Gerry Reppucci, Chair, conducted the meeting.
Members present were:
Gerry Reppucci, Chair
J.P. Boucher
Rick Johnson
David Creed
Carter Falk, AICP, Deputy Planning Manager/Zoning
Mr. Reppucci explained the Board's procedures, including the
points of law required for applicants to address relative to
variances and special exceptions. Mr. Reppucci explained how
testimony will be given by applicants, those speaking in favor
or in opposition to each request, as stated in the Zoning Board
of Adjustment (ZBA) By-laws. Mr. Reppucci also explained
procedures involving the timing light.
1. Aranco Realty, Inc. (Owner) 159 Amherst Street (Sheet 60
Lot 4) requesting the following variances to replace an
existing nonconforming ground sign: 1) to exceed maximum
sign area, 32 sq.ft allowed, 90 sq.ft existing - 75 sq.ft
proposed; 2) to exceed maximum ground sign height, 6 ft
permitted, 16 feet existing – 23 feet proposed; 3) to allow
a portion of the sign to have manually changeable copy; and
4) to encroach 10 feet into the 10 foot required setback.
LB Zone, Ward 2.
Voting on this case:
Gerry Reppucci
Rick Johnson
JP Boucher
David Creed
Attorney Thomas J. Leonard, Welts, White & Fontaine, 29 Factory
Street, Nashua, NH. Atty. Leonard said the site is the Citgo
station on Amherst Street, near Rite Aid and St. Laurent Auto.
He said it is located in the LB, Local Business Zone. He
submitted a packet of information to the Board. He said that
many of the existing uses nearby have been there for a long
Zoning Board of Adjustment
September 10, 2013
Page 2
time. He distributed some pictures to the Board, and described
the nearby businesses.
Atty. Leonard said that the existing sign is 90 square feet,
that is 16’-4” tall. He said on the drawing, the proposed sign
is on the right, it’s a narrower version, it’s the “Euro”
design, it’s 75 square feet, and has the four sections of gas
prices, and some changeable copy. He said even though the
proposed size is less than the existing sign, its nonconforming
and still over the allowable amount.
Atty. Leonard said they want the extra height mainly for
additional traffic visibility, as the existing sign is very
close to the roadway, and it interferes with visibility. He
said that another consideration is that with the changeable
copy, it shouldn’t be too low due to potential vandalism. He
said the extra height is for increased visibility and safety.
Atty. Leonard stated that they are requesting a variance for the
setback as well. He said that during their research, it was
noted that the sign was placed in a location where they didn’t
think it was, as it’s partially located on the abutting
property. He said that issue has to be resolved, and they are
requesting a zero setback. He said that the primary reason is
because with the present conditions it is very difficult to see
oncoming traffic from the east heading towards the highway. He
showed the existing and proposed signs on one of the submitted
pictures.
Atty. Leonard went over the variance points of law to the Boards
satisfaction.
Mr. Johnson asked if a sign that advertises diesel gas is
proposed. He asked about signage change at the pump islands.
Atty. Leonard said they will have a sign that has the diesel
pricing, and the signage over the pump islands is approved.
Mr. Falk said that staff doesn’t really get too involved with
the little signage on the pumps.
SPEAKING IN FAVOR:
Mr. Paul Kenney, Aranco Oil, Concord, NH. Mr. Kenney stated
that the signage is new station identification for the Citgo
Zoning Board of Adjustment
September 10, 2013
Page 3
facilities. He said the canopy will also be changed to the new
design.
SPEAKING IN OPPOSITION OR WITH QUESTIONS OR CONCERNS:
No one.
MOTION by Mr. Boucher to approve the variance on behalf of the
owner, as advertised, with all requests considered collectively.
Mr. Boucher stated that the variance is needed to enable the
applicant’s proposed use of the property, given the special
conditions of the property; and the benefit sought by the
applicant cannot be achieved by some other method reasonably
feasible for the applicant to pursue, other than an area
variance.
Mr. Boucher stated that the request is within the spirit and
intent of the ordinance; there are no adverse affects on
property values on surrounding parcels. Mr. Boucher said it is
not contrary to the public interest, and that substantial
justice is served.
SECONDED by Mr. Creed.
MOTION CARRIED UNANIMOUSLY 4-0.
2. Linear Retail Nashua #1, LLC (Owner) 221 Daniel Webster
Highway (Sheet A Lot 761) requesting variance to allow a
turn in a drive-through exit from the center line of the
pickup window at 30 feet, where 60 feet is required. HB
Zone, Ward 8.
