Contract & Supply
Regular MeetingAlbany, NY · October 4, 2022
Agenda
CITY OF ALBANY, NY
BOARD OF CONTRACT AND SUPPLY
Tuesday, October 4, 2022
Present:
GIDEON GRANDE, Budget Director
DARIUS SHAHINFAR, Treasurer
MARISA FRANCHINI, Corporation Counsel
RANDALL MILANO, City Engineering
FRANK ZEOLI, Deputy Commissioner of DGS
This meeting will be live streamed to YouTube at:
https://www.youtube.com/channel/UCw2w4CdeaI5sd8lQPUDlcyw
*Motion to accept the agenda made by Zeoli and seconded by Milano
*Motion to adjourn made by Shahinfar and seconded by Milano
Adopted by the following vote:
Grande
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 1
Tuesday, October 4, 2022
The following was offered on behalf of the Albany Water Board:
RESOLVED, that the Secretary be authorized and directed to advertise for bids on behalf
of the Albany Water Board for the following:
Feura Bush Water Filtration Plant Upgrades
BIDS TO BE RECEIVED
Said proposals to be received by the Board at a regular meeting to be held Tuesday, November 8,
2022 at 1:30 P.M., and that each bidder be required to present with the bid a deposit equal to 5%
of the purchase price in a bid bond or certified check, conditioned upon his entering into the
contract if his bid should be accepted and for the performance of the same.
Adopted by the following vote:
Grande
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 2
Tuesday, October 4, 2022
BOARD OF CONTRACT AND SUPPLY
City of Albany, NY
Date Bids Received: October 4, 2022
Title: Shed Installation & Supply Services
Department: Department of General Services
Name of Bidder Security Amount of Bid
Carports Central Not Required $116, 274.00
1018 Rockford St.
Mt. Airy, NY 27030
Adopted by the following vote:
Grande
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 3
Tuesday, October 4, 2022
BOARD OF CONTRACT AND SUPPLY
City of Albany, NY
Date Bids Received: October 4, 2022
Title: Snow Management Services Zone E
Department: Department of General Services
Name of Bidder Security Amount of Bid
H.U.R.B Landscaping, Inc. Not Required Monthly Retainer Fee: $13,000
4278 Albany St.
Albany, NY 12205
Troy Topsoil and Aggregates Inc. Not Required Monthly Retainer Fee: $18,000
748 Hudson River Rd.
Mechanicville, NY 12118
Page | 4
Adopted by the following vote:
Grande
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 5
Tuesday, October 4, 2022
BOARD OF CONTRACT AND SUPPLY
City of Albany, NY
Date Bids Received: October 4, 2022
Title: Lead Services Replacement Project - ARPA
Department: Albany Water Board
Name of Bidder Security Amount of Bid
Peter Luizzi & Bros Contracting, Inc. Bid Bond $556,210.00
857 1st Street
Watervliet, NY 12189
New Castle Paving Bid Bond $538,486.00
1 Madison Street
Troy, NY 12180
Wm. J. Keller & Sons Construction Corp Bid Bond $668,220.00
1435 Route 9
Castleton, NY 12033
Peter Luizzi & Bros Contracting
Page | 6
Peter Luizzi & Bros Contracting
New Castle Paving
Page | 7
New Castle Paving
Wm J Keller & Sons
Page | 8
Wm J Keller & Sons
Adopted by the following vote:
Grande
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 9
Tuesday, October 4, 2022
BOARD OF CONTRACT AND SUPPLY
City of Albany, NY
Date Bids Received: October 4, 2022
Title: South End Fitness Equipment Installation
Department: Department of Recreation
Name of Bidder Security Amount of Bid
Performance Wellness Recovery Not Required $20,248.00
21 Erie Blvd.
Albany, NY 12204
Adopted by the following vote:
Grande
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 10
Tuesday, October 4, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 6 to the
Beaver Creek Clean River Project Phase IV- Third Avenue Tunnel Contract with
Rifenburg Contracting Corp. for the amount of ($141,048.55). The will decrease the
contract amount to a new value of $7,468,299.45. There is no change to the Contract
Completion Date of October 3, 2022.
Adopted by the following vote:
Grande
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 11
Tuesday, October 4, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 1 to the
Alcove Facilities Upgrades and Site Improvements Contract with AMZ Construction
Services, Inc., increasing the contract amount by $157,196.50. The new contract amount
is $1,657,196.50. The contract completion date remains December 2, 2022.
Adopted by the following vote:
Grande
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 12
Tuesday, October 4, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order SP-03A to
the Alcove Reservoir Sodium Permanganate Contract with AMZ Construction Services,
Inc., increasing the contract amount by $13,491.57. The new contract amount is
$487,973.82. The new contract completion date is November 30, 2022.
Adopted by the following vote:
Grande
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 13
Tuesday, October 4, 2022
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order 2 to the
2022 Lead Service Replacement Project contract with Peter Luizzi & Bros Contracting
Inc. for the amount of $4,220.25. The will increase the contract amount to a new value
of $1,739,862.64. There is no change to the Contract Completion Date of October 31,
2022.
Adopted by the following vote:
Grande
Shahinfar
Franchini
Milano
Zeoli
Affirmative 5 Negative 0
Page | 14
Get email alerts for Albany
A daily email when new agendas and minutes are posted.