Call to Order
Meeting called to order at 3:15 p.m.
Roll Call
Present: 6 - Witkowiak, McCarthy, Wagner, Perez, Donald, Bohl
Excused: 4 - Nicolini, Diaz, Rainey, Hurtado
1. T46 Approval of the minutes of the regular meeting held on August 8, 2018
Sponsors: THE CHAIR
Attachments: August 8, 2018 Travaux Minutes.pdf
Director Bohl and Director McCarthy asked that the minutes be amended to include
Director Bohl as being "Excused" from the last meeting and not being listed as
"Absent." There being no objections, the motion to approve the minutes as amended
carried.
2. T47 Motion accepting the appointment of Kimberly A. Hurtado to the Travaux
Board of Directors
Sponsors: THE CHAIR
Attachments: HACM Resolution re Travaux Board Appointment of Kim Hurtado
Kimberly A. Hurtado Bio
3. T48 Resolution approving the adoption of a Travaux Employee Handbook
Sponsors: THE CHAIR
Attachments: Travaux Employee Handbook Draft Aug 2018
A motion was made by Dan McCarthy, seconded by James A. Bohl, that this
Travaux Resolution be ADOPTED. This motion PREVAILED by the following
vote:
Aye 5- Witkowiak McCarthy Wagner Perez Bohl
City of Milwaukee Page 1
TRAVAUX INC. BOARD OF Meeting Minutes September 13, 2018
DIRECTORS
No 0
Excused 3- Nicolini Diaz Rainey
Abstain 1- Donald
4. T49 Resolution approving a contract to Rams Contracting Limited (Lannon,
WI) for Excavation and Erosion Control for Multi-Family Apartment
Building 2.3 at Westlawn Gardens Phase 2 in the amount of $156,300.00
Sponsors: THE CHAIR
Attachments: Travaux G703 - Westlawn Gardens Ph2 Apt Bldg 2 3 09-10-18
57868 IFB tab Excavation & Erosion Control Rams Contracting Ltd
Staff explained that the Travaux Board will be approving the contract to be the General
Contractor for Westlawn Gardens Phase 2 Buildings 2.2 and 2.3 in the future, once the
Guaranteed Maximum Price has been finalized.
A motion was made by James A. Bohl, seconded by James N. Witkowiak, that
this Travaux Resolution be ADOPTED. This motion PREVAILED by the
following vote:
Aye 5- Witkowiak McCarthy Wagner Perez Bohl
No 0
Excused 3- Nicolini Diaz Rainey
Abstain 1- Donald
5. T50 Resolution approving a contract to Oostburg Concrete Products
(Oostburg, WI) for Footings and Foundation for Multi-Family Apartment
Building 2.3 at Westlawn Gardens Phase 2 in the amount of $445,250.00
Sponsors: THE CHAIR
Attachments: 57870 IFB tab Footings & Foundation Oostburg Concrete Products
A motion was made by M. Joseph Donald, seconded by James N. Witkowiak,
that this Travaux Resolution be ADOPTED. This motion PREVAILED by the
following vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
Excused 3- Nicolini Diaz Rainey
City of Milwaukee Page 2
TRAVAUX INC. BOARD OF Meeting Minutes September 13, 2018
DIRECTORS
6. T51 Resolution approving a contract to Insulation Technologies, Incorporated
(Milwaukee, WI) for Wood Windows and Patio Doors (Commodity Only)
for Multi-Family Apartment Building 2.3 at Westlawn Gardens Phase 2 in
the amount of $245,029.00
Sponsors: THE CHAIR
Attachments: 57871 IFB tab Wood Windows & Patio Doors - Comm Only insulation
Technologies Inc
Warren Jones, Travaux Vice President of Construction, explained that the initial
apparent low bidder withdrew their bid due to an error in their submission which
negated their ability to provide the commodity.
