Plan Commission
Regular MeetingSkokie, IL · February 16, 2023
Minutes
Approved Plan Commission Summary Meeting Minutes
Date: February 16, 2023
A motion to approve the minutes of the Plan Commission meeting of February 2, 2023
was made by Commissioner Burman and seconded by Commissioner Ousley.
Case Description:
Case 2023-01P – Site Plan Approval: 8610 Niles Center
Arie Crown Hebrew Day School, an Illinois Not-For-Profit Corporation, on behalf of Luz
and Associates #1, LLC, requests site plan approval for a demonstration planned
development in an R4 Multifamily Housing zoning district that includes a 192-unit
multifamily housing development with enclosed parking, and any relief that may be
discovered during the review of this case.
PINs: 10-21-214-001-0000, 10-21-214-002-0000, 10-21-214-003-0000, 10-21-214-004-
0000, 10-21-214-005-0000, 10-21-214-009-0000, 10-21-214-010-0000, 10-21-214-011-
0000, 10-21-214-012-0000, 10-21-214-0013-0000, 10-21-214-014-0000, 10-21-214-
015-0000, 10-21-214-016-0000, and 10-21-214-019-0000
Discussion and Interested Parties
Legal notice was advertised, posted, and delivered to property owners in the area as
prescribed by the Zoning Chapter. Corporation Counsel determined that notice was
proper and correct.
Mark Gershon, attorney from Polsinelli PC, representing the contract purchaser Luz &
Associates gave an overview of the project. He introduced Barry Sidel of Luz &
Associates, Mike DeRouin, architect from FitzGerald, and Luay Aboona of KLOA, Traffic
Engineers.
Mr. Gershon explained that this project is considered a demonstration planned
development to provide a solution to a unique area and is not subject to normal
requirements. The site is adjacent to the CTA Yellow Line Dempster station and is
designed to be a TOD (transit-oriented development) where renters are not dependent
on the use of a vehicle. They will be within walking distance of public transportation,
shopping, restaurants, etc. They are committed to be Green Globe certified offering
5% of the 192 units as affordable housing. They received unanimous approval from the
Appearance Commission at the January 11, 2023 meeting.
Mr. Barry Sidel, of the development group spoke of his experience and the concept of
the “new renter”; singles, young couples or empty-nesters - people that want amenities
available, so they don’t have to leave home. The new buildings have home spaces to
608860 - Plan Commission meeting minutes – Feb. 16, 2023
work remotely or a social room with a coffee bar, private offices to work in or hold
business meetings, a fitness center and even a dog park with wash area. Each unit will
have all electric appliances including laundry facilities. The locker room will have space
for groceries to be delivered or dry cleaning to be picked up or dropped off. They would
also post bus & transit schedules as well as installing electric charging stations. The
buildings offer studio, 1, or 2-bedroom options.
Mr. Mike DeRouin displayed the site plan and elevations showing the layout for the 7-
story buildings. He talked of the high walkability score being close to Dempster and
Main Streets. They have added windows to the stairwells and provided natural light in
the elevators promoting an open feeling. They will meet bird strike mitigation
guidelines.
Mr. Luay Aboona talked about the elimination of 3 curb cuts leaving one lane for
entry/exit on Conrad and also on Greenleaf Streets. The fire lane is located adjacent to
the public transit parking lot. The parking study estimates that a significant number of
renters will use public transportation and therefore will not impact the neighboring
properties. The 120 indoor parking spaces provided will be sufficient with the use of
the CTA lot, ride-sharing, and the use of zip cars. Mr. Gershon added that residents will
not be eligible for zoned parking but 2/3 of the units will have an indoor parking spot.
A commissioner inquired about the projected rents for the various units. Studios would
be about $1,600 monthly, 1-bedroom would be around $2,100 and 2-bedroom units
would be about $2,700.
In closing, Mr. Gershon stated that returning the not-for-profit property to the tax rolls
will restore revenue to the Village, surrounding schools, police and fire departments and
other government entities.
Staff requested that the report be accepted into the record as written. A demonstration
project status is used to revitalize a site to stimulate redevelopment and economic
growth to an area. Ten of the 192 units will be designated as affordable. In order to
stimulate development, several items of relief were discussed and granted.
Gail Schecter, 9033 Keating, on behalf of “Skokie Neighbors for Justice”, presented her
group’s considerations for the developer. She stated that developments should meet
the needs for people at different price points. She added that the housing offered
should match the earnings of a wide range of potential tenants. Seventy-five percent of
the units are studio or 1 bedroom. If a building is not designated as a senior building,
then it needs to be marketed and open to all; including families with children.
Other community members commented that they would like to move into this
development but could not afford to. They also spoke about environmental elements
such as making the buildings air-tight, water controls by foot pedals, triple-pane and
608860 - Plan Commission meeting minutes – Feb. 16, 2023
thermal windows, green roofs and installing solar panels, and lastly, provide the means
for composting.
Additional opinions were voiced regarding sustainability with the multiple trips made by
Uber, Lyft and food deliveries. Others suggested that the Village Trustees should
deliberate further and not rush through to approve this project before the Affordable
Housing policies are in place. The community needs more than 5% affordable units.
Another resident stated the Village Trustees mostly approve whatever the Plan
Commission recommends and that they should be more demanding of the developers
on behalf of the residents of Skokie.
Recommendations and Voting
A motion was made to approve, as presented, the staff report requesting site plan
approval for a demonstration planned development that includes a 192-unit multifamily
housing development with enclosed parking at 8610 Niles Center Road.
Motion: Burman Second: Ousley Absent: Franklin,
Lakhani, and
Shah
Ayes: 6
Nays: 0
A motion was made to accept the following items of relief:
- To allow 192 units as a demonstration project in planned development
- For multifamily residences with 3 or more units in planned developments by site
plan approval
- To allow building height of 76 feet 7 inches
- To allow rear yard setback of 20 feet
- To allow maximum land coverage of 70%
- To allow 120 parking spaces
- To allow height and FAR beyond the maximum allowed in the district
Motion: Ousley Second: Minchella Absent: Franklin,
Lakhani, and
Shah
Ayes: 6
Nays: 0
608860 - Plan Commission meeting minutes – Feb. 16, 2023
Agenda
Village of Skokie
Plan Commission
February 16, 2023, 7:30 P.M.
Skokie Village Hall
5127 Oakton Street
1. Call Meeting to Order
2. Approval of Meeting Minutes of February 2, 2023
3. 2023-01P – Site Plan Approval: 8610 Niles Center Road- Arie Crown Hebrew Day
School, an Illinois Not-For-Profit Corporation, on behalf of Luz and Associates #1, LLC,
requests site plan approval for a demonstration planned development in an R4
Multifamily Housing zoning district that includes a 192-unit multifamily housing
development with enclosed parking, and any relief that may be discovered during the
review of this case.
4. Staff Update on Affordable Housing
5. Public Comment
6. Adjournment
STAFF REPORT 2023-01P
Community Development Department Council Chambers, 7:30 PM, February 16, 2023
To: Paul Luke, Plan Commission Chairperson
From: Johanna Nyden, AICP, Community Development Director
Paul Reise, AICP, Planning Manager
Re: Primary Case: 2023-01P: Site Plan Approval
General Information
Location 8610 Niles Center
PIN: 10-21-214-001-0000, 10-21-214-002-0000, 10-21-214-003-0000, 10-
21-214-004-0000, 10-21-214-005-0000, 10-21-214-009-0000, 10-21-214-
010-0000, 10-21-214-011-0000, 10-21-214-012-0000, 10-21-214-013-
0000, 10-21-214-014-0000, 10-21-214-015-0000, 10-21-214-016-0000,
and 10-21-214-019-0000
Purpose To request a site plan approval for a demonstration project
planned development, in a R4 Multifamily Housing district, to
construct a new 7-story residential building with 192 units and
120 parking spaces. Includes any relief discovered during the
review of these cases.
Petitioner Luz and Associates #1, LLC
Size of Site 82,764± SF (1.9 acres) with frontage on Niles Center Road,
Conrad St, and Greenleaf Street
Existing Zoning & R4 Multifamily Housing district– vacant school
Land Use
Adjacent Zoning & North R4 Multifamily Housing – 3-or-more-unit multifamily
Land Use residences
South R4 Multifamily Housing – 3-or-more-unit multifamily
residences
East R4 Multifamily Housing – 3-or-more-unit multifamily
residences
West M2 Light Industry – CTA Yellow Line Dempster-Skokie
Station and parking lot
Comprehensive Plan The site is designated as pedestrian oriented mix.
SITE INFORMATION
• The subject site has an existing vacant building.
• There are 4 existing driveways on Conrad Street and 1 on Greenleaf Street.
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 1
• Public sidewalks are available in the area.
PROPOSAL SUMMARY
The petitioner is requesting a 7-story residential building with 192 units and 120
parking spaces.
• Building Square Feet (SF): 249,397
• First Floor Uses: residential amenity, residential lobby, and structured parking
• Number of Residential Units: 192 total = 12 (studio) + 132 (1 bedroom) + 48 (2
bedrooms)
• Number of Parking Spaces: 120 total proposed, including accessible
• Building Height: 7; 76’-7”
Motor vehicle access to the subject site will use 2 major access points: 1 curb cut on
Greenleaf Street and 1 curb cut off Conrad Street.
Pedestrian access will be via public sidewalks.
PETITIONER’S SUBMITTAL
The petitioner is requesting a demonstration project planned development for a 7-story
residential building with 192 residences. A demonstration project is the redevelopment
of a site for allowable uses in the district designed to stimulate redevelopment and
economic growth in the area. The site adjacent to the CTA Yellow line and the
Dempster TIF district. The proposed project must be designed to fulfill the goals of the
redevelopment district. In order to stimulate development, relief may be granted in the
area of district development standards.
The petitioner submits:
The proposed residential campus at 8610 Niles Center Road (the "Project") is designed to
provide numerous benefits to the future residents, the community and the surrounding
neighborhood. It will be harmonious with, and will not adversely affect, adjacent properties.
This will be a high-quality medium intensity Project which, typical of Niles Center Road in the
adjacent area, is proposed to be a multifamily development.
Significant attention was paid to the interaction between the Project and the uses most
proximate to it. The Project is part of an expansive multifamily area which is well established in
the community. It will both benefit from and support retail, restaurant and commercial
improvements located less than a half of a mile walk away on Dempster and a half mile walk
away on Main and Skokie Boulevard. The Skokie Valley trail is located just west of the Project
and provides access to the Village of Skokie Downtown as well as numerous other locations,
work opportunities, restaurants, entertainment and other amenities.
With the encouragement of the Village staff, this project is designed as a "Demonstration
Project", as provided for in the Village of Skokie Zoning Ordinance, to act as a true transit-
oriented development relying both on available mass transit and nearby retail, restaurants and
commercial facilities in addition to bike paths and other community benefits. It is specifically
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 2
designed to complement the existing public transportation infrastructure that surrounds the
Project site including bordering and being less than 500 feet away from the CTA Skokie Swift
Station allowing for easy access to jobs, commercial, retail and entertainment facilities
throughout Skokie, the City of Chicago and elsewhere.
The new members of this community will enjoy tangible benefits of living steps away from their
primary means of public transportation as well as nearby retail, restaurants and entertainment
establishments that surround the Project site, all of which will receive enhanced economic
support from the additional customer base. It will benefit those residents who do not have or
do not want to be reliant upon an automobile but want full access to all that Skokie, Chicago
and the surrounding communities have to offer. As provided in other communities that rely on
and encourage mass transit, biking and walking, parking will be limited (although significantly
more than in similar projects in the City of Chicago and elsewhere). At the same time, in the
event of temporary need, the Project is adjacent to significant adjacent temporary rental
parking in the CTA parking which has been shown to be almost entirely unused over multiple
years.
The existing private school on the project site has generated significant, but typical, school
traffic, particularly during applicable school start and end times. Redeveloping this site will
eliminate the real and perceived impact of educational facilities, including traffic, and add to an
already strong residential area. Either a central landlord or established site control or covenants
will ensure that maintenance of this facility is ongoing to protect and preserve this significant
asset.
Returning the currently not for profit subject property to the real estate and property tax rolls
will restore significant revenues to the Village surrounding schools, police department, fire
department, and other governmental entities that are committed to upholding the public health,
safety, morals and general welfare of the community.
Converting this existing private school area to residential uses addresses concerns raised
previously about the real or perceived impact of that school on the surrounding community. The
Project's new high-quality sustainable design, construction, and operation, including amenities
and internal open space to serve the new members of this community, will be appropriate and
provide a new vista of development for this area. The proposed Project is compatible with and
provides a high-quality newer alternative to surrounding older multi-family and other residential
uses ensuring that the Project will have no impact on the value of surrounding properties.
The traffic report from KLOA will confirm the adequacy of adjacent roadways for the
development and that it will not create undue traffic congestion. This is further seen through
the emphasis on mass transit-oriented uses and nearby amenities only a short walk or bike ride
away.
This area is already well established with services and utilities to serve residential properties.
Adequate public facilities, including roads, drainage, utilities and police and fire protection exist
to serve the requested use at the time such facilities are needed. Final engineering will comply
with Village Codes to ensure proper available public facilities, drainage and utilities. See the
submitted civil plans and our written responses to planning department questions for additional
details. We have confirmed that we will be in compliance with all comments and criteria
provided by the Village of Skokie Fire Department.
Sustainability and care for the environment are an important tenant of this project. Long before
the Village provided the public with a draft of its Environmental Sustainability Plan (the
"Sustainability Plan"), The Developer and its architect, committed to designing the Project to
meet the Green Building Initiatives ("GBI") requirements and protocols for a Green Globe
certification. As described on GBl's web site (theGBl.org), "Environmental objectives pursued
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 3
through Green Globes lead to lower energy and water bills, reduced emissions, optimized health
and wellness benefits, and minimized waste." GBI further indicates that they are "dedicated to
reducing climate impacts by improving the built environment". GBI Green Globes certification is
recognized in numerous communities, such as being included in the Evanston, Illinois Green
Building Ordinance. Green Globes has confirmed that as of June 21,2022 over 500 million
square feet of property had been certified as meeting Green Globes standards and objectives.
While the Project is not subject to the Sustainability Plan, its design forward thinking
sustainability measures and seeking of the Green Globes certification is strong evidence of its
commitment to establishing a sustainable Project which is protective of the community's health,
safety and general welfare. Modern stormwater detention, as identified on our civil engineering
plans, is also an important part of that effort.
The public health, safety, morals and general welfare of the community are protected through
this forward-thinking Demonstration Project's emphasis on mass transit, walking, bike use and
reduced traffic impact. They are further supported by the high-quality design and construction,
respect for the environment, and satisfaction of the provisions of the Village Zoning Code, Fire
Department and other requirements. The Project design allows for quality living in a modern
facility which provides low impact access to the Village and surrounding area, and amenities
benefitting the existing and future residents of the Village who will call the Project their home.
We appreciate your consideration of this project, the opportunity we have had to improve and
enhance it through working with the Village staff and look forward to the opportunity to present
it to the elected and appointed Village officials for their consideration.
STAFF REVIEW
All pertinent departments and divisions were offered an opportunity to comment on this
case. The following is a summary of principal aspects of the proposed development:
Affordable Housing
The applicant is proposing that 10 units, 5% of the 192 units within the project be
designated for rents affordable at 80% of Area Median Income (AMI). The composition
of the units would reflect the units of the apartment complex: one 1 studio, 7 one-
bedroom, and 2 two-bedroom, for a total of 10 units.
Com prehensive P lan
The Comprehensive Plan has identified uses for this site as other Residential in Sector
B. The proposed use is consistent with the comprehensive plan.
Land Use
The Planning Division supports the proposed site plan approval. The development is
adjacent to a mass transit station and will provide transit-oriented housing on site. Staff
believes that higher density developments with lower parking ratios directly adjacent to
CTA stations will provide a catalyst to the nearby retail along Dempster. The façade and
building massing are designed to be viewed from all angles and will provide an
appropriate sense of place along Niles Center Road. The reduction in curb cuts at this
location are significant improvements to public safety. The generous front setback
provides a feeling of openness to pedestrians accessing the CTA Yellow Line station.
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 4
In general, the multifamily residential space is consistent with the intent of the
Comprehensive plan, the Dempster-Skokie Station Area Plan, and zoning for the site.
The size of the site is 82,764 SF and the building area is 249,397 SF, resulting in a floor
area ratio (FAR) of 3. The allowable FAR (relief allowed beyond the maximum per
demonstration project). (Requirement is met.)
The R4 Multifamily Housing district is intended for larger, multi-family housing
developments.
Zoning R equirem ents
The proposed building bulk, density, and site improvemnets will adhere to the R4
Multifamily Housing district requirements, or as otherwise allowed with relief. In
demonstration projects, relief may be granted from FAR and height requirements
beyond the maximum allowed in the zoning district.
A demonstration project is the redevelopment of a site for allowable uses in the district
designed to stimulate redevelopment and economic growth in the area. The subject site
must be in a designated redevelopment district. The proposed project must be designed
to fulfill the goals of the redevelopment district. In order to stimulate development,
relief may be granted in the area of district development standards and other Zoning
Chapter regulations. This site is adjacent to the Dempster TIF district and covered
under the goals and objectives of the Dempster-Skokie Station Area Plan.
The Dempster-Skokie Station Area Plan supports the Village’s long-
standing efforts to improve the district’s attraction to business and
private real estate development. Redevelopment and reinvestment in
the Dempster Street Corridor will occur over several years, driven by
private developers, and encouraged by the Village’s investment and
planning efforts, such as key property acquisition, streetscape
improvements, pedestrian and bicycle trail construction, and zoning
amendments and other procedural and regulatory changes, as well as
the establishment of the West Dempster TIF district. This study
reinforces and expands the Village’s efforts by recommending the use
of excess parking capacity in station area commuter lots to support
existing and future development, as well as circulation improvements
for automobiles and pedestrians between the commuter lots and the
retail development areas. The study also examines development
strategies for several specific sites that enable the Village staff to
understand the capacity and potential of each site for differing
development strategies. By improving the physical conditions in the
study area and acquiring strategic properties, the Village has set the
table for private investment to initiate redevelopment.
• Building height (floors): 7 floors (per demonstration project)
• Building height (feet): 76’-7” (per demonstration project)
• Front yard: 21’ (per site plan approval)
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 5
• Side yard (Conrad): 17’-7.5” (per site plan approval)
• Side yard (Greenleaf): 17’ -6” (per site plan approval)
• Rear yard: 20’ (per site plan approval)
Parking:
• Total Parking: 120 proposed, .625 parking ratio (282 required)
• Bicycle: 16 spaces proposed (12 required, 10% of 120)
Items of relief requested for this development:
• §118-127(1d) to allow 192 units as demonstration project in planned
development
• §118-127(2) for multifamily residences with 3 or more units and in planned
developments: By site plan approval
• §118-127(3b) to allow building height of 76 feet 7 inches, to exceed 60 feet as
demonstration project in planned development.
• §118-127(7) to allow rear yard setback of 20 feet, rather than 30 feet
• §118-127(8) to allow maximum land coverage of 70%, rather than 40%
• §118-218(b) to allow 120 parking spaces rather than 282 as a demonstration
project in planned development.
• §118-272(c) to allow height and FAR beyond maximum allowed in zoning district
Building & Site Elem ents
Several essential concepts to consider:
• Water and Sewer Capacity. Prior to the Village Board of Trustee’s consideration,
a water supply/sewer capacity study must be prepared and submitted to the
Village. Capacity increases or changes must be approved by the Village, and
design and installation costs for any infrastructure improvements to be borne by
the developer.
• Traffic and IDOT. The pending IDOT review and approval might impact the site
and development plan.
• Metropolitan Water Reclamation District (MWRD). An MWRD determination
letter must be obtained to determine if an MWRD permit is required. Since the
proposed project includes greater than 0.50 acres of development and qualified
sewer construction, a WMO permit will be required.
• Utilities. All existing proposed overhead telecom, fiber optic, electric, etc. serving
the subject shall be buried or installed underground. Relocation of overhead
utilities in the alley serving other properties to be coordinated with Village staff.
• Resident Parking. There shall only be a maximum of 1 parking space allocated
to each unit. Potential residents with more than 1 vehicle shall make alternate
off-site parking arrangements for additional vehicles. Residents of this building
will be ineligible for zoned parking.
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 6
Building Design
The Appearance Commission reviewed the design at the Wednesday, January 11, 2023,
meeting and approved a Certificate of Appropriateness. Any relief will be subject to the
Certificate of Appropriateness for this subject site.
P arking, Access, & Circulation
The location of this proposed development is within an on-street, zoned permit parking
area; per Village practice, residents will not be eligible for zoned parking.
Com plete Streets
The following provides information regarding walkability and transit opportunities:
Public sidewalks are available along Niles Center and on the neighborhood side
streets. ADA ramps with contrasting color tactile warning indicators are available at
nearby intersections.
The Skokie Valley Trail is west of the Dempster-Skokie CTA Station and bike lanes
are available nearby on Main Street.
The CTA train station is adjacent to the west of the subject site, and nearby bus
services include Pace Bus Route 250 and CTA Routes 97 and 54A.
The site is within walking distance of other businesses, services, schools, and
shopping. Consider the needs of those who may access the site with transportation
options other than a motor vehicle.
Emergency access to the subject site is available via Niles Center, Conrad Street,
Greenleaf Street, and a fire lane.
Storm w ater M anagem ent
Per MWRD permit determination, since the proposed project includes greater than 0.50
acres of development and qualified sewer construction, a WMO permit will be required.
W ater Conservation
All buildings are required to adhere to the Illinois Plumbing Code. This includes the
incorporation of lower flow fixtures – faucets and toilets. This item will be reviewed at
the time of permit.
Electrical Conservation
The buildings are required to adhere to the Illinois Energy Conservation Code, as
amended by the State Building Code. This includes meeting minimum standards for R-
values for windows and insulation. The code requires a minimum requirement for
materials and wall thickness (in relation to insulation) that meets energy efficiency
standards. In addition, the HVAC systems are required to meet minimum efficiency
standards, and systems are required to be affixed with UL tags. The applicant will be
required to submit a “com check” at the time of permit application to show adherence
to the energy conservation code.
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 7
Consideration should be given to green construction and maintenance practices,
including the possibility of joining the ComEd Energy-Efficiency Program.
Bird Strike M itigation
The Village’s Bird Strike Mitigation regulations will apply to this project.
Sustainability
Where possible, sustainability measures should be employed in new projects. The
Developer has committed to designing the Project to meet the Green Building Initiatives
("GBI") requirements and protocols for a Green Globe certification.
