JOINT COMMITTEE ON REDEVELOPMENT OF ABANDONED AND FORECLOSED HOMES
Regular MeetingMilwaukee, WI · October 16, 2017
Minutes
200 E. Wells Street
City of Milwaukee Milwaukee, Wisconsin
53202
Meeting Minutes
JOINT COMMITTEE ON REDEVELOPMENT OF ABANDONED AND
FORECLOSED HOMES
ALD. ROBERT BAUMAN, CHAIR
Spencer Coggs, Preston Cole, Mario Higgins, Ald. Khalif
Rainey, Antonio Perez, Maria Prioletta, and Ald. Russell
Stamper, II.
Staff Assistant: Linda Elmer, 286-2231
Fax: 286-3456, lelmer@milwaukee.gov
Legislative Liaison: Aaron Cadle, 286-8666,
acadle@milwaukee.gov
Monday, October 16, 2017 10:00 AM City Hall, Room 301-A
Meeting convened: 10:04 A.M.
Members present: Preston Cole, Mario Higgins, Maria Prioletta, Ald. Robert Bauman
and Jim Klajbor for Spencer Coggs (who arrived at 11:08 A.M.), Antonio Perez (10:15
A.M.)
Members excused: Ald. Rainey and Ald. Stamper
1. Review and approval of minutes from the September 11th meeting.
Mr. Cole moved, seconded by Mr. Klajbor, for approval of the minutes. There were no
objections.
2. Communication from the Department of City Development on Housing
Infrastructure Preservation Fund Activities.
Ald. Bauman said there is a proposed budget of $100,000, which is basically one
house. Ms. Martha Brown, Dept. of City Development, said the anticipated carryover is
$151,000. There are four projects under construction with a total cost of $370,000.
There may be three projects done next year as opposed to four this year. There are
fewer foreclosures this year than in past years. The dept. has 20 properties that are
completed but not sold and the dept. wants to concentrate on those projects.
3. Communication from the Department of City Development on the
Lease-to-Own Program.
This item was included in the discussion under item #6.
4. Communication from the Department of City Development relating to the
Rehabilitation to Rent Program.
This item was included in the discussion under item #6.
City of Milwaukee Page 1
JOINT COMMITTEE ON Meeting Minutes October 16, 2017
REDEVELOPMENT OF ABANDONED
AND FORECLOSED HOMES
5. Communication from the Department of City Development on the Strong
Home Loan Program.
This item was included in the discussion under item #6.
6. Communication from the Mayor's Office, Department of City
Development, and the City Attorney's Office relating to activities, revenue
and expenditures of the Strong Neighborhoods Plan and the 2018 proposed
budget for the program.
As part of this discussion, the Legislative Reference Bureau report on Strong
Neighborhoods was used, which is attached to file 161359. Ald. Bauman sees that
there is a 38% reduction in Strong Neighborhoods funding as part of the 2018 budget.
Tom Mishefske, Dept. of Neighborhood Services, said the total appropriation is
$800,000 for the code compliance program with no signifcant carryover and they have
approximately 54 loans. It is anticipated they will have the same number of loans next
year as long as the program is still meeting the same goals that were originally set.
The DNS budget does reduce positions and will only monitor vacant buildings on a
quarterly, rather than a monthly, basis. Mr. Klajbor said the city is continuing to do the
accelerated foreclosures. Ms. Irma Yepez-Klassen said that overall delinquecies are
down to about 250-300 per year. Additional funding was needed to do the catchup, but
now it is coming out of the annual budget.
Ms. Martha Brown, Dept. of City Development, addressed Ald. Bauman's specific
questions relating to special purpose accounts and rent collection. Mr. David
Schroeder, said the rent collection money goes to RACM because back in 2007 the
Comptroller's Office felt that this was best due to the difficult of working with FMIS, the
large number of invoices, the need to estimate revenue and increased flexibility to
immediately spend these accounts.
Dave Sivyer, Forestry Manager, said the in rem vacant lot management program
manages the properties' physical, ongoing needs related to the land and the land
property management fund pays for board-up, locks, and other structural costs.
If the deconstruction ordinance advances, there will be no DPW demolitions; for DNS
the demolition numbers would reduce by around 62% for a total of 52 projects in 2018.
