Contract & Supply
Regular MeetingAlbany, NY · April 8, 2025
Agenda
Tuesday, April 8, 2025
CITY OF ALBANY, NY
BOARD OF CONTRACT AND SUPPLY
Present:
JOEL STETSON, Budget Department
DARIUS SHAHINFAR, Treasurer
ROBERT MAGEE, Corporation Counsel
HOWARD GOEBEL, City Engineering
FRANK ZEOLI, Department of General Service
*Motion to adopt the agenda was made by Frank Zeoli and seconded by Howard Goebel,
followed by a unanimous vote in the affirmative.
* Motion to adjourn was made by Darius Shahinfar and seconded, by Frank Zeoli followed by a
unanimous vote in the affirmative.
This meeting will be live streamed to YouTube at:
https://www.youtube.com/channel/UCw2w4CdeaI5sd8lQPUDlcyw
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
Mr. Goebel offered the following:
Resolved, that the Secretary be authorized and directed to advertise for bids for the following:
City of Albany
Complete Streets & Lead Service Replacement Project
Year 2025 – Contract 2
Department of Engineering
BIDS TO BE RECEIVED
Said proposals to be received by the Board at a special meeting to be held Tuesday, April 29, 2025
at 1:30 p.m. and that each bidder be required to present with the bid a deposit equal in amount to
5% of the total bid in a bid bond or certified check, conditioned upon them entering into the
contract if their bid be accepted and for the performance of the same.
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
Resolved, that the Secretary be authorized and directed to amend the bid submission date
for Albany On-Call Striping Project 2025. The new bid submission date is Tuesday, April 22,
2025.
Resolved, that the Secretary be authorize and directed to advertise the bid opening date
for the following:
Albany On-Call Striping Project 2025
Department of Engineering
City of Albany
BIDS TO BE RECEIVED
Said proposals to be received by the Board at a regular meeting to be held Tuesday, April
22, 2025 at 1:30 P.M., and that each bidder be required to present with the bid a deposit in the
amount of 5% of the total amount of the Bid in the form of a bid bond or certified check
conditioned upon the contractor entering into the contract if there be accepted and for the
performance of the same.
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following was offered:
RESOLVED, that the Secretary be authorized and directed to advertise for bids for the
following:
TREE MAINTENANCE & EMERGENCY WORK SERVICES
FOR ALBANY WATER BOARD
BIDS TO BE RECEIVED
Said proposals to be received by the Albany Water Board at a regular meeting to be held
Tuesday, April 22, 2025 at 12:00 P.M. A bid deposit is not required for this solicitation for bids.
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
BOARD OF CONTRACT AND SUPPLY
City of Albany, NY
Date Bids Received: April 8, 2025
Title: General Construction – Lincoln Park Learning Garden
Requesting Department: Engineering
Name of Bidder Security Amount of Bid
Peter Luizzi & Bros. Bid Bond Required See below
857 First Street
Watervliet, NY 12189
Wm. J. Keller and Sons Bid Bond Required See below
1435 route 9
Castleton, NY 12033
Rifenburg Contracting Corp Bid Bond Required See below
1321 Defreest Drive
Troy, NY 12180
Peter Luizzi
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
Wm. J. Keller & Sons
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
Rifenburg
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
BOARD OF CONTRACT AND SUPPLY
City of Albany, NY
Date Bids Received: April 8, 2025
Title: Electrical – Lincoln Park Learning Garden
Requesting Department: Engineering
Name of Bidder Security Amount of Bid
Harold Clune Bid Bond Required Lump Sum Base Bid:
30 Prospect St $300,000.00
Ballston Spa, NY 12020 Contractor’s Base Bid:
$275,000.00
Allowance:$25,000.00
Alternate #1: $42,800.00
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
BOARD OF CONTRACT AND SUPPLY
City of Albany, NY
Date Bids Received: April 8, 2025
Title: Plumbing – Lincoln Park Learning Garden
Requesting Department: Engineering
Name of Bidder Security Amount of Bid
No Submissions
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
BOARD OF CONTRACT AND SUPPLY
City of Albany, NY
Date Bids Received: April 8, 2025
Title: City of Albany Manning Boulevard Street Improvement Project
Requesting Department: Engineering
Name of Bidder Security Amount of Bid
Peter Luizzi & Bros. Bid Bond Required Base Bid #1: $4,679,289.00
857 First Street Base Bid #2: $890,480.00
Watervliet, NY 12189 Total Base Bid: $5,569,769.00
New Castle Paving Bid Bond Required Base Bid #1: $4,622,286.00
One Madison Street Base Bid #2: $639,811.45
Troy, NY 12180 Total Base Bid: $5,262,097.45
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9343 the Albany Water Board approves Change Order 1 to the following named contract with
the following named contractor, approving the allowance usage with no impact on the contract
price or the contract completion date. The contract amount will remain $1,742,580.00. The
contract completion date remains July 31, 2025.
