Board of Public Works
Regular MeetingNashua, NH · October 22, 2015
Minutes
Minutes of Board of Public Works
Meeting of October 22, 2015
A regular meeting of the Board of Public Works was held on Thursday, October 22, 2015 at
5:30 p.m. at the Division of Public Works, Administration & Engineering offices, 9 Riverside
Street, Nashua, NH 03062.
Members Present
Mayor Donnalee Lozeau, Chair Lisa Fauteux, Director of Public Works
Commissioner Kevin S. Moriarty, Vice Chair David Simmons, Superintendent of Wastewater
Commissioner Paul G. Bergeron Nick Caggiano, Superintendent of Parks &
Recreation
Commissioner Tracy Pappas Steve Dookran, City Engineer
Commissioner Joel Ackerman Ken Siegel, Aldermanic Liaison
Mayor Lozeau called the meeting to order at 5:30 p.m. and called the roll.
Commissioner Moriarty: Present
Commissioner Bergeron: Present
Commissioner Pappas: Present
Commissioner Ackerman: Present
Mayor Lozeau: Present
I. MOTION: Commissioner Pappas to approve the Agenda as presented.
SECONDED: Commissioner Moriarty
MOTION CARRIED: Carried Unanimously
II. MOTION: Commissioner Pappas to approve the Minutes of the Board of Public Works
Meeting of September 17, 2015.
SECONDED: Commissioner Moriarty
MOTION CARRIED: Carried Unanimously
III. Aldermanic Referrals
A. R-15-175 FIRST AMENDMENT TO THE SITE LEASE AGREEMENT WITH
SPRINT SPECTRUM REALTY COMPANY, L.P. (SUCCESSOR-IN-INTEREST TO
SPRINT SPECTRUM, L.P.) TO RELOCATE THE LESSEE’S COMMUNICATION
EQUIPMENT LOCATED AT WHIPPLE STREET, MINES FALL PARK TO THE
NEW REPLACEMENT TOWER
MOTION: Commissioner Pappas moves for a positive recommendation for Aldermanic
Referral: R-15-175.
SECONDED: Commissioner Moriarty
MOTION CARRIED: Unanimously
DISCUSSION:
Minutes of Board of Public Works Meeting of October 22, 2015 Page 1
IV. Broad Street Parkway
A. Motion: Commissioner Pappas to approve and place on file the Informational Update
of overall status on the Broad Street Parkway.
SECONDED: Commissioner Moriarty
MOTION CARRIED: Unanimously
DISCUSSION:
John Vancor provided an update on the status of the Broad Street Parkway Project.
Attached is the updated report on the project.
B. Motion: Commissioner Pappas to approve the amendment to the contract for
Environmental Services with Sanborn Head Associates in the amount of $35,500.
Funding will be through Department 160 Admin/Engineering; Fund: Bond; Activity:
Broad Street Parkway.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
The original contract awarded in July 2012 for $267,300 with Sanborn Head was
primarily for evaluating underground hazardous materials and groundwater within the
parkway footprint, as well as designing the measures to mitigate project impacts.
Amendments 1, 2 and 3, totaling $166,441, were for added environmental services
related to construction. These services included but were not limited to testing and
monitoring of the removal and disposal of large amounts of buried asbestos on Parkway
North, dealing with a buried contaminated tank found at 44 Broad St. and addressing
contaminated drilled shaft spoils related to the foundation of the Nashua River Bridge.
Amendments 4, 5, 6 and 7, totaling $109,000 incrementally provided additional budget
so that if unanticipated underground hazardous material were encountered, Sanborn
Head could react quickly and in so doing, avoid or minimize potential construction
delays.
As additional buried asbestos continued to be encountered, Amendments 8 and 9
provided budget for Sanborn Head to further increase the efforts to monitor ongoing
excavation within the Millyard. Sanborn Head provided staff whenever excavation
occurred in the Millyard. This effort enhanced awareness, reduced the timeline needed
to sample suspect excavated material and reduced reaction time as additional pockets of
asbestos were encountered.
Amendment 10 provides further budget for this oversight. More asbestos has been
encountered. In some cases the nature of the material encountered has required different
disposal procedures. The effort to address asbestos continues to take greater time by the
Contractor than anticipated requiring more oversight.
V. Wastewater Department:
A. Motion: Commissioner Pappas to approve the User Warrants as presented.
SECONDED: Commissioner Moriarty
Minutes of Board of Public Works Meeting of October 22, 2015 Page 2
MOTION CARRIES: Unanimously
DISCUSSION:
B. Motion: Commissioner Pappas to approve the contract in an amount not to exceed of
$45,000 over a 3 year period with Chemserve Environmental Analyst of Milford, NH for
water quality sampling of the Nashua and Merrimack Rivers in conjunction with the
CSO Post Construction Monitoring Plan. Funding will be through Department: 169
Wastewater; Fund: Wastewater; Account Classification: 53 Professional & Technical
Services.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
The EPA Consent Decree mandated CSO improvements are now complete. The
Consent Decree requires a post construction monitoring plan including sampling of the
Nashua and Merrimack Rivers at 4 locations for dry and wet weather conditions four
times a year. The purpose of this request is to hire a sampling and water quality analysis
company for a 3-years contract to collect and analyze the required samples.