There are currently 360 demolition orders pending. At this point, there are no other
sources being directed to demolition or deconstruction.
Ms. Brown said that neither the challenge fund nor the rental rehabilitation loan
program will be funded in 2018. The remaining programs are Lease to Own and
Homebuyer Assistance Programs. Mr. Larry Kilmer, Dept. of Cit Development, said 88
loans were approved this year and there are some pending. There is approximately
$200,000-$300,000 in the strong loans program. Loan repayments are included as part
of this budget. Ms. Prioletta is predicting $700,000 from loan repayments and 1/3 of
in-rem sales are still being sent to RACM. Ms. Brown noted that employees are no
longer working for RACM, but they do still have out-of-pocket expenses related to
real-estate management. Ald. Bauman questioned if this will be a profit-maker in the
future, why not add more money? Mr. Higgins noted that 25% of the loan is forgiven
and city staff time is not included in the cost-calculation. Mr. Higgins asked if this
program could be changed to operate differently as it continues to evolve. Ald.
Bauman noted that assessments are not increasing in the neighborhoods and they are
severely challenged. Sixty four properties have been sold in the greater Sherman Park
neighborhood that will be eligible for state funds.
City of Milwaukee Page 2
JOINT COMMITTEE ON Meeting Minutes October 16, 2017
REDEVELOPMENT OF ABANDONED
AND FORECLOSED HOMES
The Commercial Investment Program, which has been part of Strong Neighborhoods
since last year, is the facade loan program. Ald. Bauman asked if there would be a
reduction in staff; Mr. Mishefske said that there will be cuts in that department. Ms.
Brown noted there is no staff reduction in DCD as staff works across multiple
programs and the programs being eliminated weren't staff-intensive.
Ms. Karen Taylor, Dept. of City Development, said that RACM gets 30% of the in-rem
property sales for its costs. Ald. Bauman questioned if the $325,000 paid to the City
Attorney's Office could be bid out to a private firm cheaper but that amount is not
solely spent on in-rem properties. This reduces the tax levy by $325,000. Mr. Perez
noted that the City Attorney's Office can track how much time it spends on doing this
work, which it does and bills the city quarterly for all legal work done for DCD and
RACM.
7. Communication from the Department of Neighborhood Services relating to
the Compliance Loan Program.
This item was included in the discussion under item #6.
8. Communication from the Department of Neighborhood Services relating to
demolition and deconstruction.
This item was included in the discussion under item #6.
9. Communication from the Treasurer's Office, Department of Neighborhood
Services and the City Attorney's Office relating to efforts to pierce the
corporate veil of legal entities such as LLC's that own real property in the
City of Milwaukee in order to expedite the collection of funds owed the city
and to expedite compliance with DNS orders.
Kail Decker, Asst. City Attorney, referred to the October 16th update which his office
provided.
RECESS: 10:54 A.M.
RECONVENE: 10:55 A.M
The City Attorney's Office met with the Treasurer's Office, which will annually submit a
list of tax-delinquent LLCs, and the City Attorney's Office will go through the list and
figure out who actually owns the LLCs and prioritize those who are not paying and will
go after the top offenders.
Ald. Witkowski asked that the correspondence be submitted to the appropriate
committee so the proposed plan can be institutionalized.
Ald. Bauman asked about the status of 2408 W. Kilbourn for which the owner has
been judged to be in contempt of court and accruing daily forfeitures. A property at
27th and Juneau was demolished, which had been a problem property for 30 years.
Mr. Cole noted that revenues don't return to the program. Ald. Bauman feels that the
demolition funds aren't as limited as they appear as the money is reimbursed
(hopefully).
RACM typically works with DNS for demolitions. Ald. Bauman suggested selling all
in-rem properties to RACM. Atty. Decker noted that a precedent of this would be a
land bank, but Ms. Brown noted those cities don't take properties and Milwaukee is
already operating a de facto land bank.
City of Milwaukee Page 3
JOINT COMMITTEE ON Meeting Minutes October 16, 2017
REDEVELOPMENT OF ABANDONED
AND FORECLOSED HOMES
10. Public Comment
There were no members of the public present.