PROJECT TITLE: Academy Road Constructed Wetlands Project
CONTRACTOR: Peter Luizzi & Bros. Contracting, Inc.
AMOUNT OF INCREASE: $0.00
AMOUNT OF NEW CONTRACT: $1,742,580.00
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9343 the Albany Water Board approves Change Order 2 to the following named contract with
the following named contractor, approving the allowance usage with no impact on the contract
price or the contract completion date. The contract amount will remain $1,742,580.00. The
contract completion date remains July 31, 2025.
PROJECT TITLE: Academy Road Constructed Wetlands Project
CONTRACTOR: Peter Luizzi & Bros. Contracting, Inc.
AMOUNT OF INCREASE: $0.00
AMOUNT OF NEW CONTRACT: $1,742,580.00
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9140 the Albany Water Board approves Change Order 5G-22 to the following named contract
with the following named contractor. The contract completion date remains December 31, 2023.
PROJECT TITLE: Beaver Creek Clean River Project Phase 3/5 - General
CONTRACTOR: Wm. J. Keller & Sons Construction
AMOUNT OF INCREASE: $237,475.00
AMOUNT OF NEW CONTRACT: $36,018,639.82
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9146 the Albany Water Board approves Change Order 5H-08 to the following named contract
with the following named contractor. The contract completion date remains December 31, 2023.
PROJECT TITLE: Beaver Creek Clean River Project Phase 5 - HVAC
CONTRACTOR: DiGesare Mechanical, Inc.
AMOUNT OF INCREASE: $13,698.09
AMOUNT OF NEW CONTRACT: $1,018,595.76
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9369 the Albany Water Board approves Change Order AB-H-01 to the following named
contract with the following named contractor, updating the terms and conditions with no impact
on the contract price or the contract completion date. The contract amount will remain
$117,900.00. The contract completion date remains December 4, 2025.
PROJECT TITLE: Feura Bush WFP – Aeration Room Renovation - HVAC
CONTRACTOR: Gallo Construction Corp
AMOUNT OF INCREASE: $0.00
AMOUNT OF NEW CONTRACT: $117,900.00
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9376 the Albany Water Board approves Change Order LM-E-01 to the following named
contract with the following named contractor, updating the terms and conditions with no impact
on the contract price or the contract completion date. The contract amount will remain
$473,808.00. The contract completion date remains December 31, 2025.
PROJECT TITLE: Feura Bush WFP – Lime and Maintenance Building - Electrical
CONTRACTOR: Stilsing Electric, Inc.
AMOUNT OF INCREASE: $0.00
AMOUNT OF NEW CONTRACT: $473,808.00
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9378 the Albany Water Board approves Change Order LM-P-01 to the following named
contract with the following named contractor, updating the terms and conditions with no impact
on the contract price or the contract completion date. The contract amount will remain
$167,705.00. The contract completion date remains January 17, 2026.
PROJECT TITLE: Feura Bush WFP – Lime and Maintenance Building - Plumbing
CONTRACTOR: Eckert Mechanical, LLC
AMOUNT OF INCREASE: $0.00
AMOUNT OF NEW CONTRACT: $167,705.00
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9294 the Albany Water Board approves Change Order 1 to the following named contract with
the following named contractor, approving the allowance credit, reducing the contract amount to
$294,600.00 with no impact on the contract completion date. The new contract amount will be
$294,600.00. The contract completion date remains June 28, 2024.
PROJECT TITLE: UV Equipment Installation at Loudonville Reservoir
CONTRACTOR: Flach Industries, Inc.
AMOUNT OF CHANGE: (-$100,000.00)
AMOUNT OF NEW CONTRACT: $294,600.00
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9140 the Albany Water Board approves Change Order 5G-21 to the following named contract
with the following named contractor, approving the allowance credit, reducing the contract
amount by $84,610.00 with no impact on the contract completion date. The new contract amount
will be $35,781,164.82. The contract completion date remains December 31, 2023.
PROJECT TITLE: Beaver Creek Clean River Project Phase 3/5 - General
CONTRACTOR: Wm. J. Keller & Sons Construction
AMOUNT OF CHANGE: (-$84,610.00)
AMOUNT OF NEW CONTRACT: $35,781,164.82
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9140 the Albany Water Board approves Change Order 5G-23 to the following named contract
with the following named contractor. The contract completion date remains December 31, 2023.
