Norwalk Facilities Construction Commission
Regular MeetingNorwalk, CT · August 4, 2009
Minutes
Norwalk Facilities Construction Commission August 4, 2009 Minutes (Final)
CITY OF NORWALK
FACILITIES CONSTRUCTION COMMISSION
AUGUST 2, 2006
ATTENDANCE: Mayor Richard A. Moccia; Paul Arcario; Stuart Opdahl;
Stuart Wells; John Tobin; David Murchie;
Gwen Briggs (for Doug Sutton); Nick Pacella (6:00 p.m.)
STAFF: John Hawley, Gilbane; Amar Shamas, Gilbane;
OTHER: Ben Burdsall, Gilbane
CALL TO ORDER
Mayor Moccia called the meeting to order at 5:35 p.m. He welcomed back Mr.
Stuart Wells, who is replacing Mr. Avery.
MINUTES OF PREVIOUS MEETING (S)
July 5, 2006 and July 19, 2006
** MR. TOBIN MOVED TO APPROVE THE MINUTES OF JULY 5
AND JULY 19, 2006.
** MOTION PASSED WITH TWO ABSTENTIONS (BRIGGS AND
WELLS).
NORWALK SCHOOL PROJECTS
A. Brien McMahon High School/Center for Global Studies Improvement
Project
1. Project update by John Hawley (Program Manager)
Mr. Hawley said that the removal of the portables is about 80% complete.
They will begin demolishing the foundations. They will then begin the
last phase, which is the construction of the softball field. The punchlist
work is underway. All but a few pieces of the FF&E have been delivered.
.
2. Review and approve the following change orders:
CITY OF NORWALK
FACILITIES CONSTRUCTION COMMISSION
AUGUST 2, 2006
CCA #312 $ 40,789.00 Increase GMP Provide revisions to the
loading dock
area per RFI 146
CCA #30033 $ 1,553.00 Increase GMP Provide revs at
existing 3B conditions
to blend masonry and EIFS to
match
CCA #30039 $ 5,018.00 Increase GMP Provide new
gypsum shaft in print room
due to clearance at existing
condition
CCA #30051 $ 3,250.00 Increase GMP Recalibrate fire
pump and re-test due to
existing flow deficiencies from
water co
Mr. Hawley explained CCA #312, $40,789.00 for the loading dock
revisions. This had been carried in the cost report at a $50,000 value for
about two years. This is more of a claim status. When Fletcher
Thompson finished the drawings, the loading dock area had not been fully
developed and a claim was filed by Brennan.
** MR. OPDAHL MOVED TO APPROVE THE ABOVE LISTED
CHANGE
ORDERS.
** MOTION PASSED UNANIMOUSLY.
B. Kendall Elementary School
1. Project update – by Amar Shamas (Program Manager)
Mr. Shamas said they are in the last phase of the F wing, which is the
cafeteria, kitchen, corridor, gym and boiler room. The majority of the
work will be completed within the next two weeks. They are planning to
CITY OF NORWALK
FACILITIES CONSTRUCTION COMMISSION
AUGUST 2, 2006
move back in the week of August 21. The FF&E package is about 95%
complete.
2. Review and approve the following change orders:
COR #077 $ 7,023.00 Increase GMP Provide new
railing at the exterior stair
located at the loading dock per A/E
SKA21
COR #078 $ 2,640.00 Increase GMP Provide new
paving and asphalt overlay
at the exterior sidewalks and
basketball
area.
** MR. ARCARIO MOVED TO APPROVE THE ABOVE LISTED
CHANGE ORDERS.
** MOTION PASSED UNANIMOUSLY.
3. Review only, changes approved by staff:
COR #075 $ 4,565.00 Increase GMP Provide 2 drawer filing
cabinets at the
front office reception area.
COR #076 $10,536.00 Increase GMP Provide repairs and install
new T-111
wall panels at the gym, interior
walls.
AL-036 $ 5,378.00 CM Extend ventilation duct work to
gym,
Contingency office and custodial area per A/E
SKM 11.
4. Review and approve the following change order to Bojan Development,
LLC for additional abatement services at Kendall:
CITY OF NORWALK
FACILITIES CONSTRUCTION COMMISSION
AUGUST 2, 2006
CO#7 $ 2,300.00 Setup, removal and disposal of an
additional containment and staging
above stage area.
Mr. Shamas explained that this was abatement work for the stage area and
air handling units.
** MR. MURCHIE MOVED TO APPROVE THE ABOVE LISTED
CHANGE ORDER.
