Regular MeetingAlbany, NY · July 18, 2023
Agenda
CITY OF ALBANY, NY
BOARD OF CONTRACT AND SUPPLY
Tuesday, July 18, 2023
Present:
JOEL STETSON, Budget Department
DARIUS SHAHINFAR, Treasurer
MARISA FRANCHINI, Corporation Counsel
RANDY MILANO, City Engineering
* Motion to adopt the agenda was made by Darius Shahinfar and seconded by Randy Milano, followed by
a unanimous vote in the affirmative
* Motion to adjourn was made by Randy Milano and seconded by Darius Shahinfar, followed by a
unanimous vote in the affirmative
This meeting will be live streamed to YouTube at:
https://www.youtube.com/channel/UCw2w4CdeaI5sd8lQPUDlcyw
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Affirmative 4 Negative 0
Page | 1
Tuesday, July 18, 2023
The Department of Planning and Development has offered:
RESOLVED, That the Secretary be authorized and directed to advertise for bids for the
following:
LUCID: ALBANY; A WEST HILL ALLEYWAY REVITALIZATION PROJECT
BIDS TO BE RECEIVED
Said proposals to be received by the Board at a regular meeting to be held Tuesday,
August 22 , 2023 at 1:30 P.M., and that each bidder be required to present with the bid a
deposit equal in amount to 5% of the total bid in cash or certified check, conditioned upon his
entering into the contract if his bid be accepted and for the performance of the same.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Affirmative 4 Negative 0
Page | 2
Tuesday, July 18, 2022
Mr. Milano offered the following:
Resolved, that the bid of the following named bidder be accepted and the contract
awarded to them, at and for the prices specified in their proposal, they being the lowest
qualified bidder and theirs being the lowest qualified bid, and that the Mayor be authorized
to sign the contract on behalf of the City and affix its seal thereto.
Project Title: Upper Madison Avenue Sidewalk Improvements Phase 2
DGS-Division of Engineering
Low Bidder: Trinity Construction Inc.
P.O. Box 39
Selkirk, New York 12158
Amount: $563,613.00
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Affirmative 4 Negative 0
Page | 3
Tuesday, July 18, 2023
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board approves Change Order 4 to the 2022 Lead
Service Replacement Project contract with Peter Luizzi & Bros Contracting Inc. for the amount of
$33,526.71. This will decrease the contract amount to a new value of $1,665,159.43. There is no
change to the Contract Completion Date of October 31, 2022.
Adopted by the following vote:
Stetson
Shahinfar
Franchini
Milano
Affirmative 4 Negative 0
Page | 4