Voting on this case:
Gerry Reppucci
Rick Johnson
David Creed
J.P. Boucher
Bob Cormier, Cuoco and Cormier, 74 Northeastern Boulevard,
Nashua, NH. Mr. Cormier stated that the property is in the
Highway Business Zone. He said the building is the existing
Pier One Imports at Daniel Webster Plaza. He said that Pier One
is planning on relocating, and the westerly portion of the
building, approximately 1,900 square feet, will become a
Zoning Board of Adjustment
September 10, 2013
Page 4
Starbucks Coffee Shop. He said the other side of the building
will be a restaurant. He said they appeared before the Planning
Board last Thursday, and received a conditional approval to go
ahead with the site plan, pending Zoning Board approval.
Mr. Cormier said that a professional traffic study done, and
gave a copy of it to the Board, and briefly described it. He
said the Starbucks at Exit 6 is very similar to this site. He
said at that site, they have 42 feet from the pickup window to
the exit, so they don’t meet the Ordinance as well, as evidenced
by the pictures that were submitted.
Mr. Cormier said that the spirit and intent of the Ordinance is
met because the proposed drive-through lane is contained within
property, and is approximately 1,000 feet from the public right-
of-way. He said there won’t be any traffic impacts to the
roadway. He said there will be no impact to property values,
and the proposed site layout will improve the views from Daniel
Webster Highway with additional green spaces. He said the
public benefit will be met, and substantial justice is served.
Mr. Boucher asked if the traffic flow coming into the drive-
through lane could be coming from the front of the building or
from the side, he asked if there is a designated lane on where
to go.
Mr. Cormier said it will be a one-way system around the
building, there will be crosswalks, too. He said that according
to the traffic study, coffee shops typically have 11-13 vehicles
cueing, the proposed site has room for 14 cars up to the
crosswalk before you get to the front of the building.
Mr. Boucher asked if there will be any planned outside seating.
Mr. Cormier said there will be a sitting area on the easterly
side of the restaurant.
Mr. Creed asked if there will be one or two lanes in the drive-
through.
Mr. Cormier said two, one for cueing, and one for bypass. He
said that during the morning traffic rush, all the stores in the
Plaza are closed.
Zoning Board of Adjustment
September 10, 2013
Page 5
Mr. Boucher asked if there will be any cross-access with the new
development currently under construction next door.
Mr. Cormier said that there is a retaining wall about 8 feet
down. He said the driveway by the pickup window will go down by
the Walgreens Pharmacy, so people could get over to the traffic
light at Royal Ridge Drive. He said there will be a lot of
cross-connectivity between these properties.
Mr. Reppucci asked why this case went before the Planning Board
before coming to the Zoning Board.
Mr. Cormier said that the reason was that there was a lease
obligation with the tenant, and they didn’t want to lose the
tenant. He said if they waited, they’d lose the tenant. He
said that the Planning Board had a condition that it has to get
approved by the Zoning Board.
Mr. Boucher asked about the window location.
SPEAKING IN FAVOR:
Gordon Whitman, Linear Retail Properties, Burlington, MA. Mr.
Whitman said that the tenant wouldn’t accept any other location.
He said the problem with that other back location is that it’s
not optimal in serving customers.
SPEAKING IN OPPOSITION OR WITH QUESTIONS OR CONCERNS:
No one.
MOTION by Mr. Reppucci to grant the variance on behalf of the
applicant as advertised.
Mr. Reppucci stated that the variance is needed to enable the
applicant’s proposed use of the property, given the special
conditions of the property; and the benefit sought by the
applicant cannot be achieved by some other method reasonably
feasible for the applicant to pursue. He said that the plan was
reviewed by the Planning Board, and they considered it a good
plan.
Mr. Reppucci said that the case is within the spirit and intent
of the ordinance, it will not adversely affect the property
Zoning Board of Adjustment
September 10, 2013
Page 6
values of surrounding parcels, it is not contrary to the public
interest, and substantial justice is served.
SECONDED by Mr. Boucher.
MOTION CARRIED UNANIMOUSLY 4-0.
3. Galen Rose (Owner) “L” Monica Drive (Sheet B Lots 854 &
855) requesting special exception to construct two single
family homes on two vacant lots of record. R18 Zone, Ward
8.
