Norwalk Facilities Construction Commission
Regular MeetingNorwalk, CT · July 1, 2009
Minutes
Norwalk Facilities Construction Commission July 1, 2009 Minutes (Final)
CITY OF NORWALK
NORWALK FACILITIES CONSTRUCTION COMMISSION
JULY 1, 2009
ATTENDANCE: Mayor Richard A. Moccia; James Feigenbaum, Richard
Bonenfant; Dan Cook; Paul Arcario; Joseph Beggan,
Steve Kershner,
OTHER: Amar Shamas, Gilbane;
Call to Order
Mayor Moccia called the meeting to order at 5:30 p.m.
Approval of Minutes
** MR. KERSHNER MOTIONED TO APPROVE THE MINUTES OF
THE MAY 6, 2009 MEETING AS SUBMITTED.
** MOTION PASSED UNANIMOUSLY.
Norwalk School Projects
Norwalk High School
Mayor Moccia stated that prior to the project update, he wanted to notify the
Commission that Mark Gorian and Dan Cook will be meeting to review further
cost savings. He added that this would include a pool cover to help with the water
evaporation and loss of chemicals, the installation of timers, and minor
modifications to improve the ventilation and reduce humidity levels in pool areas.
Project Update
Mr. Shamas stated that the project was in the final stages in preparation for the
state audit, which determines the final reimbursement to the City of Norwalk.
City of Norwalk
Norwalk Facilities Construction Commission
July 1, 2009
Page 1 of 4
He presented detail and back-up documents for review only, of the following
change orders that have been approved by staff:
Change Order Amount Description Status
PCO#00433 ($ 6,106.17) Decrease GMP Credit associated with deleting flex
connectors at various AC and HV units per
A/E request.
PCO#00443 $ 2,794.64 Increase GMP
Provide roofing work at the dry cooler
dump radiator to meet requirements
PCO#00444 $ 4,421.34 Increase GMP Provide speed switch at various noisy fan
coil units at the interior classrooms
PCO#00445 $ 3,151.58 CM Contingency Provide premium time work for site
contractor during summer 2008 work.
PCO#00446 $ 391.78 Increase GMP Additional bond costs associated with
change order for painting contractor.
PCO#00447 $ 3,274.79 CM Contingency Provide custom size thresholds at the main
Entry doors due to existing conditions.
PCO#00448 $ 428.33 CM Contingency Provide custom opening at the existing
millwork for access to plumbing services.
PCO#00449 $ 4,149.15 Increase GMP Provide railing at the stairwell windows as
Requested by FM.
PCO#00450 $ 37,323.00 Increase GMP Provide additional glycol at the existing
heating and cooling system to protect from
freeze-ups.
Ponus Ridge Middle School
Mr. Shamas reviewed the following items and indicated that Newfield’s CO#16
represents the balance remaining in Newfield’s (CM) current GMP for the project.
Mr. Shamas also added that based on the contract requirements between the City
and Newfield Construction, all balance remaining within the GMP, such as CM
allowances, Contingencies and trade allowances shall be credited back to the City
upon completion of the project. The project currently shows a balance remaining
within the overall project budget. He cautioned the NFCC members that the
balance of funds for each projects are affected by the final audit by the state and
reimbursement. In certain projects such as Brien McMahon HS and Center of
Global Studies where the project final costs are currently within the project budget,
a shortfall is anticipated based on the final costs and the amount of the final
ineligible costs on the project. Similarly for NHS, where due to high ineligible
costs as well as the reduction in reimbursement rate on the project as indicated in
City of Norwalk
Norwalk Facilities Construction Commission
July 1, 2009
Page 2 of 4
the state Dept. of Education letter dating back to Jan of 2008, the state share is
expected to be reduced. Mr. Shamas indicated that at this time they are waiting the
state approval of final State change orders in order to finalize the projected state
share for both Ponus Ridge and Nathan Hale and these projects could be presented
to the Board of Education sometime within the next two months for final
acceptance in order to request state audit.
He presented detail and back-up documents for review only, of the following
change orders that have been approved by staff:
Change Order Amount Description Status
CO# 0015 $ 7,028.45 Increase GMP Provide additional CM Fee associated
with change order work per contract.
