Committee on Infrastructure
Regular MeetingNashua, NH · February 25, 2015
Agenda
COMMITTEE ON INFRASTRUCTURE
FEBRUARY 25, 2015
7:00 p.m. Aldermanic Chamber
ROLL CALL
PUBLIC COMMENT
COMMUNICATIONS – None
PETITIONS – None
UNFINISHED BUSINESS
Broad Street Parkway Update
Nashua TS Lodging, LLC and 110 Grill Two, LLC Request for Installation of Directional Signage in City
Street Rights-of-Way; Chapter 320, Vehicles and Traffic, Section 320-9
Referred to Cmte and Division of Public Works – 12/23/14
NEW BUSINESS – RESOLUTIONS – None
NEW BUSINESS – ORDINANCES
O-15-039
Endorser: Alderman David Schoneman
AMENDING THE PARKING TIME LIMIT ZONES ON A PORTION OF CANAL STREET
O-15-041
Endorser: Alderman-at-Large Brian S. McCarthy
RESCINDING THE AUTHORIZATION FOR PARKING AND PARKING METERS ON THE SOUTH
SIDE OF EAST HOLLIS STREET BETWEEN MAIN STREET AND MEDICAL CENTER DRIVE
O-15-042
Endorser: Alderman-at-Large Brian S. McCarthy
ESTABLISHING A VALET PARKING PROGRAM
TABLED IN COMMITTEE
R-14-018
Endorser: Alderman-at-Large David W. Deane
APPROVING 44 BROAD STREET AS THE REPLACEMENT SITE FOR THE DAVID W. DEANE
SKATEBOARD PARK CURRENTLY LOCATED ON BRIDGE STREET AND CHANGING THE
AGENT TO EXPEND FOR THE DAVID W. DEANE SKATEBOARD PARK EXPENDABLE TRUST
FUND
Amended & Tabled – 4/9/14
R-14-021
Endorser: Alderman-at-Large Diane Sheehan
REGARDING THE RELOCATION OF THE PARKS AND RECREATION OFFICES AND
BUILDINGS IN GREELEY PARK
Also assigned to the Board of Public Works; Tabled 4/24/14
Tabled 5/14/14
R-14-079
Endorser: Alderman David Schoneman
APPROVING THE LOCATION OF A NEW BENCH IN GREELEY PARK NEAR MANCHESTER
STREET
Tabled 11/13/14
R-15-103
Endorsers: Mayor Donnalee Lozeau
Alderman-at-Large Lori Wilshire
Alderwoman Pamela T. Brown
Alderwoman Mary Ann Melizzi-Golja
Alderman Richard A. Dowd
AUTHORIZATION TO OFFER TO PURCHASE LAND AND BUILDINGS AT 11-13 MULBERRY
STREET (MAP 82, LOT 26) FOR RELOCATION OF THE DIVISION OF PUBLIC HEALTH AND
COMMUNITY SERVICES
Also assigned to NCPB; Favorable Recommendation Issued 2/5/15
Tabled 2/11/15
O-14-010
Endorser: Alderman-at-Large Brian S. McCarthy
AUTHORIZING ANGLED PARKING ON A PORTION OF THE WEST SIDE OF MAIN STREET
Tabled – 2/26/14
O-14-023
Endorser: Alderman-at-Large Jim Donchess
PROHIBITING A RIGHT TURN ON RED FROM ADVENTURE WAY NORTH ONTO DANIEL
WEBSTER HIGHWAY
Tabled – 7/09/14
O-14-024
Endorsers: Alderman-at-Large Jim Donchess
Alderman Richard A. Dowd
Alderman-at-Large Diane Sheehan
AUTHORIZING STOP SIGNS ON BEAUVIEW AVENUE AT ITS INTERSECTION WITH HOOKER
STREET
Tabled – 8/27/14
O-14-032
Endorser: Alderwoman Pamela T. Brown
ESTABLISHING A HANDICAPPED PARKING SPACE IN FRONT OF 66 ASH STREET
Tabled 11/13/14
O-14-035
Endorser: Alderwoman Pamela T. Brown
PROHIBITING PARKING OR STOPPING AT ANY TIME ON A PORTION OF WEST HOLLIS
STREET
Tabled 12/10/14
Schematic Design for an Accessible Public Playground prepared by
Institute for Human Centered Design
Referred to Cmte at Special BOA Mtg of 10/13/14; Tabled in Cmte 10/22/14
GENERAL DISCUSSION
PUBLIC COMMENT
REMARKS BY THE ALDERMEN
POSSIBLE NON-PUBLIC SESSION
ADJOURNMENT
Broad Street Parkway
Construction Contract Status Update
Prepared February 11, 2015
Parkway North/Baldwin Street Bridge
As Reported
Update
January 7, 2015
Contract Amount $11,077,804.31 $10,876,731
Progress Report:
The Baldwin Street Bridge is open to traffic.
Installation of the retaining wall is complete.
Paving of 3,000 linear feet of the Parkway has been completed.
Over 3,600 linear feet of granite curb has been installed.
Relocation of overhead utilities is complete.
Next Month Look Ahead:
Winter shutdown.
Broad Street Parkway
Construction Contract Status Update
Prepared February 11, 2015
Combined River Bridge and Fairmount Street Bridge Contract
As Reported
Update
January 7, 2015
Contract Amount $13,936,821.13 $14,440,506.38
Progress Report:
Drilling of shafts continues to present concerns to schedule.
o Mechanical issues with equipment and slow productivity.
o Recurring difficulty achieving “seal” of steel casing into rock prior to concrete
pour.
o Contractor suggests some delay is due to differing site conditions.