This project will benefit the City by ensuring that CSO discharges meet the design storm
they are supposed to discharge in order to keep the Nashua and Merrimack Rivers as
clean as possible during storm conditions. Since the EPA mandated Consent Decree
CSO improvements are complete a water quality sampling and analysis program is
required to assess the effectiveness of the 7 CSO structures with outfall discharges. In
addition to the water quality benefits of the sampling and analysis, this program will
keep the City in good standing with the EPA which could implements fines should the
City fail to have in place a water quality monitoring plan.
Six environmental consultants were given proposals, two provided bids, as follows:
Consultant Costs for 3 Years Annual Costs
Chemserve Environmental $45,000 $15,000
Normandeau Associates $74,767.28 $24,922.43
The consultant’s bid the project over a 3 year period, but in Addendum-1 it specifies the
maximum number of samples to be taken per year. Each year the same maximum
number of samples will be collected so the total samples and costs are divided by 3 to
come up with the annual (not to exceed) costs.
The Wastewater Plant currently uses Chemserve to perform laboratory analyses of
certain constituents in the plant and industrial wastewater that the lab does not have the
capability to analyze. They have provided well for the laboratory for many years and we
recommend that they be approved for these services.
C. Motion: Commissioner Pappas to accept and place on file that John Adie, Plant
Operations Supervisor, is the recipient of the 2015 Water Environment Federation
William D. Hatfield Award.
Minutes of Board of Public Works Meeting of October 22, 2015 Page 3
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
Commissioner Pappas acknowledged John Adie for his hard work. Superintendent Dave
Simmons explained that the award is for the outstanding commitment to operations in
the field of wastewater and is a great honor to receive.
Commissioner Moriarty requested that the Board send a letter to Mr. Adie
congratulating him on receiving the award.
D. Informational: EPA Permit Status
MOTION: Commissioner Pappas to approve the EPA Permit Status update.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
A packet was handed out to the commissioners and is attached.
Director Fauteux acknowledged Mayor Lozeau for her part in this process which has
been very beneficial. Commissioner Bergeron recalled a time not too long ago when the
City’s rivers were very unhealthy and commended the City’s efforts to improve the
quality of them.
E. Motion: Commissioner Pappas to approve the contract with Highland Power of
Brockton, MA in the amount of $11,500 for Waukesha Generator repairs. Funding will
be through Department: 169 Wastewater; Fund: Wastewater; Account Classification: 54
Property Services.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
Highland Power was been the sole provider of repairs to the Waukesha generator since
2008. This has been documented by previous sole source letters. The Waukesha
generator produces electricity for the plant or power grid by burning methane produced
through the digestion process.
The generator is in need of a resealed oil plan. After the repair, Highland will test run the
unit and check for leaks.
For these reasons, I recommend that we hire Highland Power to perform the necessary
repairs.
F. Informational: Hazen and Sawyer EPA Appeal Invoice
MOTION: Commissioner Pappas to approve the EPA Appeal Invoice update.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
Minutes of Board of Public Works Meeting of October 22, 2015 Page 4
Mayor Lozeau summarized the update, stating that there was a misunderstanding as to
who Hazen and Sawyer would invoice for their services. Hazen Sawyer invoiced the
City instead of Rath, Young, Pignatelli which was the City Staff’s original assumption,
so the City has brought the invoice before the Board as an informational piece. The cost
of the service came in under the original estimate.
VI. Parks Department:
A. Motion: Commissioner Pappas to approve the selection of Mr. Shawn Dyer of
Merrimack, NH to the position of Groundskeeper / Maintenance at the Parks and
Recreation Department. Starting salary for this position will be $24.81 per hour for a
yearly salary of $51,188.8. Funding is through Department: 171 Parks and Recreation;
Fund: General; Account Classification: 51-Salary & Wages.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
This position was posted per the AFSCME CBA and there were three internal applicants
from the department.
The interview team of Nick Caggiano, Parks and Recreation Superintendent, Eric Ryder
Streets Superintendent and Jeff Lafleur Solid Waste Superintendent developed interview
questions related to the job and scored and rated the applicant. The candidates were then
administered a general knowledge written test based on the requirements of the position
as well as a field test. After review of the interview and test scores, the applicant that
met minimum qualifications and with the most department seniority was selected. Mr
Dyer met the guidelines and is recommended for the position.
Mr. Dyer has been employed by the city for the past 20 years. He started out as summer
help then became a Groundsman I and then was promoted to Truck Driver. Mr Dyer
currently holds a Commercial Driver’s License, and has performed his duties well.
Parks and Recreation Superintendent Nick Caggiano joined the discussion.
Commissioner Pappas wanted to confirm that Mr. Dyer can plow. Superintendent
Caggiano confirmed that he can and that he is one of the department’s better drivers.
Commissioner Moriarty noted that driving requirements were not listed on the
application. Superintendent Caggiano responded that it is a current system limitation that
internal candidates are not asked to list their driving credentials. He will follow up with
Human Resources again about making that change.
B. Motion: Commissioner Pappas to approve the elimination of the Truck Driver positon at
the Parks and Recreation Department, and the creation of a Groundsman I position.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
Minutes of Board of Public Works Meeting of October 22, 2015 Page 5
This proposal will eliminate the vacant Driver position and create a Groundsman I
position. This change will save the department $2,849 per year and will help with the
2017 budget. This change will eliminate the only driver position in the department
which will streamline the process of assigning work in the morning. This will provide a
more versatile work group for both the winter and summer seasons. This position will
also provide an individual to work on grass crews, mowing, trimming, weeding, and
setting up ball fields and rectangular fields. With the removal of the one Park and
Recreation Truck Driver classification we will be able to assign work without going
through the time consuming process of calling this out on days when needed. There will
be a positive annual financial impact of $2,849 by downgrading this position from a rate
of $21.70 per hour to a rate of $20.33 per hour. It is the Superintendents
recommendation that this change be made.