A motion was made by Dan McCarthy, seconded by M. Joseph Donald, that
this Travaux Resolution be ADOPTED. This motion PREVAILED by the
following vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
Excused 3- Nicolini Diaz Rainey
7. T52 Resolution approving a contract to Great Lakes Components LLC
(Elkhorn, WI) for Wood Panelization (Furnish and Install) for Multi-Family
Apartment Building 2.3 at Westlawn Gardens Phase 2 in the amount of
$1,274,997.00
Sponsors: THE CHAIR
Attachments: 57872 IFB tab Wood Panelization -Furnish & Install- Great Lakes
Components
A motion was made by James A. Bohl, seconded by M. Joseph Donald, that
this Travaux Resolution be ADOPTED. This motion PREVAILED by the
following vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
Excused 3- Nicolini Diaz Rainey
City of Milwaukee Page 3
TRAVAUX INC. BOARD OF Meeting Minutes September 13, 2018
DIRECTORS
8. T53 Resolution approving a contract to JMarincic LLC (Milwaukee, WI) for
Masonry for Multi-Family Apartment Building 2.2 at Westlawn Gardens
Phase 2 in the amount of $352,440.00
Sponsors: THE CHAIR
Attachments: Travaux G703 - Westlawn Gardens Ph2 Apt Bldg 2 2 09-10-18
57874 IFB tab Masonry JMarincic
A motion was made by James N. Witkowiak, seconded by Antonio Perez, that
this Travaux Resolution be ADOPTED. This motion PREVAILED by the
following vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
Excused 3- Nicolini Diaz Rainey
9. T54 Resolution approving a contract to Schindler Elevator Corporation
(Menomonee Falls, WI) for Elevators for Multi-Family Apartment Building
2.2 at Westlawn Gardens Phase 2 in the amount of $249,900.00
Sponsors: THE CHAIR
Attachments: 57875 IFB Tab Elevators Schindler Elevator Corp
A motion was made by James A. Bohl, seconded by Dan McCarthy, that this
Travaux Resolution be ADOPTED. This motion PREVAILED by the following
vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
Excused 3- Nicolini Diaz Rainey
10. T55 Resolution approving a contract to Action Heating & Cooling (Milwaukee,
WI) for Mechanical for Multi-Family Apartment Building 2.2 at Westlawn
Gardens Phase 2 in the amount of $973,000.00
Sponsors: THE CHAIR
Attachments: 57877 IFB tab Mechanical Action Heating & Cooling
A motion was made by Dan McCarthy, seconded by James A. Bohl, that this
Travaux Resolution be ADOPTED. This motion PREVAILED by the following
vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
Excused 3- Nicolini Diaz Rainey
City of Milwaukee Page 4
TRAVAUX INC. BOARD OF Meeting Minutes September 13, 2018
DIRECTORS
11. T56 Resolution approving a contract to Hurt Electric (Menomonee Falls, WI)
for Electrical for Multi-Family Apartment Building 2.2 at Westlawn
Gardens Phase 2 in the amount of $1,248,690.00
Sponsors: THE CHAIR
Attachments: 57878 IFB tab Electrical Hurt Electric
A motion was made by James A. Bohl, seconded by James N. Witkowiak, that
this Travaux Resolution be ADOPTED. This motion PREVAILED by the
following vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
Excused 3- Nicolini Diaz Rainey
12. T57 Resolution approving a contract to Bohmann & Vick, Incorporated
(Brookfield, WI) for Plumbing for Multi-Family Apartment Building 2.2 at
Westlawn Gardens Phase 2 in the amount of $968,300.00
Sponsors: THE CHAIR
Attachments: 57879 IFB tab Plumbing Bohmann & Vick
A motion was made by James A. Bohl, seconded by M. Joseph Donald, that
this Travaux Resolution be ADOPTED. This motion PREVAILED by the
following vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