Concrete has been placed in 10 out of 16 foundation shafts.
Work on the south abutment is completed to roadway elevation.
Work on north abutment footing has commenced with forming and rebar placement.
Installation of retaining wall precast panels is 95 percent complete.
Fairmount Street Bridge east and west abutment footings have been poured.
Next Month Look Ahead:
Drilling for River Bridge shaft foundation will continue.
As drilling of individual shafts is completed concrete will be placed.
Continued work on north abutment footing.
Continued work on Fairmount Street Bridge foundation.
Broad Street Parkway
Construction Contract Status Update
Prepared February 11, 2015
Parkway South
As Reported
Update
January 7, 2015
Contract Amount $7,102,394 $7,102,394
Progress Report:
Notice to Proceed was issued November 21, 2014.
Preconstruction submittals reviewed.
Asbestos remediation has started in steam tunnels.
Next Month Look Ahead:
Asbestos remediation to continue.
Work in advance of existing pump house demolition will commence.
Broad Street Parkway
Construction Contract Status Update
Prepared February 11, 2015
As Reported
Other Contracts Update
January 7, 2015
Chimney Work inside chimney is Work inside chimney is
continuing. continuing.
Fire Pump Relocation Installation of 12-inch Installation of 12-inch
water main is complete. water main is complete.
Completion of pump Fire pump chamber has
installation is scheduled been set.
to start in December. Pump testing is late.
Completion expected in
February 2015.
Broad Street Parkway
Construction Contract Status Update
Prepared February 11, 2015
STATUS OF THE RIGHT OF WAY ACQUISITION
The City is continuing to work with NHDOT to understand the implications of recent
communications regarding disposition of surplus property.
PUBLIC MEETINGS
Between June 2007 and August 2010, there were eight public meetings that focused on progress
of the Parkway Supplementary Analysis; the Cost Reduction Study and the ongoing
Environmental Re-Evaluation.
These meetings are summarized in an August 12, 2010 memorandum prepared by Nashua
Regional Planning Commission (NRPC).
In addition, Mayor Lozeau and Project Manager John Vancor attended the Aldermanic
Infrastructure Committee meeting on March 10, 2010 to discuss the acquisition of 40 Pine Street
for the project.
Leon Kenison, P.E., Director of Public Works and Stephen Dookran, P.E., City Engineer
attended the Aldermanic Infrastructure meeting on May 12, 2010 and discussed several aspects
of the project.
The Parkway project has also been discussed at several meetings of the Board of Public Works.
The Aldermanic Infrastructure Committee held a meeting which included a walk of the route of
the portion of the project south of the Nashua River on September 25, 2010.
A joint meeting of the Planning and Economic Development Committee and the Business &
Industrial Development Authority (BIDA) was held on December 7, 2010. The meeting focused
on redevelopment of the former Mohawk Tannery site.
Project Manager John Vancor attended Aldermanic Infrastructure Committee meetings on
October 13, 2010; December 8, 2010; January 26, 2011; October 26, 2011; January 5, 2012,
February 22, 2012, April 25, 2012, June 27, 2012, October 24, 2012, May 22, 2013, June 26,
July 24, September 25, 2013, February 26, 2014, April 9, 2014, May 14, 2014, July 9, 2014,
October 22, 2014, November 13, 2014 and December 10, 2014 to provide updates on several
aspects of the project.
Project Administrator Leon Kenison, P.E. attended the Aldermanic Infrastructure Committee
Meeting on April 13, 2011 to provide an update on several aspects of the project.
Broad Street Parkway
Construction Contract Status Update
Prepared February 11, 2015
Meetings of City Staff and consultants continue with numerous stakeholders to discuss plans and
progress of the Project. There are monthly progress briefings of the Board of Public Works
Commissioners and members of the Aldermanic Infrastructure Committee.
Mayor Lozeau, Director of Public Works Lisa Fauteux, Community Development Director
Kathy Hersh, Economic Development Director Tom Galligani and Project Manager John Vancor
presented information regarding surplus property to the Board of Alderman on October 23, 2012.
A Public Information Meeting was held on December 3, 2012. Mayor Lozeau, Director of
Public Works Lisa Fauteux, City Engineer Stephen Dookran and Project Manager John Vancor
were present to provide information on project status.
A joint meeting of the Board of Aldermen and the Board of Public Works was held on January 3,
2013. Mayor Lozeau, Director of Public Works Lisa Fauteux, City Engineer Stephen Dookran
and Project Manager John Vancor were present to provide information on possible enhancements
to the three bridges.
A neighborhood meeting was held at the Amherst Street School on October 21, 2013 to discuss
the Parkway North Construction Project.
A neighborhood meeting was held at the Amherst Street School on February 20, 2014 to discuss
the Parkway North Construction Project as well as the Combined River Bridge and Fairmount
Street Bridge Contract.
A neighborhood meeting was held at the Amherst Street School on August 7, 2014 to provide an
update on ongoing construction contracts.
On November 13, 2014, a presentation was made to a joint meeting of the Board of Aldermen
and the Board of Public Works. This presentation showed alternatives under consideration for
enhancing the bridge rail at the Nashua River Bridge.
A neighborhood meeting was held at the Amherst Street School on December 16, 2014 to
provide an update on ongoing construction contracts.