Voting on this case:
Gerry Reppucci
Rick Johnson
David Creed
J.P. Boucher
Bob Cormier, Cuoco and Cormier, 74 Northeastern Boulevard,
Nashua, NH. Mr. Cormier said these are the two last remaining
lots in the subdivision, they go back to 1964, before the
wetlands ordinance was in place. He said the wetlands were
identified by a certified wetland scientist, and they are
surveyed. He said it is a 75-foot buffer designation from
Salmon Brook.
Mr. Cormier said the buffer is the yellow line on the plan. He
said the lot on the left would have a small encroachment into
the wetland buffer, and the disturbed area would be reclaimed
afterwards. He said the applicant would build his own home
there, and has a specific building footprint in mind. He said
that one corner of the house would occupy 165 square feet of the
buffer
Mr. Cormier said the other lot on the right side, the buffer
swings closer to Monica Drive, almost to the building setback
line. He said the footprint is similar, but has no idea if the
person buying the lot would have a need to have the house all on
one floor, or to go to two stories.
Mr. Reppucci read the Conservation Commission letter, #7. He
said that the letter says that the house shall be made smaller.
He asked how much into the setback would the house be.
Zoning Board of Adjustment
September 10, 2013
Page 7
Mr. Cormier said the buffer comes very close to the front yard
setback of the lot, and there would only be 5-10 feet in the
right hand corner. He said that whatever type of home is built
on this lot, it is substantial. He said that both of these
house lots are on a fairly level area, before they slope down to
the brook. He said they’re 20-25 feet above the wetlands and
the flood plain. He said none of the construction will impede
the flow of the brook, and the houses would be quite elevated
above the wetlands.
Mr. Cormier said that any trees cut on the lot will have their
stumps remain in place. He said there will be erosion control
set up during construction, there will be a stone drainage
channel around both homes for ground recharge, and other than
the asphalted driveways, any patios, sidewalks, back-up spaces
will be porous pavers. He said that there are no endangered
species on the property. He went over the Conservation
Commission stipulations of approval, and the special exception
points of law for approval.
SPEAKING IN FAVOR:
Galen Rose, Monica Drive, Nashua, NH. Mr. Rose said he’s
looking to build a single-story home. He said he used to live
right up the road on East Dunstable Road, and knows several
neighbors. He said these homes will complete the neighborhood,
and they’ve been looking for this for a long time. He said the
vacant lots aren’t good for the neighborhood.
Mr. Creed asked about the bank, the buffer, and the stability of
the water body’s bank.
Mr. Rose said they walked the property with the Conservation
Commission. He said the lots are very flat, and the bank drops
off rather sharply to the water. He said there will be no
building on the bank, it’ll be kept as is. He said if need be,
there may be a small retaining wall to maintain the flatness for
a small back yard. He said they should be able to get almost
any home within the building envelope as shown.
Mr. Reppucci said for the house on the right, he didn’t
understand what impact the building footprint would have on the
buffer.
Zoning Board of Adjustment
September 10, 2013
Page 8
Mr. Cormier said the house on the right would have a substantial
part of the footprint in the wetland buffer. He said that the
Conservation Commission wanted to see the proposed building
footprint.
Mr. Rose said that the Commission wanted less roof space, so
there would be less water runoff to the river.
Mr. Reppucci asked if there will be a difference, at all, to the
impact to this site from a 2,400 square foot footprint, to a
2,000 square foot footprint.
Mr. Cormier said it would be very insignificant, and there is
the ability with recharge chambers to absorb that back into the
ground.
Mr. Johnson asked how the home would be supported.
Mr. Cormier said there would be a foundation, it would be a
normal house on the foundation. He said the house will be built
in the flat area, not within the slope.
Bill Machell, 8 Monica Drive, Nashua, NH. Mr. Machell said he
lives right across the street, and has no objection to the
houses being built here.
SPEAKING IN OPPOSITION OR WITH QUESTIONS OR CONCERNS:
Ron Eskin, 5 Monica Drive, Nashua, NH. Mr. Eskin said he lives
to the right of the subject lots. He asked if a retaining wall
is required at the corner.
Mr. Reppucci said if this case is approved, the Board will allow
activity in the wetland buffer to a very specific delineated
line. He said if the applicant is going to exceed the line,
they’ll have to come back to the Board. He said that
ultimately, any applicant cannot do any long-term harm to the
buffer, and restore it to its original situation. He said if
they put in a retaining wall within the area they’re approved to
work in, it’s ok.