** MOTION PASSED UNANIMOUSLY.
C. Norwalk High School
1. Project update – by Amar Shamas (Program Manager)
Mr. Shamas explained that the work is underway and will take most of
August and September to complete. They will shut the power to the
building for approximately two weeks from August 7 to August 18. All
activities have been coordinated with the proper authorities. The
foundation work will begin in September; the steel work will begin in
November. The orchestra foundation work will be in October. The boiler
room work will be done during September and October. The permits
have been filed for the co-gen system.
2. Review the following and refer to Common Council for approval:
“a.Authorize the Mayor, Richard A. Moccia, to execute a second
amendment to O&G Industries, Inc. for the construction phase at
Norwalk High School Project to increase the GMP by the sum of
$1,710,881.00. Acct #0904-5010-5777-B0310.
b. Increase the allowance for Owner’s Contingency by the amount of
$200,000.
c. Authorize the NFCC to issue change orders on contract for a total
not to exceed the Owner’s Contingency Allowance.”
CITY OF NORWALK
FACILITIES CONSTRUCTION COMMISSION
AUGUST 2, 2006
** MR. OPDAHL MOVED TO AUTHORIZE THE MAYOR, RICHARD
A. MOCCIA, TO EXECUTE A SECOND AMENDMENT TO O&G
INDUSTRIES, INC. FOR THE CONSTRUCTION PHASE AT
NORWALK HIGH SCHOOL PROJECT TO INCREASE THE GMP
BY THE SUM OF $1,710,881.00. ACCT #0904-5010-5777-B0310.
** MR. OPDAHL MOVED TO INCREASE THE ALLOWANCE FOR
OWNER’S CONTINGENCY BY THE AMOUNT OF $200,000.
** MR. OPDAHL MOVED TO AUTHORIZE THE NFCC TO ISSUE
CHANGE ORDERS ON CONTRACT FOR A TOTAL NOT TO
EXCEED THE OWNER’S CONTINGENCY ALLOWANCE.
** MOTION PASSED UNANIMOUSLY.
Mayor Moccia thanked everyone involved for their efforts in moving this
project forward.
D. Tracey Elementary School
1. Project update – by Ben Burdsall (Program Manager)
Mr. Burdsall explained that the utilities are being installed. The sprinkler
system is being completed. New boilers have been installed. The entire
project should be complete by about October 1, 2006. The job is going
according to schedule, and they expect to have the temporary CO issued
on August 23, 2006.
2. Review and approve the following change orders:
CER #11.1 $14,750.00 Increase GMP Add new path
and feeder between
MDP and Panel S.
CER #13.1 $11,516.00 Increase GMP Incorporate
changes to HHWS/R
piping per SKM-01 through
SKM-05.
CITY OF NORWALK
FACILITIES CONSTRUCTION COMMISSION
AUGUST 2, 2006
CER #16.1 $ 2,724.00 Increase GMP Remove non-
used existing fire
alarm devices in attic and
gym.
CER #18.1 $ 3,890.00 Increase GMP Add sprinkler
heads under stage
per SKP-01.
CER #23.1 $ 2,500.00 Increase GMP Use existing
louvers as transfer
Grilles at stage per RFI #22.
CER #28.1 $ 3,206.00 Increase GMP Add electric
door strike per
SKE-2 and SKE-3.
CER #29.1 $ 6,151.00 Increase GMP Admin. Office
relocations per
principal’s request.
** MR. TOBIN MOVED TO APPROVE THE ABOVE LISTED CHANGE
ORDERS.
Mr. Burdsall explained that CER #18.1 for $3,890.00 for sprinkler heads under
the stage was requested by the Fire Marshal.
** MOTION PASSED UNANIMOUSLY.
E. Columbus Elementary School
1. Project update – by Ben Burdsall (Program Manager)
Mr. Burdsall explained that this is similar to the work being done at
Tracey, and it is following along on the same schedule. They expect to
have it completed by the start of the school year.
2. Review and approve the following change orders:
CITY OF NORWALK
FACILITIES CONSTRUCTION COMMISSION
AUGUST 2, 2006
CER #9.1 $ 9,194.00 Increase GMP Remove
existing fuel oil pump
and provide new fuel oil
pump
set.
CER #10.1 $ 7,646.00 Increase GMP SNEW charges
to replace Pole
#664 and install new
underground
electrical service.
** MR. ARCARIO MOVED TO APPROVE THE ABOVE LISTED
CHANGE ORDERS.
** MOTION PASSED UNANIMOUSLY.
F. Roton Middle School
1. Project update – By Ben Burdsall (Program Manager)
Mr. Burdsall said that Roton was underdesigned and was reviewed by the
State last December. It was considerably over-budget. It was decided to
review the scope of the project and go out to re-bid this Fall. There is a
summary of the items considered included in the packet.
NATHANIEL ELY CENTER
A. Project update – By John Hawley (Program Manager)
Mr. Hawley said the bidding was completed during July. The project came
in at its target budget.