Tree P reservation & Landscaping
Prior to Board of Trustees review, an updated landscape plan with updated species
compatible with Village Environment and Sustainability Plan
STAFF RECOMMENDATIONS
Staff recommends that the petitioner’s request a site plan approval for a demonstration
project planned development for a 7-story residential with 192 units and 120 parking
spaces of indoor parking in a R4 Multifamily Housing district be APPROVED for 8610
Niles Center Road, based upon the Proposed Findings of Fact and subject to the
recommended site plan approval conditions listed below.
Staff further recommends providing relief from the following:
• §118-127(1d) to allow 192 units as demonstration project in planned
development
• §118-127(2) for multifamily residences with 3 or more units and in planned
developments: By site plan approval
• §118-127(3b) to allow building height of 76 feet 7 inches, to exceed 60 feet as
demonstration project in planned development.
• §118-127(7) to allow rear yard setback of 20 feet, rather than 30 feet
• §118-127(8) to allow maximum land coverage of 70%, rather than 40%
• §118-218(b) to allow 120 parking spaces rather than 282 as a demonstration
project in planned development.
• §118-272(c) to allow height and FAR beyond maximum allowed in zoning district
RECOMMENDED SITE PLAN APPROVAL CONDITIONS (2023-01P)
Prior to the hearing of the subject case before the Board of Trustees, the
petitioners must provide the following:
a. A water supply/sewer capacity study must be prepared and submitted to
the Village for review. Capacity analysis cannot be completed until the
development provides preliminary water and sewer engineering plans.
Water and sewer upgrades to the existing public system and/or changes
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 8
to the proposed onsite water and sewer improvements may be required of
the development in order to provide sufficient capacity.
b. Provide preliminary comments from IDOT for staff review.
c. The trip generation rate used was, "Multifamily Housing (Mid-rise) Not
Close To Transit." instead of, "Multifamily Housing (Mid-rise) Close To
Transit." A transit station exists within 1/2 mile of the site entrance.
Reasoning was provided by KLOA through email that it was for
conservative purposes. Using the "Multifamily Housing (Mid-rise) Close To
Transit." would decrease the trip generation. Please provide clarification
on the Traffic Impact Study on the next submittal.
d. On figure 10, the volumes do not balance at the intersection of Niles
Center Road and Greenleaf Street for right turns on the NB approach.
Traffic is not expected to increase here due to the new site and should be
the same as the 2029 No-Build Traffic Volume.
e. A 15% reduction in traffic was applied to the trip generation and parking
generation due to the site being classified as a Transit-Oriented
Development. Please add census data source as mentioned in the study.
Site and Use
1. The petitioner shall develop the Subject Property in substantial conformance with
the final Village approved site plans dated <insert date of final approved plan>,
engineering plans dated <insert date of final approved plan>, landscape plans dated
<insert date of final approved plan>, sign plans dated <insert date of final approved
plan>, and building elevations dated <insert date of final approved plan>. (Standard)
2. Prior to the issuance of building permits, the petitioner shall submit for approval a
lighting photometrics plan, fully developed civil engineering plans that comply with
the county WMO requirements and Village’s stormwater control provisions, and
redevelopment engineering plans to address all aspects of private and public utility
services. Any reconfigurations within state ROW will require an IDOT highway/utility
permit. (Standard)
3. Exterior lighting shall meet Illuminating Engineering Society of North America (IES)
standards, be full cut-off design, and be directed away from adjacent properties,
subject to the approval of the Engineering Division. (Standard)
4. All existing damaged public sidewalks or public sidewalks damaged due to the
implementation of this plan shall be replaced. (Standard)
5. No objects are allowed within a 15' sight distance triangle in all non-residential
zoning districts between 30" and 84" in height from grade, except traffic control
devices listed in the Manual on Uniform Traffic Control Devices and as indicated in
the approved site plan and floor plans.
6. Prior to the issuance of building permits, the petitioner shall provide a Construction
Management Plan that includes a temporary pedestrian, bicycle, and transit
circulation plan for the public right-of-way, including routing, signage, and barriers,
to be in place prior to the commencement of construction, subject to the approval of
the Engineering Division. If during construction any lane closures or sidewalk
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 9
closures are intended in the public right-of-way, the owner/contractor must apply for
Public Way Obstruction or Use permit with Engineering. The application may be
obtained with engineering or on Village website. Traffic control plan and fees will
apply. (Standard)
7. Owner will allocate 10 units of affordable housing within the apartment complex for
lease at rents affordable at 80% of Area Median Income. The composition of the
units would reflect the unit mix of the apartment complex: 1 studio, 7 one-bedroom,
and 2 two-bedroom, for a total of 10 units. Rent for these 10 units would be
established at the rent, pursuant to income limits for Chicago-Naperville-Joliet, IL
HUD Metro FMR Area for 80% Area Median Income.
8. Project will be designed and constructed to meet the Green Building Initiatives
("GBI") requirements and protocols for a Green Globe certification.
Maintenance
9. All fencing, walls, sidewalks, driveways, curbs, wheel stops, parking areas, signage,
landscaping, structures, and any other facilities or infrastructure on the Subject
Property shall be maintained in a good state of repair, and when needed, be
repaired or replaced in a timely manner. (Standard)
10. All private and public sidewalks shall be maintained free of snow, ice, sleet, or other
objects that may impede travel. (Standard)
11. Trash shall only be allowed within a designated trash enclosure and shall be
screened from public view in an enclosure approved by the Appearance Commission.
Parking
12. Any plan to modify parking lot striping must be approved by the Director of
Engineering. (Standard)
13. The proposed development shall have a minimum of 120 off-street vehicle parking
spaces, including 5 handicapped parking spaces, and a minimum of 16 bicycle
parking spaces, as indicated on the Subject Property plan dated <insert date of final
approved plan>. (Standard)
14. The handicapped parking spaces shall be installed and maintained in compliance with
State of Illinois Accessibility Standards and the Skokie Village Code, including required
signage. (Standard)
15. Vehicles shall not be allowed to be parked in or otherwise block common driveways,
sidewalks, aisles, or other points of access at any time, shall only be parked in
designated parking spaces, and shall not overlap the striped lines of designated
parking spaces. (Standard)
Residential
16. Cable access shall not be denied to any residents in the building. All cable providers
shall be given access to provide service. All cable and other fixtures necessary to
provide service to the building shall be placed underground and conduit shall be
provided inside the building for wiring. (Standard)
Utilities
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 10
17. Prior to issuance of building permits, the petitioner shall submit evidence of issuance
of permits for the construction and operation of the water main and associated
equipment by the Illinois Environmental Protection Agency (IEPA) or provide a
determination by IEPA that such permits are not required. Water mains that feed
multiple building structures and/or create a "looped" system that require an IEPA
permit will also require an easement and custodial agreement with the Village.
(Standard)
18. All overhead utilities on or serving the Subject Property shall be placed underground
or relocated. The petitioner shall bear the full cost of this utility relocation and/or
conflicts.
Landscaping
19. The petitioner shall sign an "Agreement for Installation and Maintenance of
Landscaping" to assure that the Subject Property and parkway landscaping is
completed and maintained, including trimming, watering, and replacing of dead
plant materials in a timely manner in accordance with the final approved landscape
plan. This “Agreement for Installation and Maintenance of Landscaping" shall be
recorded at the petitioner’s expense. (Standard)
Governance
20. All new construction, alterations, and remodeling shall meet current International
Building and NFPA Life Safety Codes as amended. (Standard)
21. The petitioner shall obtain all required permits and approvals for improvements to
County, State, or Federal rights-of-way from the governing jurisdiction. (Standard)
22. The Subject Property must conform to the Village's storm water control requirements
as contained in the Skokie Village Code, including the disconnection of any
downspouts. (Standard)
23. All signage shall conform to the Skokie Village Code. Any sign on the Subject
Property that is in violation of that Code must be removed or modified to conform
with the Village Code prior to the issuance of an occupancy permit. (Standard)
24. All modifications to building elevations, signage, and landscaping shall be subject to
the review and approval of the Skokie Appearance Commission. (Standard)
25. The petitioner shall submit to the Planning Division electronic files of the site plan
and landscape plan in their approved and finalized form. (Standard)
26. Prior to the issuance of building permits, the petitioner shall submit to the Planning
Division of the Community Development Department the name, property address,
email address, and telephone number of the company and contact person
responsible for site maintenance in compliance with this site plan approval. (Standard)
27. If work is to be performed on public property or if public property is utilized or
impacted during construction and/or development, the owner shall provide, or shall
cause the developer and/or contractor to provide, the Village of Skokie with a
certificate of insurance naming the Village of Skokie as additionally insured for any
and all claims related to any and all work. The owner shall hold, and shall cause the
developer and/or contractor to hold, the Village of Skokie harmless and indemnify
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 11
the Village for any and all claims for property damage or personal injury related to
work on or use of public property. (Standard)
28. The petitioner shall comply with all Federal and State statutes, laws, rules and
regulations and all Village codes, ordinances, rules, and regulations. (Standard)
29. Failure to abide by any and all terms of this Ordinance shall be cause for the Village
to initiate hearings to determine whether the subject Ordinance, as well as any
applicable business licenses, should be revised or revoked. The petitioner shall pay
all costs related to any hearings conducted as a result of non-compliance with any of
the provisions of the enabling ordinance. The costs shall include but not be limited
to court reporter fees, attorney fees, and staff time required researching and
conducting said hearing. (Standard)
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 12
ATTACHMENTS
1. Proposed Findings of Fact for 2023-01P: Site Plan Approval & Planned Development
2. 8610 Niles Center Zoning Map
3. Proposed Site Plan, Landscape Plan, Floor Plans, Building Elevations, Rendering, and
Photos, all dated February 16, 2022
4. KLOA Traffic Impact Study, dated February 1, 2023
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 13
PROPOSED FINDINGS OF FACT 2023-01P: Site Plan Approval
Community Development Department Council Chambers, 7:30 PM, February 16, 2023
Consideration Finding
The request is harmonious with and does The request will be harmonious with and
not adversely affect adjacent properties. will not adversely affect adjacent
properties as long as the conditions of the
planned development for site plan
approval are met.
The request can demonstrate that The request will have adequate public
adequate public facilities, including roads, facilities, including roads, drainage,
drainage, utilities, and police and fire utilities, and police and fire protection,
protection exist or will exist to serve the which exist or will exist to serve the
requested use at the time such facilities are requested use at the time such facilities
needed. are needed.
The request demonstrates adequate The request will have adequate provision
provision for maintenance of the associated for maintenance of the associated
structures. structures.
The request has considered and, to the No adverse effects on the natural
degree possible, addressed the adverse environment are anticipated.
effects on the natural environment.
The request will not create undue traffic The request will not create undue traffic
congestion. congestion as long as the conditions of
the site plan approval are met.
The request will not adversely affect public The request will not adversely affect
health, safety, and welfare. public health, safety, and welfare.
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 14
Planned Development Additional Findings of Fact
Consideration Finding
The proposed use of the particular site, The request will provide an amenity, or
including any exceptions to use, shall be facility that will contribute to the general
shown as necessary or desirable to provide well-being of the surrounding area.
a service, amenity, or facility that will
contribute to the general well-being of the
surrounding area.
Under the circumstances of the particular The proposed use will not be detrimental
case, the proposed use will not be to the health, safety, or general welfare
detrimental to the health, safety, or general of persons residing within or in the
welfare of persons residing within or in the vicinity of the PD
vicinity of the PD
VOSDOCS-#606227-v1-8610_Niles_Center_Staff_Report_2023-01P 15
8610 Niles Center zoning map
0 450 900 Print Date: 2/10/2023 Notes
ft
Disclaimer: The GIS Consortium and MGP Inc. are not liable for any use, misuse, modification or disclosure of any map provided under applicable law. This map is for general information purposes only. Although the information is believed to be generally accurate, errors may
exist and the user should independently confirm for accuracy. The map does not constitute a regulatory determination and is not a base for engineering design. A Registered Land Surveyor should be consulted to determine precise location boundaries on the ground.
Luz and Associates #1 LLC Plan Commission
8610 Niles Center Road
Skokie, Illinois | February 16, 2023
Luz and Associates #1 LLC Site Survey
8610 Niles Center Road 1
Skokie, Illinois | February 16, 2023
Material Storage
During Construction
All Elevators are Stretcher Size
NOTE: CONSTRUCTION
WORKER PARKING DURING
CONSTRUCTION TO BE
NEGOTIATED.
Luz and Associates #1 LLC Ground Floor Plan
8610 Niles Center Road 2
Skokie, Illinois | February 16, 2023
Luz and Associates #1 LLC Landscape Plan
8610 Niles Center Road 3
Skokie, Illinois | February 16, 2023
Luz and Associates #1 LLC 2nd Floor Plan
8610 Niles Center Road 4
Skokie, Illinois | February 16, 2023
Luz and Associates #1 LLC 3rd - 7th Floor Plans
8610 Niles Center Road 5
Skokie, Illinois | February 16, 2023
METAL BALCONY 3 COLORS OF FIBER METAL BALCONY 3 COLORS OF FIBER
AND RAILING BOARD CEMENT - SEE MATERIALS AND RAILING CEMENT - SEE MATERIALS
BRICK BASE
80’-7”
76’-7”
65’-7”
54’-7”
43’-7”
32’-7”
21’-7”
10’-7”
Greenleaf Elevation (South) Niles Center Elevation (East)
METAL BALCONY 3 COLORS OF FIBER METAL BALCONY 3 COLORS OF FIBER
AND RAILING CEMENT - SEE MATERIALS AND RAILING CEMENT - SEE MATERIALS
BRICK BASE
Conrad Elevation (North) West Elevation
APARTMENT BUILDINGS: TYPE III CONSTRUCTION
Luz and Associates #1 LLC Building Elevations
8610 Niles Center Road 6
Skokie, Illinois | February 16, 2023
1 Fiber Cement Panel 2 Fiber Cement Board 3 Fiber Cement Board 4 Fiber Cement Panel 5 Brick Base 6 Brick Base 7 Perforated Metal Railing
Color #1 Color #2 Color #3 Color #4 Color #5 Color #6
5 4 1 2 7 5 3 1 4 7 5 1 3 2 7 1 3 2 5
80’-7”
76’-7”
65’-7”
7
54’-7”
43’-7”
32’-7”
6
21’-7”
10’-7”
Typical South Elevation Typical North Elevation Typical East Elevation Typical West Elevation
Luz and Associates #1 LLC Materials
8610 Niles Center Road 7
Skokie, Illinois | February 16, 2023
BALCONY
76’-7”
65’-7”
54’-7”
43’-7”
32’-7”
21’-7”
10’-7”
FIRE FIRE
TRUCK TRUCK
EAST-WEST ELEVATION DIAGRAM
FIRETRUCK AERIAL APPARTUS
NORTH-SOUTH SECTION DIAGRAM
Luz and Associates #1 LLC Section Diagram
8610 Niles Center Road 8
Skokie, Illinois | February 16, 2023
A SW corner of Site from Greenleaf St
B Looking from SE corner of site down
Greenleaf St and Niles Center Rd
Conrad St.
Cente
r Rd.
C Looking from SE corner of site down Niles
Greenleaf St and Niles Center Rd
B C
A Greenleaf St.
Luz and Associates #1 LLC Context Photos
8610 Niles Center Road 9
Skokie, Illinois | February 16, 2023
D SE corner of Site from Greenleaf St looking
North up Niles Center Rd
E From East side of site looking South
down Niles Center Rd
F
Conrad St.
E
F Looking from NE corner of site at
Cente
Conrad St and Niles Center Rd r Rd.
Niles
Greenleaf St.
D
Luz and Associates #1 LLC Context Photos
8610 Niles Center Road 10
Skokie, Illinois | February 16, 2023
G NE corner of Site looking down Conrad St &
Niles Center Rd
H Looking South at NE corner of Site
down Niles Center Rd
H
I Conrad St.
G
I Looking East down Conrad St
Cente
r Rd.
Niles
Greenleaf St.
Luz and Associates #1 LLC Context Photos
8610 Niles Center Road 11
Skokie, Illinois | February 16, 2023
Traffic Impact Study
8610 Niles Center Road
Residential Development
Skokie, Illinois
Prepared For:
Luz and Associates #1, LLC
February 1, 2023
1. Introduction
This report summarizes the results of a traffic impact study conducted by Kenig, Lindgren, O’Hara,
Aboona, Inc. (KLOA, Inc.) for a proposed residential development to be located in Skokie, Illinois.
The site, which is currently occupied by Arie Crown Early Childhood Campus, is located at 8610
Niles Center Road. As proposed, the site will be redeveloped with a residential development
containing 192 apartments units and 131 parking spaces. Access to the development is proposed to
be provided off Conrad Street and Greenleaf Street.
The sections of this report present the following:
• Existing roadway conditions including vehicle, pedestrian, and bicycle traffic volumes for the
weekday morning and weekday evening peak hours
• A detailed description of the proposed development
• Vehicle trip generation for the proposed development
• Directional distribution of development-generated traffic
• Regional growth in traffic and background development traffic for Year 2029 no-build
conditions
• Future transportation conditions including access to and from the development
Traffic capacity analyses were conducted for the weekday morning and weekday evening peak hours
for the following three conditions:
1. Existing Conditions – Analyzes the capacity of the existing roadway system using existing
peak hour traffic volumes in the surrounding area.
2. Year 2029 No-Build Conditions – Analyzes the capacity of the existing roadway system using
the existing traffic volumes increased by an ambient growth factor (growth not attributable to
and particular development).
3. Year 2029 Total Projected Conditions – The total projected traffic volumes includes the
existing traffic volumes increased by an ambient growth factor and the traffic estimated to be
generated by the proposed subject development.
The purpose of this study was to examine existing traffic conditions to establish a base condition,
assess the impact that the proposed development would have on traffic conditions in the area, and
determine the roadway and traffic control improvements needed to mitigate this development’s
impact based on Year 2029 projected traffic conditions.
8610 Niles Center Road
Skokie, Illinois 1
2. Existing Conditions
Existing traffic and roadway conditions were documented based on field visits and traffic counts
conducted by KLOA, Inc. The following provides a detailed description of the physical
characteristics of the roadways including geometry and traffic control, adjacent land uses, and peak
hour traffic flows along area roadways.
Site Location
The site is currently occupied by the Arie Crown Early Childhood Campus in Skokie, Illinois. The
site is bounded by Niles Center Road, Conrad Street, Greenleaf Street, and the Skokie Swift south
parking lot. Land uses to the north, east, and south are primarily residential. The Skokie Swift CTA
rapid transit line and its associated parking lot is located to the north and west. Figure 1 shows the
location of the site in relation to the area roadway system. Figure 2 shows an aerial view of the site.
Existing Roadway Characteristics
Some of the key characteristics of the existing roadways within the study area are described below
and are illustrated in Figure 3.
Dempster Street (IL Route 58) is an east-west other principal arterial roadway that generally provides
two lanes in each direction in the vicinity of the site. At its signalized intersection with the Skokie
Swift Access Drive, Dempster Street provides a through lane and a combined through/right-turn lane
on the eastbound approach. On the westbound approach, Dempster Street provides a left-turn lane
and two through lanes. A paved crosswalk is provided on the west leg and a standard-style crosswalk
is provided on the east leg. The west leg has a landscaped median and the east leg has a raised concrete
median. Dempster Street is a Strategic Regional Arterial (SRA) and is under the jurisdiction of the
Illinois Department of Transportation (IDOT). Dempster Street carries an Annual Average Daily
Traffic (AADT) volume of 30,200 vehicles (IDOT 2019). Dempster Street has a posted speed limit
of 35 miles per hour.
Niles Center Road is a north-south major collector roadway that provides one lane in each direction
in the vicinity of the site. At its unsignalized intersections with Conrad Street and Greenleaf Street,
Niles Center Road provides a combined left-turn/through/right-turn lane on the northbound and
southbound approaches. Niles Center Road is under the jurisdiction of IDOT, carries an AADT
volume of 6,700 vehicles (IDOT 2018), and has a posted speed limit of 30 miles per hour.
Conrad Street is an east-west local roadway that provides one lane in each direction. At its
unsignalized intersection with Niles Center Road, Conrad Street provides a left-turn/through/right-
turn lane on the eastbound and westbound approaches, which are under stop sign control. Standard-
style crosswalks are provided on the east and west legs. Conrad Street is under the jurisdiction of the
Village of Skokie.
8610 Niles Center Road
Skokie, Illinois 2
SITE
Site Location Figure 1
8610 Niles Center Road
Skokie, Illinois 3
SITE
Aerial View of Site Figure 2
8610 Niles Center Road
Skokie, Illinois 4
N
NOT TO SCALE
DEMPSTER
58
STREET
NI
LE
S
C
RO EN
STARBUCKS TARGET
AD TE
R
ACC FT
WI
ES
KI VE
SKO DRI
ESS
W
LLO
YE
NE
LI
O
(SK
RESIDENTIAL
RESIDENTIAL
E
KI
FT)
I
SW
CONRAD
STREET
LEGEND RESIDENTIAL
SITE
- TRAVEL LANE
- TRAFFIC SIGNAL
30
- STOP SIGN
XX - SPEED LIMIT GREENLEAF
STREET
- NO U-TURN
- DO NOT ENTER SIGN
RESIDENTIAL 30
- PAVED CROSSWALK RESIDENTIAL
- STANDARD CROSSWALK
- HIGH VISIBILITY CROSSWALK
8610 Niles Center Road
Residential Development Existing Roadway Characteristics Kenig,Lindgren,O'Hara,Aboona,Inc.
Skokie, Illinois
Job No: 22-406 Figure: 3
Greenleaf Street is an east-west local roadway that provides one lane in each direction. At its
unsignalized intersection with Niles Center Road, Greenleaf Street provides a left-turn/through/right-
turn lane on the eastbound and westbound approaches, which are under stop sign control. Greenleaf
Street is under the jurisdiction of the Village of Skokie.
Skokie Swift Access Drive is a north-south access drive that provides access to the Skokie Swift
commuter parking lots and Starbucks to the south and provides access from the retail strip to the
north. At its signalized intersection with Dempster Street, the access drive provides a left-turn lane
and a right-turn lane on the northbound approach. On the southbound approach, which is an exit-only
access drive, a combined left-turn/through/right-turn lane is provided. A high-visibility crosswalk is
provided on the south leg.
Public Transportation
The public transportation serving the area is summarized below and illustrated in Figure 4.
CTA Rapid Transit. The area is served by the Chicago Transit Authority (CTA) rapid transit “Skokie
Swift” Yellow Line via the Dempster-Skokie station, the western most station on the line. The station
is located approximately 550 feet to the northwest of the site. The CTA Yellow Line operates daily
between Dempster-Skokie and Howard from early morning to late night. Connections to the CTA
Red and Purple lines are available at Howard.