C. Informational: Commissioner Pappas to accept and place on file the 2015 Summer
Camp Revenue summary report.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
Superintendent Caggiano reviewed the 2015 Summer Camp Revenue summary report.
He also discussed two new camps for next year – yoga camp and fitness camp.
Commissioner Pappas mentioned that she has received requests to restripe the parking
lot at Main Dunstable Soccer Field. Superintendent Caggiano said he would look into it
and agreed that it probably hasn’t been painted in years.
Commissioner Pappas also suggested that soccer coaches be asked that if snacks or
drinks were given to kids they or their parents please take the trash home with them.
Superintendent Caggiano said that the City currently empties 220 trash cans there every
Monday and Friday.
Commissioner Bergeron noted how fantastic it is that these camps are profitable. He also
noted the wonderful variety of camps offered.
VII. Engineering Department:
A. Motion: Commissioner Bergeron to approve the Residential and Commercial
Wastewater Service Permits and Fees as submitted.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
Minutes of Board of Public Works Meeting of October 22, 2015 Page 6
Residential and Commercial Wastewater Service Permits
September 1 through September 30, 2015
Connection 10% Discount
Betterment
Date Permit Appl Location Address Name Comments Fees
# #
Entrance
278 Daniel Webster
9/01/2015 23589 13420 Mike Silva Increase Use $295.00 X
Hwy
Holly Original
9/16/2015 23590 13421 52 Legacy Dr $295.00 X
McCarty Application
Holly Original
9/16/2015 23591 13422 53 Legacy Dr $295.00 X
McCarty Application
5 Pine St Ext-N, Stephen
9/16/2015 23592 13423 Increase Use $0.00 X
Unit 1D Bonnette
17 Courtney Ln, Original
9/22/2017 23593 13424 Robert Dion $295.00 X
Unit 7 Application
354 Amherst St,
9/30/2015 23594 13425 Ed Campbell Increase Use $0.00 X
Unit 5
TOTAL $1,180.00
B. Motion Removed From Agenda
Mayor Lozeau removed the motion from the agenda. She provided an update on the
status of the completion of the two crosswalks on Main Street. The Finance Committee
did not approve the crosswalks on the 10/21 meeting. The bid from Hutter was at least
twice as much as it would cost for the City to complete the work. She hopes to be able to
find a compromise to still get the crosswalks completed before winter – possibly by
having the City do some of the work and contracting less work from Hutter.
Commissioner Bergeron expressed his support for getting the crosswalks completed this
year. He also feels that the businesses on Main Street and the residents of Nashua would
be in support. The Main Street infrastructure project has lasted four construction seasons
which is the equivalent of 27 months – completing it this year would be ideal.
C. Motion: Commissioner Pappas to accept and place on file the Paving Program Update.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
Minutes of Board of Public Works Meeting of October 22, 2015 Page 7
Attached is an update of the status of the streets included in the 2014/2015 Paving
Program.
Engineering is working with utilities, contractors and the Wastewater and Street
Departments to prepare streets for paving. Coordination of paving with other city
projects is ongoing.
Manchester St paving was completed on Saturday, October 10, 2015. East Hobart St,
Oak St, and Whitney St are scheduled for the week of October 19. This will conclude
paving for the year.
Paving of Mulberry St., Tolles St (Whitney to Canal), and Canal St. will be delayed until
the required sewer repairs are completed.
D. Motion: Commissioner Pappas moves to accept and place on file the Consent Decree
(Civil Action No. 05-376-PB, dated December 26, 2005) on Combined Sewer
Overflows – July 1 to September 30, 2015 Quarterly Report on Compliance.
SECONDED: NONE
MOTION CARRIES: Unanimously
DISCUSSION:
VIII. Street Department:
A. Motion: Commissioner Pappas to approve the purchase of four Swenson EV100
1056SS Stainless Steel V-Box Spreaders from H.P. Fairfield, Pembroke, NH for the
price of $10,500 each for a total purchase of $42,000. Funding will be through
Department: 161 Streets; Fund: Prior Year Escrows; Account Classification: 71
Equipment.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
The Street Department went out to bid April 25, 2014 to up-fit four, six-wheel dump
trucks purchased in March 2014. This bid included the purchase of Stainless Steel V-
Box Spreaders. H. P. Fairfield has offered to hold the pricing of the sanders to the price
quoted per the bid.
The current tailgate spreaders are showing signs of excess wear and corrosion.
The stainless steel drop in sanders with ground speed controls will more effectively
control the amount of material being applied, and they are preferable as the stainless
sanders have a 20 year life expectancy plus the ability to mount the sander onto a
different truck should there be a need.
Commissioner Ackerman asked if we were getting government pricing. Superintendent
Caggiano said that we have purchased from H.P. Fairfield in the past and the Purchasing
Department allows us to not have to go out to bid again if a vendor holds their price
Minutes of Board of Public Works Meeting of October 22, 2015 Page 8
within a certain period of time. H.P. Fairfield held their price so we didn’t have to go out
to bid.
B. Motion: Commissioner Pappas approve the award of the FY16 Pavement Markings
contract to Hi-Way Safety Systems, Inc. of Rockland, MA in the amount of $155,525.
