Stormwater Commission
Regular MeetingNiles, IL · January 7, 2016
Minutes
Stormwater Commission
Meeting Summary
Thursday, January 7, 2016
Members Present: Chair Joe LoVerde, Fred Kudert, Steven Vinezeano, Chuck Ostman, Rich
Wlodarski, Andrew Vitale, Thomas Powers, Mary Anderson, Robert Callero.
Others present: Jeff Wickenkamp from Hey & Associates, Jack Grana Utilities Superintendent,
Joseph Annunzio Village Attorney, Dan Randolph Civil Engineer III, Louella Preston, resident
The Stormwater Commission meeting convened at 8:30 a.m. in the Council Chambers
Conference Room at Village Hall.
July 9 Meeting Summary: The Meeting Summary for July 9, 2015 was not ready for approval.
Old Business: The following topics were presented and discussed.
Cleveland Corridor Project Bid Update: The Village Attorney(Joseph Annunzio) provided an
update as to the legal status. The Judge will be providing his final decision tomorrow. Chair
LoVerde asked as whether the contractor had been contacted regarding their position outside of
the courts. Mr. Annunzio stated that the contractor Dimeo would not drop the case short of the
Village rebidding the project. After the decision tomorrow, if the contractor loses he has 30 days
to appeal which would be a 6-8month process. Chair Lo Verde asked as whether the third bidder
would be asking for additional compensation from a delay due to the legal proceedings.
Commissioner Anderson indicated the contractor has been involved throughout, has provided
previous bid price extensions, and really wants to do the work. Further formal extension of his
bid has been on hold pending the case outcome.
CY2015 Construction Projects: An attachment was provided that detailed the 2015 projects.
It was noted that the MaryHill and OLR project received an award from the Illinois Section of
the American Society of Civil Engineers. The following summary was provided:
Calendar 2015 Stormwater Projects In Design/Completed:
$100,000 annual sewer lining project – approximately 2,700 linear feet of 8” to 18” diameter
pipe lined during calendar 2015.
135,800 feet of sewer pipe cleaned and televised in various neighborhoods in town
2 new catch basins installed on National in the Chesterfield area
Cleveland Corridor Sewer Improvements Project final design, permitting and bidding
completed. Construction project has been tentatively awarded, but project is tied up in
litigation.
Completed final close-out of contracts for Maryhill and Our Lady of Ransom detention basins.
The projects closed out approximately $700,000 under budget.
Design of Oak Park bio-swale and permeable paver project being completed for 2016
construction. A meeting is scheduled with the MWRD to request funding assistance.
Peer Engineer Review of Hey & Associates proposed improvement to the Oconto/Mulford
intersection
Design of 2 small stormwater projects in the 8000 block of Churchill and the intersection of
Milwaukee/Kedzie/Ottawa for construction sometime during 2016
Conceptual evaluation and subsequent purchase of 9101 Greenwood for future stormwater
detention as identified in Tier 2 project areas
Flood Control Assistance Program: The status of the Flood Control Assistance Program was
presented. After discussion it was decided that $100,000 would be budgeted for the next fiscal
year. It was also discussed that it is difficult to budget for a typical year however that if there is a
big rain event the budget would have to be revisited by the Board.
Public Comment: None
New Business:
MWRD Inflow/Infiltration Program Information
Dan Randolph provided a summary of the MWRD Inflow/Infiltration control program (IICP) that
is a newly required program. The key elements that remain to be completed include establishing a
rehabilitation and capital improvement program, private sector program, and developing a long
term Operation and Maintenance program. Initial investigation indicate 100 homes were identified
to have defects within the initial 10% testing of our system. Chairman LoVerde asked that
downspout disconnection be handled as a standard inspection item when the Village is reviewing a
property for other building issues. A concern was raised regarding the correction of foundation
drains connected to the sanitary sewer. It was clarified that the requirement for the IICP program
applies to the separate sewer area which is approximately 50% of the town. It was also stated how
the Village being a leader in this program will provide long term benefits to the Village in terms of
obtaining funding from the MWRD and the reduction of basement flooding. There was discussion
about whether sewer separation projects would be appropriate to separate foundation drains.
Public Services felt it would be more likely that the issue would be handled on a case by case
basis, and would involve sump pump retrofits. Right now the MWRD is only requiring the low
cost repairs such as downspout disconnection and cleanout caps. Commissioner Anderson
recommended a staff level subcommittee to help develop the program.
Alternatives for Purchase of Flood Prone Properties in Niles
Three properties (8401 western, 7746 Oconto, 7740 Oconto) were submitted to the MWRD and
found to be not eligible for their acquisition program. The properties will now be submitted to
Cook County. The properties were previously submitted to FEMA and did not meet the damage
requirements for benefit/cost ratio.
FY2016/17 Proposed CIP Projects for Stormwater
A list of projects was provided.
Review of Stormwater Master Plan and Consideration of Tier 2 and Small
The current stormwater relief program is four years old. Potential upcoming projects
include incomplete/tabled Tier1 projects, Tier 2 projects, and the small projects. There
is a need to develop a 5-year capital plan to assist with budgeting and reprioritization of
projects. A presentation was provided by Hey and Associates on how to implement a
Master plan update.
Stormwater Projects Priorities
Stormwater project priorities were discussed and the need to reprioritize the projects based on
work to date and feasibility. The benefit to having a shovel ready project was discussed. The
commission agreed that having shovel ready projects would assist with obtaining grants and
potentially more fully utilizing the TARP system when McCook Reservoir comes on line.
Prospect Street Flooding Concerns
Community Development was performing a routine inspection and the neighbors around Prospect
Court behind the bank on Oakton mentioned that they had persistent street flooding. Village
records indicate one (1) street flooding complaint since 2007. Older Village records indicate
flooding during the large storm in 1987. Follow up indicated that the pictures were from the large
summer storm in 2013. The location would be potentially reviewed to see if there were any simple
tweaks that could be made and the intensity of the storms that caused flooding would be
investigated.
New business
The Village Manager discussed the National League of Cities service line warranty program and
the benefits it could provide to residents. It was agreed that the National League of Cities would
attend the next stormwater meeting to provide a presentation
The committee reiterated that stormwater budget should include analysis of Oakton/Dobson and
other areas. A shovel project should be prepared in the next fiscal year. The master plan update
would also be budgeted.
Public Comment: Louella Preston stated that the Village historically has had shovel ready
projects. She also requested an annual written update to the stormwater plan.
The date of the next meeting will be determined at the call of the Chairman.
The meeting was adjourned at 10:25 a.m.
Agenda
STORMWATER COMMISSION MEETING
Thursday, January 7, 2016 at 8:00 a.m.
VILLAGE HALL, Council Chambers (1st FL)
I. Call to order
II. Roll Call
III. Approve Meeting Summary from July 9, 2015
IV. Old Business –
a. Cleveland Corridor Sewer Improvements Bid Status – Court ruling due to be issued on January 6
b. 2015 Construction and Design Summary of Activities
c. Status of Flood Control Assistance Program
d. Other Projects
V. New Business –
a. MWRD Inflow/Infiltration Program Information
b. Alternatives for Purchase of Flood Prone Properties in Niles
c. FY2016/17 Proposed CIP Projects for Stormwater
d. Review of Stormwater Master Plan and Consideration of Tier 2 and Small Stormwater Projects
Priorities
e. Prospect Street Flooding Concerns
VI. Other Business
VII. Public Comment
VIII. Future Meeting Date
IX. Adjourn