It should be noted that according to the Transit Friendly Development Guide, produced in part by
CDOT (Chicago Department of Transportation) and the CTA, the area surrounding the Dempster-
Skokie Yellow Line station is considered a Local Activity Center (LC). This classification describes
station areas that exist in the centers of identifiable neighborhoods and is focused on supporting the
surrounding area or community. A mixture of higher intensity and denser land uses surround them
providing a mix of employment in retail, service, and other sectors. Higher density of residential and
employment uses at the core of the local center are common in the immediate surrounding area.
CTA Bus Routes. The area is also served by the following bus routes, which have bus stops within
the vicinity of the site:
• Route 54A (North Cicero/Skokie Boulevard) provides service on Cicero Avenue/Skokie
Boulevard between the Irving Park Blue Line station and Old Orchard Mall/Skokie
Courthouse. Notable points of interest along the route include Six Corners, Mayfair
Milwaukee District-North Metra station, LaBagh Woods Forest Preserve, Oakton Community
College, CTA Oakton-Skokie Yellow Line station, CTA Dempster-Skokie Yellow Line
station, Weber Leisure Center, Old Orchard Mall, Niles North High School, and the Skokie
Courthouse. Service is provided weekdays during morning and evening rush periods.
• Route 97 (Skokie) provides service within Skokie between the Howard Red/Purple/Yellow
Lines station and Old Orchard Mall. Notable points of interest along the route include the
Levy Senior Center, James Park, Skokie Sports Park, the CTA Rail Maintenance Facility,
Oakton Park, CTA Oakton-Skokie Yellow Line station, downtown Skokie, CTA Dempster-
Skokie Yellow Line station, Weber Leisure Center, and Old Orchard Mall. Service is provided
seven days a week, from early morning to late evening.
8610 Niles Center Road
Skokie, Illinois 6
N
NOT TO SCALE
#250 DEMPSTER STREET
#626
CAROLSTREET
#54A
D DEMPSTER-
A
O SKOKIE CRAI
N STREET
R STATION
T
IN
PO
SS
M
TER
O
R CONRAD STREET
G
NAL
SITE
I
NUE
A VE
GREENLEAFSTREET
LARAM I
E AVENUE LECLAI
RE AVENUE
D
OA WRI
GHTTERRACE
EN
TER
R
NI
LES
LEESTREET
C
ELM STREET
#97
MAI
N STREET
LEGEND
SKO KI
E BO ULEVARD
- ROUTE 54A - NORTH CICERO/SKOKIE BOULEVARD
- ROUTE 97 - SKOKIE
- ROUTE 250 - DEMPSTER STREET
- ROUTE 626 - SKOKIE-BUFFALO GROVE LIMITED
- CTA YELLOW LINE
- BUS STOP
- BUS STOP WITH SHELTER
8610 Niles Center Road
Residential Development Public Transportation Kenig,Lindgren,O'Hara,Aboona,Inc.
Skokie, Illinois
Job No: 22-406 Figure: 4
Pace Bus Routes. The area is also served by the following bus routes, which have bus stops within
the vicinity of the site:
• Route 250 (Dempster Street) provides service on Dempster Street between the CTA Davis
Purple Line Station and the O’Hare Multi-Modal Facility (MMF). Notable points of interest
along the route include downtown Evanston, CTA Dempster-Skokie Yellow Line station,
Notre Dame High School, Lutheran General Hospital, Maine East High School, downtown
Des Plaines, Maine West High School, and the Allstate Arena. The O’Hare MMF provides
direct access to O’Hare International Airport via the Airport Transit System. Service is
provided daily, from early morning to late night.
• Route 626 (Skokie-Buffalo Grove Limited) provides service between the Dempster-Skokie
Yellow Line station and Lincolnshire Corporate Center. Notable points of interest along the
route include Northbrook Court, Lake Cook Road Milwaukee District-North Metra station,
Riverwoods Corporate Center, Wolters Kluwer, Riverwalk, the Pace Buffalo Grove Park-n-
Ride, and Lincolnshire Corporate Center. Service is provided weekdays during morning and
evening rush periods.
Existing Traffic Volumes
In order to determine current vehicle, pedestrian, and bicycle conditions within the study area, KLOA,
Inc. conducted peak period traffic, pedestrian, and bicycle counts during the morning (7:00 A.M. to
9:00 A.M.) and evening (4:00 P.M. to 6:00 P.M.) peak periods, on Tuesday, January 10, 2023 for the
following intersections:
• Dempster Street with Skokie Swift access drive
• Niles Center Road with Conrad Street
• Niles Center Road with Greenleaf Street
The results of the traffic counts show that the peak hours generally occur between:
• 7:45 A.M. and 8:45 A.M. during the weekday morning peak hour
• 4:00 P.M. and 5:00 P.M. during the weekday evening peak hour
Figure 5 illustrates the existing peak hour vehicle traffic volumes. Figure 6 illustrates the existing
peak hour bike and pedestrian volumes. Summaries of the traffic counts are included in the Appendix.
8610 Niles Center Road
Skokie, Illinois 8
N
1(
16) 0 (
0) 1(
8)
NOT TO SCALE
838 (
966)
43 (36)
DEMPSTER
58
STREET
800 (959)
96 (80)
NI
LE
31)
(
30 S
C
69)
82
(
RO EN
AD TE
R
ACC FT
WI
ES
KI VE
SKO DRI
ESS
W
LLO
YE
NE
LI
O
(SK
E
KI
FT)
I 4 (
SW
6)
201
(
227
5 ( ) 27 (13)
9)
59 (21)
7 (2)
CONRAD
STREET
12 (13)
45
17 (29) (19)
251
39 (25) (
245
)
8 (
5 ( 9)
1)
SITE 245
(
255
53 )
(
26) 35 (13)
4 (3)
8 (4)
GREENLEAF
STREET
3 (0)
4 (2) 9 (
257 4)
3 (2)
LEGEND (
245
)
5 (
00 - AM PEAK HOUR (7:45-8:45 AM) 10)
(00) - PM PEAK HOUR (4:00-5:00 PM)
8610 Niles Center Road
Residential Development Existing Traffic Volumes Kenig,Lindgren,O'Hara,Aboona,Inc.
Skokie, Illinois
Job No: 22-406 Figure: 5
0 (
0)
N
0 (7) NOT TO SCALE
0 (
0) 1 (
4)
0 (0)
DEMPSTER
0 (0)
58
STREET
NI
LE
3 (3)
S
C
RO EN
FT
AD TE
0) WI
0 (
R
ACC
ES
KI VE
SKO DRI
ESS
W
LLO
YE
NE
LI
O
(SK
E
KI
0 (
FT)
0)
I
SW
11 (4)
1(
0 (0)
1) 9 ( CONRAD
5) STREET
0 (1)
7 (6)
0 (
0)
0 (
SITE 0)
1 (1)
9 ( 0 (0)
6) 0 ( GREENLEAF
1) STREET
LEGEND 0 (0)
00 - AM PEAK HOUR (7:45-8:45 AM)
0 (1)
(00) - PM PEAK HOUR (4:00-5:00 PM)
00 (00)
- PEDESTRIAN VOLUME
0 (
- BICYCLE VOLUME 0)
00 (00)
8610 Niles Center Road
Existing Pedestrian and Bicycle
Residential Development Kenig,Lindgren,O'Hara,Aboona,Inc.
Skokie, Illinois
Traffic Volumes
Job No: 22-406 Figure: 6
Crash Data Summary
KLOA, Inc. obtained crash data1 from IDOT for the most recent available past five years (2017 to
2021) for the three intersections in the study area. The crash data is summarized in Tables 1 through
3. No fatal crashes were reported at any of the intersections during the study period.
Table 1
DEMPSTER STREET WITH SKOKIE SWIFT ACCESS DRIVE – CRASH SUMMARY
Type of Crash Frequency
Year
Angle Head On Object Rear End Sideswipe Turning Other Total
2017 0 0 0 2 0 0 1 3
2018 0 0 0 2 0 1 0 3
2019 0 0 0 0 1 0 0 1
2020 1 0 0 0 0 0 0 1
2021 0 0 0 0 0 1 0 1
Total 1 0 0 4 1 2 1 9
Average <1.0 0.0 0.0 <1.0 <1.0 <1.0 <1.0 1.8
Table 2
NILES CENTER ROAD WITH CONRAD STREET – CRASH SUMMARY
Type of Crash Frequency
Year
Angle Head On Object Rear End Sideswipe Turning Other Total
2017 1 0 0 0 0 0 0 1
2018 1 0 0 0 0 0 0 1
2019 1 0 0 0 0 0 0 1
2020 0 0 0 0 0 0 1 1
2021 1 0 0 0 0 0 0 1
Total 4 0 0 0 0 0 1 5
Average <1.0 0.0 0.0 0.0 0.0 0.0 <1.0 1.0
1
IDOT DISCLAIMER: The motor vehicle crash data referenced herein was provided by the Illinois Department of Transportation.
Any conclusions drawn from analysis of the aforementioned data are the sole responsibility of the data recipient(s). Additionally, for
coding years 2015 to present, the Bureau of Data Collection uses the exact latitude/longitude supplied by the investigating law
enforcement agency to locate crashes. Therefore, location data may vary in previous years since data prior to 2015 was physically
located by bureau personnel.
8610 Niles Center Road
Skokie, Illinois 11
Table 3
NILES CENTER ROAD WITH GREENLEAF STREET – CRASH SUMMARY
Type of Crash Frequency
Year
Angle Head On Object Rear End Sideswipe Turning Other Total
2017 0 0 0 0 0 0 0 0
2018 0 0 0 0 0 0 0 0
2019 0 0 0 0 0 0 0 0
2020 1 0 0 0 0 0 0 1
2021 0 0 0 0 0 1 0 1
Total 1 0 0 0 0 1 0 2
Average <1.0 0.0 0.0 0.0 0.0 <1.0 0.0 <1.0
8610 Niles Center Road
Skokie, Illinois 12
3. Traffic Characteristics of the Proposed Development
To evaluate the impact of the subject development on the area roadway system, it was necessary to
quantify the number of vehicle trips the overall site will generate during the weekday morning and
weekday evening peak hours and then determine the directions from which the proposed traffic will
approach and depart the site, given the proposed access points that will serve the overall development.
Proposed Site and Land-Use Plan
As proposed, the site will be developed into a residential development providing 192 apartment units
and 131 parking spaces. The development will consist of two seven-story residential buildings joined
at the ground level by a covered parking garage, lobby, and resident amenity area. Each building will
contain 96 units consisting of six studio units, 66 one-bedroom units, and 24 two-bedroom units.
There will be 16 units on each floor. Within the parking garage, 16 bicycle parking spaces will be
provided.
Access to the garage will be provided via two new access drives, one on Conrad Street and one on
Greenleaf Street. The access drives will be full access and will provide one inbound lane and one
outbound lane. Outbound movements should be under stop sign control.
A copy of the proposed site plan is included in the Appendix.
Directional Distribution of Development Traffic
The directional distribution of how traffic will approach and depart the site was estimated based on
the general travel patterns through the study area derived from the peak hour traffic volumes. Figure
7 shows the directional distribution established for this development. Further, Figure 7 shows the
distance, in feet, between the existing and proposed intersections analyzed in this study.
Development Traffic Generation
The number of peak hour trips estimated to be generated by the proposed residential development
was based on vehicle trip generation rates contained in Trip Generation Manual, 11th Edition,
published by the Institute of Transportation Engineers (ITE). The Multifamily Housing – Mid-Rise
(Land-Use Code 221) rate was used. It should be noted that given the proximity of the site to the
Skokie Swift station and based on a review of Census data, approximately 15 percent of residents in
the area use public transportation to commute to and from work. As such, the estimated total trips
were reduced accordingly. Copies of the ITE trip generation sheets are included in the Appendix.
Table 4 tabulates the vehicle trips anticipated for this development for the weekday morning and
weekday evening peak hours as well as the daily (two-way) traffic volumes.
8610 Niles Center Road
Skokie, Illinois 13
N
NOT TO SCALE
DEMPSTER
58
STREET
40%
NI
LE
S
C
RO EN
AD TE
R
ACC FT
WI
ES
KI VE
SKO DRI
ESS
30%
W
LLO
YE
NE
LI
O
(SK
E
KI
FT)
I
SW
10%
CONRAD
STREET
345
SITE '
10%
GREENLEAF
STREET
10%
LEGEND
00% - PERCENT DISTRIBUTION
00' - DISTANCE IN FEET
8610 Niles Center Road
Residential Development Directional Distribution Kenig,Lindgren,O'Hara,Aboona,Inc.
Skokie, Illinois
Job No: 22-406 Figure: 7
Table 4
PROJECTED PEAK HOUR SITE-GENERATED TRIPS
ITE Weekday Morning Weekday Evening
Land Daily Traffic
Type/Size Peak Hour Peak Hour
Use
Code In Out Total In Out Total In Out Total
Multifamily Housing
221 17 56 73 46 29 75 435 435 870
(Mid-Rise) [192 Units]
TOD Reduction (15%) -3 -8 -11 -7 -4 -11 -65 -65 -130
Total 14 48 62 39 25 64 370 370 740
Trip Generation Comparison
The amount of traffic estimated to be generated by the proposed residential development was
compared to the traffic generated by Arie Crown Early Childhood Campus, which currently occupies
the site, with a maximum enrollment of 200 children. The trips were estimated utilizing the Day Care
(Land-Use Code 565) rate published in the Trip Generation Manual. Table 5 shows the results of the
comparison and copies of the ITE trip generation sheets are included in the Appendix.
Table 5
TRIP GENERATION COMPARISON
ITE Weekday Morning Weekday Evening
Land Daily Traffic
Type/Size Peak Hour Peak Hour
Use
Code In Out Total In Out Total In Out Total
Proposed Residential
221 Development (192 14 48 62 39 25 64 370 370 740
Units)
Arie Crown Campus
565 74 66 140 63 71 134 380 380 760
(200 Students)
Difference -60 -18 -78 -24 -46 -70 -10 -10 -20
As can be seen, the proposed development will generate less traffic during the weekday morning and
evening peak hours and on a daily basis, and, as such, the proposed development will have a lower
traffic impact on area roadways.
8610 Niles Center Road
Skokie, Illinois 15
4. Projected Traffic Conditions
The total projected traffic volumes include the existing traffic volumes, increase in background traffic
due to growth, and the traffic estimated to be generated by the proposed development.
Development Traffic Assignment
The peak hour traffic volumes projected to be generated by the proposed development (Table 4) were
assigned to the area roadways based on the directional distribution analysis (Figure 7). Figure 8
shows the assignment of the new vehicle trips.
Year 2029 Background (No-Build) Traffic Conditions
The existing traffic volumes (Figure 5) were increased by a regional growth factor to account for the
increase in existing traffic related to regional growth in the area (i.e., not attributable to any particular
planned development). Based on Annual Average Daily Traffic (AADT) projections provided by the
Chicago Metropolitan Agency for Planning (CMAP) in a letter dated January 16, 2023, the existing
traffic volumes are projected to increase by a total of approximately 2.0 percent (0.3 percent
compounded annually) to represent Year 2029 no-build conditions (one-year buildout plus five
years). A copy of the CMAP projections letter is included in the Appendix. The Year 2029 no-build
traffic volumes are illustrated in Figure 9.
Year 2029 Total Projected Traffic Volumes
The Year 2029 total projected traffic volumes include the Year 2028 no-build traffic volumes (Figure
9) plus the traffic estimated to be generated by the proposed subject development (Figure 8). Figure
10 shows the Year 2029 total projected traffic volumes.
8610 Niles Center Road
Skokie, Illinois 16
N
NOT TO SCALE
1 (1)
DEMPSTER
58
6 (15) STREET
NI
LE
1)
1( S
10) C
19 ( RO EN
AD TE
R
ACC FT
WI
ES
KI VE
SKO DRI
4 (
10)
ESS
13
(
7)
W
LLO
YE
NE
LI
O
(SK
E
KI
FT)
I
SW
3 (
7)
1(
3)
1 (4) CONRAD
STREET
10 (5)
0 (
5 (2) 1)
1 (1) 3 (
2)
SITE
1(
3)
1(
1)
1 (4)
GREENLEAF
STREET
3 (2)
5 (2) 1(
3)
4 (2) 0 (
LEGEND 1)
00 - AM PEAK HOUR (7:45-8:45 AM)
(00) - PM PEAK HOUR (4:00-5:00 PM)
8610 Niles Center Road
Residential Development Site-Generated Traffic Volumes Kenig,Lindgren,O'Hara,Aboona,Inc.
Skokie, Illinois
Job No: 22-406 Figure: 8
N
1(
16) 0 (
0) 1(
8)
NOT TO SCALE
855 (
985)
43 (36)
DEMPSTER
58
STREET
816 (978)
96 (80)
NI
LE
31)
(
30 S
C
69)
82
(
RO EN
AD TE
R
ACC FT
WI
ES
KI VE
SKO DRI
ESS
W
LLO
YE
NE
LI
O
(SK
E
KI
FT)
I
4 (
SW
6)
205
(
232
5 ( ) 27 (13)
9)
59 (21)
7 (2)
CONRAD
STREET
12 (13)
45
17 (29) (19)
256
39 (25) (250
)
8 (
5 ( 9)
1)
SITE 250
(260
53 )
(
26)
35 (13)
4 (3)
8 (4)
GREENLEAF
STREET
3 (0)
4 (2) 9 (
262 4)
3 (2)
LEGEND (
250
)
5 (
00 - AM PEAK HOUR (7:45-8:45 AM) 10)
(00) - PM PEAK HOUR (4:00-5:00 PM)
8610 Niles Center Road
Residential Development Year 2029 No-Build Traffic Volumes Kenig,Lindgren,O'Hara,Aboona,Inc.
Skokie, Illinois
Job No: 22-406 Figure: 9
N
1(
16) 0 (
0) 1(
8)
NOT TO SCALE
855 (
985)
44 (37)
DEMPSTER
58
STREET
816 (978)
102 (95)
NI
LE
32) S
31 (
C
79)
( RO EN
101
AD TE
R
ACC FT
WI
ES
KI VE
SKO DRI
ESS
W
LLO
YE
NE
LI
O
(SK
E
KI
FT)
I
7 (
13)
SW 206
(235
5 ( ) 27 (13)
9)
60 (25)
7 (2)
CONRAD
STREET
22 (18)
45
22 (31) (
20)
259
40 (26) (
252
)
8 (
6 ( 9)
SITE 251
4)
(261
53 )
(
26) 35 (13)
5 (7)
8 (4)
GREENLEAF
STREET
6 (2)
9 (4) 10
(
7)
7 (4) 262
LEGEND (
251
)
6 (
00 - AM PEAK HOUR (7:45-8:45 AM) 10)
(00) - PM PEAK HOUR (4:00-5:00 PM)
8610 Niles Center Road
Residential Development Year 2029 Total Traffic Volumes Kenig,Lindgren,O'Hara,Aboona,Inc.
Skokie, Illinois
Job No: 22-406 Figure: 10
5. Traffic Analysis and Recommendations
The following provides an evaluation conducted for the weekday midday and weekday evening peak
hours. The analysis includes conducting capacity analyses to determine how well the roadway system
and access drives are projected to operate and whether any roadway improvements or modifications
are required.
Traffic Analyses
Intersection analyses were performed for the weekday morning and weekday evening for the existing,
Year 2029 no-build, and Year 2029 total projected traffic volumes.
The traffic analyses were performed using the methodologies outlined in the Transportation Research
Board’s Highway Capacity Manual (HCM), 6th Edition and analyzed using Synchro/SimTraffic 11
software. The analysis for the traffic-signal controlled intersections were accomplished using existing
cycle lengths and phasings to determine the average overall vehicle delay and levels of service.
The analyses for the unsignalized intersections determine the average control delay to vehicles at an
intersection. Control delay is the elapsed time from a vehicle joining the queue at a stop sign (includes
the time required to decelerate to a stop) until its departure from the stop sign and resumption of free
flow speed. The methodology analyzes each intersection approach controlled by a stop sign and
considers traffic volumes on all approaches and lane characteristics.
The ability of an intersection to accommodate traffic flow is expressed in terms of level of service,
which is assigned a letter from A to F based on the average control delay experienced by vehicles
passing through the intersection. The Highway Capacity Manual definitions for levels of service and
the corresponding control delay for signalized intersections and unsignalized intersections are
included in the Appendix of this report.
Summaries of the traffic analysis results showing the level of service and overall intersection delay
(measured in seconds) for the existing, no-build, and Year 2029 total projected conditions are
presented in Tables 6 through 9. A discussion of the intersections follows. Summary sheets for the
capacity analyses are included in the Appendix.
8610 Niles Center Road
Skokie, Illinois 20
Table 6
DEMSTER STREET WITH SKOKIE SWIFT ACCESS DRIVE – SIGNALIZED
Eastbound Westbound Northbound Southbound
Peak Hour Overall
T/R L T L R L/T/R
A A E D
Weekday 3.6 3.9 62.3 51.4 A
A – 7.6 D – 44.0
Existing Morning
A – 3.8 E – 59.4
9.0
Conditions
A A E D
Weekday 3.4 3.7 61.9 53.7 A
A – 6.8 D – 48.2
Evening 8.3
A – 3.7 E – 59.3
A A E D
Year 2029 No-
Weekday 3.6 3.9 62.3 51.4 A
A – 7.6 D – 44.0
Morning 9.0
A – 3.9 E – 59.4
A A E D
Build Conditions
Weekday 3.4 3.8 61.9 53.7 A
A – 6.9 D – 48.2
Evening 8.3
A – 3.8 E – 59.3
A A E D
Weekday 4.2 4.8 62.6 48.8 B
Year 2029 A – 8.9 D – 42.0
Morning 10.4
A – 4.7 E – 59.4
Projected
A A E D
Conditions Weekday 3.7 4.1 62.8 52.2 A
A – 7.4 D – 47.0
Evening 8.9
A – 4.0 E – 59.7
Letter denotes Level of Service L – Left Turn R – Right Turn
Delay is measured in seconds. T – Through
8610 Niles Center Road
Skokie, Illinois 21
Table 7
CAPACITY ANALYSIS RESULTS – EXISTING CONDITIONS – UNSIGNALIZED
Weekday Morning Weekday Evening
Intersection Peak Hour Peak Hour
LOS Delay LOS Delay
Niles Center Road with Conrad Street1
• Eastbound Approach B 13.0 B 14.0
• Westbound Approach C 15.2 B 13.2
• Northbound Left Turn A 7.7 A 7.8
• Southbound Left Turn A 7.8 A 7.8
Niles Center Road with Greenleaf Street1
• Eastbound Approach C 15.4 B 12.6
• Westbound Approach B 12.4 B 12.0
• Northbound Left Turn A 7.9 A 8.2
• Southbound Left Turn A 8.0 A 7.9
LOS = Level of Service 1 – Two-way stop control
Delay is measured in seconds.