Excused 3- Nicolini Diaz Rainey
13. T58 Resolution approving a contract to Roofed Right America (Milwaukee,
WI) for Thermoplastic Membrane Roofing (TPO) for Multi-Family
Apartment Building 2.2 at Westlawn Gardens Phase 2 in the amount of
$286,506.00
Sponsors: THE CHAIR
Attachments: 57880 IFB tab Thermoplastic Membrane Roofing Roofed Right
America
A motion was made by James N. Witkowiak, seconded by Dan McCarthy, that
this Travaux Resolution be ADOPTED. This motion PREVAILED by the
following vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
Excused 3- Nicolini Diaz Rainey
City of Milwaukee Page 5
TRAVAUX INC. BOARD OF Meeting Minutes September 13, 2018
DIRECTORS
14. T59 Resolution approving a contract to Insulation Technologies, Incorporated
(Milwaukee, WI) for Fiber Cement Siding for Multi-Family Apartment
Building 2.2 at Westlawn Gardens Phase 2 in the amount of $376,543.00
Sponsors: THE CHAIR
Attachments: 57881 IFB tab Fiber Cement Siding Insulation Technologies
A motion was made by James N. Witkowiak, seconded by M. Joseph Donald,
that this Travaux Resolution be ADOPTED. This motion PREVAILED by the
following vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
Excused 3- Nicolini Diaz Rainey
15. T60 Resolution approving a contract to B & D Contractors, Incorporated (New
Berlin, WI) for Aluminum-Framed Entrances and Storefronts for
Multi-Family Apartment Building 2.2 at Westlawn Gardens Phase 2 in the
amount of $171,100.00
Sponsors: THE CHAIR
Attachments: 57882 IFB tab Aluminum-Framed Entrances & Storefronts B & D
Contractors
A motion was made by James N. Witkowiak, seconded by M. Joseph Donald,
that this Travaux Resolution be ADOPTED. This motion PREVAILED by the
following vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
Excused 3- Nicolini Diaz Rainey
16. T61 Resolution approving a contract to Sanchez Painting Contractors,
Incorporated (Wauwatosa, WI) for Cold-Formed Metal Framing, Gypsum
Board and Insulation for Multi-Family Apartment Building 2.2 at Westlawn
Gardens Phase 2 in the amount of $753,838.00
Sponsors: THE CHAIR
Attachments: 57883 IFB tab Cold-Formed Metal Framing, Gypsum Board, and
Insulation Sanchez Painting Contractors
A motion was made by James N. Witkowiak, seconded by M. Joseph Donald,
that this Travaux Resolution be ADOPTED. This motion PREVAILED by the
following vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
City of Milwaukee Page 6
TRAVAUX INC. BOARD OF Meeting Minutes September 13, 2018
DIRECTORS
Excused 3- Nicolini Diaz Rainey
17. T62 Resolution approving a contract to Cardinal Fabricating Corporation
(Milwaukee, WI) for Structural Steel Framing for Multi-Family Apartment
Building 2.2 at Westlawn Gardens Phase 2 in the amount of $629,000.00
Sponsors: THE CHAIR
Attachments: 57884 IFB tab Structural Steel Framing Cardinal Fabricating Corp
A motion was made by James A. Bohl, seconded by M. Joseph Donald, that
this Travaux Resolution be ADOPTED. This motion PREVAILED by the
following vote:
Aye 6- Witkowiak McCarthy Wagner Perez Donald Bohl
No 0
Excused 3- Nicolini Diaz Rainey
18. T63 Report from the President
Sponsors: THE CHAIR
President Perez noted that there is an upcoming Contractor Fair on September 20th
that already has over 110 interested potential vendors for work on future HACM and
Travaux projects.
Adjournment
There being no further business, Director Bohl made a motion to adjourn the meeting
at 3:55 p.m. Director McCarthy seconded the motion. There being no objections, the
motion carried.