11. Set next meeting date.
Nov. 27th at 10 a.m.
Meeting adjourned: 11:17 A.M.
Linda M. Elmer
Staff Assistant
This meeting can be viewed in its entirety through the City's Legislative Research
Center at http://milwaukee.legistar.com/calendar.
Matters to be considered for this meeting and materials related to activities of the task
force can be found within the file:
161359 Communication relating to the 2017 activities of the Joint Committee on
the Redevelopment of Abandoned and Foreclosed Homes.
Sponsors: THE CHAIR
City of Milwaukee Page 4
Agenda
200 E. Wells Street
City of Milwaukee Milwaukee, Wisconsin
53202
Meeting Agenda
JOINT COMMITTEE ON REDEVELOPMENT OF ABANDONED AND
FORECLOSED HOMES
ALD. ROBERT BAUMAN, CHAIR
Spencer Coggs, Preston Cole, Mario Higgins, Ald. Khalif Rainey,
Antonio Perez, Maria Prioletta, and Ald. Russell Stamper, II.
Staff Assistant: Linda Elmer, 286-2231
Fax: 286-3456, lelmer@milwaukee.gov
Legislative Liaison: Aaron Cadle, 286-8666,
acadle@milwaukee.gov
Monday, October 16, 2017 10:00 AM City Hall, Room 301-A
1. Review and approval of minutes from the September 11th meeting.
2. Communication from the Department of City Development on Housing
Infrastructure Preservation Fund Activities.
3. Communication from the Department of City Development on the
Lease-to-Own Program.
4. Communication from the Department of City Development relating to the
Rehabilitation to Rent Program.
5. Communication from the Department of City Development on the Strong
Home Loan Program.
6. Communication from the Mayor's Office, Department of City
Development, and the City Attorney's Office relating to activities, revenue
and expenditures of the Strong Neighborhoods Plan and the 2018 proposed
budget for the program.
7. Communication from the Department of Neighborhood Services relating to
the Compliance Loan Program.
8. Communication from the Department of Neighborhood Services relating to
demolition and deconstruction.
City of Milwaukee Page 1 Printed on 10/13/2017
JOINT COMMITTEE ON Meeting Agenda October 16, 2017
REDEVELOPMENT OF ABANDONED
AND FORECLOSED HOMES
9. Communication from the Treasurer's Office, Department of Neighborhood
Services and the City Attorney's Office relating to efforts to pierce the
corporate veil of legal entities such as LLC's that own real property in the
City of Milwaukee in order to expedite the collection of funds owed the city
and to expedite compliance with DNS orders.
10. Public Comment
11. Set next meeting date.
Matters to be considered for this meeting and materials related to activities of the task force can be
found within the file:
161359 Communication relating to the 2017 activities of the Joint Committee on
the Redevelopment of Abandoned and Foreclosed Homes.
Sponsors: THE CHAIR
This meeting will be webcast live at www.milwaukee.gov/channel25.
Members of the Common Council and its standing committees who are not members of this committee may
attend this meeting to participate or to gather information. Notice is given that this meeting may constitute a
meeting of the Common Council or any of its standing committees, although they will not take any formal action
at this meeting.
Upon reasonable notice, efforts will be made to accommodate the needs of persons with disabilities through
sign language interpreters or auxiliary aids. For additional information or to request this service, contact the
Council Services Division ADA Coordinator at 286-2998, (FAX)286-3456, (TDD)286-2025 or by writing
to the Coordinator at Room 205, City Hall, 200 E. Wells Street, Milwaukee, WI 53202.
Limited parking for persons attending meetings in City Hall is available at reduced rates (5 hour limit) at the
Milwaukee Center on the southwest corner of East Kilbourn and North Water Street. Parking tickets must be
validated in the first floor Information Booth in City Hall.
Persons engaged in lobbying as defined in s. 305-43-4 of the Milwaukee Code of Ordinances are required to
register with the City Clerk's Office License Division. Registered lobbyists appearing before a Common
Council committee are required to identify themselves as such. More information is available at
http://city.milwaukee.gov/Lobbying.
City of Milwaukee Page 2 Printed on 10/13/2017
Get email alerts for Milwaukee
A daily email when new agendas and minutes are posted.