polenske
Staff Assistant: Chris Lee, 286-2232, Fax: 286-3456,
clee@milwaukee.gov
Friday, July 10, 2015 9:00 AM Room 301-B, Third Floor, City Hall
1. Call to Order
Meeting called to order at 9:05 a.m.
2. Roll Call
Sarah Zarate appearing for Ald. Michael Murphy.
Present 6 - Korban, Bauman, Matson, Marcoux, Boehme and Zarate
Excused 3 - Polenske, Gonda and Kovac
Individuals also present:
Timothy Clancy, The Concord Group
Ashley Booth, HNTB Corporation
Mr. Clancy and Booth gave a PowerPoint presentation and updates for agenda items
3, 4, and 5. The PowerPoint can be found within CCFN 141879.
3. Project Status
-30 Day Look Back
Vehicle proposals were received last week, July 2, 2015, in response to the request
for proposal (RFP). Progress has been made over the last two months regarding the
investigation of alignment modifications and the finalization of the alignment. Some
alternative alignments previously announced included moving the routes from Wells
Street to the of Kilbourn Avenue and from Van Buren Street to Jackson Street. There
has been investigation over the last month for additional alignment modifications on
Broadway north of Wells Street onto Kilbourn Avenue. We Energies proposed a
couple of alignment modifications to save money. Two of those options were looked
at, but changes were not made to the alignment due to their additional impacts to
public utilities and AT&T infrastructure.
City of Milwaukee Page 1
JOINT COMMITTEE ON Meeting Minutes July 10, 2015
DOWNTOWN STREETCAR
IMPLEMENTATION
From a project coordination standpoint, the alignment has been pinned and finalized.
Two aspects that needed completion before pinning the alignment were coordination
with key project stakeholders and investigation of additional alternate alignments.
We Energies is now on the same page and in agreement with an alignment
modification as of last week. Locking and pinning the alignment were critical to
progress design of the other streetcar disciplines and for We Energies to start
focusing on engineering and design of the modifications to their facilities.
The appropriate documents have been submitted to the Federal Transit
Administration (FTA) concerning the environmental analysis update associated with
the Kilbourn and Jackson alignment modifications. FTA is working with the State
Historic Preservation Office (SHPO) to concur that there are no adverse effects due
to the alignment modifications. Region 5 of FTA has been expeditious in
correspondence and review of the environmental analysis update.
Utility coordination is ongoing. The team made updates to the project management
plan and sub plans including the quality management plan, safety and security
management plan, the risk register and others. The updates are in the progress of
being provided to FTA. The final design has progressed. The survey work along the
alignment has been completed, including the Lakefront Line. The design teams will
start moving forward with locking in the alignment for the Lakefront Line through
project meetings with We Energies and other stakeholders along the alignment.
Some significant progress has been made on the mainline design and water main
design.
-90 Day Look Ahead
The vehicle evaluation process will include review of proposals and interview of
proposers. An approval is expected over the next 90 days from FTA regarding the
environmental analysis update associated with the Kilbourn/Jackson alignment
modifications. The schedule for the environmental analysis update approval had
initially been scheduled to be complete in mid-July and we are now hoping to have
approval by the end of July. The federal grant agreement should be amended in the
next 30 days. Private and public utility coordination are continuing. The project
schedule for Phase 1 will be finalized and baselined once remaining private utility
design agreements are completed and the environmental analysis update approval
has been obtained. An update to the draft project schedule is being worked through
internally.
The Streetcar Public Information (PI) program during construction will be modeled
after the successful Department of Public Works (DPW) business support program.
Step one of the program will involve obtaining contact information and identifying
special concerns from property owners and occupants along the routes throughout
the end of July through August. Business Improvement District 21, their
ambassadors, and the PI team will assist with gathering contact information.
Outreach efforts will include sending postcards and having door to door visits. There
is a plan to have a 24/7 hotline phone number staffed by a PI team member.
Development of a hotline is common in for streetcar projects.
-Overall Project Schedule
Dates for the public utilities (water) schedule have been pushed back based on
realignment investigations taking a longer time than expected. Previously, design
was to be completed in July, contracts to be awarded in August, and construction to
City of Milwaukee Page 2
JOINT COMMITTEE ON Meeting Minutes July 10, 2015
DOWNTOWN STREETCAR
IMPLEMENTATION
start in September. Current expectation is for design to be completed in August,
contracts to be awarded in September, and construction to start in October.