Table 8
CAPACITY ANALYSIS RESULTS – YEAR 2029 NO-BUILD CONDITIONS – UNSIGNALIZED
Weekday Morning Weekday Evening
Intersection Peak Hour Peak Hour
LOS Delay LOS Delay
Niles Center Road with Conrad Street1
• Eastbound Approach B 13.0 B 14.2
• Westbound Approach C 15.4 B 13.4
• Northbound Left Turn A 7.7 A 7.8
• Southbound Left Turn A 7.8 A 7.8
Niles Center Road with Greenleaf Street1
• Eastbound Approach C 15.6 B 12.7
• Westbound Approach B 12.5 B 12.1
• Northbound Left Turn A 7.9 A 8.2
• Southbound Left Turn A 8.0 A 7.9
LOS = Level of Service 1 – Two-way stop control
Delay is measured in seconds.
8610 Niles Center Road
Skokie, Illinois 22
Table 9
CAPACITY ANALYSIS RESULTS – YEAR 2029 TOTAL CONDITIONS – UNSIGNALIZED
Weekday Morning Weekday Evening
Intersection Peak Hour Peak Hour
LOS Delay LOS Delay
Niles Center Road with Conrad Street1
• Eastbound Approach B 14.5 B 14.9
• Westbound Approach C 15.6 B 13.8
• Northbound Left Turn A 7.8 A 7.8
• Southbound Left Turn A 7.8 A 7.9
Niles Center Road with Greenleaf Street1
• Eastbound Approach C 16.0 B 13.7
• Westbound Approach B 12.8 B 12.9
• Northbound Left Turn A 7.9 A 8.3
• Southbound Left Turn A 8.0 A 7.9
LOS = Level of Service 1 – Two-way stop control
Delay is measured in seconds.
8610 Niles Center Road
Skokie, Illinois 23
Discussion and Recommendations
The following summarizes how the intersections are projected to operate and identifies any
roadway and traffic control improvements necessary to accommodate the development-generated
traffic.
Dempster Street with Skokie Swift Access Drive
The results of the capacity analysis indicate that currently the intersection operates overall at Level
of Service (LOS) A during the weekday morning and weekday evening peak hours. The eastbound
and westbound approaches currently operate at LOS A during the peak hours. The northbound and
southbound approaches currently operate at LOS E or better during the peak hours. This is common
and expected when a minor approach intersects with a major approach as the major approach,
especially along an SRA route, is allocated the majority of the green time during a signal cycle.
Under Year 2029 no-build conditions, the overall intersection and approaches are projected to
continue operating at the current levels of service with increases in delay of less than one second
over existing conditions. Under Year 2029 total projected conditions, the intersection is projected
to operate at LOS B during the weekday morning peak hour and LOS A during the weekday
evening peak hour with increases in delay of approximately one second or less over no-build
conditions. The eastbound and westbound approaches are projected to operate at LOS A during
the peak hours. The northbound and southbound approaches are projected to operate at LOS E or
better during the peak hours. As such, the intersection has sufficient capacity to accommodate the
traffic projected to be generated by the proposed residential development and no roadway or traffic
signal improvements are needed at the intersection in conjunction with the proposed development.
Niles Center Road with Conrad Street
The results of the capacity analysis indicates that the eastbound and westbound approaches
currently operate at LOS C or better during the weekday morning and weekday evening peak
hours. The northbound and southbound left turns currently operate at LOS A during the peak hours.
Under Year 2029 no-build and total projected conditions, the eastbound and westbound approaches
are projected to continue operating at LOS C or better during the peak hours with increases in
delay of approximately two seconds or less over existing conditions. The northbound and
southbound left turns are projected to continue to operate at LOS A during the peak hours. As
such, no roadway or traffic control improvements are needed in conjunction with the proposed
development.
Niles Center Road with Greenleaf Street
The results of the capacity analysis indicates that the eastbound and westbound approaches
currently operate at LOS C or better during the weekday morning and evening peak hours. The
northbound and southbound left turns currently operate at LOS A during the peak hours. Under
Year 2029 no-build and total projected conditions, the eastbound and westbound approaches are
projected to continue operating at LOS C or better during the peak hours with increases in delay
of approximately one second or less over existing conditions. The northbound and southbound left
turns are projected to continue to operate at LOS A during the peak hours. As such, no roadway
or traffic control improvements are needed in conjunction with the proposed development.
8610 Niles Center Road
Skokie, Illinois 24
Parking Evaluation
As indicated earlier, the proposed development with 192 units will provide 131 parking spaces,
which translates into a ratio of 0.68 spaces per unit. While this ratio is lower than the Village of
Skokie requirements and the ITE Parking Generation Manual (1.07 spaces per unit for transit
served locations), the proposed parking supply should be adequate for the following reasons:
• The site is located in close proximity to the Skokie Swift station, qualifying it as a Transit-
Oriented Development (TOD)
• As discussed earlier and based on Census data, approximately 15 percent of residents will
be expected to utilize public transportation.
• Approximately 75 percent of the proposed units will be studios and one-bedrooms, thus
having a lower parking requirement.
• Should additional parking be required, the adjacent Skokie Swift commuter parking lot can
be utilized by residents and/or guests. This is especially true on weekday evenings/nights
and weekends, when the commuter parking demand is minimal.
8610 Niles Center Road
Skokie, Illinois 25
6. Conclusion
Based on the proceeding analyses and recommendations, the following conclusions have been
made:
• The site is well-located with respect to the local and regional roadway system.
• The site is located in close proximity to the Skokie Swift station, which qualifies it as a
Transit-Oriented Development (TOD).
• The traffic that will be generated by the proposed development will not be significant and
can be accommodated by the existing roadway system.
• When compared to the traffic generated by Arie Crown Early Childhood Campus, the
proposed development will generate less traffic during the weekday morning and evening
peak hours and, as such, the proposed development will have a lower traffic impact on area
roadways.
• The proposed access drives will be adequate in accommodating traffic entering and exiting
the site.
• The proposed parking supply in combination with available parking in the Skokie Swift
station parking lot will be adequate in meeting the parking needs of the proposed
development.
8610 Niles Center Road
Skokie, Illinois 26
Appendix
Traffic Count Summary Sheets
Site Plan
ITE Trip Generation Sheets
CMAP 2050 Projections Letter
Level of Service Criteria
Capacity Analysis Summary Sheets
Traffic Count Summary Sheets
Kenig Lindgren O'Hara Aboona, Inc. Count Name: Dempster St with Skokie Swift
9575 W. Higgins Rd., Suite 400 Access Dr
Site Code:
Rosemont, Illinois, United States 60018 Start Date: 01/10/2023
(847)518-9990 kpachowicz@kloainc.com Page No: 1
Turning Movement Data
Dempster St Dempster St Skokie Swift Access Dr Access Dr
Eastbound Westbound Northbound Southbound
Start Time App. App. App. App.
U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds Int. Total
Total Total Total Total
7:00 AM 0 0 176 24 0 200 0 11 204 0 1 215 0 11 0 7 2 18 0 0 0 0 0 0 433
7:15 AM 0 0 175 22 0 197 0 18 233 0 0 251 0 12 0 10 1 22 0 0 0 0 0 0 470
7:30 AM 0 0 197 26 0 223 0 10 230 0 0 240 0 22 0 7 1 29 0 0 0 0 0 0 492
7:45 AM 0 0 211 33 0 244 0 12 192 0 0 204 0 20 0 7 0 27 0 1 0 0 0 1 476
Hourly Total 0 0 759 105 0 864 0 51 859 0 1 910 0 65 0 31 4 96 0 1 0 0 0 1 1871
8:00 AM 0 0 202 16 0 218 0 9 222 0 1 231 0 23 0 8 2 31 0 0 0 0 0 0 480
8:15 AM 0 0 201 25 0 226 1 11 207 0 0 219 0 27 0 6 1 33 0 0 0 0 0 0 478
8:30 AM 1 0 185 22 0 208 0 10 217 0 0 227 0 12 0 9 0 21 0 0 0 1 0 1 457
8:45 AM 0 0 209 17 0 226 0 13 155 0 0 168 0 11 0 9 0 20 0 0 0 0 0 0 414
Hourly Total 1 0 797 80 0 878 1 43 801 0 1 845 0 73 0 32 3 105 0 0 0 1 0 1 1829
*** BREAK *** - - - - - - - - - - - - - - - - - - - - - - - - -
4:00 PM 0 0 242 12 0 254 0 9 234 0 0 243 0 20 2 7 1 29 0 1 0 3 1 4 530
4:15 PM 0 0 241 22 0 263 0 8 228 0 1 236 0 22 0 8 1 30 0 4 0 3 3 7 536
4:30 PM 0 0 217 27 0 244 0 10 264 0 3 274 0 19 0 8 1 27 0 0 0 7 2 7 552
4:45 PM 1 0 258 19 0 278 0 9 240 0 0 249 0 6 0 8 0 14 0 3 0 3 1 6 547
Hourly Total 1 0 958 80 0 1039 0 36 966 0 4 1002 0 67 2 31 3 100 0 8 0 16 7 24 2165
5:00 PM 0 0 222 12 0 234 0 12 228 0 0 240 0 23 0 11 2 34 0 0 0 0 1 0 508
5:15 PM 0 0 264 25 0 289 0 8 233 0 1 241 0 12 0 9 4 21 0 1 0 3 1 4 555
5:30 PM 0 0 222 12 0 234 0 7 195 1 1 203 0 19 0 7 0 26 0 3 0 0 2 3 466
5:45 PM 0 0 230 18 0 248 0 7 167 0 1 174 0 9 0 9 1 18 0 1 0 2 0 3 443
Hourly Total 0 0 938 67 0 1005 0 34 823 1 3 858 0 63 0 36 7 99 0 5 0 5 4 10 1972
Grand Total 2 0 3452 332 0 3786 1 164 3449 1 9 3615 0 268 2 130 17 400 0 14 0 22 11 36 7837
Approach % 0.1 0.0 91.2 8.8 - - 0.0 4.5 95.4 0.0 - - 0.0 67.0 0.5 32.5 - - 0.0 38.9 0.0 61.1 - - -
Total % 0.0 0.0 44.0 4.2 - 48.3 0.0 2.1 44.0 0.0 - 46.1 0.0 3.4 0.0 1.7 - 5.1 0.0 0.2 0.0 0.3 - 0.5 -
Lights 2 0 3356 307 - 3665 1 109 3380 1 - 3491 0 247 2 71 - 320 0 14 0 22 - 36 7512
% Lights 100.0 - 97.2 92.5 - 96.8 100.0 66.5 98.0 100.0 - 96.6 - 92.2 100.0 54.6 - 80.0 - 100.0 - 100.0 - 100.0 95.9
Buses 0 0 20 21 - 41 0 52 11 0 - 63 0 21 0 55 - 76 0 0 0 0 - 0 180
% Buses 0.0 - 0.6 6.3 - 1.1 0.0 31.7 0.3 0.0 - 1.7 - 7.8 0.0 42.3 - 19.0 - 0.0 - 0.0 - 0.0 2.3
Single-Unit Trucks 0 0 52 3 - 55 0 3 37 0 - 40 0 0 0 3 - 3 0 0 0 0 - 0 98
% Single-Unit 0.0 - 1.5 0.9 - 1.5 0.0 1.8 1.1 0.0 - 1.1 - 0.0 0.0 2.3 - 0.8 - 0.0 - 0.0 - 0.0 1.3
Trucks
Articulated Trucks 0 0 24 0 - 24 0 0 21 0 - 21 0 0 0 1 - 1 0 0 0 0 - 0 46
% Articulated 0.0 - 0.7 0.0 - 0.6 0.0 0.0 0.6 0.0 - 0.6 - 0.0 0.0 0.8 - 0.3 - 0.0 - 0.0 - 0.0 0.6
Trucks
Bicycles on Road 0 0 0 1 - 1 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 1
% Bicycles on 0.0 - 0.0 0.3 - 0.0 0.0 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 - 0.0 - 0.0 0.0
Road
Pedestrians - - - - 0 - - - - - 9 - - - - - 17 - - - - - 11 - -
% Pedestrians - - - - - - - - - - 100.0 - - - - - 100.0 - - - - - 100.0 - -
Kenig Lindgren O'Hara Aboona, Inc. Count Name: Dempster St with Skokie Swift
9575 W. Higgins Rd., Suite 400 Access Dr
Site Code:
Rosemont, Illinois, United States 60018 Start Date: 01/10/2023
(847)518-9990 kpachowicz@kloainc.com Page No: 3
Turning Movement Peak Hour Data (7:45 AM)
Dempster St Dempster St Skokie Swift Access Dr Access Dr
Eastbound Westbound Northbound Southbound
Start Time App. App. App. App.
U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds Int. Total
Total Total Total Total
7:45 AM 0 0 211 33 0 244 0 12 192 0 0 204 0 20 0 7 0 27 0 1 0 0 0 1 476
8:00 AM 0 0 202 16 0 218 0 9 222 0 1 231 0 23 0 8 2 31 0 0 0 0 0 0 480
8:15 AM 0 0 201 25 0 226 1 11 207 0 0 219 0 27 0 6 1 33 0 0 0 0 0 0 478
8:30 AM 1 0 185 22 0 208 0 10 217 0 0 227 0 12 0 9 0 21 0 0 0 1 0 1 457
Total 1 0 799 96 0 896 1 42 838 0 1 881 0 82 0 30 3 112 0 1 0 1 0 2 1891
Approach % 0.1 0.0 89.2 10.7 - - 0.1 4.8 95.1 0.0 - - 0.0 73.2 0.0 26.8 - - 0.0 50.0 0.0 50.0 - - -
Total % 0.1 0.0 42.3 5.1 - 47.4 0.1 2.2 44.3 0.0 - 46.6 0.0 4.3 0.0 1.6 - 5.9 0.0 0.1 0.0 0.1 - 0.1 -
PHF 0.250 0.000 0.947 0.727 - 0.918 0.250 0.875 0.944 0.000 - 0.953 0.000 0.759 0.000 0.833 - 0.848 0.000 0.250 0.000 0.250 - 0.500 0.985
Lights 1 0 762 91 - 854 1 29 818 0 - 848 0 76 0 16 - 92 0 1 0 1 - 2 1796
% Lights 100.0 - 95.4 94.8 - 95.3 100.0 69.0 97.6 - - 96.3 - 92.7 - 53.3 - 82.1 - 100.0 - 100.0 - 100.0 95.0
Buses 0 0 6 3 - 9 0 13 2 0 - 15 0 6 0 11 - 17 0 0 0 0 - 0 41
% Buses 0.0 - 0.8 3.1 - 1.0 0.0 31.0 0.2 - - 1.7 - 7.3 - 36.7 - 15.2 - 0.0 - 0.0 - 0.0 2.2
Single-Unit Trucks 0 0 23 2 - 25 0 0 10 0 - 10 0 0 0 2 - 2 0 0 0 0 - 0 37
% Single-Unit 0.0 - 2.9 2.1 - 2.8 0.0 0.0 1.2 - - 1.1 - 0.0 - 6.7 - 1.8 - 0.0 - 0.0 - 0.0 2.0
Trucks
Articulated Trucks 0 0 8 0 - 8 0 0 8 0 - 8 0 0 0 1 - 1 0 0 0 0 - 0 17
% Articulated 0.0 - 1.0 0.0 - 0.9 0.0 0.0 1.0 - - 0.9 - 0.0 - 3.3 - 0.9 - 0.0 - 0.0 - 0.0 0.9
Trucks
Bicycles on Road 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0
% Bicycles on 0.0 - 0.0 0.0 - 0.0 0.0 0.0 0.0 - - 0.0 - 0.0 - 0.0 - 0.0 - 0.0 - 0.0 - 0.0 0.0
Road
Pedestrians - - - - 0 - - - - - 1 - - - - - 3 - - - - - 0 - -
% Pedestrians - - - - - - - - - - 100.0 - - - - - 100.0 - - - - - - - -
Kenig Lindgren O'Hara Aboona, Inc. Count Name: Dempster St with Skokie Swift
9575 W. Higgins Rd., Suite 400 Access Dr
Site Code:
Rosemont, Illinois, United States 60018 Start Date: 01/10/2023
(847)518-9990 kpachowicz@kloainc.com Page No: 4
Turning Movement Peak Hour Data (4:00 PM)
Dempster St Dempster St Skokie Swift Access Dr Access Dr
Eastbound Westbound Northbound Southbound
Start Time App. App. App. App.
U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds Int. Total
Total Total Total Total
4:00 PM 0 0 242 12 0 254 0 9 234 0 0 243 0 20 2 7 1 29 0 1 0 3 1 4 530
4:15 PM 0 0 241 22 0 263 0 8 228 0 1 236 0 22 0 8 1 30 0 4 0 3 3 7 536
4:30 PM 0 0 217 27 0 244 0 10 264 0 3 274 0 19 0 8 1 27 0 0 0 7 2 7 552
4:45 PM 1 0 258 19 0 278 0 9 240 0 0 249 0 6 0 8 0 14 0 3 0 3 1 6 547
Total 1 0 958 80 0 1039 0 36 966 0 4 1002 0 67 2 31 3 100 0 8 0 16 7 24 2165
Approach % 0.1 0.0 92.2 7.7 - - 0.0 3.6 96.4 0.0 - - 0.0 67.0 2.0 31.0 - - 0.0 33.3 0.0 66.7 - - -
Total % 0.0 0.0 44.2 3.7 - 48.0 0.0 1.7 44.6 0.0 - 46.3 0.0 3.1 0.1 1.4 - 4.6 0.0 0.4 0.0 0.7 - 1.1 -
PHF 0.250 0.000 0.928 0.741 - 0.934 0.000 0.900 0.915 0.000 - 0.914 0.000 0.761 0.250 0.969 - 0.833 0.000 0.500 0.000 0.571 - 0.857 0.981
Lights 1 0 947 73 - 1021 0 24 948 0 - 972 0 62 2 17 - 81 0 8 0 16 - 24 2098
% Lights 100.0 - 98.9 91.3 - 98.3 - 66.7 98.1 - - 97.0 - 92.5 100.0 54.8 - 81.0 - 100.0 - 100.0 - 100.0 96.9
Buses 0 0 2 7 - 9 0 12 2 0 - 14 0 5 0 14 - 19 0 0 0 0 - 0 42
% Buses 0.0 - 0.2 8.8 - 0.9 - 33.3 0.2 - - 1.4 - 7.5 0.0 45.2 - 19.0 - 0.0 - 0.0 - 0.0 1.9
Single-Unit Trucks 0 0 5 0 - 5 0 0 12 0 - 12 0 0 0 0 - 0 0 0 0 0 - 0 17
% Single-Unit 0.0 - 0.5 0.0 - 0.5 - 0.0 1.2 - - 1.2 - 0.0 0.0 0.0 - 0.0 - 0.0 - 0.0 - 0.0 0.8
Trucks
Articulated Trucks 0 0 4 0 - 4 0 0 4 0 - 4 0 0 0 0 - 0 0 0 0 0 - 0 8
% Articulated 0.0 - 0.4 0.0 - 0.4 - 0.0 0.4 - - 0.4 - 0.0 0.0 0.0 - 0.0 - 0.0 - 0.0 - 0.0 0.4
Trucks
Bicycles on Road 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0
% Bicycles on 0.0 - 0.0 0.0 - 0.0 - 0.0 0.0 - - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 - 0.0 - 0.0 0.0
Road
Pedestrians - - - - 0 - - - - - 4 - - - - - 3 - - - - - 7 - -
% Pedestrians - - - - - - - - - - 100.0 - - - - - 100.0 - - - - - 100.0 - -
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400 Count Name: Conrad St with Niles Center Rd.
Site Code:
Rosemont, Illinois, United States 60018 Start Date: 01/10/2023
(847)518-9990 kpachowicz@kloainc.com Page No: 1
Turning Movement Data
Conrad St Conrad St Niles Center Rd Niles Center Rd
Eastbound Westbound Northbound Southbound
Start Time App. App. App. App.