Mr. Falk said that the applicant has submitted a plan for
development of the two homes. He said if the request turns out
to be that they’re going further into the wetland buffer as the
plan shows, they’ll have to come back to the Board.
Zoning Board of Adjustment
September 10, 2013
Page 9
Mr. Eskin asked if the plan implies that fill will be brought in
to make the lot level, how the lot will be finished off, or if
it’ll be backfilled, or if the retaining wall is required
because of the fill. He asked if it would be stepped down at
all.
Mr. Reppucci said that the applicant isn’t building a house on
the slope, he’s building on the flat surface that’s there. He
said the slope doesn’t start until the area past where they are
building.
SPEAKING IN FAVOR – REBUTTAL:
Mr. Cormier said that they indicated the limits of construction,
it’s all designated. He said they understand that they have to
accomplish their program within that area, for the house and any
re-grading. He said they’re not going to exceed anything that
is being asked for this evening.
Mr. Rose said that the idea of the retaining wall and/or a deck
area is to make sure that for the future, if we have to work on
the back of the building, that we won’t be in the slope, but
rather, in the flat surface to get ladders back there.
SPEAKING IN OPPOSITION OR WITH QUESTIONS OR CONCERNS – REBUTTAL:
Mr. Eskin said if a retaining wall is required, it’s more of an
engineering decision, rather than a Conservation Commission
decision.
Mr. Cormier said that no matter what, we can’t exceed the limit
of construction as shown on the plan.
Mr. Creed said he has some issues with this case procedurally.
He said he can support Lot 855, but not Lot 854, it’s so much
into the wetland buffer, and the house is right at the edge. He
said it’s an undefined envelope, and we should have had two
different applications.
Mr. Reppucci said the request doesn’t say exactly how much of an
incursion, it’s just to work in the buffer. He said he
understands Mr. Creed’s position. He said he has a problem,
procedurally, with the Conservation Commission’s letter,
stipulation #7. He said that he tremendously respects the
Zoning Board of Adjustment
September 10, 2013
Page 10
Commission, but said that they sometimes think they have
authority that they do not have. He said they can’t do
stipulation #7, as they have no statutory authority to do that
at all. He said that they are strictly a recommending body. He
said he heard testimony that the impact is negligible for a
smaller building footprint. He said he is in favor of removing
stipulation #7.
Mr. Johnson agreed with Mr. Creed, in that there should have
been two separate applications. He agreed that the Conservation
Commission is a recommending body, and it’s encroaching on their
authority. He said that stipulation #7 should be struck, and
they should comply with the remaining seven guidelines from the
Conservation Commission’s letter. He said he’d go along with
approving this case, but not with stipulation #7, as it exceeds
their authority.
Mr. Boucher said he really questions stipulation #7 as well. He
said that in hearing the testimony from the engineer, he feels
very comfortable whether the house is the proposed size or
smaller. He said the recharge will be the same, too. He said
he really respects the Conservation Commission, but feels that
stipulation #7 should be struck.
Mr. Creed said for stipulation #7, maybe this isn’t a valid
approval, meaning that the Conservation Commission, there’s
problems with how they go about their business, and that the
whole approval letter is flawed. He said their job as a
recommending Board, and not an approval Board, what they did was
that they took a undefinitized proposal, a blank check for 2,400
square feet, and said to go ahead and start, and come back to us
so we can give approval. He said that’s not an approval at all,
it’s not a decision at all, it’s a random thought.
Mr. Reppucci suggested it should have said that the project
received a positive recommendation from the Conservation
Commission, it shouldn’t say that they got approval from them.
He said that their letter is not a binding letter, with respect
to land use. He said he could look at the letter, and take
seven out of the eight stipulations to carry forward.
MOTION by Mr. Reppucci to grant the special exception on behalf
of the applicant, as advertised. Mr. Reppucci said that the
request is listed in the Table of Uses, Section 190-112. He
stated that it will not create undue traffic congestion or
Zoning Board of Adjustment
September 10, 2013
Page 11
unduly impair pedestrian safety. He said that it will not
overload public water, drainage or sewer or other municipal
systems.
Mr. Reppucci said that all the special regulations are
fulfilled, the wetland special conditions identified in the
zoning/land use code, and all nine of those conditions are met
by testimony of the applicant.