The operations maintenance facility (OMF) schedule is being reevaluated and
baslined after vehicle selection so that vehicle specifications can be coordinated with
the design of the facility. The OMF is not a critical path element. Design efforts have
been dedicated to alignment modifications and other project disciplines. Previously,
the OMF design was to be completed in October, construction to start next spring
2016, and be completed by spring of 2017. The construction duration is around ten
months. Current expectation is to push back the schedule at least three months or
potentially further, possibly with construction to occur in 2017. The completion
schedule of the OMF is predicated on the delivery and storing of vehicles, especially
the first vehicle.
The Phase 1 mainline (roadway, trackwork, systems / overhead contact system)
design is expected to be completed in November. The prolonged alignment
investigation should not impact the completion of the design. The awarding of
contracts and construction are expected for spring 2016.
Revenue service is anticipated to begin in July 2018.
-Budget Status
$6.6 million in total has been expended through June 2015. About $180,000 was
expended in June 2015.
4. Utility Coordination
There was a technical meeting with We Energies on June 18, 2015 with staff
reviewing some of the alignments. Cost savings associated with the revised
alignment are being confirmed and are anticipated to be in excess of $1 million. The
design agreement should hopefully be executed soon. Negotiations are ongoing
through meetings with We Energies, City staff, and attorneys. There is predominant
agreement on the agreement language, but exhibits are still being finalized. There
will be regular meetings with We Energies with a meeting at the end of July to review
locking the alignment for the Lakefront Line. The working relationship with We
Energies has been good and has yielded substantial project benefits. The executed
agreement with We Energies will become a template agreement that can be used
with other utilities, telecommunications, and private entities that may be impacted by
the streetcar project.
5. Vehicle Procurement Status
Proposals were received July 2, 2015. The identities of the applicants and quantity of
proposals are being kept confidential out of respect for the evaluation process.
Interviews and best and final offers are anticipated in August. Notification of the
selected car builder is expected to occur in September. Notice to proceed is
expected to occur by the end of September.
6. Adjournment
Meeting adjourned at 9:18 a.m.
Chris Lee, Staff Assistant
City of Milwaukee Page 3
JOINT COMMITTEE ON Meeting Minutes July 10, 2015
DOWNTOWN STREETCAR
IMPLEMENTATION
City of Milwaukee Page 4
Agenda
200 E. Wells Street
City of Milwaukee Milwaukee, Wisconsin
53202
Meeting Agenda
JOINT COMMITTEE ON DOWNTOWN STREETCAR
IMPLEMENTATION
Ghassan Korban, Chair
Ald. Robert Bauman, Vice Chair
Mayor Tom Barrett, Common Council President Michael
Murphy, Ald. Nik Kovac, Comptroller Martin Matson, Dan
Boehme, Rocky Marcoux, and Jeff Polenske
Staff Assistant: Chris Lee, 286-2232, Fax: 286-3456,
clee@milwaukee.gov
Friday, July 10, 2015 9:00 AM Room 301-B, Third Floor, City Hall
1. Call to Order
2. Roll Call
3. Project Status
-30 Day Look Back
-90 Day Look Ahead
-Overall Project Schedule
-Budget Status
4. Utility Coordination
5. Vehicle Procurement Status
6. Adjournment
Members of the Common Council and its standing committees who are not members of this committee
may attend this meeting to participate or to gather information. Notice is given that this meeting may
constitute a meeting of the Common Council or any of its standing committees, although they will not
take any formal action at this meeting.
Upon reasonable notice, efforts will be made to accommodate the needs of persons with disabilities
through sign language interpreters or auxiliary aids. For additional information or to request this
service, contact the City Clerk's Office ADA Coordinator at 286-2998, (FAX)286-3456,
(TDD)286-2025 or by writing to the Coordinator at Room 205, City Hall, 200 E. Wells Street,
Milwaukee, WI 53202.
Limited parking for persons attending meetings in City Hall is available at reduced rates (5 hour limit)
at the Milwaukee Center on the southwest corner of East Kilbourn and North Water Street. Parking
tickets must be validated in the first floor Information Booth in City Hall.
City of Milwaukee Page 1 Printed on 7/9/2015
JOINT COMMITTEE ON Meeting Agenda July 10, 2015
DOWNTOWN STREETCAR
IMPLEMENTATION
Persons engaged in lobbying as defined in s. 305-43-4 of the Milwaukee Code of Ordinances are
required to register with the City Clerk's Office License Division. Registered lobbyists appearing
before a Common Council committee are required to identify themselves as such. More information is
available at http://city.milwaukee.gov/Lobbying.
City of Milwaukee Page 2 Printed on 7/9/2015
Get email alerts for Milwaukee
A daily email when new agendas and minutes are posted.