U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds Int. Total
Total Total Total Total
7:00 AM 0 0 1 2 0 3 0 2 0 2 0 4 0 0 32 0 1 32 0 1 21 0 0 22 61
7:15 AM 0 2 7 2 0 11 0 0 2 3 0 5 0 2 25 2 0 29 0 1 20 0 0 21 66
7:30 AM 0 5 6 6 1 17 0 3 7 5 2 15 0 1 43 0 5 44 0 3 38 1 0 42 118
7:45 AM 0 0 3 12 1 15 0 3 2 2 6 7 0 6 62 1 2 69 0 4 55 1 7 60 151
Hourly Total 0 7 17 22 2 46 0 8 11 12 8 31 0 9 162 3 8 174 0 9 134 2 7 145 396
8:00 AM 0 2 4 4 0 10 0 0 20 6 1 26 0 12 62 4 2 78 0 0 60 0 0 60 174
8:15 AM 0 4 3 9 0 16 0 3 24 14 2 41 0 18 57 0 3 75 0 1 43 1 4 45 177
8:30 AM 0 6 7 14 0 27 1 0 13 5 0 19 0 9 70 3 0 82 0 0 43 2 0 45 173
8:45 AM 0 4 4 9 0 17 0 1 6 2 1 9 0 4 51 3 2 58 0 0 32 0 1 32 116
Hourly Total 0 16 18 36 0 70 1 4 63 27 4 95 0 43 240 10 7 293 0 1 178 3 5 182 640
*** BREAK *** - - - - - - - - - - - - - - - - - - - - - - - - -
4:00 PM 0 5 13 6 0 24 1 1 11 2 2 15 0 7 63 4 1 74 0 4 54 1 1 59 172
4:15 PM 0 0 3 8 0 11 0 0 4 4 0 8 0 6 50 2 1 58 1 0 55 0 0 56 133
4:30 PM 0 3 9 7 1 19 0 0 4 6 1 10 0 4 62 2 1 68 0 2 58 5 3 65 162
4:45 PM 0 5 4 4 0 13 0 0 2 1 2 3 0 2 70 1 3 73 0 2 60 0 0 62 151
Hourly Total 0 13 29 25 1 67 1 1 21 13 5 36 0 19 245 9 6 273 1 8 227 6 4 242 618
5:00 PM 0 3 4 6 0 13 0 2 1 5 1 8 0 3 56 1 1 60 0 2 60 2 0 64 145
5:15 PM 0 4 6 5 0 15 0 1 1 2 0 4 0 1 59 1 0 61 0 6 54 2 0 62 142
5:30 PM 0 5 5 7 0 17 0 2 2 4 1 8 0 4 74 2 0 80 0 3 58 0 1 61 166
5:45 PM 0 6 3 2 3 11 0 0 2 4 1 6 0 5 77 0 5 82 0 1 53 0 0 54 153
Hourly Total 0 18 18 20 3 56 0 5 6 15 3 26 0 13 266 4 6 283 0 12 225 4 1 241 606
Grand Total 0 54 82 103 6 239 2 18 101 67 20 188 0 84 913 26 27 1023 1 30 764 15 17 810 2260
Approach % 0.0 22.6 34.3 43.1 - - 1.1 9.6 53.7 35.6 - - 0.0 8.2 89.2 2.5 - - 0.1 3.7 94.3 1.9 - - -
Total % 0.0 2.4 3.6 4.6 - 10.6 0.1 0.8 4.5 3.0 - 8.3 0.0 3.7 40.4 1.2 - 45.3 0.0 1.3 33.8 0.7 - 35.8 -
Lights 0 53 80 100 - 233 2 17 101 66 - 186 0 84 876 23 - 983 1 30 742 15 - 788 2190
% Lights - 98.1 97.6 97.1 - 97.5 100.0 94.4 100.0 98.5 - 98.9 - 100.0 95.9 88.5 - 96.1 100.0 100.0 97.1 100.0 - 97.3 96.9
Buses 0 1 1 1 - 3 0 1 0 0 - 1 0 0 26 3 - 29 0 0 15 0 - 15 48
% Buses - 1.9 1.2 1.0 - 1.3 0.0 5.6 0.0 0.0 - 0.5 - 0.0 2.8 11.5 - 2.8 0.0 0.0 2.0 0.0 - 1.9 2.1
Single-Unit Trucks 0 0 0 2 - 2 0 0 0 1 - 1 0 0 11 0 - 11 0 0 2 0 - 2 16
% Single-Unit - 0.0 0.0 1.9 - 0.8 0.0 0.0 0.0 1.5 - 0.5 - 0.0 1.2 0.0 - 1.1 0.0 0.0 0.3 0.0 - 0.2 0.7
Trucks
Articulated Trucks 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0 0 5 0 - 5 5
% Articulated - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.7 0.0 - 0.6 0.2
Trucks
Bicycles on Road 0 0 1 0 - 1 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 1
% Bicycles on - 0.0 1.2 0.0 - 0.4 0.0 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 - 0.0 0.0
Road
Pedestrians - - - - 6 - - - - - 20 - - - - - 27 - - - - - 17 - -
% Pedestrians - - - - 100.0 - - - - - 100.0 - - - - - 100.0 - - - - - 100.0 - -
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400 Count Name: Conrad St with Niles Center Rd.
Site Code:
Rosemont, Illinois, United States 60018 Start Date: 01/10/2023
(847)518-9990 kpachowicz@kloainc.com Page No: 3
Turning Movement Peak Hour Data (7:45 AM)
Conrad St Conrad St Niles Center Rd Niles Center Rd
Eastbound Westbound Northbound Southbound
Start Time App. App. App. App.
U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds Int. Total
Total Total Total Total
7:45 AM 0 0 3 12 1 15 0 3 2 2 6 7 0 6 62 1 2 69 0 4 55 1 7 60 151
8:00 AM 0 2 4 4 0 10 0 0 20 6 1 26 0 12 62 4 2 78 0 0 60 0 0 60 174
8:15 AM 0 4 3 9 0 16 0 3 24 14 2 41 0 18 57 0 3 75 0 1 43 1 4 45 177
8:30 AM 0 6 7 14 0 27 1 0 13 5 0 19 0 9 70 3 0 82 0 0 43 2 0 45 173
Total 0 12 17 39 1 68 1 6 59 27 9 93 0 45 251 8 7 304 0 5 201 4 11 210 675
Approach % 0.0 17.6 25.0 57.4 - - 1.1 6.5 63.4 29.0 - - 0.0 14.8 82.6 2.6 - - 0.0 2.4 95.7 1.9 - - -
Total % 0.0 1.8 2.5 5.8 - 10.1 0.1 0.9 8.7 4.0 - 13.8 0.0 6.7 37.2 1.2 - 45.0 0.0 0.7 29.8 0.6 - 31.1 -
PHF 0.000 0.500 0.607 0.696 - 0.630 0.250 0.500 0.615 0.482 - 0.567 0.000 0.625 0.896 0.500 - 0.927 0.000 0.313 0.838 0.500 - 0.875 0.953
Lights 0 12 17 37 - 66 1 5 59 27 - 92 0 45 236 7 - 288 0 5 193 4 - 202 648
% Lights - 100.0 100.0 94.9 - 97.1 100.0 83.3 100.0 100.0 - 98.9 - 100.0 94.0 87.5 - 94.7 - 100.0 96.0 100.0 - 96.2 96.0
Buses 0 0 0 1 - 1 0 1 0 0 - 1 0 0 9 1 - 10 0 0 4 0 - 4 16
% Buses - 0.0 0.0 2.6 - 1.5 0.0 16.7 0.0 0.0 - 1.1 - 0.0 3.6 12.5 - 3.3 - 0.0 2.0 0.0 - 1.9 2.4
Single-Unit Trucks 0 0 0 1 - 1 0 0 0 0 - 0 0 0 6 0 - 6 0 0 1 0 - 1 8
% Single-Unit - 0.0 0.0 2.6 - 1.5 0.0 0.0 0.0 0.0 - 0.0 - 0.0 2.4 0.0 - 2.0 - 0.0 0.5 0.0 - 0.5 1.2
Trucks
Articulated Trucks 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0 0 3 0 - 3 3
% Articulated - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 1.5 0.0 - 1.4 0.4
Trucks
Bicycles on Road 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0
% Bicycles on - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 0.0
Road
Pedestrians - - - - 1 - - - - - 9 - - - - - 7 - - - - - 11 - -
% Pedestrians - - - - 100.0 - - - - - 100.0 - - - - - 100.0 - - - - - 100.0 - -
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400 Count Name: Conrad St with Niles Center Rd.
Site Code:
Rosemont, Illinois, United States 60018 Start Date: 01/10/2023
(847)518-9990 kpachowicz@kloainc.com Page No: 4
Turning Movement Peak Hour Data (4:00 PM)
Conrad St Conrad St Niles Center Rd Niles Center Rd
Eastbound Westbound Northbound Southbound
Start Time App. App. App. App.
U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds Int. Total
Total Total Total Total
4:00 PM 0 5 13 6 0 24 1 1 11 2 2 15 0 7 63 4 1 74 0 4 54 1 1 59 172
4:15 PM 0 0 3 8 0 11 0 0 4 4 0 8 0 6 50 2 1 58 1 0 55 0 0 56 133
4:30 PM 0 3 9 7 1 19 0 0 4 6 1 10 0 4 62 2 1 68 0 2 58 5 3 65 162
4:45 PM 0 5 4 4 0 13 0 0 2 1 2 3 0 2 70 1 3 73 0 2 60 0 0 62 151
Total 0 13 29 25 1 67 1 1 21 13 5 36 0 19 245 9 6 273 1 8 227 6 4 242 618
Approach % 0.0 19.4 43.3 37.3 - - 2.8 2.8 58.3 36.1 - - 0.0 7.0 89.7 3.3 - - 0.4 3.3 93.8 2.5 - - -
Total % 0.0 2.1 4.7 4.0 - 10.8 0.2 0.2 3.4 2.1 - 5.8 0.0 3.1 39.6 1.5 - 44.2 0.2 1.3 36.7 1.0 - 39.2 -
PHF 0.000 0.650 0.558 0.781 - 0.698 0.250 0.250 0.477 0.542 - 0.600 0.000 0.679 0.875 0.563 - 0.922 0.250 0.500 0.946 0.300 - 0.931 0.898
Lights 0 12 27 25 - 64 1 1 21 13 - 36 0 19 236 8 - 263 1 8 222 6 - 237 600
% Lights - 92.3 93.1 100.0 - 95.5 100.0 100.0 100.0 100.0 - 100.0 - 100.0 96.3 88.9 - 96.3 100.0 100.0 97.8 100.0 - 97.9 97.1
Buses 0 1 1 0 - 2 0 0 0 0 - 0 0 0 7 1 - 8 0 0 3 0 - 3 13
% Buses - 7.7 3.4 0.0 - 3.0 0.0 0.0 0.0 0.0 - 0.0 - 0.0 2.9 11.1 - 2.9 0.0 0.0 1.3 0.0 - 1.2 2.1
Single-Unit Trucks 0 0 0 0 - 0 0 0 0 0 - 0 0 0 2 0 - 2 0 0 1 0 - 1 3
% Single-Unit - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 - 0.0 - 0.0 0.8 0.0 - 0.7 0.0 0.0 0.4 0.0 - 0.4 0.5
Trucks
Articulated Trucks 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0 0 1 0 - 1 1
% Articulated - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.4 0.0 - 0.4 0.2
Trucks
Bicycles on Road 0 0 1 0 - 1 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 1
% Bicycles on - 0.0 3.4 0.0 - 1.5 0.0 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 - 0.0 0.2
Road
Pedestrians - - - - 1 - - - - - 5 - - - - - 6 - - - - - 4 - -
% Pedestrians - - - - 100.0 - - - - - 100.0 - - - - - 100.0 - - - - - 100.0 - -
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400 Count Name: Niles Center Rd with Greenleaf St
Site Code:
Rosemont, Illinois, United States 60018 Start Date: 01/10/2023
(847)518-9990 kpachowicz@kloainc.com Page No: 1
Turning Movement Data
Greenleaf St Greenleaf St Niles Center Rd Niles Center Rd
Eastbound Westbound Northbound Southbound
Start Time App. App. App. App.
U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds Int. Total
Total Total Total Total
7:00 AM 0 0 1 0 1 1 0 2 0 1 1 3 0 0 31 0 0 31 0 0 23 0 0 23 58
7:15 AM 0 0 0 0 3 0 0 0 0 3 2 3 0 0 29 0 0 29 0 2 24 0 0 26 58
7:30 AM 0 0 0 0 0 0 0 1 0 1 1 2 0 0 49 3 0 52 0 2 49 1 0 52 106
7:45 AM 0 1 0 0 2 1 0 2 1 3 0 6 0 2 66 3 0 71 0 4 72 2 0 78 156
Hourly Total 0 1 1 0 6 2 0 5 1 8 4 14 0 2 175 6 0 183 0 8 168 3 0 179 378
8:00 AM 0 1 0 0 0 1 0 3 0 12 0 15 0 1 67 1 0 69 0 0 52 1 0 53 138
8:15 AM 0 0 4 1 4 5 0 1 3 12 0 16 0 4 60 1 0 65 0 31 69 1 1 101 187
8:30 AM 0 1 0 2 3 3 0 2 0 8 0 10 0 2 64 0 0 66 1 17 52 1 0 71 150
8:45 AM 0 0 1 1 1 2 0 2 0 2 0 4 0 0 50 2 0 52 1 2 32 1 0 36 94
Hourly Total 0 2 5 4 8 11 0 8 3 34 0 45 0 7 241 4 0 252 2 50 205 4 1 261 569
*** BREAK *** - - - - - - - - - - - - - - - - - - - - - - - - -
4:00 PM 0 0 1 1 3 2 0 3 0 4 1 7 0 1 64 4 0 69 0 18 72 1 0 91 169
4:15 PM 0 0 1 1 1 2 0 0 1 3 0 4 0 0 48 2 0 50 0 2 62 0 1 64 120
4:30 PM 0 0 0 0 1 0 0 1 1 4 0 6 0 1 70 2 0 73 0 4 62 0 0 66 145
4:45 PM 0 0 0 0 1 0 0 0 1 2 0 3 0 2 63 2 1 67 0 2 59 0 0 61 131
Hourly Total 0 0 2 2 6 4 0 4 3 13 1 20 0 4 245 10 1 259 0 26 255 1 1 282 565
5:00 PM 0 0 0 1 0 1 0 0 0 1 0 1 0 1 62 4 0 67 0 3 61 0 0 64 133
5:15 PM 0 0 0 1 0 1 0 2 1 2 0 5 0 0 61 1 0 62 0 4 55 0 0 59 127
5:30 PM 0 1 0 0 1 1 0 0 0 6 1 6 0 1 77 1 0 79 0 4 60 0 0 64 150
5:45 PM 0 0 0 0 0 0 0 3 0 1 0 4 0 0 70 3 0 73 0 8 40 1 0 49 126
Hourly Total 0 1 0 2 1 3 0 5 1 10 1 16 0 2 270 9 0 281 0 19 216 1 0 236 536
Grand Total 0 4 8 8 21 20 0 22 8 65 6 95 0 15 931 29 1 975 2 103 844 9 2 958 2048
Approach % 0.0 20.0 40.0 40.0 - - 0.0 23.2 8.4 68.4 - - 0.0 1.5 95.5 3.0 - - 0.2 10.8 88.1 0.9 - - -
Total % 0.0 0.2 0.4 0.4 - 1.0 0.0 1.1 0.4 3.2 - 4.6 0.0 0.7 45.5 1.4 - 47.6 0.1 5.0 41.2 0.4 - 46.8 -
Lights 0 4 8 8 - 20 0 22 8 65 - 95 0 14 893 29 - 936 2 103 817 9 - 931 1982
% Lights - 100.0 100.0 100.0 - 100.0 - 100.0 100.0 100.0 - 100.0 - 93.3 95.9 100.0 - 96.0 100.0 100.0 96.8 100.0 - 97.2 96.8
Buses 0 0 0 0 - 0 0 0 0 0 - 0 0 1 30 0 - 31 0 0 18 0 - 18 49
% Buses - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 6.7 3.2 0.0 - 3.2 0.0 0.0 2.1 0.0 - 1.9 2.4
Single-Unit Trucks 0 0 0 0 - 0 0 0 0 0 - 0 0 0 8 0 - 8 0 0 8 0 - 8 16
% Single-Unit - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 0.9 0.0 - 0.8 0.0 0.0 0.9 0.0 - 0.8 0.8
Trucks
Articulated Trucks 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0 0 1 0 - 1 1
% Articulated - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.1 0.0 - 0.1 0.0
Trucks
Bicycles on Road 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0
% Bicycles on - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 - 0.0 0.0
Road
Pedestrians - - - - 21 - - - - - 6 - - - - - 1 - - - - - 2 - -
% Pedestrians - - - - 100.0 - - - - - 100.0 - - - - - 100.0 - - - - - 100.0 - -
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400 Count Name: Niles Center Rd with Greenleaf St
Site Code:
Rosemont, Illinois, United States 60018 Start Date: 01/10/2023
(847)518-9990 kpachowicz@kloainc.com Page No: 3
Turning Movement Peak Hour Data (7:45 AM)
Greenleaf St Greenleaf St Niles Center Rd Niles Center Rd
Eastbound Westbound Northbound Southbound
Start Time App. App. App. App.
U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds Int. Total
Total Total Total Total
7:45 AM 0 1 0 0 2 1 0 2 1 3 0 6 0 2 66 3 0 71 0 4 72 2 0 78 156
8:00 AM 0 1 0 0 0 1 0 3 0 12 0 15 0 1 67 1 0 69 0 0 52 1 0 53 138
8:15 AM 0 0 4 1 4 5 0 1 3 12 0 16 0 4 60 1 0 65 0 31 69 1 1 101 187
8:30 AM 0 1 0 2 3 3 0 2 0 8 0 10 0 2 64 0 0 66 1 17 52 1 0 71 150
Total 0 3 4 3 9 10 0 8 4 35 0 47 0 9 257 5 0 271 1 52 245 5 1 303 631
Approach % 0.0 30.0 40.0 30.0 - - 0.0 17.0 8.5 74.5 - - 0.0 3.3 94.8 1.8 - - 0.3 17.2 80.9 1.7 - - -
Total % 0.0 0.5 0.6 0.5 - 1.6 0.0 1.3 0.6 5.5 - 7.4 0.0 1.4 40.7 0.8 - 42.9 0.2 8.2 38.8 0.8 - 48.0 -
PHF 0.000 0.750 0.250 0.375 - 0.500 0.000 0.667 0.333 0.729 - 0.734 0.000 0.563 0.959 0.417 - 0.954 0.250 0.419 0.851 0.625 - 0.750 0.844
Lights 0 3 4 3 - 10 0 8 4 35 - 47 0 9 241 5 - 255 1 52 232 5 - 290 602
% Lights - 100.0 100.0 100.0 - 100.0 - 100.0 100.0 100.0 - 100.0 - 100.0 93.8 100.0 - 94.1 100.0 100.0 94.7 100.0 - 95.7 95.4
Buses 0 0 0 0 - 0 0 0 0 0 - 0 0 0 10 0 - 10 0 0 7 0 - 7 17
% Buses - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 3.9 0.0 - 3.7 0.0 0.0 2.9 0.0 - 2.3 2.7
Single-Unit Trucks 0 0 0 0 - 0 0 0 0 0 - 0 0 0 6 0 - 6 0 0 6 0 - 6 12
% Single-Unit - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 2.3 0.0 - 2.2 0.0 0.0 2.4 0.0 - 2.0 1.9
Trucks
Articulated Trucks 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0
% Articulated - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 - 0.0 0.0
Trucks
Bicycles on Road 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0
% Bicycles on - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 - 0.0 0.0
Road
Pedestrians - - - - 9 - - - - - 0 - - - - - 0 - - - - - 1 - -
% Pedestrians - - - - 100.0 - - - - - - - - - - - - - - - - - 100.0 - -
Kenig Lindgren O'Hara Aboona, Inc.
9575 W. Higgins Rd., Suite 400 Count Name: Niles Center Rd with Greenleaf St
Site Code:
Rosemont, Illinois, United States 60018 Start Date: 01/10/2023
(847)518-9990 kpachowicz@kloainc.com Page No: 4
Turning Movement Peak Hour Data (4:00 PM)
Greenleaf St Greenleaf St Niles Center Rd Niles Center Rd
Eastbound Westbound Northbound Southbound
Start Time App. App. App. App.
U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds U-Turn Left Thru Right Peds Int. Total
Total Total Total Total
4:00 PM 0 0 1 1 3 2 0 3 0 4 1 7 0 1 64 4 0 69 0 18 72 1 0 91 169
4:15 PM 0 0 1 1 1 2 0 0 1 3 0 4 0 0 48 2 0 50 0 2 62 0 1 64 120
4:30 PM 0 0 0 0 1 0 0 1 1 4 0 6 0 1 70 2 0 73 0 4 62 0 0 66 145
4:45 PM 0 0 0 0 1 0 0 0 1 2 0 3 0 2 63 2 1 67 0 2 59 0 0 61 131
Total 0 0 2 2 6 4 0 4 3 13 1 20 0 4 245 10 1 259 0 26 255 1 1 282 565
Approach % 0.0 0.0 50.0 50.0 - - 0.0 20.0 15.0 65.0 - - 0.0 1.5 94.6 3.9 - - 0.0 9.2 90.4 0.4 - - -
Total % 0.0 0.0 0.4 0.4 - 0.7 0.0 0.7 0.5 2.3 - 3.5 0.0 0.7 43.4 1.8 - 45.8 0.0 4.6 45.1 0.2 - 49.9 -
PHF 0.000 0.000 0.500 0.500 - 0.500 0.000 0.333 0.750 0.813 - 0.714 0.000 0.500 0.875 0.625 - 0.887 0.000 0.361 0.885 0.250 - 0.775 0.836
Lights 0 0 2 2 - 4 0 4 3 13 - 20 0 3 236 10 - 249 0 26 251 1 - 278 551
% Lights - - 100.0 100.0 - 100.0 - 100.0 100.0 100.0 - 100.0 - 75.0 96.3 100.0 - 96.1 - 100.0 98.4 100.0 - 98.6 97.5
Buses 0 0 0 0 - 0 0 0 0 0 - 0 0 1 8 0 - 9 0 0 3 0 - 3 12
% Buses - - 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 25.0 3.3 0.0 - 3.5 - 0.0 1.2 0.0 - 1.1 2.1
Single-Unit Trucks 0 0 0 0 - 0 0 0 0 0 - 0 0 0 1 0 - 1 0 0 0 0 - 0 1
% Single-Unit - - 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 0.4 0.0 - 0.4 - 0.0 0.0 0.0 - 0.0 0.2
Trucks
Articulated Trucks 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0 0 1 0 - 1 1
% Articulated - - 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 0.4 0.0 - 0.4 0.2
Trucks
Bicycles on Road 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0 0 0 0 - 0 0
% Bicycles on - - 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 - 0.0 0.0 0.0 - 0.0 0.0
Road
Pedestrians - - - - 6 - - - - - 1 - - - - - 1 - - - - - 1 - -
% Pedestrians - - - - 100.0 - - - - - 100.0 - - - - - 100.0 - - - - - 100.0 - -
Site Plan
Material Storage
During Construction
All Elevators are Stretcher Size
NOTE: CONSTRUCTION
WORKER PARKING DURING
CONSTRUCTION TO BE
NEGOTIATED.
Luz and Associates #1 LLC Ground Floor Plan
8610 Niles Center Road 8
Skokie, Illinois | December 28, 2022
Luz and Associates #1 LLC 2nd Floor Plan
8610 Niles Center Road 9
Skokie, Illinois | December 28, 2022
Luz and Associates #1 LLC 3rd - 7th Floor Plans
8610 Niles Center Road 10
Skokie, Illinois | December 28, 2022
BALCONY
76’-7”
65’-7”
54’-7”
43’-7”
32’-7”
21’-7”
FIRE
10’-7”
TRUCK
EAST-WEST ELEVATION DIAGRAM
FIRETRUCK AERIAL APPARTUS
76’-7”
65’-7”
54’-7”
43’-7”
32’-7”
21’-7”
10’-7”
NORTH-SOUTH SECTION DIAGRAM
Luz and Associates #1 LLC Section Diagram
8610 Niles Center Road 12
Skokie, Illinois | December 28, 2022
ITE Trip Generation Sheets
Land Use: 221
Multifamily Housing (Mid-Rise)
Description
Mid-rise multifamily housing includes apartments and condominiums located in a building that
has between four and 10 floors of living space. Access to individual dwelling units is through an
outside building entrance, a lobby, elevator, and a set of hallways.
