Board of Public Works
Regular MeetingNashua, NH · August 6, 2015
Minutes
Minutes of Board of Public Works
Special Meeting of August 6, 2015
A regular meeting of the Board of Public Works was held on Thursday, August 6, 2015 at 2:00
p.m. at the Division of Public Works, Administration & Engineering offices, 9 Riverside Street,
Nashua, NH 03062.
Members Present
Mayor Donnalee Lozeau, Chair Lisa Fauteux, Director of Public Works
Commissioner Kevin S. Moriarty, Vice Chair Wayne Husband, City Traffic Engineer
Commissioner Paul G. Bergeron
Absent: Commissioner Tracy Pappas
Mayor Lozeau called the meeting to order at 2:00 p.m. and called the roll.
Commissioner Moriarty: Present
Commissioner Bergeron: Present
Mayor Lozeau: Present
I. MOTION: Commissioner Bergeron to approve the Agenda as presented.
SECONDED: Commissioner Moriarty
MOTION CARRIED: Carried Unanimously
II. Public Comment
None.
III. Engineering
A. Motion: Commissioner Bergeron Moves to approve the purchase of eight (8)
mast arm assemblies from Union Metal Corporation in the amount of
$32,655 funding will be through Department 160 Admin/Engineering; Fund:
General; Activity: Amherst Street Road and Traffic Improvement.
SECONDED: Commissioner Moriarty
MOTION CARRIED: Carried Unanimously
DISCUSSION:
The City is currently in the process of soliciting bids from contractors for the
reconstruction of Amherst Street from the Charron Avenue intersection easterly to
the existing jug handle across from Wholefood retail. This project is needed to
provide additional capacity through this area of Amherst Street (Route 101A).
In order to meet an expedited construction schedule, the City is purchasing the mast
arm assemblies directly from the manufacturer. This allows the City to accelerate
the delivery time in advance of awarding a construction contract. There is typically
a considerable lead time that needs to be planned for the manufacture and delivery of
mast arms.
The City put out three bid alternates for the manufacture and delivery time frames
(60 days, 90 days, and 120 days). This was done in an effort to offer an incentive to
Minutes of Board of Public Works Meeting of August 6, 2015 Page 1
manufacturers to expedite the manufacture and delivery of these assemblies and
allows us to see the additional cost associated with an expedited delivery.
The following bids were received,
Vendor Bid Alt # 1 Bid Alt # 2 Bid Alt # 3
60 Days 90 Days 120 Days
Union Metal Corporation No Bid $32,655 $29,662
Hi-Way Safety No Bid $43,655 $32,320
The Division of Public Works recommends the City purchase the Mast Arm
Assemblies from Union Metal for $32,655. This will allow a delivery time of 90
days and avoid the added costs and difficulties if the project is delayed.
Mayor Lozeau confirmed that the Finance Committee approved this purchase at the
meeting on August 5th. Commissioner Bergeron asked when the project will be
moving forward. Mayor Lozeau responded that when it originally went out to bid, no
one showed up to the mandatory pre-bid meeting. Engineering has since reached out
to try to find some companies willing to bid and found two who were willing to look
at the project.
Senior Traffic Engineer Wayne Husband joined the discussion. He said that bids are
due on August 17th. The target completion date for the bulk of the work is before the
end of the season so residents can benefit from the changes before the winter.
Meeting adjourned at 2:10 pm
Minutes of Board of Public Works Meeting of August 6, 2015 Page 2
Agenda
City of Nashua
Public Works Division
9 Riverside Street (603) 589-3140
Nashua, NH 03062 Fax (603) 589-3169
Special Board of Public Works Meeting of August 6, 2015
Agenda
A special meeting of the Board of Public Works is scheduled for Thursday, August 6, 2015 at 2:00
p.m. at the Division of Public Works, Administration & Engineering offices, 9 Riverside Street,
Nashua, NH 03062.
I. Motion: To approve the Agenda as presented.
II. Public Comment
III. Engineering
A. Motion: To approve the purchase of eight (8) mast arm assemblies from
Union Metal Corporation in the amount of $32,655 funding will be through
Department 160 Admin/Engineering; Fund: General; Activity: Amherst
Street Road and Traffic Improvement.
Administration Street City Parks-Recreation Solid Waste Wastewater
Business Office Department Engineer Department Department Treatment Plant
(603) 589-3140 (603) 589-4750 (603) 589-3120 (603) 589-3370 (603) 589-3410 (603) 589-3560
City of Nashua, Public Works Division
To: Board of Public Works Meeting Date: August 6, 2015
From: Wayne Husband, P.E., Senior Traffic Engineer
Engineering Department
Re: Mast Arm Assemblies for Charron Ave. and Wholefood Retail intersections
A. Motion: To approve the purchase of eight (8) mast arm assemblies from Union Metal
Corporation in the amount of $32,655 funding will be through Department 160
Admin/Engineering; Fund: General; Activity: Amherst Street Road and Traffic
Improvement.
Discussion: The City is currently in the process of soliciting bids from contractors for the
reconstruction of Amherst Street from the Charron Avenue intersection easterly to
the existing jug handle across from Wholefood retail. This project is needed to
provide additional capacity through this area of Amherst Street (Route 101A).
In order to meet an expedited construction schedule, the City is purchasing the
mast arm assemblies directly from the manufacturer. This allows the City to
accelerate the delivery time in advance of awarding a construction contract.
There is typically a considerable lead time that needs to be planned for the
manufacture and delivery of mast arms.
The City put out three bid alternates for the manufacture and delivery time frames
(60 days, 90 days, and 120 days). This was done in an effort to offer an incentive
to manufacturers to expedite the manufacture and delivery of these assemblies
and allows us to see the additional cost associated with an expedited delivery.
The following bids were received,
Vendor Bid Alt # 1 Bid Alt # 2 Bid Alt # 3
60 Days 90 Days 120 Days
Union Metal Corporation No Bid $32,655 $29,662
Hi-Way Safety No Bid $43,655 $32,320
The Division of Public Works recommends the City purchase the Mast Arm
Assemblies from Union Metal for $32,655. This will allow a delivery time of 90
days and avoid the added costs and difficulties if the project is delayed.