Funding for this contract is through Department 161: Streets; Fund: General; Account
Classification: 54 – Property Services.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
DISCUSSION:
City of Nashua annual Pavement Marking Program was put out to bid in July 2014.
Three bids were received on July 17, 2014 as follows,
HI-Way Safety Systems, Inc. $155,525
Markings Inc. $160,125
L&D Safety Marking $257,250
Highway Safety Systems, Inc. was awarded the contract for FY 2015, and their
performance has been satisfactory for the past several years. Highway Safety has agreed
to hold their unit prices for the same quantities from their FY 2015 bid during FY 2016.
It is the recommendation of the Superintendent of Streets to extend their contract into
FY 2016 given the contractor has agreed to hold their last years pricing.
Commissioner Bergeron asked if we were happy with the service provided by Hi-Way
Safety Systems since we’ve had a number of issues with paint and striping and new
techniques. Mayor Lozeau responded that our issues with Thermoplastic in the past has
been related to putting it down when it is too cold or when the pavement isn’t fresh
enough. The City has been happy overall with this company’s work.
Commissioner Bergeron asked about the status of the striping on Manchester and
Concord Street. Director Fauteux said it should be completed in about three weeks.
IX. Administration
A. Informational:
i. Motion: Commissioner Pappas to accept and place on file the Main Street
Sidewalk Update.
SECONDED: Commissioner Moriarty
MOTION CARRIES: Unanimously
ii. Director’s Report
A series of slides showing various current Public Works projects and activities
were shown.
X. Commissioner’s Comments
Minutes of Board of Public Works Meeting of October 22, 2015 Page 9
None.
Meeting adjourned at 6:51 pm
Minutes of Board of Public Works Meeting of October 22, 2015 Page 10
Broad Street Parkway
Construction Contract Status Update
Prepared October 15, 2015
Parkway North/Baldwin Street Bridge
As Reported
Update
September 9, 2015
Contract Amount $10,884,025 $10,884,025
Progress Report:
Work on this contract is substantially complete.
Only punchlist tasks remain.
Agenda
City of Nashua
Public Works Division
9 Riverside Street Phone (603) 589-3140
Nashua, NH 03062 Fax (603) 589-3169
Board of Public Works Meeting of October 22, 2015
Agenda
A meeting of the Board of Public Works is scheduled for Thursday, October 22, 2015 at 5:30
p.m. at the Division of Public Works, Administration & Engineering offices, 9 Riverside Street,
Nashua, NH 03062.
I. Motion: To approve the Agenda as presented.
II. Motion: To approve the Minutes of the Board of Public Works Meeting of September
17, 2015.
III. Public Comment
IV. Aldermanic Referrals
A. R-15-175 - APPROVING A FIRST AMENDMENT TO THE SITE LEASE
AGREEMENT WITH SPRINT SPECTRUM REALTY COMPANY, L.P.
(SUCCESSOR-IN-INTEREST TO SPRINT SPECTRUM, L.P.) TO RELOCATE
THE LESSEE’S COMMUNICATION EQUIPMENT LOCATED AT WHIPPLE
STREET, MINES FALL PARK TO THE NEW REPLACEMENT TOWER
V. Broad Street Parkway
A. Informational: Overall Status of the Broad Street Parkway.
B. Motion: To approve Amendment to contract for Environmental Services with
Sanborn Head Associates in the amount of $35,500. Funding will be through
Department 160 Admin/Engineering; Fund: Bond; Activity: Broad Street Parkway.
VI. Wastewater Department:
A. Motion: To approve the User Warrants as presented.
B. Motion: To approve the contract in an amount not to exceed of $45,000 over a 3
year period with Chemserve Environmental Analyst of Milford, NH for water
quality sampling of the Nashua and Merrimack Rivers in conjunction with the CSO
Post Construction Monitoring Plan. Funding will be through Department: 169
Wastewater; Fund: Wastewater; Account Classification: 53 Professional &
Technical Services.
C. Informational: To acknowledge that John Adie, Plant Operations Supervisor, is the
recipient of the 2015 Water Environment Federation William D. Hatfield Award.
D. Informational: EPA Permit Status
Administration Street City Parks-Recreation Solid Waste Wastewater
Business Office Department Engineer Department Department Treatment Plant
(603) 589-3140 (603) 589-4750 (603) 589-3120 (603) 589-3370 (603) 589-3410 (603) 589-3560
Board of Public Works Meeting of October 22, 2015 Agenda Page | 2
E. Motion: To approve the contract with Highland Power of Brockton, MA in the
amount of $11,500 for Waukesha Generator repairs. Funding will be through
Department: 169 Wastewater; Fund: Wastewater; Account Classification: 54
Property Services.
F. Informational: Hazen and Sawyer EPA Appeal Invoice
VII. Engineering Department:
A. Motion: To approve the Residential and Commercial Wastewater Service Permits
and Fees as submitted.
B. Motion: To approve the construction contract for the Main Street Mid-Block
Crosswalks to Hutter Construction, Inc. of New Ipswich, NH in an amount not to
exceed $184,000. Funding will be through: Department: 161 - Street; Fund:
General; Activity Description: Main Street.
C. Informational: Paving Program Update
D. Informational: Consent Decree (Civil Action No. 05-376-PB, dated December 26,
2005) on Combined Sewer Overflows – July 1 to September 30, 2015 Quarterly
Report on Compliance.