Multifamily housing (low-rise) (Land Use 220), multifamily housing (high-rise) (Land Use 222), off-
campus student apartment (mid-rise) (Land Use 226), and mid-rise residential with ground-floor
commercial (Land Use 231) are related land uses.
Land Use Subcategory
Data are presented for two subcategories for this land use: (1) not close to rail transit and (2)
close to rail transit. A site is considered close to rail transit if the walking distance between the
residential site entrance and the closest rail transit station entrance is ½ mile or less.
Additional Data
For the six sites for which both the number of residents and the number of occupied dwelling
units were available, there were an average of 2.5 residents per occupied dwelling unit.
For the five sites for which the numbers of both total dwelling units and occupied dwelling units
were available, an average of 96 percent of the total dwelling units were occupied.
The technical appendices provide supporting information on time-of-day distributions for this
land use. The appendices can be accessed through either the ITETripGen web app or the trip
generation resource page on the ITE website (https://www.ite.org/technical-resources/topics/trip-
and-parking-generation/).
It is expected that the number of bedrooms and number of residents are likely correlated to the
trips generated by a residential site. To assist in future analysis, trip generation studies of all
multifamily housing should attempt to obtain information on occupancy rate and on the mix of
residential unit sizes (i.e., number of units by number of bedrooms at the site complex).
The sites were surveyed in the 1990s, the 2000s, the 2010s, and the 2020s in Alberta (CAN),
California, District of Columbia, Florida, Georgia, Illinois, Maryland, Massachusetts, Minnesota,
Montana, New Jersey, New York, Ontario (CAN), Oregon, Utah, and Virginia.
Source Numbers
168, 188, 204, 305, 306, 321, 818, 857, 862, 866, 901, 904, 910, 949, 951, 959, 963, 964, 966, 967,
969, 970, 1004, 1014, 1022, 1023, 1025, 1031, 1032, 1035, 1047, 1056, 1057, 1058, 1071, 1076
General Urban/Suburban and Rural (Land Uses 000–399) 273
Multifamily Housing (Mid-Rise)
Not Close to Rail Transit (221)
Vehicle Trip Ends vs: Dwelling Units
On a: Weekday
Setting/Location: General Urban/Suburban
Number of Studies: 11
Avg. Num. of Dwelling Units: 201
Directional Distribution: 50% entering, 50% exiting
Vehicle Trip Generation per Dwelling Unit
Average Rate Range of Rates Standard Deviation
4.54 3.76 - 5.40 0.51
Data Plot and Equation
2000
T = Trips Ends 1000
0
0 100 200 300 400
X = Number of Dwelling Units
Study Site Fitted Curve Average Rate
Fitted Curve Equation: T = 4.77(X) - 46.46 R²= 0.93
274 Trip Generation Manual 11th Edition • Volume 3
Multifamily Housing (Mid-Rise)
Not Close to Rail Transit (221)
Vehicle Trip Ends vs: Dwelling Units
On a: Weekday,
Peak Hour of Adjacent Street Traffic,
One Hour Between 7 and 9 a.m.
Setting/Location: General Urban/Suburban
Number of Studies: 30
Avg. Num. of Dwelling Units: 173
Directional Distribution: 23% entering, 77% exiting
Vehicle Trip Generation per Dwelling Unit
Average Rate Range of Rates Standard Deviation
0.37 0.15 - 0.53 0.09
Data Plot and Equation
300
200
T = Trips Ends
100
0
0 100 200 300 400 500
X = Number of Dwelling Units
Study Site Fitted Curve Average Rate
Fitted Curve Equation: T = 0.44(X) - 11.61 R²= 0.91
General Urban/Suburban and Rural (Land Uses 000–399) 275
Multifamily Housing (Mid-Rise)
Not Close to Rail Transit (221)
Vehicle Trip Ends vs: Dwelling Units
On a: Weekday,
Peak Hour of Adjacent Street Traffic,
One Hour Between 4 and 6 p.m.
Setting/Location: General Urban/Suburban
Number of Studies: 31
Avg. Num. of Dwelling Units: 169
Directional Distribution: 61% entering, 39% exiting
Vehicle Trip Generation per Dwelling Unit
Average Rate Range of Rates Standard Deviation
0.39 0.19 - 0.57 0.08
Data Plot and Equation
200
T = Trips Ends 100
0
0 100 200 300 400 500
X = Number of Dwelling Units
Study Site Fitted Curve Average Rate
Fitted Curve Equation: T = 0.39(X) + 0.34 R²= 0.91
276 Trip Generation Manual 11th Edition • Volume 3
Land Use: 565
Day Care Center
Description
A day care center is a facility where care for pre-school age children is provided, normally during
daytime hours. A day care facility generally includes classrooms, offices, eating areas, and
playgrounds. A center may also provide after-school care for school-age children.
Additional Data
The technical appendices provide supporting information on time-of-day distributions for this
land use. The appendices can be accessed through either the ITETripGen web app or the trip
generation resource page on the ITE website (https://www.ite.org/technical-resources/topics/trip-
and-parking-generation/).
The sites were surveyed in the 1980s, the 1990s, the 2000s, and the 2010s in California, Florida,
Georgia, Maryland, Minnesota, New Hampshire, New Jersey, New York, North Carolina, Oregon,
Pennsylvania, Tennessee, Texas, Virginia, and Wisconsin.
Source Numbers
169, 208, 216, 253, 335, 336, 337, 355, 418, 423, 536, 550, 562, 583, 633, 734, 866, 869, 877, 878,
954, 959, 981
508 Trip Generation Manual 11th Edition • Volume 4
Day Care Center
(565)
Vehicle Trip Ends vs: Students
On a: Weekday
Setting/Location: General Urban/Suburban
Number of Studies: 14
Avg. Num. of Students: 89
Directional Distribution: 50% entering, 50% exiting
Vehicle Trip Generation per Student
Average Rate Range of Rates Standard Deviation
4.09 2.50 - 7.06 1.21
Data Plot and Equation
1000
800
600
T = Trips Ends
400
200
0
0 100 200 300
X = Number of Students
Study Site Fitted Curve Average Rate
Fitted Curve Equation: T = 3.56(X) + 47.23 R²= 0.72
General Urban/Suburban and Rural (Land Uses 400–799) 509
Day Care Center
(565)
Vehicle Trip Ends vs: Students
On a: Weekday,
Peak Hour of Adjacent Street Traffic,
One Hour Between 7 and 9 a.m.
Setting/Location: General Urban/Suburban
Number of Studies: 75
Avg. Num. of Students: 71
Directional Distribution: 53% entering, 47% exiting
Vehicle Trip Generation per Student
Average Rate Range of Rates Standard Deviation
0.78 0.39 - 1.78 0.25
Data Plot and Equation
200
T = Trips Ends 100
0
0 100 200 300
X = Number of Students
Study Site Fitted Curve Average Rate
Fitted Curve Equation: T = 0.66(X) + 8.42 R²= 0.69
510 Trip Generation Manual 11th Edition • Volume 4
Day Care Center
(565)
Vehicle Trip Ends vs: Students
On a: Weekday,
Peak Hour of Adjacent Street Traffic,
One Hour Between 4 and 6 p.m.
Setting/Location: General Urban/Suburban
Number of Studies: 75
Avg. Num. of Students: 72
Directional Distribution: 47% entering, 53% exiting
Vehicle Trip Generation per Student
Average Rate Range of Rates Standard Deviation
0.79 0.24 - 1.72 0.30
Data Plot and Equation
200
T = Trips Ends 100
0
0 100 200 300
X = Number of Students
Study Site Fitted Curve Average Rate
Fitted Curve Equation: Ln(T) = 0.87 Ln(X) + 0.29 R²= 0.57
General Urban/Suburban and Rural (Land Uses 400–799) 511
CMAP 2050 Projections Letter
January 16, 2023
Kelly Pachowicz
Consultant
Kenig, Lindgren, O'Hara, Aboona, Inc.
9575 West Higgins Road
Suite 400
Rosemont, IL 60018
Subject: Dempster Street (IL 58) and Niles Center Road
IDOT
Dear Mr. Pachowicz:
In response to a request made on your behalf and dated January 16, 2023, we have
developed year 2050 average daily traffic (ADT) projections for the subject location.
ROAD SEGMENT Current ADT Year 2050 ADT
Dempster St (IL 58) west of Skokie Blvd (US 41) 30,200 32,000
Niles Center Rd south of Dempster St 6,700 7,500
Traffic projections are developed using existing ADT data provided in the request letter
and the results from the October 2022 CMAP Travel Demand Analysis. The regional
travel model uses CMAP 2050 socioeconomic projections and assumes the
implementation of the ON TO 2050 Comprehensive Regional Plan for the Northeastern
Illinois area. The provision of this data in support of your request does not constitute a
CMAP endorsement of the proposed development or any subsequent developments.
If you have any questions, please call me at (312) 386-8806.
Sincerely,
Jose Rodriguez, PTP, AICP
Senior Planner, Research & Analysis
cc: Rios (IDOT)
S:\AdminGroups\ResearchAnalysis\2023_TrafficForecasts\Skokie\ck-04-23\ck-04-23.docx
Level of Service Criteria
LEVEL OF SERVICE CRITERIA
Signalized Intersections
Average Control
Level of Delay
Service Interpretation (seconds per vehicle)
A Favorable progression. Most vehicles arrive during the ≤10
green indication and travel through the intersection without
stopping.
B Good progression, with more vehicles stopping than for >10 - 20
Level of Service A.
C Individual cycle failures (i.e., one or more queued vehicles >20 - 35
are not able to depart as a result of insufficient capacity
during the cycle) may begin to appear. Number of vehicles
stopping is significant, although many vehicles still pass
through the intersection without stopping.
D The volume-to-capacity ratio is high and either progression >35 - 55
is ineffective or the cycle length is too long. Many vehicles
stop and individual cycle failures are noticeable.
E Progression is unfavorable. The volume-to-capacity ratio >55 - 80
is high and the cycle length is long. Individual cycle
failures are frequent.
F The volume-to-capacity ratio is very high, progression is >80.0
very poor, and the cycle length is long. Most cycles fail to
clear the queue.
Unsignalized Intersections
Level of Service Average Total Delay (SEC/VEH)
A 0 - 10
B > 10 - 15
C > 15 - 25
D > 25 - 35
E > 35 - 50
F > 50
Source: Highway Capacity Manual, 2010.
Capacity Analysis Summary Sheets
Existing Weekday Morning Peak Hour
Lanes, Volumes, Timings
1: Skokie Swift Access & Dempster Street 01/19/2023
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Volume (vph) 0 800 96 43 838 0 82 0 30 1 0 1
Future Volume (vph) 0 800 96 43 838 0 82 0 30 1 0 1
Ideal Flow (vphpl) 1900 1900 1900 1900 2000 1900 1900 1900 1900 1900 1900 1900
Lane Width (ft) 12 12 12 12 12 12 12 12 12 12 12 12
Grade (%) 0% 0% 0% 0%
Storage Length (ft) 0 0 150 0 0 0 0 0
Storage Lanes 0 0 1 0 1 1 0 0
Taper Length (ft) 25 100 25 25
Lane Util. Factor 1.00 0.95 0.95 1.00 0.95 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Ped Bike Factor 1.00 1.00 0.99 1.00
Frt 0.984 0.850 0.932
Flt Protected 0.950 0.950 0.976
Satd. Flow (prot) 0 3374 0 1388 3725 0 1687 0 1099 0 1728 0
Flt Permitted 0.279 0.757 0.976
Satd. Flow (perm) 0 3374 0 407 3725 0 1344 0 1084 0 1727 0
Right Turn on Red No No No No
Satd. Flow (RTOR)
Link Speed (mph) 35 35 25 25
Link Distance (ft) 634 754 238 113
Travel Time (s) 12.4 14.7 6.5 3.1
Confl. Peds. (#/hr) 3 3 1 1
Confl. Bikes (#/hr)
Peak Hour Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98
Growth Factor 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Heavy Vehicles (%) 0% 5% 5% 30% 2% 0% 7% 0% 47% 0% 0% 0%
Bus Blockages (#/hr) 0 0 0 0 0 0 0 0 0 0 0 0
Parking (#/hr)
Mid-Block Traffic (%) 0% 0% 0% 0%
Shared Lane Traffic (%)
Lane Group Flow (vph) 0 914 0 44 855 0 84 0 31 0 2 0
Turn Type NA pm+pt NA Perm Perm Perm NA
Protected Phases 2 1 6 4
Permitted Phases 6 8 8 4
Detector Phase 2 1 6 8 8 4 4
Switch Phase
Minimum Initial (s) 15.0 3.0 15.0 8.0 8.0 8.0 8.0
Minimum Split (s) 43.0 9.5 24.0 36.0 36.0 36.0 36.0
Total Split (s) 71.0 13.0 84.0 36.0 36.0 36.0 36.0
Total Split (%) 59.2% 10.8% 70.0% 30.0% 30.0% 30.0% 30.0%
Yellow Time (s) 4.5 3.5 4.5 4.5 4.5 4.5 4.5
All-Red Time (s) 1.5 0.0 1.5 1.5 1.5 1.5 1.5
Lost Time Adjust (s) 0.0 0.0 0.0 0.0 0.0 0.0
Total Lost Time (s) 6.0 3.5 6.0 6.0 6.0 6.0
Lead/Lag Lag Lead
Lead-Lag Optimize? Yes Yes
Recall Mode C-Min None Min None None None None
Act Effct Green (s) 90.2 99.5 98.2 13.8 13.8 13.8
Actuated g/C Ratio 0.75 0.83 0.82 0.12 0.12 0.12
22-406 Residential Development - Skokie Synchro 11 Report
Existing Weekday Morning Peak Hour KP
Lanes, Volumes, Timings
1: Skokie Swift Access & Dempster Street 01/19/2023
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
v/c Ratio 0.36 0.11 0.28 0.55 0.25 0.01
Control Delay 7.6 3.6 3.9 62.3 51.4 44.0
Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0
Total Delay 7.6 3.6 3.9 62.3 51.4 44.0
LOS A A A E D D
Approach Delay 7.6 3.8 59.4 44.0
Approach LOS A A E D
Queue Length 50th (ft) 135 5 80 62 22 1
Queue Length 95th (ft) 207 16 128 111 51 9
Internal Link Dist (ft) 554 674 158 33
Turn Bay Length (ft) 150
Base Capacity (vph) 2536 415 3049 336 271 431
Starvation Cap Reductn 0 0 0 0 0 0
Spillback Cap Reductn 0 0 0 0 0 0
Storage Cap Reductn 0 0 0 0 0 0
Reduced v/c Ratio 0.36 0.11 0.28 0.25 0.11 0.00
Intersection Summary
Area Type: Other
Cycle Length: 120
Actuated Cycle Length: 120
Offset: 107 (89%), Referenced to phase 2:EBT, Start of Green
Natural Cycle: 90
Control Type: Actuated-Coordinated
Maximum v/c Ratio: 0.55
Intersection Signal Delay: 9.0 Intersection LOS: A
Intersection Capacity Utilization 59.2% ICU Level of Service B
Analysis Period (min) 15
Splits and Phases: 1: Skokie Swift Access & Dempster Street
22-406 Residential Development - Skokie Synchro 11 Report
Existing Weekday Morning Peak Hour KP
HCM 6th TWSC
2: Niles Center Road & Conrad Street 01/18/2023
Intersection
Int Delay, s/veh 4
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 12 17 39 7 59 27 45 251 8 5 201 4
Future Vol, veh/h 12 17 39 7 59 27 45 251 8 5 201 4
Conflicting Peds, #/hr 11 0 7 7 0 11 1 0 9 9 0 1
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 95 95 95 95 95 95 95 95 95 95 95 95
Heavy Vehicles, % 0 0 5 14 0 0 0 6 13 0 4 0
Mvmt Flow 13 18 41 7 62 28 47 264 8 5 212 4
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 643 600 222 632 598 288 217 0 0 281 0 0
Stage 1 225 225 - 371 371 - - - - - - -
Stage 2 418 375 - 261 227 - - - - - - -
Critical Hdwy 7.1 6.5 6.25 7.24 6.5 6.2 4.1 - - 4.1 - -
Critical Hdwy Stg 1 6.1 5.5 - 6.24 5.5 - - - - - - -
Critical Hdwy Stg 2 6.1 5.5 - 6.24 5.5 - - - - - - -
Follow-up Hdwy 3.5 4 3.345 3.626 4 3.3 2.2 - - 2.2 - -
Pot Cap-1 Maneuver 389 417 810 377 418 756 1365 - - 1293 - -
Stage 1 782 721 - 625 623 - - - - - - -
Stage 2 616 621 - 718 720 - - - - - - -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 314 394 804 328 395 742 1364 - - 1282 - -
Mov Cap-2 Maneuver 314 394 - 328 395 - - - - - - -
Stage 1 749 717 - 594 592 - - - - - - -
Stage 2 503 590 - 657 716 - - - - - - -
Approach EB WB NB SB
HCM Control Delay, s 13 15.2 1.1 0.2
HCM LOS B C
Minor Lane/Major Mvmt NBL NBT NBR EBLn1WBLn1 SBL SBT SBR
Capacity (veh/h) 1364 - - 524 449 1282 - -
HCM Lane V/C Ratio 0.035 - - 0.137 0.218 0.004 - -
HCM Control Delay (s) 7.7 0 - 13 15.2 7.8 0 -
HCM Lane LOS A A - B C A A -
HCM 95th %tile Q(veh) 0.1 - - 0.5 0.8 0 - -
22-406 Residential Development - Skokie Synchro 11 Report
Existing Weekday Morning Peak Hour KP
HCM 6th TWSC
3: Niles Center Road & Greenleaf Street 01/18/2023
Intersection
Int Delay, s/veh 2
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 3 4 3 8 4 35 9 257 5 53 245 5
Future Vol, veh/h 3 4 3 8 4 35 9 257 5 53 245 5
Conflicting Peds, #/hr 1 0 0 0 0 1 9 0 0 0 0 9
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 84 84 84 84 84 84 84 84 84 84 84 84
Heavy Vehicles, % 0 0 0 0 0 0 0 6 0 0 5 0
Mvmt Flow 4 5 4 10 5 42 11 306 6 63 292 6
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 786 764 304 757 764 310 307 0 0 312 0 0
Stage 1 430 430 - 331 331 - - - - - - -
Stage 2 356 334 - 426 433 - - - - - - -
Critical Hdwy 7.1 6.5 6.2 7.1 6.5 6.2 4.1 - - 4.1 - -
Critical Hdwy Stg 1 6.1 5.5 - 6.1 5.5 - - - - - - -
Critical Hdwy Stg 2 6.1 5.5 - 6.1 5.5 - - - - - - -
Follow-up Hdwy 3.5 4 3.3 3.5 4 3.3 2.2 - - 2.2 - -
Pot Cap-1 Maneuver 312 336 740 327 336 735 1265 - - 1260 - -
Stage 1 607 587 - 687 649 - - - - - - -
Stage 2 666 647 - 610 585 - - - - - - -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 273 309 734 304 309 734 1254 - - 1260 - -
Mov Cap-2 Maneuver 273 309 - 304 309 - - - - - - -
Stage 1 595 547 - 679 642 - - - - - - -
Stage 2 616 640 - 566 545 - - - - - - -
Approach EB WB NB SB
HCM Control Delay, s 15.4 12.4 0.3 1.4
HCM LOS C B
Minor Lane/Major Mvmt NBL NBT NBR EBLn1WBLn1 SBL SBT SBR
Capacity (veh/h) 1254 - - 357 541 1260 - -
HCM Lane V/C Ratio 0.009 - - 0.033 0.103 0.05 - -
HCM Control Delay (s) 7.9 0 - 15.4 12.4 8 0 -
HCM Lane LOS A A - C B A A -
HCM 95th %tile Q(veh) 0 - - 0.1 0.3 0.2 - -
22-406 Residential Development - Skokie Synchro 11 Report
Existing Weekday Morning Peak Hour KP
Capacity Analysis Summary Sheets
Existing Weekday Evening Peak Hour
Lanes, Volumes, Timings
1: Skokie Swift Access & Dempster Street 01/19/2023
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Volume (vph) 0 959 80 36 966 0 69 0 31 8 0 16
Future Volume (vph) 0 959 80 36 966 0 69 0 31 8 0 16
Ideal Flow (vphpl) 1900 1900 1900 1900 2000 1900 1900 1900 1900 1900 1900 1900
Lane Width (ft) 12 12 12 12 12 12 12 12 12 12 12 12
Grade (%) 0% 0% 0% 0%