CO# 0016 ($156,296.64) Decrease GMP Credit associated with closing out
Newfield’s GMP for un-used general
Conditions, CM Contingency and
Allowances – Final Closeout of Costs.
Nathan Hale Middle School
Mr. Shamas presented a project update and the following change orders for review
only, as approved by staff:
Change Order Amount Description Status
CO# 0015 $ 2,088.85 Increase GMP Provide additional CM Fee associated
with change order work per contract.
CO# 0016 ($216,601.89) Decrease GMP Credit associated with closing out
Newfield’s GMP for un-used general
Conditions, CM Contingency and
Allowances – Final Closeout of Costs.
Mr. Shamas noted that Nathan Hale is very similar to Ponus Ridge in terms of
funding and finalization of state reimbursement, once approval of the change
orders is received from the State, they can be in a position to submit for final
acceptance by the Board of Education as complete. The state audit can then
commence and state reimbursement can be determined. He recommended that all
remaining project balance should remain within the project account, similar to
previous projects, until the final audit by the State is completed.
City of Norwalk
Norwalk Facilities Construction Commission
July 1, 2009
Page 3 of 4
Miscellaneous Items
There were no items discussed.
Adjournment
** MR.BONENFANT MOTIONED TO ADJOURN.
** THE MOTION PASSED UNANIMOUSLY.
The meeting was adjourned at 6:20 p.m.
Respectfully submitted,
Marilyn Knox
Telesco Secretarial Services
City of Norwalk
Norwalk Facilities Construction Commission
July 1, 2009
Page 4 of 4
Agenda
Norwalk Facilities Construction Commission July 1, 2009 Agenda (Final)
NORWALK FACILITIES CONSTRUCTION COMMISSION
(NFCC)
MEETING, WEDNESDAY, July 1, 2009
5:30 P.M. IN CITY HALL ROOM #231
I. ROLL CALL
II. MINUTES OF PREVIOUS MEETING(S)
May 6, 2009, Special Meeting
III. NORWALK SCHOOL PROJECTS
A. Norwalk High School
1. Project update - by Amar Shamas (Program Manager)
2. Review only, changes approved by staff:
PCO#00433 ($ 6,106.17) Decrease GMP Credit associated with deleting flex
connectors at various AC and HV units per
A/E request.
PCO#00443 $ 2,794.64 Increase GMP Provide roofing work at the dry cooler
dump radiator to meet requirements
PCO#00444 $ 4,421.34 Increase GMP Provide speed switch at various noisy fan
coil units at the interior classrooms
PCO#00445 $ 3,151.58 CM Contingency Provide premium time work for site
contractor during summer 2008 work.
PCO#00446 $ 391.78 Increase GMP Additional bond costs associated with
change order work for the painting
contractor
PCO#00447 $ 3,274.79 CM Contingency Provide custom size thresholds at the main
Entry doors due to existing conditions.
PCO#00448 $ 428.33 CM Contingency Provide custom opening at the existing
millwork for access to plumbing services.
PCO#00449 $ 4,149.15 Increase GMP Provide railing at the stairwell windows as
Requested by FM.
PCO#00450 $ 37,323.00 Increase GMP Provide additional glycol at the existing
heating and cooling system to protect from
freeze-ups.
1
B. Ponus Ridge Middle School
1. Project update - by Amar Shamas (Program Manager)
2. Review only, changes approved by staff:
CO# 0015 $ 7,028.45 Increase GMP Provide additional CM Fee associated
with change order work per contract
requirements.
CO# 0016 ($156,296.64) Decrease GMP Credit associated with closing out
Newfield’s GMP for un-used general
Conditions, CM Contingency and
Allowances – Final Closeout of Costs.
C. Nathan Hale Middle School
1. Project update - by Amar Shamas (Program Manager)
2. Review only, changes approved by staff:
CO# 0015 $ 2,088.85 Increase GMP Provide additional CM Fee associated
with change order work per contract
requirements.
CO# 0016 ($216,601.89) Decrease GMP Credit associated with closing out
Newfield’s GMP for un-used general
Conditions, CM Contingency and
Allowances – Final Closeout of Costs.
VI. MISCELLANEOUS ITEM(S)
Prepared by Alan Lo
Dated: June 18, 2009
2