Mr. Reppucci said the request will not impair the integrity or
be out of character with the neighborhood, or be detrimental to
the health, morals or welfare of the residents, actually,
testimony was heard from an abutter who felt it would improve
the neighborhood.
Mr. Reppucci said the approval is simply to work within the
wetland buffer. He said for a special condition, in referencing
the September 9, 2013 letter from the Conservation Commission,
they recommend project approval on 8 conditions. He said that
the Zoning Board finds that those are all special conditions
that they meet, with the exception of #7 (stipulation read). He
said that the minutes of said Conservation Commission meeting be
incorporated into the ZBA’s minutes.
Mr. Reppucci said the approval is based upon the submitted plan
in the application.
SECONDED by Mr. Johnson.
MOTION CARRIED 3-1 (Mr. Creed).
MISCELLANEOUS:
REGIONAL IMPACT:
The Board did not see any cases of Regional Impact.
MINUTES:
None.
Mr. Reppucci said that Mr. Currier is now an Alderman candidate,
and will not be attending the Zoning Board meetings until after
the election is over. He said that since Mr. Currier is the
Vice Chairman, if he (Mr. Reppucci) cannot make a meeting as
Zoning Board of Adjustment
September 10, 2013
Page 12
Chairman, the By-Laws are not clear as to who would run the
meeting in the absence of the Chairman and Vice Chairman. He
said the By-Laws do not allow alternate members to vote on
cases.
MOTION by Mr. Reppucci to amend the By-Laws to say that if
neither the Chair or Vice Chair is present, but a quorum is
present, including full members or alternate members, that all
members present have the authority to decide to appoint a
Chairman for that evening to run the meeting.
Mr. Johnson said if the Clerk is there, he/she could run the
meeting.
Mr. Reppucci said that is fine.
Mr. Boucher said if the Clerk isn’t there, then a vote could be
done amongst the members present who’d run the meeting.
Mr. Falk said he’d provide the Board with a draft of the revised
By-Laws by the next meeting.
ADJOURNMENT:
Mr. Reppucci called the meeting closed at 8:30 p.m.
Submitted by: Mr. Johnson, Clerk.
CF
Taped Hearing
Agenda
Community Development 589-3095
City of Nashua Planning and Zoning
Building Safety
589-3090
589-3080
Code Enforcement 589-3100
Urban Programs 589-3085
Community Development Division Economic Development 589-3070
Conservation Commission 589-3105
City Hall, 229 Main Street, PO Box 2019 FAX 589-3119
Nashua, New Hampshire 03061-2019 www.gonashua.com
August 27, 2013
The following is to be published on ROP August 31, 2013, under
the Seal of the City of Nashua, Public Notice Format 65 MP 51.
Notice is hereby given that a Public Hearing of the City of
Nashua Zoning Board of Adjustment will be held on Tuesday,
September 10, 2013, at 6:30 PM at the Nashua City Hall
Auditorium, 3rd floor, 229 Main Street.
1. Aranco Realty, Inc. (Owner) 159 Amherst Street (Sheet 60
Lot 4) requesting the following variances to replace an
existing nonconforming ground sign: 1) to exceed maximum
sign area, 32 sq.ft allowed, 90 sq.ft existing - 75 sq.ft
proposed; 2) to exceed maximum ground sign height, 6 ft
permitted, 16 feet existing – 23 feet proposed; 3) to allow
a portion of the sign to have manually changeable copy; and
4) to encroach 10 feet into the 10 foot required setback.
LB Zone, Ward 2.
2. Linear Retail Nashua #1, LLC (Owner) 221 Daniel Webster
Highway (Sheet A Lot 761) requesting variance to allow a
turn in a drive-through exit from the center line of the
pickup window at 30 feet, where 60 feet is required. HB
Zone, Ward 8.
3. Galen Rose (Owner) “L” Monica Drive (Sheet B Lots 854 &
855) requesting special exception to work within the 75-
foot prime wetland buffer of Salmon Brook to construct two
single family homes on two vacant lots of record. R18
Zone, Ward 8.
1. Review of Motion for Rehearing:
2. Review of upcoming agenda to determine proposals of
regional impact.
3. Approval of Minutes for previous hearings/meetings.
"SUITABLE ACCOMMODATIONS FOR THE SENSORY IMPAIRED
WILL BE PROVIDED UPON ADEQUATE ADVANCE NOTICE."
Get email alerts for Nashua
A daily email when new agendas and minutes are posted.