Storage Length (ft) 0 0 150 0 0 0 0 0
Storage Lanes 0 0 1 0 1 1 0 0
Taper Length (ft) 25 100 25 25
Lane Util. Factor 1.00 0.95 0.95 1.00 0.95 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Ped Bike Factor 1.00 1.00 0.98 1.00
Frt 0.988 0.850 0.910
Flt Protected 0.950 0.950 0.984
Satd. Flow (prot) 0 3503 0 1357 3725 0 1687 0 1114 0 1701 0
Flt Permitted 0.237 0.742 0.984
Satd. Flow (perm) 0 3503 0 338 3725 0 1318 0 1094 0 1698 0
Right Turn on Red No No No No
Satd. Flow (RTOR)
Link Speed (mph) 35 35 25 25
Link Distance (ft) 634 754 238 113
Travel Time (s) 12.4 14.7 6.5 3.1
Confl. Peds. (#/hr) 7 3 3 7 4 4
Confl. Bikes (#/hr)
Peak Hour Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98
Growth Factor 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Heavy Vehicles (%) 0% 1% 9% 33% 2% 0% 7% 0% 45% 0% 0% 0%
Bus Blockages (#/hr) 0 0 0 0 0 0 0 0 0 0 0 0
Parking (#/hr)
Mid-Block Traffic (%) 0% 0% 0% 0%
Shared Lane Traffic (%)
Lane Group Flow (vph) 0 1061 0 37 986 0 70 0 32 0 24 0
Turn Type NA pm+pt NA Perm Perm Perm NA
Protected Phases 2 1 6 4
Permitted Phases 6 8 8 4
Detector Phase 2 1 6 8 8 4 4
Switch Phase
Minimum Initial (s) 15.0 3.0 15.0 8.0 8.0 8.0 8.0
Minimum Split (s) 43.0 9.5 24.0 32.0 32.0 32.0 32.0
Total Split (s) 75.0 13.0 88.0 32.0 32.0 32.0 32.0
Total Split (%) 62.5% 10.8% 73.3% 26.7% 26.7% 26.7% 26.7%
Yellow Time (s) 4.5 3.5 4.5 4.5 4.5 4.5 4.5
All-Red Time (s) 1.5 0.0 1.5 1.5 1.5 1.5 1.5
Lost Time Adjust (s) 0.0 0.0 0.0 0.0 0.0 0.0
Total Lost Time (s) 6.0 3.5 6.0 6.0 6.0 6.0
Lead/Lag Lag Lead
Lead-Lag Optimize? Yes Yes
Recall Mode C-Min None Min None None None None
Act Effct Green (s) 93.2 100.5 99.2 12.8 12.8 12.8
Actuated g/C Ratio 0.78 0.84 0.83 0.11 0.11 0.11
22-406 Residential Development - Skokie Synchro 11 Report
Existing Weekday Evening Peak Hour KP
Lanes, Volumes, Timings
1: Skokie Swift Access & Dempster Street 01/19/2023
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
v/c Ratio 0.39 0.11 0.32 0.50 0.28 0.13
Control Delay 6.8 3.4 3.7 61.9 53.7 48.2
Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0
Total Delay 6.8 3.4 3.7 61.9 53.7 48.2
LOS A A A E D D
Approach Delay 6.8 3.7 59.3 48.2
Approach LOS A A E D
Queue Length 50th (ft) 157 4 91 52 23 17
Queue Length 95th (ft) 236 13 144 97 54 42
Internal Link Dist (ft) 554 674 158 33
Turn Bay Length (ft) 150
Base Capacity (vph) 2719 363 3080 285 237 367
Starvation Cap Reductn 0 0 0 0 0 0
Spillback Cap Reductn 0 0 0 0 0 0
Storage Cap Reductn 0 0 0 0 0 0
Reduced v/c Ratio 0.39 0.10 0.32 0.25 0.14 0.07
Intersection Summary
Area Type: Other
Cycle Length: 120
Actuated Cycle Length: 120
Offset: 84 (70%), Referenced to phase 2:EBT, Start of Green
Natural Cycle: 85
Control Type: Actuated-Coordinated
Maximum v/c Ratio: 0.50
Intersection Signal Delay: 8.3 Intersection LOS: A
Intersection Capacity Utilization 59.2% ICU Level of Service B
Analysis Period (min) 15
Splits and Phases: 1: Skokie Swift Access & Dempster Street
22-406 Residential Development - Skokie Synchro 11 Report
Existing Weekday Evening Peak Hour KP
HCM 6th TWSC
2: Niles Center Road & Conrad Street 01/19/2023
Intersection
Int Delay, s/veh 2.6
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 13 29 25 2 21 13 19 245 9 9 227 6
Future Vol, veh/h 13 29 25 2 21 13 19 245 9 9 227 6
Conflicting Peds, #/hr 4 0 6 6 0 4 1 0 5 5 0 1
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90
Heavy Vehicles, % 8 3 0 0 0 0 0 4 11 0 2 0
Mvmt Flow 14 32 28 2 23 14 21 272 10 10 252 7
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 619 606 263 636 604 286 260 0 0 287 0 0
Stage 1 277 277 - 324 324 - - - - - - -
Stage 2 342 329 - 312 280 - - - - - - -
Critical Hdwy 7.18 6.53 6.2 7.1 6.5 6.2 4.1 - - 4.1 - -
Critical Hdwy Stg 1 6.18 5.53 - 6.1 5.5 - - - - - - -
Critical Hdwy Stg 2 6.18 5.53 - 6.1 5.5 - - - - - - -
Follow-up Hdwy 3.572 4.027 3.3 3.5 4 3.3 2.2 - - 2.2 - -
Pot Cap-1 Maneuver 392 410 781 393 415 758 1316 - - 1287 - -
Stage 1 716 679 - 692 653 - - - - - - -
Stage 2 661 645 - 703 683 - - - - - - -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 358 396 776 344 401 752 1315 - - 1281 - -
Mov Cap-2 Maneuver 358 396 - 344 401 - - - - - - -
Stage 1 702 672 - 675 637 - - - - - - -
Stage 2 610 630 - 636 676 - - - - - - -
Approach EB WB NB SB
HCM Control Delay, s 14 13.2 0.5 0.3
HCM LOS B B
Minor Lane/Major Mvmt NBL NBT NBR EBLn1WBLn1 SBL SBT SBR
Capacity (veh/h) 1315 - - 473 477 1281 - -
HCM Lane V/C Ratio 0.016 - - 0.157 0.084 0.008 - -
HCM Control Delay (s) 7.8 0 - 14 13.2 7.8 0 -
HCM Lane LOS A A - B B A A -
HCM 95th %tile Q(veh) 0 - - 0.6 0.3 0 - -
22-406 Residential Development - Skokie Synchro 11 Report
Existing Weekday Evening Peak Hour KP
HCM 6th TWSC
3: Niles Center Road & Greenleaf Street 01/19/2023
Intersection
Int Delay, s/veh 0.9
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 0 2 2 4 3 13 4 245 10 26 255 1
Future Vol, veh/h 0 2 2 4 3 13 4 245 10 26 255 1
Conflicting Peds, #/hr 1 0 1 1 0 1 6 0 1 1 0 6
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 84 84 84 84 84 84 84 84 84 84 84 84
Heavy Vehicles, % 0 0 0 0 0 0 25 4 0 0 2 0
Mvmt Flow 0 2 2 5 4 15 5 292 12 31 304 1
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 692 688 312 679 682 300 311 0 0 305 0 0
Stage 1 373 373 - 309 309 - - - - - - -
Stage 2 319 315 - 370 373 - - - - - - -
Critical Hdwy 7.1 6.5 6.2 7.1 6.5 6.2 4.35 - - 4.1 - -
Critical Hdwy Stg 1 6.1 5.5 - 6.1 5.5 - - - - - - -
Critical Hdwy Stg 2 6.1 5.5 - 6.1 5.5 - - - - - - -
Follow-up Hdwy 3.5 4 3.3 3.5 4 3.3 2.425 - - 2.2 - -
Pot Cap-1 Maneuver 361 372 733 368 375 744 1130 - - 1267 - -
Stage 1 652 622 - 705 663 - - - - - - -
Stage 2 697 659 - 654 622 - - - - - - -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 339 357 728 355 360 743 1124 - - 1266 - -
Mov Cap-2 Maneuver 339 357 - 355 360 - - - - - - -
Stage 1 645 600 - 701 659 - - - - - - -
Stage 2 675 655 - 630 600 - - - - - - -
Approach EB WB NB SB
HCM Control Delay, s 12.6 12 0.1 0.7
HCM LOS B B
Minor Lane/Major Mvmt NBL NBT NBR EBLn1WBLn1 SBL SBT SBR
Capacity (veh/h) 1124 - - 479 539 1266 - -
HCM Lane V/C Ratio 0.004 - - 0.01 0.044 0.024 - -
HCM Control Delay (s) 8.2 0 - 12.6 12 7.9 0 -
HCM Lane LOS A A - B B A A -
HCM 95th %tile Q(veh) 0 - - 0 0.1 0.1 - -
22-406 Residential Development - Skokie Synchro 11 Report
Existing Weekday Evening Peak Hour KP
Capacity Analysis Summary Sheets
Year 2029 No-Build Weekday Morning Peak Hour
Lanes, Volumes, Timings
1: Skokie Swift Access & Dempster Street 01/19/2023
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Volume (vph) 0 816 96 43 855 0 82 0 30 1 0 1
Future Volume (vph) 0 816 96 43 855 0 82 0 30 1 0 1
Ideal Flow (vphpl) 1900 1900 1900 1900 2000 1900 1900 1900 1900 1900 1900 1900
Lane Width (ft) 12 12 12 12 12 12 12 12 12 12 12 12
Grade (%) 0% 0% 0% 0%
Storage Length (ft) 0 0 150 0 0 0 0 0
Storage Lanes 0 0 1 0 1 1 0 0
Taper Length (ft) 25 100 25 25
Lane Util. Factor 1.00 0.95 0.95 1.00 0.95 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Ped Bike Factor 1.00 1.00 0.99 1.00
Frt 0.984 0.850 0.932
Flt Protected 0.950 0.950 0.976
Satd. Flow (prot) 0 3374 0 1388 3725 0 1687 0 1099 0 1728 0
Flt Permitted 0.274 0.757 0.976
Satd. Flow (perm) 0 3374 0 400 3725 0 1344 0 1084 0 1727 0
Right Turn on Red No No No No
Satd. Flow (RTOR)
Link Speed (mph) 35 35 25 25
Link Distance (ft) 634 754 238 113
Travel Time (s) 12.4 14.7 6.5 3.1
Confl. Peds. (#/hr) 3 3 1 1
Confl. Bikes (#/hr)
Peak Hour Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98
Growth Factor 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Heavy Vehicles (%) 0% 5% 5% 30% 2% 0% 7% 0% 47% 0% 0% 0%
Bus Blockages (#/hr) 0 0 0 0 0 0 0 0 0 0 0 0
Parking (#/hr)
Mid-Block Traffic (%) 0% 0% 0% 0%
Shared Lane Traffic (%)
Lane Group Flow (vph) 0 931 0 44 872 0 84 0 31 0 2 0
Turn Type NA pm+pt NA Perm Perm Perm NA
Protected Phases 2 1 6 4
Permitted Phases 6 8 8 4
Detector Phase 2 1 6 8 8 4 4
Switch Phase
Minimum Initial (s) 15.0 3.0 15.0 8.0 8.0 8.0 8.0
Minimum Split (s) 43.0 9.5 24.0 36.0 36.0 36.0 36.0
Total Split (s) 71.0 13.0 84.0 36.0 36.0 36.0 36.0
Total Split (%) 59.2% 10.8% 70.0% 30.0% 30.0% 30.0% 30.0%
Yellow Time (s) 4.5 3.5 4.5 4.5 4.5 4.5 4.5
All-Red Time (s) 1.5 0.0 1.5 1.5 1.5 1.5 1.5
Lost Time Adjust (s) 0.0 0.0 0.0 0.0 0.0 0.0
Total Lost Time (s) 6.0 3.5 6.0 6.0 6.0 6.0
Lead/Lag Lag Lead
Lead-Lag Optimize? Yes Yes
Recall Mode C-Min None Min None None None None
Act Effct Green (s) 90.2 99.5 98.2 13.8 13.8 13.8
Actuated g/C Ratio 0.75 0.83 0.82 0.12 0.12 0.12
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 No-Build Weekday Morning Peak Hour KP
Lanes, Volumes, Timings
1: Skokie Swift Access & Dempster Street 01/19/2023
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
v/c Ratio 0.37 0.11 0.29 0.55 0.25 0.01
Control Delay 7.6 3.6 3.9 62.3 51.4 44.0
Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0
Total Delay 7.6 3.6 3.9 62.3 51.4 44.0
LOS A A A E D D
Approach Delay 7.6 3.9 59.4 44.0
Approach LOS A A E D
Queue Length 50th (ft) 138 5 82 62 22 1
Queue Length 95th (ft) 212 16 131 111 51 9
Internal Link Dist (ft) 554 674 158 33
Turn Bay Length (ft) 150
Base Capacity (vph) 2536 409 3049 336 271 431
Starvation Cap Reductn 0 0 0 0 0 0
Spillback Cap Reductn 0 0 0 0 0 0
Storage Cap Reductn 0 0 0 0 0 0
Reduced v/c Ratio 0.37 0.11 0.29 0.25 0.11 0.00
Intersection Summary
Area Type: Other
Cycle Length: 120
Actuated Cycle Length: 120
Offset: 107 (89%), Referenced to phase 2:EBT, Start of Green
Natural Cycle: 90
Control Type: Actuated-Coordinated
Maximum v/c Ratio: 0.55
Intersection Signal Delay: 9.0 Intersection LOS: A
Intersection Capacity Utilization 59.2% ICU Level of Service B
Analysis Period (min) 15
Splits and Phases: 1: Skokie Swift Access & Dempster Street
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 No-Build Weekday Morning Peak Hour KP
HCM 6th TWSC
2: Niles Center Road & Conrad Street 01/19/2023
Intersection
Int Delay, s/veh 3.9
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 12 17 39 7 59 27 45 256 8 5 205 4
Future Vol, veh/h 12 17 39 7 59 27 45 256 8 5 205 4
Conflicting Peds, #/hr 11 0 7 7 0 11 1 0 9 9 0 1
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 95 95 95 95 95 95 95 95 95 95 95 95
Heavy Vehicles, % 0 0 5 14 0 0 0 6 13 0 4 0
Mvmt Flow 13 18 41 7 62 28 47 269 8 5 216 4
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 652 609 226 641 607 293 221 0 0 286 0 0
Stage 1 229 229 - 376 376 - - - - - - -
Stage 2 423 380 - 265 231 - - - - - - -
Critical Hdwy 7.1 6.5 6.25 7.24 6.5 6.2 4.1 - - 4.1 - -
Critical Hdwy Stg 1 6.1 5.5 - 6.24 5.5 - - - - - - -
Critical Hdwy Stg 2 6.1 5.5 - 6.24 5.5 - - - - - - -
Follow-up Hdwy 3.5 4 3.345 3.626 4 3.3 2.2 - - 2.2 - -
Pot Cap-1 Maneuver 384 412 806 371 414 751 1360 - - 1288 - -
Stage 1 778 718 - 622 620 - - - - - - -
Stage 2 613 617 - 715 717 - - - - - - -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 310 390 800 323 392 737 1359 - - 1277 - -
Mov Cap-2 Maneuver 310 390 - 323 392 - - - - - - -
Stage 1 745 714 - 592 589 - - - - - - -
Stage 2 500 586 - 654 713 - - - - - - -
Approach EB WB NB SB
HCM Control Delay, s 13 15.4 1.1 0.2
HCM LOS B C
Minor Lane/Major Mvmt NBL NBT NBR EBLn1WBLn1 SBL SBT SBR
Capacity (veh/h) 1359 - - 519 445 1277 - -
HCM Lane V/C Ratio 0.035 - - 0.138 0.22 0.004 - -
HCM Control Delay (s) 7.7 0 - 13 15.4 7.8 0 -
HCM Lane LOS A A - B C A A -
HCM 95th %tile Q(veh) 0.1 - - 0.5 0.8 0 - -
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 No-Build Weekday Morning Peak Hour KP
HCM 6th TWSC
3: Niles Center Road & Greenleaf Street 01/19/2023
Intersection
Int Delay, s/veh 2
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 3 4 3 8 4 35 9 262 5 53 250 5
Future Vol, veh/h 3 4 3 8 4 35 9 262 5 53 250 5
Conflicting Peds, #/hr 1 0 0 0 0 1 9 0 0 0 0 9
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 84 84 84 84 84 84 84 84 84 84 84 84
Heavy Vehicles, % 0 0 0 0 0 0 0 6 0 0 5 0
Mvmt Flow 4 5 4 10 5 42 11 312 6 63 298 6
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 798 776 310 769 776 316 313 0 0 318 0 0
Stage 1 436 436 - 337 337 - - - - - - -
Stage 2 362 340 - 432 439 - - - - - - -
Critical Hdwy 7.1 6.5 6.2 7.1 6.5 6.2 4.1 - - 4.1 - -
Critical Hdwy Stg 1 6.1 5.5 - 6.1 5.5 - - - - - - -
Critical Hdwy Stg 2 6.1 5.5 - 6.1 5.5 - - - - - - -
Follow-up Hdwy 3.5 4 3.3 3.5 4 3.3 2.2 - - 2.2 - -
Pot Cap-1 Maneuver 306 331 735 321 331 729 1259 - - 1253 - -
Stage 1 603 583 - 681 645 - - - - - - -
Stage 2 661 643 - 606 582 - - - - - - -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 267 305 729 299 305 728 1248 - - 1253 - -
Mov Cap-2 Maneuver 267 305 - 299 305 - - - - - - -
Stage 1 592 543 - 674 638 - - - - - - -
Stage 2 611 636 - 561 542 - - - - - - -
Approach EB WB NB SB
HCM Control Delay, s 15.6 12.5 0.3 1.4
HCM LOS C B
Minor Lane/Major Mvmt NBL NBT NBR EBLn1WBLn1 SBL SBT SBR
Capacity (veh/h) 1248 - - 351 534 1253 - -
HCM Lane V/C Ratio 0.009 - - 0.034 0.105 0.05 - -
HCM Control Delay (s) 7.9 0 - 15.6 12.5 8 0 -
HCM Lane LOS A A - C B A A -
HCM 95th %tile Q(veh) 0 - - 0.1 0.3 0.2 - -
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 No-Build Weekday Morning Peak Hour KP
Capacity Analysis Summary Sheets
Year 2029 No-Build Weekday Evening Peak Hour
Lanes, Volumes, Timings
1: Skokie Swift Access & Dempster Street 01/19/2023
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Volume (vph) 0 978 80 36 985 0 69 0 31 8 0 16
Future Volume (vph) 0 978 80 36 985 0 69 0 31 8 0 16
Ideal Flow (vphpl) 1900 1900 1900 1900 2000 1900 1900 1900 1900 1900 1900 1900
Lane Width (ft) 12 12 12 12 12 12 12 12 12 12 12 12
Grade (%) 0% 0% 0% 0%
Storage Length (ft) 0 0 150 0 0 0 0 0
Storage Lanes 0 0 1 0 1 1 0 0
Taper Length (ft) 25 100 25 25
Lane Util. Factor 1.00 0.95 0.95 1.00 0.95 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Ped Bike Factor 1.00 1.00 0.98 1.00
Frt 0.989 0.850 0.910
Flt Protected 0.950 0.950 0.984
Satd. Flow (prot) 0 3507 0 1357 3725 0 1687 0 1114 0 1701 0
Flt Permitted 0.231 0.742 0.984
Satd. Flow (perm) 0 3507 0 330 3725 0 1318 0 1094 0 1698 0
Right Turn on Red No No No No
Satd. Flow (RTOR)
Link Speed (mph) 35 35 25 25
Link Distance (ft) 634 754 238 113
Travel Time (s) 12.4 14.7 6.5 3.1
Confl. Peds. (#/hr) 7 3 3 7 4 4
Confl. Bikes (#/hr)
Peak Hour Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98
Growth Factor 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Heavy Vehicles (%) 0% 1% 9% 33% 2% 0% 7% 0% 45% 0% 0% 0%
Bus Blockages (#/hr) 0 0 0 0 0 0 0 0 0 0 0 0
Parking (#/hr)
Mid-Block Traffic (%) 0% 0% 0% 0%
Shared Lane Traffic (%)
Lane Group Flow (vph) 0 1080 0 37 1005 0 70 0 32 0 24 0
Turn Type NA pm+pt NA Perm Perm Perm NA
Protected Phases 2 1 6 4
Permitted Phases 6 8 8 4
Detector Phase 2 1 6 8 8 4 4
Switch Phase
Minimum Initial (s) 15.0 3.0 15.0 8.0 8.0 8.0 8.0
Minimum Split (s) 43.0 9.5 24.0 32.0 32.0 32.0 32.0
Total Split (s) 75.0 13.0 88.0 32.0 32.0 32.0 32.0
Total Split (%) 62.5% 10.8% 73.3% 26.7% 26.7% 26.7% 26.7%
Yellow Time (s) 4.5 3.5 4.5 4.5 4.5 4.5 4.5
All-Red Time (s) 1.5 0.0 1.5 1.5 1.5 1.5 1.5
Lost Time Adjust (s) 0.0 0.0 0.0 0.0 0.0 0.0
Total Lost Time (s) 6.0 3.5 6.0 6.0 6.0 6.0
Lead/Lag Lag Lead
Lead-Lag Optimize? Yes Yes
Recall Mode C-Min None Min None None None None
Act Effct Green (s) 93.2 100.5 99.2 12.8 12.8 12.8
Actuated g/C Ratio 0.78 0.84 0.83 0.11 0.11 0.11
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 No-Build Weekday Morning Peak Hour KP
Lanes, Volumes, Timings
1: Skokie Swift Access & Dempster Street 01/19/2023
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
v/c Ratio 0.40 0.11 0.33 0.50 0.28 0.13
Control Delay 6.9 3.4 3.8 61.9 53.7 48.2
Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0
Total Delay 6.9 3.4 3.8 61.9 53.7 48.2
LOS A A A E D D
Approach Delay 6.9 3.8 59.3 48.2
Approach LOS A A E D
Queue Length 50th (ft) 161 4 94 52 23 17
Queue Length 95th (ft) 242 13 147 97 54 42
Internal Link Dist (ft) 554 674 158 33
Turn Bay Length (ft) 150
Base Capacity (vph) 2722 357 3080 285 237 367
Starvation Cap Reductn 0 0 0 0 0 0
Spillback Cap Reductn 0 0 0 0 0 0
Storage Cap Reductn 0 0 0 0 0 0
Reduced v/c Ratio 0.40 0.10 0.33 0.25 0.14 0.07
Intersection Summary
Area Type: Other
Cycle Length: 120
Actuated Cycle Length: 120
Offset: 84 (70%), Referenced to phase 2:EBT, Start of Green
Natural Cycle: 85
Control Type: Actuated-Coordinated
Maximum v/c Ratio: 0.50
Intersection Signal Delay: 8.3 Intersection LOS: A
Intersection Capacity Utilization 59.2% ICU Level of Service B
Analysis Period (min) 15
Splits and Phases: 1: Skokie Swift Access & Dempster Street
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 No-Build Weekday Morning Peak Hour KP
HCM 6th TWSC
2: Niles Center Road & Conrad Street 01/19/2023
Intersection
Int Delay, s/veh 2.6
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 13 29 25 2 21 13 19 250 9 9 232 6
Future Vol, veh/h 13 29 25 2 21 13 19 250 9 9 232 6
