Contract & Supply
Regular MeetingAlbany, NY · September 8, 2023
Agenda
CITY OF ALBANY, NY
BOARD OF CONTRACT AND SUPPLY
Friday, September 8, 2023
Present:
GIDEON GRANDE, Budget Department
DARIUS SHAHINFAR, Treasurer
ROBERT MAGEE, Corporation Counsel
CHRISTOPHER MARINI, City Engineering
FRANK ZEOLI, Deputy Commissioner of DGS
This meeting will be live streamed to YouTube at:
https://www.youtube.com/channel/UCw2w4CdeaI5sd8lQPUDlcyw
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Affirmative 5 Negative 0
Page | 1
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Affirmative 5 Negative 0
Page | 2
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Affirmative 5 Negative 0
Page | 3
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Affirmative 5 Negative 0
Page | 4
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Page | 5 Affirmative 5 Negative 0
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Affirmative 5 Negative 0
Page | 6
Friday, September 8, 2023
The Following was offered:
RESOLVED, that the Secretary be authorized and directed to advertise for bids for the following:
DEMOLITON AND REMOVAL OF THE LINCOLN PARK POOL AND SELECT
ASSOCIATED INFRASTRUCTURE
BIDS TO BE RECEIVED
Said proposals to be received by the Board at a regular meeting to be held on October 17, 2023 at
1:30 p.m. and that each bidder be required to present with the bid a deposit in the amount equal
to 5% of the total bid in a bid bond or certified check, conditioned upon entering into the contract
if the bid is accepted and for the performance of the same.
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Affirmative 5 Negative 0
Page | 7
Friday, September 8, 2023
BOARD OF CONTRACT AND SUPPLY
City of Albany, NY
Date Bids Received: September 8, 2023
Title: Roadway Safety Improvements Speed Hump Project 2023
Requesting Department: Engineering
Name of Bidder Security Amount of Bid
New Castle Paving Bid Bond Total Base Bid: $567,683.56
1 Madison St Suite 100 Alternate 1 Bid: $117,484.40
Troy, NY 12180 Total Base w/Alternate 1: $685,167.96
Peter Luizzi & Bros Contracting Bid Bond Total Base Bid: $597,735.00
857 1st St Alternate 1 Bid: $162,750.00
Watervliet, NY 12189 Total Base w/ Alternate: $760,485.00
Callanan Industries Bid Bond Total Base Bid: $599,150.25
PO Box 15097 Alternate 1 Bid: $129,182.50
Albany, NY 12212-5097 Total Base w/Alternate: $728,332.75
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Affirmative 5 Negative 0
Page | 8
Friday, September 8, 2023
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board authorizes Change Order #3 to the 2022 AWB Water
& Sewer Project with Wm. J. Keller & Sons Construction Company, decreasing the contract amount by
$61,982.71. The new contract value is $3,274,189.29.
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Affirmative 5 Negative 0
Page | 9
Friday, September 8, 2023
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board approves Change Order 5G-12 to the Beaver
Creek Clean River Project Phase 3/5 Contract with Wm. J. Keller & Sons Construction Corp.
increasing the contract amount $111,418.03. The new contract value is $34,476,384.83. The
contract completion date is December 31, 2023.
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Affirmative 5 Negative 0
Page | 10
September 8, 2023
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board approves Change Order 3 to the Beaver Creek
Clean River Project Phase V – Plumbing contract with DiGesare Mechanical, Inc. increasing the
amount by $1,263.75. The new contract amount is $305,263.75. The contract completion date is
December 31, 2023.
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Affirmative 5 Negative 0
Page | 11
September 8, 2023
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board approves Change Order 1 to the Lead Service
Replacement Project-ARPA contract with New Castle Paving, LLC for the amount of $35,300.76.
This will increase the contract amount to a new value of $573,786.76. There is no change to the
contract completion date of May 31, 2023.
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Affirmative 5 Negative 0
Page | 12
Friday, September 8, 2023
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that the Albany Water Board approves Change Order 5 to the Marlborough
Ct. & Northern Blvd. Improvements Contract with WM. J. Keller & Sons Construction Corp
decreasing the contract amount by $4,551.17. The new contract amount is $591,879.83 the
contract completion date remains June 15, 2023.
Adopted by the following vote:
Grande
Shahinfar
MaGee
Marini
Zeoli
Affirmative 5 Negative 0
Page | 13
Get email alerts for Albany
A daily email when new agendas and minutes are posted.