VIII. Parks Department:
A. Motion: To approve the selection of Mr. Shawn Dyer of Merrimack, NH to the
position of Groundskeeper / Maintenance at the Parks and Recreation Department.
Starting salary for this position will be $24.81 per hour for a yearly salary of
$51,188.8. Funding is through Department: 171 Parks and Recreation; Fund:
General; Account Classification: 51-Salary & Wages.
B. Motion: To approve the elimination of the Truck Driver positon at the Parks and
Recreation Department, and the creation of a Groundsman I position.
C. Informational: To accept and place on file the 2015 Summer Camp Revenue
summary report.
IX. Street Department:
A. Motion: To approve the purchase of four Swenson EV100 1056SS Stainless Steel
V-Box Spreaders from H.P. Fairfield, Pembroke, NH for the price of $10,500 each
for a total purchase of $42,000. Funding will be through Department: 161 Streets;
Fund: Prior Year Escrows; Account Classification: 71 Equipment.
B. Motion: To approve the award of the FY16 Pavement Markings contract to Hi-Way
Safety Systems, Inc. of Rockland, MA in the amount of $155,525. Funding for this
contract is through Department 161: Streets; Fund: General; Account Classification:
54 – Property Services.
X. Administration
A. Informational:
i. Main Street Sidewalk Update
ii. Director’s Report
C. Commissioner’s Comments
D. Possible Non-Public Session
2
Broad Street Parkway Project
Budget v Projections
As of 10-16-2015
This report provides updates based on the $68,107,000
budget to complete the project as estimated in July,
2008.
At that time, total project cost, including costs already
Revenue Federal 1 Bond Total Revenue incurred before the City took over management, was
$ 30,507,000 $ 37,600,000 $ 68,107,000 projected to be $82,453,000
Expenses
Budget Budget Projection Projection Committed Costs to Date
July, 2008 January, 2011 9/10/2015 10/16/2015 Federal Bond Balance
Overall Project $ 68,107,000
Construction $ 39,790,000 $ 32,004,470 $ 32,077,864 $ 19,142,373 $ 12,935,491 $ 0
Construction Administration $ 4,270,000 $ 3,916,521 $ 3,916,521 $ 195,000 $ 3,706,727 $ 14,794
Design $ 2,880,000 $ 2,898,015 $ 2,898,015 $ 2,075,093 $ 757,922 $ 65,000
Project Admin/Prof. Services * $ 3,426,586 $ 3,426,586 $ 379,113 $ 2,704,482 $ 342,991
Utility Relocation $ 1,510,000 $ 743,718 $ 743,718 $ - $ 623,216 $ 120,502
Right-of-Way $ 7,550,000 $ 8,346,300 $ 8,346,300 $ 7,945,500 $ 400,800 $ -
Hazardous Mitigation $ 3,470,000 $ 2,498,921 $ 2,498,921 $ - $ 2,498,921 $ -
Environmental Mitigation $ 640,000 $ 815,485 $ 815,485 $ 27,876 $ 767,609 $ 20,000
Other Costs - Allowances $ 7,220,000 $ 4,400,000 $ 4,494,000 $ 1,073,450 $ 3,063,441 $ 357,109 2
Total $ 68,107,000 $ 67,330,000 $ 59,050,016 $ 59,217,410 $ 30,838,405 $ 27,458,609 $ 920,396
* Included under "Other Costs - Allowances"
1
Current Projections reflect updated escalation factor Note: the total Federal Funds listed is the total as of July, 2008 when the maximun bond
Bond Sales: amount was established. The City has secured additional Federal funding since this time. This
$2,205,000 8/10 additional funding will serve to reduce the amount of City Bond which will be required.
$2,500,000 10/11
$1,662,000 4/13 Federal Grant received for sidewalks on River Bridge = $487,000
$17,000,000 6/14 Funding through Federal Railroad Crossing Program = $304,274
$8,000,000 4/15
$31,367,000
2
$6,233,000 Remaining Bond balance Note: The proceeds of the sale of surplus property to date ($420,847) have been added to the
budget for other costs and allowances
City of Nashua
Public Works Division Wastewater Department
9 Riverside Street (603) 589-3560
Nashua, NH 03062 Fax (603) 594-3474
Board of Public Works Meeting of October 22, 2015
Wastewater Department
Agenda
A. Motion: To approve the User Warrants as presented.
B. Motion: To approve the contract in an amount not to exceed of $45,000 over a 3
year period with Chemserve Environmental Analyst of Milford, NH for water quality
sampling of the Nashua and Merrimack Rivers in conjunction with the CSO Post
Construction Monitoring Plan. Funding will be through Department: 169
Wastewater; Fund: Wastewater; Account Classification: 53 Professional & Technical
Services.
C. Informational: To acknowledge that John Adie, Plant Operations Supervisor, is the
recipient of the 2015 Water Environment Federation William D. Hatfield Award.
D. Informational: EPA Permit Status
E. Motion: To approve the contract with Highland Power of Brockton, MA in the
amount of $11,500 for Waukesha Generator repairs. Funding will be through
Department: 169 Wastewater; Fund: Wastewater; Account Classification: 54
Property Services.