B. Refer the following to Common Council for approval:
“a.Authorize the Mayor, Richard A. Moccia, to execute an amendment
to W&M Construction Corporation for the construction phase
(including pre-construction phase services) of the Nathaniel Ely Child
CITY OF NORWALK
FACILITIES CONSTRUCTION COMMISSION
AUGUST 2, 2006
Care Center for a total not-to-exceed $3,729,663. Acct #09064074-
5777-C0346.
b. Establish an allowance for the Owner’s Contingency in the amount of
$360,000.
c. Authorize the NFCC to issue change orders on contract for a total not
to exceed the Owner’s Contingency.”
** MR. WELLS MOVED TO AUTHORIZE THE MAYOR, RICHARD A.
MOCCIA, TO EXECUTE AN AMENDMENT TO W&M
CONSTRUCTION CORPORATION FOR THE CONSTRUCTION
PHASE (INCLUDING PRE-CONSTRUCTION PHASE SERVICES)
OF THE NATHANIEL ELY CHILD CARE CENTER FOR A TOTAL
NOT-TO-EXCEED $3,729,663. ACCT#09064074-5777-C0346.
** MR. WELLS MOVED TO ESTABLISH AN ALLOWANCE FOR THE
OWNER’S CONTINGENCY IN THE AMOUNT OF $360,000.
** MR. WELLS MOVED TO AUTHORIZE THE NFCC TO ISSUE
CHANGE ORDERS ON CONTRACT FOR A TOTAL NOT TO
EXCEED THE OWNER’S CONTINGENCY.
Mayor Moccia explained that they did get the additional commitment of
$750,000 from CHEFA, but they do not have the letter of confirmation. He
said they will move forward with this, but without the letter of commitment,
they might have to table it before the next Council meeting.
** MOTION PASSED UNANIMOUSLY.
C. Review the following and refer to Common Council for approval:
“a.Authorize the Mayor, Richard A. Moccia, to execute a contract with
AAIS Corp. of West Haven, CT for asbestos abatement services at the
Nathaniel Ely Child Care Center for a total not-to-exceed $48,500.
Acct #09064074-5777-C0346.
b. Establish an allowance for the Owner’s Contingency in the amount of
$6000.
CITY OF NORWALK
FACILITIES CONSTRUCTION COMMISSION
AUGUST 2, 2006
c. Authorize the NFCC to issue change orders on contract for a total not
to exceed the Owner’s Contingency.”
** MR. MURCHIE MOVED TO AUTHORIZE THE MAYOR, RICHARD
A. MOCCIA, TO EXECUTE A CONTRACT WITH AAIS
CORPORATION OF WEST HAVEN, CT FOR ASBESTOS
ABATEMENT SERVICES AT THE NATHANIEL ELY CHILD CARE
CENTER FOR A TOTAL NOT-TO-EXCEED $48,500. ACCT
#09064074-5777-C0346.
** MR. MURCHIE MOVED TO ESTABLISH AN ALLOWANCE FOR
THE OWNER’S CONTINGENCY IN THE AMOUNT OF $6000.
** MR. MURCHIE MOVED TO AUTHORIZE THE NFCC TO ISSUE
CHANGE ORDERS ON CONTRACT FOR A TOTAL NOT TO
EXCEED THE OWNER’S CONTINGENCY.
** MOTION PASSED UNANIMOUSLY.
MISCELLANEOUS ITEMS
None.
ADJOURNMENT
** MR. WELLS MOVED TO ADJOURN.
** MOTION PASSED UNANIMOUSLY.
The meeting was adjourned at 6:00 p.m.
Respectfully submitted,
Carolyn Marr
Telesco Secretarial Services
CITY OF NORWALK
FACILITIES CONSTRUCTION COMMISSION
AUGUST 2, 2006
Agenda
Norwalk Facilities Construction Commission August 4, 2009 Agenda (Final)
NORWALK FACILITIES CONSTRUCTION COMMISSION (NFCC)
SPECIAL MEETING
TUESDAY, AUGUST 4, 2009
5:30 P.M. IN CITY HALL ROOM #231
I. ROLL CALL
II. MINUTES OF PREVIOUS MEETING(S)
July 1, 2009, Special Meeting
III. NORWALK SCHOOL PROJECTS
A. Norwalk High School
1. Update on the pool filtration project
2. Pool energy conservation measures and operating cost reductions
B. DEMHS Grant – Security enhancement project
1. Update on the CCTV cameras, monitors and keyless entry systems
improvements at 17 schools and approve final payment.
IV. MISCELLANEOUS ITEM(S)
Prepared by Alan Lo
Dated: July 30, 2009
1