Upon reasonable notice, efforts will be made to accommodate the needs of persons with disabilities through sign language
interpreters or auxiliary aids. For additional information or to request this service, contact the Housing Authority ADA
Coordinator, Patricia Schmidtknecht at 286-5100, (FAX) 286-3456, (TDD) 286-3504 or by writing to the Coordinator at 650 West
Reservoir, Milwaukee, WI 53212.
Persons engaged in lobbying as defined in s. 305-43-4 of the Milwaukee Code of Ordinances are required to register with the
City Clerk's Office License Division. Registered lobbyists appearing before a Common Council committee are required to
identify themselves as such. More information is available at http://city.milwaukee.gov/Lobbying.
City of Milwaukee Page 7
Agenda
P.O. Box 324
City of Milwaukee Milwaukee, WI
53201-0324
Meeting Agenda
TRAVAUX INC. BOARD OF DIRECTORS
Antonio M. Perez, President, James A. Bohl, Jr., Ricardo Diaz,
Hon. M. Joseph Donald, Daniel McCarthy, Mark Nicolini, Mark
Wagner, James N. Witkowiak, and Ald. Khalif Rainey
Thursday, September 13, 2018 2:30 PM City Hall, Room 301-A, 200 East Wells Street
Call to Order
Roll Call
1. T46 Approval of the minutes of the regular meeting held on August 8, 2018
Attachments: August 8, 2018 Travaux Minutes
2. T47 Motion accepting the appointment of Kimberly A. Hurtado to the Travaux
Board of Directors
Attachments: HACM Resolution re Travaux Board Appointment of Kim Hurtado
Kimberly A. Hurtado Bio
3. T48 Resolution approving the adoption of a Travaux Employee Handbook
Attachments: Travaux Employee Handbook Draft Aug 2018
4. T49 Resolution approving a contract to Rams Contracting Limited (Lannon, WI)
for Excavation and Erosion Control for Multi-Family Apartment Building 2.3
at Westlawn Gardens Phase 2 in the amount of $156,300.00
Attachments: Travaux G703 - Westlawn Gardens Ph2 Apt Bldg 2 3 09-10-18
57868 IFB tab Excavation & Erosion Control Rams Contracting Ltd
5. T50 Resolution approving a contract to Oostburg Concrete Products (Oostburg,
WI) for Footings and Foundation for Multi-Family Apartment Building 2.3 at
Westlawn Gardens Phase 2 in the amount of $445,250.00
Attachments: 57870 IFB tab Footings & Foundation Oostburg Concrete Products
6. T51 Resolution approving a contract to Insulation Technologies, Incorporated
(Milwaukee, WI) for Wood Windows and Patio Doors (Commodity Only) for
Multi-Family Apartment Building 2.3 at Westlawn Gardens Phase 2 in the
amount of $245,029.00
Attachments: 57871 IFB tab Wood Windows & Patio Doors - Comm Only insulation Technologies Inc
7. T52 Resolution approving a contract to Great Lakes Components LLC
(Elkhorn, WI) for Wood Panelization (Furnish and Install) for Multi-Family
Apartment Building 2.3 at Westlawn Gardens Phase 2 in the amount of
City of Milwaukee Page 1 Printed on 9/10/2018
TRAVAUX INC. BOARD OF Meeting Agenda September 13, 2018
DIRECTORS
$1,274,997.00
Attachments: 57872 IFB tab Wood Panelization -Furnish & Install- Great Lakes Components
8. T53 Resolution approving a contract to JMarincic LLC (Milwaukee, WI) for
Masonry for Multi-Family Apartment Building 2.2 at Westlawn Gardens
Phase 2 in the amount of $352,440.00
Attachments: Travaux G703 - Westlawn Gardens Ph2 Apt Bldg 2 2 09-10-18
57874 IFB tab Masonry JMarincic
9. T54 Resolution approving a contract to Schindler Elevator Corporation
(Menomonee Falls, WI) for Elevators for Multi-Family Apartment Building