Conflicting Peds, #/hr 4 0 6 6 0 4 1 0 5 5 0 1
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90
Heavy Vehicles, % 8 3 0 0 0 0 0 4 11 0 2 0
Mvmt Flow 14 32 28 2 23 14 21 278 10 10 258 7
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 631 618 269 648 616 292 266 0 0 293 0 0
Stage 1 283 283 - 330 330 - - - - - - -
Stage 2 348 335 - 318 286 - - - - - - -
Critical Hdwy 7.18 6.53 6.2 7.1 6.5 6.2 4.1 - - 4.1 - -
Critical Hdwy Stg 1 6.18 5.53 - 6.1 5.5 - - - - - - -
Critical Hdwy Stg 2 6.18 5.53 - 6.1 5.5 - - - - - - -
Follow-up Hdwy 3.572 4.027 3.3 3.5 4 3.3 2.2 - - 2.2 - -
Pot Cap-1 Maneuver 385 404 775 386 409 752 1310 - - 1280 - -
Stage 1 711 675 - 687 649 - - - - - - -
Stage 2 656 641 - 698 679 - - - - - - -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 351 390 770 338 395 746 1309 - - 1274 - -
Mov Cap-2 Maneuver 351 390 - 338 395 - - - - - - -
Stage 1 697 668 - 671 633 - - - - - - -
Stage 2 605 626 - 631 672 - - - - - - -
Approach EB WB NB SB
HCM Control Delay, s 14.2 13.4 0.5 0.3
HCM LOS B B
Minor Lane/Major Mvmt NBL NBT NBR EBLn1WBLn1 SBL SBT SBR
Capacity (veh/h) 1309 - - 466 471 1274 - -
HCM Lane V/C Ratio 0.016 - - 0.16 0.085 0.008 - -
HCM Control Delay (s) 7.8 0 - 14.2 13.4 7.8 0 -
HCM Lane LOS A A - B B A A -
HCM 95th %tile Q(veh) 0 - - 0.6 0.3 0 - -
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 No-Build Weekday Morning Peak Hour KP
HCM 6th TWSC
3: Niles Center Road & Greenleaf Street 01/19/2023
Intersection
Int Delay, s/veh 0.9
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 0 2 2 4 3 13 4 250 10 26 260 1
Future Vol, veh/h 0 2 2 4 3 13 4 250 10 26 260 1
Conflicting Peds, #/hr 1 0 1 1 0 1 6 0 1 1 0 6
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 84 84 84 84 84 84 84 84 84 84 84 84
Heavy Vehicles, % 0 0 0 0 0 0 25 4 0 0 2 0
Mvmt Flow 0 2 2 5 4 15 5 298 12 31 310 1
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 704 700 318 691 694 306 317 0 0 311 0 0
Stage 1 379 379 - 315 315 - - - - - - -
Stage 2 325 321 - 376 379 - - - - - - -
Critical Hdwy 7.1 6.5 6.2 7.1 6.5 6.2 4.35 - - 4.1 - -
Critical Hdwy Stg 1 6.1 5.5 - 6.1 5.5 - - - - - - -
Critical Hdwy Stg 2 6.1 5.5 - 6.1 5.5 - - - - - - -
Follow-up Hdwy 3.5 4 3.3 3.5 4 3.3 2.425 - - 2.2 - -
Pot Cap-1 Maneuver 354 366 727 362 369 739 1124 - - 1261 - -
Stage 1 647 618 - 700 659 - - - - - - -
Stage 2 692 655 - 649 618 - - - - - - -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 332 351 722 349 354 738 1118 - - 1260 - -
Mov Cap-2 Maneuver 332 351 - 349 354 - - - - - - -
Stage 1 640 596 - 696 655 - - - - - - -
Stage 2 670 651 - 624 596 - - - - - - -
Approach EB WB NB SB
HCM Control Delay, s 12.7 12.1 0.1 0.7
HCM LOS B B
Minor Lane/Major Mvmt NBL NBT NBR EBLn1WBLn1 SBL SBT SBR
Capacity (veh/h) 1118 - - 472 533 1260 - -
HCM Lane V/C Ratio 0.004 - - 0.01 0.045 0.025 - -
HCM Control Delay (s) 8.2 0 - 12.7 12.1 7.9 0 -
HCM Lane LOS A A - B B A A -
HCM 95th %tile Q(veh) 0 - - 0 0.1 0.1 - -
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 No-Build Weekday Morning Peak Hour KP
Capacity Analysis Summary Sheets
Year 2029 Total Projected Weekday Morning Peak Hour
Lanes, Volumes, Timings
1: Skokie Swift Access & Dempster Street 01/19/2023
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Volume (vph) 0 816 102 44 855 0 101 0 31 1 0 1
Future Volume (vph) 0 816 102 44 855 0 101 0 31 1 0 1
Ideal Flow (vphpl) 1900 1900 1900 1900 2000 1900 1900 1900 1900 1900 1900 1900
Lane Width (ft) 12 12 12 12 12 12 12 12 12 12 12 12
Grade (%) 0% 0% 0% 0%
Storage Length (ft) 0 0 150 0 0 0 0 0
Storage Lanes 0 0 1 0 1 1 0 0
Taper Length (ft) 25 100 25 25
Lane Util. Factor 1.00 0.95 0.95 1.00 0.95 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Ped Bike Factor 1.00 1.00 0.99 1.00
Frt 0.983 0.850 0.932
Flt Protected 0.950 0.950 0.976
Satd. Flow (prot) 0 3370 0 1388 3725 0 1687 0 1099 0 1728 0
Flt Permitted 0.266 0.757 0.976
Satd. Flow (perm) 0 3370 0 388 3725 0 1344 0 1084 0 1727 0
Right Turn on Red No No No No
Satd. Flow (RTOR)
Link Speed (mph) 35 35 25 25
Link Distance (ft) 634 754 238 113
Travel Time (s) 12.4 14.7 6.5 3.1
Confl. Peds. (#/hr) 3 3 1 1
Confl. Bikes (#/hr)
Peak Hour Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98
Growth Factor 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Heavy Vehicles (%) 0% 5% 5% 30% 2% 0% 7% 0% 47% 0% 0% 0%
Bus Blockages (#/hr) 0 0 0 0 0 0 0 0 0 0 0 0
Parking (#/hr)
Mid-Block Traffic (%) 0% 0% 0% 0%
Shared Lane Traffic (%)
Lane Group Flow (vph) 0 937 0 45 872 0 103 0 32 0 2 0
Turn Type NA pm+pt NA Perm Perm Perm NA
Protected Phases 2 1 6 4
Permitted Phases 6 8 8 4
Detector Phase 2 1 6 8 8 4 4
Switch Phase
Minimum Initial (s) 15.0 3.0 15.0 8.0 8.0 8.0 8.0
Minimum Split (s) 43.0 9.5 24.0 36.0 36.0 36.0 36.0
Total Split (s) 71.0 13.0 84.0 36.0 36.0 36.0 36.0
Total Split (%) 59.2% 10.8% 70.0% 30.0% 30.0% 30.0% 30.0%
Yellow Time (s) 4.5 3.5 4.5 4.5 4.5 4.5 4.5
All-Red Time (s) 1.5 0.0 1.5 1.5 1.5 1.5 1.5
Lost Time Adjust (s) 0.0 0.0 0.0 0.0 0.0 0.0
Total Lost Time (s) 6.0 3.5 6.0 6.0 6.0 6.0
Lead/Lag Lag Lead
Lead-Lag Optimize? Yes Yes
Recall Mode C-Min None Min None None None None
Act Effct Green (s) 84.4 95.1 92.6 15.4 15.4 15.4
Actuated g/C Ratio 0.70 0.79 0.77 0.13 0.13 0.13
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 Total Weekday Morning Peak Hour KP
Lanes, Volumes, Timings
1: Skokie Swift Access & Dempster Street 01/19/2023
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
v/c Ratio 0.40 0.12 0.30 0.60 0.23 0.01
Control Delay 8.9 4.2 4.8 62.6 48.8 42.0
Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0
Total Delay 8.9 4.2 4.8 62.6 48.8 42.0
LOS A A A E D D
Approach Delay 8.9 4.7 59.4 42.0
Approach LOS A A E D
Queue Length 50th (ft) 147 6 88 76 23 1
Queue Length 95th (ft) 230 18 143 129 52 9
Internal Link Dist (ft) 554 674 158 33
Turn Bay Length (ft) 150
Base Capacity (vph) 2370 386 2873 336 271 431
Starvation Cap Reductn 0 0 0 0 0 0
Spillback Cap Reductn 0 0 0 0 0 0
Storage Cap Reductn 0 0 0 0 0 0
Reduced v/c Ratio 0.40 0.12 0.30 0.31 0.12 0.00
Intersection Summary
Area Type: Other
Cycle Length: 120
Actuated Cycle Length: 120
Offset: 107 (89%), Referenced to phase 2:EBT, Start of Green
Natural Cycle: 90
Control Type: Actuated-Coordinated
Maximum v/c Ratio: 0.60
Intersection Signal Delay: 10.4 Intersection LOS: B
Intersection Capacity Utilization 59.2% ICU Level of Service B
Analysis Period (min) 15
Splits and Phases: 1: Skokie Swift Access & Dempster Street
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 Total Weekday Morning Peak Hour KP
HCM 6th TWSC
2: Niles Center Road & Conrad Street 01/19/2023
Intersection
Int Delay, s/veh 4.3
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 22 22 40 7 60 27 45 259 8 5 206 7
Future Vol, veh/h 22 22 40 7 60 27 45 259 8 5 206 7
Conflicting Peds, #/hr 11 0 7 7 0 11 1 0 9 9 0 1
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 95 95 95 95 95 95 95 95 95 95 95 95
Heavy Vehicles, % 0 0 5 14 0 0 0 6 13 0 4 0
Mvmt Flow 23 23 42 7 63 28 47 273 8 5 217 7
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 660 616 229 650 615 297 225 0 0 290 0 0
Stage 1 232 232 - 380 380 - - - - - - -
Stage 2 428 384 - 270 235 - - - - - - -
Critical Hdwy 7.1 6.5 6.25 7.24 6.5 6.2 4.1 - - 4.1 - -
Critical Hdwy Stg 1 6.1 5.5 - 6.24 5.5 - - - - - - -
Critical Hdwy Stg 2 6.1 5.5 - 6.24 5.5 - - - - - - -
Follow-up Hdwy 3.5 4 3.345 3.626 4 3.3 2.2 - - 2.2 - -
Pot Cap-1 Maneuver 379 409 803 366 409 747 1356 - - 1283 - -
Stage 1 775 716 - 618 617 - - - - - - -
Stage 2 609 615 - 710 714 - - - - - - -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 305 387 797 315 387 733 1355 - - 1272 - -
Mov Cap-2 Maneuver 305 387 - 315 387 - - - - - - -
Stage 1 742 712 - 588 586 - - - - - - -
Stage 2 496 584 - 644 710 - - - - - - -
Approach EB WB NB SB
HCM Control Delay, s 14.5 15.6 1.1 0.2
HCM LOS B C
Minor Lane/Major Mvmt NBL NBT NBR EBLn1WBLn1 SBL SBT SBR
Capacity (veh/h) 1355 - - 469 439 1272 - -
HCM Lane V/C Ratio 0.035 - - 0.189 0.225 0.004 - -
HCM Control Delay (s) 7.8 0 - 14.5 15.6 7.8 0 -
HCM Lane LOS A A - B C A A -
HCM 95th %tile Q(veh) 0.1 - - 0.7 0.9 0 - -
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 Total Weekday Morning Peak Hour KP
HCM 6th TWSC
3: Niles Center Road & Greenleaf Street 01/19/2023
Intersection
Int Delay, s/veh 2.3
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 6 9 7 8 5 35 10 262 5 53 251 6
Future Vol, veh/h 6 9 7 8 5 35 10 262 5 53 251 6
Conflicting Peds, #/hr 1 0 0 0 0 1 9 0 0 0 0 9
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 84 84 84 84 84 84 84 84 84 84 84 84
Heavy Vehicles, % 0 0 0 0 0 0 0 6 0 0 5 0
Mvmt Flow 7 11 8 10 6 42 12 312 6 63 299 7
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 802 780 312 777 780 316 315 0 0 318 0 0
Stage 1 438 438 - 339 339 - - - - - - -
Stage 2 364 342 - 438 441 - - - - - - -
Critical Hdwy 7.1 6.5 6.2 7.1 6.5 6.2 4.1 - - 4.1 - -
Critical Hdwy Stg 1 6.1 5.5 - 6.1 5.5 - - - - - - -
Critical Hdwy Stg 2 6.1 5.5 - 6.1 5.5 - - - - - - -
Follow-up Hdwy 3.5 4 3.3 3.5 4 3.3 2.2 - - 2.2 - -
Pot Cap-1 Maneuver 305 329 733 317 329 729 1257 - - 1253 - -
Stage 1 601 582 - 680 643 - - - - - - -
Stage 2 659 642 - 601 580 - - - - - - -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 265 302 727 288 302 728 1246 - - 1253 - -
Mov Cap-2 Maneuver 265 302 - 288 302 - - - - - - -
Stage 1 589 542 - 672 635 - - - - - - -
Stage 2 607 634 - 547 540 - - - - - - -
Approach EB WB NB SB
HCM Control Delay, s 16 12.8 0.3 1.4
HCM LOS C B
Minor Lane/Major Mvmt NBL NBT NBR EBLn1WBLn1 SBL SBT SBR
Capacity (veh/h) 1246 - - 354 519 1253 - -
HCM Lane V/C Ratio 0.01 - - 0.074 0.11 0.05 - -
HCM Control Delay (s) 7.9 0 - 16 12.8 8 0 -
HCM Lane LOS A A - C B A A -
HCM 95th %tile Q(veh) 0 - - 0.2 0.4 0.2 - -
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 Total Weekday Morning Peak Hour KP
Capacity Analysis Summary Sheets
Year 2029 Total Projected Weekday Evening Peak Hour
Lanes, Volumes, Timings
1: Skokie Swift Access & Dempster Street 01/19/2023
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Volume (vph) 0 978 95 37 985 0 79 0 32 8 0 16
Future Volume (vph) 0 978 95 37 985 0 79 0 32 8 0 16
Ideal Flow (vphpl) 1900 1900 1900 1900 2000 1900 1900 1900 1900 1900 1900 1900
Lane Width (ft) 12 12 12 12 12 12 12 12 12 12 12 12
Grade (%) 0% 0% 0% 0%
Storage Length (ft) 0 0 150 0 0 0 0 0
Storage Lanes 0 0 1 0 1 1 0 0
Taper Length (ft) 25 100 25 25
Lane Util. Factor 1.00 0.95 0.95 1.00 0.95 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Ped Bike Factor 1.00 1.00 0.98 1.00
Frt 0.987 0.850 0.910
Flt Protected 0.950 0.950 0.984
Satd. Flow (prot) 0 3496 0 1357 3725 0 1687 0 1114 0 1701 0
Flt Permitted 0.226 0.742 0.984
Satd. Flow (perm) 0 3496 0 323 3725 0 1318 0 1094 0 1698 0
Right Turn on Red No No No No
Satd. Flow (RTOR)
Link Speed (mph) 35 35 25 25
Link Distance (ft) 634 754 238 113
Travel Time (s) 12.4 14.7 6.5 3.1
Confl. Peds. (#/hr) 7 3 3 7 4 4
Confl. Bikes (#/hr)
Peak Hour Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98
Growth Factor 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Heavy Vehicles (%) 0% 1% 9% 33% 2% 0% 7% 0% 45% 0% 0% 0%
Bus Blockages (#/hr) 0 0 0 0 0 0 0 0 0 0 0 0
Parking (#/hr)
Mid-Block Traffic (%) 0% 0% 0% 0%
Shared Lane Traffic (%)
Lane Group Flow (vph) 0 1095 0 38 1005 0 81 0 33 0 24 0
Turn Type NA pm+pt NA Perm Perm Perm NA
Protected Phases 2 1 6 4
Permitted Phases 6 8 8 4
Detector Phase 2 1 6 8 8 4 4
Switch Phase
Minimum Initial (s) 15.0 3.0 15.0 8.0 8.0 8.0 8.0
Minimum Split (s) 43.0 9.5 24.0 32.0 32.0 32.0 32.0
Total Split (s) 75.0 13.0 88.0 32.0 32.0 32.0 32.0
Total Split (%) 62.5% 10.8% 73.3% 26.7% 26.7% 26.7% 26.7%
Yellow Time (s) 4.5 3.5 4.5 4.5 4.5 4.5 4.5
All-Red Time (s) 1.5 0.0 1.5 1.5 1.5 1.5 1.5
Lost Time Adjust (s) 0.0 0.0 0.0 0.0 0.0 0.0
Total Lost Time (s) 6.0 3.5 6.0 6.0 6.0 6.0
Lead/Lag Lag Lead
Lead-Lag Optimize? Yes Yes
Recall Mode C-Min None Min None None None None
Act Effct Green (s) 92.3 99.7 98.4 13.6 13.6 13.6
Actuated g/C Ratio 0.77 0.83 0.82 0.11 0.11 0.11
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 Total Weekday Morning Peak Hour KP
Lanes, Volumes, Timings
1: Skokie Swift Access & Dempster Street 01/19/2023
Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
v/c Ratio 0.41 0.12 0.33 0.54 0.27 0.12
Control Delay 7.4 3.7 4.1 62.8 52.2 47.0
Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0
Total Delay 7.4 3.7 4.1 62.8 52.2 47.0
LOS A A A E D D
Approach Delay 7.4 4.0 59.7 47.0
Approach LOS A A E D
Queue Length 50th (ft) 170 5 98 60 24 17
Queue Length 95th (ft) 257 14 155 108 55 42
Internal Link Dist (ft) 554 674 158 33
Turn Bay Length (ft) 150
Base Capacity (vph) 2689 350 3054 285 237 367
Starvation Cap Reductn 0 0 0 0 0 0
Spillback Cap Reductn 0 0 0 0 0 0
Storage Cap Reductn 0 0 0 0 0 0
Reduced v/c Ratio 0.41 0.11 0.33 0.28 0.14 0.07
Intersection Summary
Area Type: Other
Cycle Length: 120
Actuated Cycle Length: 120
Offset: 84 (70%), Referenced to phase 2:EBT, Start of Green
Natural Cycle: 85
Control Type: Actuated-Coordinated
Maximum v/c Ratio: 0.54
Intersection Signal Delay: 8.9 Intersection LOS: A
Intersection Capacity Utilization 59.2% ICU Level of Service B
Analysis Period (min) 15
Splits and Phases: 1: Skokie Swift Access & Dempster Street
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 Total Weekday Morning Peak Hour KP
HCM 6th TWSC
2: Niles Center Road & Conrad Street 01/19/2023
Intersection
Int Delay, s/veh 2.9
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 18 31 26 2 25 13 20 252 9 9 235 13
Future Vol, veh/h 18 31 26 2 25 13 20 252 9 9 235 13
Conflicting Peds, #/hr 4 0 6 6 0 4 1 0 5 5 0 1
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90
Heavy Vehicles, % 8 3 0 0 0 0 0 4 11 0 2 0
Mvmt Flow 20 34 29 2 28 14 22 280 10 10 261 14
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 643 628 275 660 630 294 276 0 0 295 0 0
Stage 1 289 289 - 334 334 - - - - - - -
Stage 2 354 339 - 326 296 - - - - - - -
Critical Hdwy 7.18 6.53 6.2 7.1 6.5 6.2 4.1 - - 4.1 - -
Critical Hdwy Stg 1 6.18 5.53 - 6.1 5.5 - - - - - - -
Critical Hdwy Stg 2 6.18 5.53 - 6.1 5.5 - - - - - - -
Follow-up Hdwy 3.572 4.027 3.3 3.5 4 3.3 2.2 - - 2.2 - -
Pot Cap-1 Maneuver 378 398 769 379 401 750 1299 - - 1278 - -
Stage 1 706 671 - 684 647 - - - - - - -
Stage 2 651 638 - 691 672 - - - - - - -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 341 384 764 329 387 744 1298 - - 1272 - -
Mov Cap-2 Maneuver 341 384 - 329 387 - - - - - - -
Stage 1 691 664 - 667 631 - - - - - - -
Stage 2 596 622 - 621 665 - - - - - - -
Approach EB WB NB SB
HCM Control Delay, s 14.9 13.8 0.6 0.3
HCM LOS B B
Minor Lane/Major Mvmt NBL NBT NBR EBLn1WBLn1 SBL SBT SBR
Capacity (veh/h) 1298 - - 448 454 1272 - -
HCM Lane V/C Ratio 0.017 - - 0.186 0.098 0.008 - -
HCM Control Delay (s) 7.8 0 - 14.9 13.8 7.9 0 -
HCM Lane LOS A A - B B A A -
HCM 95th %tile Q(veh) 0.1 - - 0.7 0.3 0 - -
22-406 Residential Development - Skokie Synchro 11 Report
Year 2029 Total Weekday Morning Peak Hour KP
HCM 6th TWSC
3: Niles Center Road & Greenleaf Street 01/19/2023
Intersection
Int Delay, s/veh 1.2
Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR
Lane Configurations
Traffic Vol, veh/h 2 4 4 4 7 13 7 251 10 26 261 4
Future Vol, veh/h 2 4 4 4 7 13 7 251 10 26 261 4
Conflicting Peds, #/hr 1 0 1 1 0 1 6 0 1 1 0 6
Sign Control Stop Stop Stop Stop Stop Stop Free Free Free Free Free Free
RT Channelized - - None - - None - - None - - None
Storage Length - - - - - - - - - - - -
Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 -
Grade, % - 0 - - 0 - - 0 - - 0 -
Peak Hour Factor 84 84 84 84 84 84 84 84 84 84 84 84
Heavy Vehicles, % 0 0 0 0 0 0 25 4 0 0 2 0
Mvmt Flow 2 5 5 5 8 15 8 299 12 31 311 5
Major/Minor Minor2 Minor1 Major1 Major2
Conflicting Flow All 716 710 321 704 706 307 322 0 0 312 0 0
Stage 1 382 382 - 322 322 - - - - - - -
Stage 2 334 328 - 382 384 - - - - - - -
Critical Hdwy 7.1 6.5 6.2 7.1 6.5 6.2 4.35 - - 4.1 - -
Critical Hdwy Stg 1 6.1 5.5 - 6.1 5.5 - - - - - - -
Critical Hdwy Stg 2 6.1 5.5 - 6.1 5.5 - - - - - - -
Follow-up Hdwy 3.5 4 3.3 3.5 4 3.3 2.425 - - 2.2 - -
Pot Cap-1 Maneuver 348 361 724 354 363 738 1119 - - 1260 - -
Stage 1 645 616 - 694 655 - - - - - - -
Stage 2 684 651 - 645 615 - - - - - - -
Platoon blocked, % - - - -
Mov Cap-1 Maneuver 323 345 719 337 347 737 1113 - - 1259 - -
Mov Cap-2 Maneuver 323 345 - 337 347 - - - - - - -
Stage 1 635 594 - 687 648 - - - - - - -
Stage 2 654 644 - 616 593 - - - - - - -
Approach EB WB NB SB
HCM Control Delay, s 13.7 12.9 0.2 0.7
HCM LOS B B
Minor Lane/Major Mvmt NBL NBT NBR EBLn1WBLn1 SBL SBT SBR
Capacity (veh/h) 1113 - - 428 483 1259 - -
HCM Lane V/C Ratio 0.007 - - 0.028 0.059 0.025 - -
HCM Control Delay (s) 8.3 0 - 13.7 12.9 7.9 0 -
HCM Lane LOS A A - B B A A -
HCM 95th %tile Q(veh) 0 - - 0.1 0.2 0.1 - -
22-406 Residential Development - Skokie Synchro 11 Report