F. Informational: Hazen and Sawyer EPA Appeal Invoice
Administration Street City Parks-Recreation Solid Waste Wastewater
Business Office Department Engineer Department Department Treatment Plant
(603) 589-3140 (603) 589-4750 (603) 589-3120 (603) 589-3370 (603) 589-3410 (603) 589-3560
City of Nashua, Public Works Division
To: Board of Public Works Meeting Date: October 22, 2015
From: David A. Simmons, Superintendent
Wastewater Department
Re: EPA Permit Status
D. Informational: EPA Permit Status
Attachment: Memorandum
City of Nashua, Public Works Division
To: Board of Public Works Meeting Date: October 22, 2015
From: David A. Simmons, Superintendent
Wastewater Department
Re: Waukesha Generator Repairs
Attachment: Quote
E. Motion: To approve the contract with Highland Power of Brockton, MA in the amount of
$11,500 for Waukesha Generator repairs. Funding will be through Department: 169
Wastewater; Fund: Wastewater; Account Classification: 54 Property Services.
Discussion: Highland Power was been the sole provider of repairs to the Waukesha generator
since 2008. This has been documented by previous sole source letters. The Waukesha
generator produces electricity for the plant or power grid by burning methane
produced through the digestion process.
The generator is in need of a resealed oil plan. After the repair, Highland will test run
the unit and check for leaks.
For these reasons, I recommend that we hire Highland Power to perform the
necessary repairs.
City of Nashua
Public Works Division Wastewater Department
9 Riverside Street Sawmill Rd, Nashua, NH 03060
Nashua, NH 03062 Fax (603) 594-3474
Memorandum
Date: October 15, 2015
To: Lisa Fauteux, Director of Board of Public Works
From: David A. Simmons, Wastewater Superintendent
Re: Hazen and Sawyer Invoices for EPA Appeal Process
__________________________________________________________________________________________________
The legal firm of Rath, Young, Pignatelli, P.C. was hired by the City of Nashua to provide legal representation
in the appeal process with the EPA in reference to the new NPDES Permit that was issued in March 2015. Rath,
Young, Pignatelli, P.C. retained the services of Hazen and Sawyer to provide the technical data required to
proceed with the permit appeal.
Rath, Young, Pignatelli asked Hazen and Sawyer to provide a scope of services and an estimate. They estimated
a cost of $67,514 to complete the work. The scope and estimate was accepted and Rath, Young, Pignatelli
began their work with Hazen and Sawyer. It was the City’s understanding that Hazen and Sawyer would invoice
the City through Rath, Young, Pignatelli which didn’t happen.
As a result, the City will now need to create a purchase order for the agreed upon services and pay Hazen
Sawyer directly. The invoice total is $9,532.85 below the original budget estimate of $67,514.
Administration Street/Traffic City Parks-Recreation Solid Waste Wastewater
Business Office Department Engineer Department Department Treatment Plant
(603) 589-3140 (603) 589-4750 (603) 589-3120 (603) 589-3370 (603) 589-3410 (603) 589-3560
City of Nashua, Public Works Division
To: Board of Public Works Meeting Date: October 22, 2015
From: Stephen Dookran, P.E., City Engineer
Engineering Department
Re: Main Street Mid-Block Crosswalks – Construction Contract
B. Motion: To approve the construction contract for the Main Street Mid-Block Crosswalks
to Hutter Construction, Inc. of New Ipswich, NH in an amount not to exceed
$184,000. Funding will be through: Department: 161 - Street; Fund: General;
Activity Description: Main Street.
Discussion: The Main Street Mid-Block Crosswalks project includes improvements to two
crosswalks, one located near the intersection of High Street and the other near the
intersection of Eldridge Street. These crosswalks will be similar to the two
existing mid-block crosswalks located at the Main Street Bridge and near 100
Main Street.
In anticipation of this work, the City is purchasing the granite and brick materials
needed for this project. Recently, Hutter Construction, Inc. was approached for a
quote to perform the installation of these crosswalks to keep the Main Street
project on schedule for completion this year. Attached is a proposal from Hutter
to complete both crosswalk improvements for a total cost of $164,060 by the end
of this year. In order to ensure completion of the project by the end of the year, a
twelve percent (12%) contingency has been added to the proposal cost to allow
for any unknown conditions during construction.
The price submitted by Hutter is reasonable. Hutter is constructing crosswalks for
the City on Manchester St and Concord St with satisfactory results. Further,
Hutter has recently successfully completed similar sidewalk and crosswalk
improvements for Rivier University.
October 22, 2015
Paving Program Status Update as of 10/19/15
Streets to be paved
Status
Name From To
Dow St Summer St Lock St Completed
Haines St Arlington St Gillis St Completed
Rogers St Concord St Webster St Completed
Stanley Ln Entire length Completed
Cross St Lock St Summer St Completed
Freemont St
(Including Dublin St Dublin Ave Woodland Dr Completed
intersection)
Ritter St Kinsley St Ross St Completed
Mulberry St Chestnut St Walnut St Delayed due to required sewer work.
Holbrook Dr Yarmouth Dr Nutmeg Dr Completed
Boulder Cir Entire length Completed
Faxon St Entire length Completed
Tolles St Courtland St Whitney St Completed
Kinsley St Hanover St Main St Delayed due to required sewer work.
Canal St Howard Ct Jackson Ave Delayed due to required sewer work.
Manchester St Concord St Ferry Rd Completed
Ledge St 165 Ledge St Seventh St Completed
Major utility work is planned. Milling and patching distressed
Main St Allds St Orchard Ave
areas for the winter will be completed by others.
East Hobart St Entire length Completed
Sewer Project Streets
Belmont St Entire length Completed
Grove St Whitney St to Lock St Completed
Robinson Ct Entire length Completed
Eldridge St Entire length Reclaimed & base paved. Final paving October*
Oak St Entire length Reclaimed & base paved. Final paving October*
Whitney St 61 Whitney St Tolles St Reclaimed & base paved. Final paving October*
Cross St Holman St Lock St Completed.