2.2 at Westlawn Gardens Phase 2 in the amount of $249,900.00
Attachments: 57875 IFB Tab Elevators Schindler Elevator Corp
10. T55 Resolution approving a contract to Action Heating & Cooling (Milwaukee,
WI) for Mechanical for Multi-Family Apartment Building 2.2 at Westlawn
Gardens Phase 2 in the amount of $973,000.00
Attachments: 57877 IFB tab Mechanical Action Heating & Cooling
11. T56 Resolution approving a contract to Hurt Electric (Menomonee Falls, WI) for
Electrical for Multi-Family Apartment Building 2.2 at Westlawn Gardens
Phase 2 in the amount of $1,248,690.00
Attachments: 57878 IFB tab Electrical Hurt Electric
12. T57 Resolution approving a contract to Bohmann & Vick, Incorporated
(Broofield, WI) for Plumbing for Multi-Family Apartment Building 2.2 at
Westlawn Gardens Phase 2 in the amount of $968,300.00
Attachments: 57879 IFB tab Plumbing Bohmann & Vick
13. T58 Resolution approving a contract to Roofed Right America (Milwaukee, WI)
for Thermoplastic Membrane Roofing (TPO) for Multi-Family Apartment
Building 2.2 at Westlawn Gardens Phase 2 in the amount of $286,506.00
Attachments: 57880 IFB tab Thermoplastic Membrane Roofing Roofed Right America
14. T59 Resolution approving a contract to Insulation Technologies, Incorporated
(Milwaukee, WI) for Fiber Cement Siding for Multi-Family Apartment
Building 2.2 at Westlawn Gardens Phase 2 in the amount of $376,543.00
Attachments: 57881 IFB tab Fiber Cement Siding Insulation Technologies
15. T60 Resolution approving a contract to B & D Contractors, Incorporated (New
Berlin, WI) for Aluminum-Framed Entrances and Storefronts for
Multi-Family Apartment Building 2.2 at Westlawn Gardens Phase 2 in the
amount of $171,100.00
Attachments: 57882 IFB tab Aluminum-Framed Entrances & Storefronts B & D Contractors
16. T61 Resolution approving a contract to Sanchez Painting Contractors,
City of Milwaukee Page 2 Printed on 9/10/2018
TRAVAUX INC. BOARD OF Meeting Agenda September 13, 2018
DIRECTORS
Incorporated (Wauwatosa, WI) for Cold-Formed Metal Framing, Gypsum
Board and Insulation for Multi-Family Apartment Building 2.2 at Westlawn
Gardens Phase 2 in the amount of $753,838.00
Attachments: 57883 IFB tab Cold-Formed Metal Framing, Gypsum Board, and Insulation Sanchez Painting Co
17. T62 Resolution approving a contract to Cardinal Fabricating Corporation
(Milwaukee, WI) for Structural Steel Framing for Multi-Family Apartment
Building 2.2 at Westlawn Gardens Phase 2 in the amount of $629,000.00
Attachments: 57884 IFB tab Structural Steel Framing Cardinal Fabricating Corp
18. T63 Report from the President
Adjournment
Upon reasonable notice, efforts will be made to accommodate the needs of persons with disabilities through sign language interpreters or
auxiliary aids. For additional information or to request this service, contact the Housing Authority ADA Coordinator, Patricia Schmidtknecht
at 286-5100, (FAX) 286-3456, (TDD) 286-3504 or by writing to the Coordinator at 650 West Reservoir, Milwaukee, WI 53212.
Persons engaged in lobbying as defined in s. 305-43-4 of the Milwaukee Code of Ordinances are required to register with the City Clerk's
Office License Division. Registered lobbyists appearing before a Common Council committee are required to identify themselves as such.
More information is available at http://city.milwaukee.gov/Lobbying.
City of Milwaukee Page 3 Printed on 9/10/2018
Get email alerts for Milwaukee
A daily email when new agendas and minutes are posted.