*Final schedule to be determined. Schedule dependent upon progress with preparation work. Paving schedule is also
weather dependent.
City of Nashua, Public Works Division
To: Board of Public Works Meeting Date: October 22, 2015
From: Eric Ryder, Superintendent
Street Department
Re: Purchase of four Swenson EV100 1056SS Stainless Steel V-Box Spreaders.
A. Motion: To approve the purchase of four Swenson EV100 1056SS Stainless Steel V-Box
Spreaders from H.P. Fairfield, Pembroke, NH for the price of $10,500 each for a
total purchase of $42,000. Funding will be through Department: 161 Streets;
Fund: Prior Year Escrows; Account Classification: 71 Equipment.
Attachments: Quote sheet and Dealer letter
Discussion: The Street Department went out to bid April 25, 2014 to up-fit four, six-wheel
dump trucks purchased in March 2014. This bid included the purchase of
Stainless Steel V-Box Spreaders. H. P. Fairfield has offered to hold the pricing of
the sanders to the price quoted per the bid.
The current tailgate spreaders are showing signs of excess wear and corrosion.
The stainless steel drop in sanders with ground speed controls will more
effectively control the amount of material being applied, and they are preferable
as the stainless sanders have a 20 year life expectancy plus the ability to mount
the sander onto a different truck should there be a need.
Board of Public Works Meeting of October 22, 2015
Department Report
Street Department
Main Street Sidewalks. Work on Block 3 continues with the installation of underground
drainage. The brick ribbons continue to be installed along with the brick work in front of Nashua
Bank. The framing and pouring of the remaining concrete pads on Block 3 will continue the
week of 10/12. The electricians along with the traffic technicians have been working to get the
street light on Blocks 4 & 5 working.
Sidewalks. Crews have installed new concrete sidewalks along Lake Street from Lewis Street to
Monroe Street.
Potholes. Crews have filled over 35 potholes this month along with patching manhole and catch
basin excavations.
Manhole Repairs. Crews continue to repair manhole and catch basin frames that had become
compromised this past winter. Some of the repair work was minor with just new pavement while
others required new frames and covers or a completely new structure.
Street Sweeping. The sweepers continue to clean the residential areas. The downtown sweeper
has been working keeping the inner city clean.
Signs and Pavement Markings. Over the past month more than 25 signs have been replaced or
repaired including Stop signs, several street name signs and several parking regulations.
We have also been recoating thermoplastic markings along major routes at night. Crosswalk
painting continues on every suitable weather day. The Crew has been painting the overnight
parking spots.
Fleet Department. Preventative Maintenance is scheduled and performed daily on all DPW
department vehicles. Backline plow trucks are being readied for winter operations. State
inspections on the fleet currently at 99 % completed with the remaining backline trucks in the
repair process.
Weld Shop. The Welders are repairing body rot and corrosion on the beds, bodies and tailgates
on various trucks. Plows are being repaired for winter.
Traffic Signals. The traffic signal technicians investigated and/or fixed calls for 20 traffic
signals. There were 4 after hour call in’s for signals not working properly. We also assisted other
departments by installing variable message boards at several locations for different projects. We
installed the street light poles on Block 4 & 5. The crew has installed the new solar crosswalk at
Hills Ferry Rd. @ Manchester St.
Parks & Recreation Department
2015 Trips. Our next trip will be to New York City in December. Followed by a trip to see
Cirque Du Soleil and then to a Bruins Game. Please look at the website for details.
Holman Stadium. The stadium is in maintenance mode. There will be facility and field work to
do for the remainder of the season.
Stellos Stadium. The fall season is in full production. The stadium has a very busy schedule for
the fall. Playoff schedules will be posted as they become available.
1
Fall Ball. The fall baseball programs are wrapping up for the year. This instructional step up
program helps develop player skills.
Ball field Maintenance. Work has been completed at the Haines Street complex as well as
Murray Field and Ledge Street. The next complexes scheduled for work are Shady Lane and
Lyons Field.
Centennial Pool. Work has started on the renovations at the pool. A set of stairs, new coping
and a liner are scheduled for installation this fall.
Pools. The pools are being winterized for the season. Meetings were held with the pool
coordinators to develop maintenance list for 2016.
Gate City Fall Festival. The Fall Festival was held on Saturday October 17th. A parade was held
going up Main Street which ended at Holman Stadium. At the Stadium there were crafts, games,
performances and a costume contest.
Biddy Basketball. The 2015 / 2016 season is underway. Tryouts have occurred and the draft
was held. Practices start up in November.
Fright Night. Fright Night is scheduled for Friday October 30th at Greeley Park. The nun will
start at 6:30. Please join us for a haunted hay ride and try to get through the garden maze of
terror.
Columbus Day Soccer Tournament. The holiday weather provided a wonderful weekend for
over 150 teams to travel to Nashua. Games were held at the Main Dunstable Fields, Mine Falls
Park Fields and Stellos Stadium.
Roadside Mowing. Road side mowing of the levies, trails and intersections is ongoing and
should continue through mid-November.
Main Street. Trees, plants and irrigation work are being done as the sidewalks are completed.
Plant and tree maintenance continues to be done along all of the existing beds along Main Street.
Broad Street Parkway Tree Planting. The planting of 330 trees started on October 12th. This
project is scheduled to be completed by the end of the month.
Bicentennial Park. The park rehabilitation work is underway. Demolition and the moving of the
monument were complete over October 8th – October 11th. The project is scheduled for
completion this fall.
Mine Falls Park Red Trail. All of the City approvals have been secured. There are still some
environmental permits that are coming in. Mobilization will begin as soon as these permits are
received.
Summerfun. Our 2016 fund raising campaign will be beginning soon. A recap of the 2015
season will be presented in November.
Senior Outing. The 2015 Outing is scheduled to be held on Sunday November 8th at the Crowne
Plaza Hotel. The event is sold out.
Engineering Department
CSO# 005 and CSO # 006 Screening and Disinfection Facility. Certificate of Occupancy has
been issued and a follow up training session was held on October 6th.
Burke Street Sewer Phase 2. Two construction crews and two lining crews are working to
install/remediate lateral service connections for sewer and drainage.
2015 Sewer Replacement Project. Pennichuck is continuing their work on the water line in
Temple St. Defelice has completed the sewer surface patches from East Hollis St to Amory St.
2
The sewer replacement effort between Franklin St and Auburn St is complete with the section to
be lined scheduled for this month.
2014 Sewer Replacement Project. Sidewalks restoration and final pavement on Belmont St
were completed.
Main Street Sidewalk Improvements. Engineering is overseeing construction while
coordinating material purchases and construction contracts with outside vendors. Construction
on Block 3 is nearing completion with just brick, planting, irrigation and electrical work
remaining. The two remaining mid-block crosswalks are in the process of being contracted out
for installation this year.
CDBG Manchester/Concord St Crosswalk Improvements. Hutter Construction has
completed two of the crosswalks in front of the Mt. Pleasant St School and is continuing with the
Concord St and Orange St location. Paving in the vicinity of these three locations is complete as
part of 2015 Paving Program.
Concord Street Crosswalks. Initial work on the Concord St crosswalks is being staged. Some
drainage adjustments are required to meet the intent of the work effort.
East Hollis Railroad Crossing. Scheduling and other logistical elements have held up progress
on the project. Engineering continues to work with DOT toward moving the project forward.
2014/2015 Street Paving Program. Manchester St paving is complete. East Hobart St, Oak St,
and Whitney St are scheduled for the week of October 19. This will conclude paving for the
year.
Amherst Street Improvements - Charron Ave to Diesel Road. Work continues on easement
documents and utility relocation. Project to be rebid for spring construction.
Merrimack River Levee. The annual inspection with the USACE took place on September 16.
Staff from the NHDES Dam Bureau were also in attendance.
Legacy Park-Cleveland Street. No bids were received on Sept 17 with construction scheduled
for this fall. It was determined that due to the lead time required for the playground equipment;
construction of the park would be better served if it is in spring 2016. The project was re
advertised with a bid opening on October 30th.
Yudicky Park -Access Road. The project was advertised on August 24. Three bids were
received on Sept. 9. The City selected J Parker & Daughters, the qualified low bidder, and
construction is scheduled to start early-mid October.
Site Development Review. Engineering has reviewed the following Site Development and
Subdivision plans: 323 Daniel Webster Highway, 621 & 625 Amherst St, 104 Canal St, and 19
Conant Rd.
Street Acceptance. Engineering is working on the street acceptance of a portion of Cherrywood
Dr, Moonstone Ct, Tamora Ct and Annabelle Ct. Three abutters have contacted us and we are
working with the developer to resolve those issues.
Construction Bond Guarantee. Bonds were reviewed and reduced for 260 East Dunstable
Road and new bonds were reviewed for 242 Main St (CVS).
Construction Inspection. The inspectors have provided inspection for the following projects:
2014 Paving Program, 2014 Sewer Rehabilitation, 2015 Sewer Rehabilitation, Burke St Sewer
Rehabilitation, Monis Farms Phase 2, 270 Amherst St, Rivier Crosswalk, 565 Amherst St, Lovell
and Ash Senior Housing project, Gagnon Farms and inspections for sewer service repairs
throughout the city.
Engineering Survey. Ongoing survey projects include: Southwest Park trail layout,
Bicentennial Park layout, ROW for Hartwell Brook, Dawn St, Crown Hill Pool and Fowell Ave,
3
Research of Mechanic St, raised crosswalk survey at Reservoir and Ledge Sts, Warner St survey,
Whitney St grading issue and Eldridge St survey.
Street Opening Permits. Engineering issued 87 Street Opening Permits and 10 Permits to
Encumber in September.
Sewer Permits. Six sewer permits were issued and $1,180.00 in fees was collected from
September 1 to September 30, 2015.
Solid Waste Department
Landfill Gas Expansion Project. Work started on October 8th on the Landfill Gas Expansion
project one week ahead of schedule. The project includes the installation of 8 new vertical wells
and 8 horizontal collectors. Completion of this work is expected by the second week of
November.
Recyclables Shipped in September 2015.
373 tons of single stream recycled materials
22 tons of electronic waste
14 tons textiles and Books
1047 fluorescent bulbs and ballasts
500 gallons of waste oil
3 boxes rechargeable batteries
Recycling Bins & Carts.
92 recycling carts were sold in August.
30 recycling bins were given to 16 residents, including 2 new units
28 Trash carts distributed
Permits Sold
13532 Residential
621 Commercial
Collected Curbside
MSW 5299 tons
Soft Yard Waste 500 tons
4