PROJECT TITLE: Beaver Creek Clean River Project Phase 3/5 - General
CONTRACTOR: Wm. J. Keller & Sons Construction
AMOUNT OF INCREASE: $16,892.00
AMOUNT OF NEW CONTRACT: $36,035,531.82
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9368 the Albany Water Board approves Change Order AB-E-01 to the following named
contract with the following named contractor, updating the terms and conditions with no impact
on the contract price or the contract completion date. The contract amount will remain
$75,357.00. The contract completion date remains December 6, 2025.
PROJECT TITLE: Feura Bush WFP – Aeration Room Renovation - Electric
CONTRACTOR: Stilsing Electric, Inc.
AMOUNT OF INCREASE: $0.00
AMOUNT OF NEW CONTRACT: $75,357.00
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9432 the Albany Water Board approves Change Order E-01 to the following named contract
with the following named contractor. There is no change to the original contract timeframe of 365
days.
PROJECT TITLE: Feura Bush Water Filtration Plant Upgrades
CONTRACTOR: Stilsing Electric, Inc.
AMOUNT OF INCREASE: $15,498.00
AMOUNT OF NEW CONTRACT: $112,498.00
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9379 the Albany Water Board approves Change Order LM-H-01 to the following named
contract with the following named contractor, updating the terms and conditions with no impact
on the contract price or the contract completion date. The contract amount will remain
$93,100.00. The contract completion date remains January 8, 2026.
PROJECT TITLE: Feura Bush WFP – Lime and Maintenance Building - HVAC
CONTRACTOR: T. McElligott, Inc.
AMOUNT OF INCREASE: $0.00
AMOUNT OF NEW CONTRACT: $93,100.00
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The following resolution was offered on behalf of the Albany Water Board:
RESOLVED, that in accordance with the existing contract provisions of City Contract
No. 9367 the Albany Water Board approves Change Order AB-G-02 to the following named
contract with the following named contractor, updating allowance descriptions and the terms and
conditions with no impact on the contract price or the contract completion date. The contract
amount will remain $2,834,780.00. The contract completion date remains October 23, 2025.
PROJECT TITLE: Feura Bush WFP – Aeration Room Renovation - General
CONTRACTOR: Gallo Construction Corp
AMOUNT OF INCREASE: $0.00
AMOUNT OF NEW CONTRACT: $2,834,780.00
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The Following was offered by the Department of Recreation:
RESOLVED, that the Secretary be authorized and directed to extend the bid opening for the
following:
Albany South Community Center - General Construction
BIDS TO BE RECEIVED
Said proposals to be received by the Board by 12pm on 4/22/25. Said proposals to be opened by
the Board at a regular meeting to be held on 4/22/25 at 1:30 pm and that each bidder be required
to present with the bid a deposit in the amount equal to 5% of the total bid in a bid bond or
certified check, conditioned upon entering into the contract if the bid is accepted and for the
performance of the same.
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The Following was offered by the Department of Recreation:
RESOLVED, that the Secretary be authorized and directed to extend the bid opening for the
following:
Albany South Community Center - Plumbing
BIDS TO BE RECEIVED
Said proposals to be received by the Board by 12pm on 4/22025. Said proposals to be opened by
the Board at a regular meeting to be held on 4/22/25 at 1:30 pm and that each bidder be required
to present with the bid a deposit in the amount equal to 5% of the total bid in a bid bond or
certified check, conditioned upon entering into the contract if the bid is accepted and for the
performance of the same.
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The Following was offered by the Department of Recreation:
RESOLVED, that the Secretary be authorized and directed to extend the bid opening for the
following:
Albany South Community Center - Electrical
BIDS TO BE RECEIVED
Said proposals to be received by the Board by 12pm on 4/22/25. Said proposals to be opened by
the Board at a regular meeting to be held on 4/22/25 at 1:30 pm and that each bidder be required
to present with the bid a deposit in the amount equal to 5% of the total bid in a bid bond or
certified check, conditioned upon entering into the contract if the bid is accepted and for the
performance of the same.
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0
Tuesday, April 8, 2025
The Following was offered by the Department of Recreation:
RESOLVED, that the Secretary be authorized and directed to extend the bid opening for the
following:
Albany South Community Center – Mechanical
BIDS TO BE RECEIVED
Said proposals to be received by the Board by 12pm on 4/22/25. Said proposals to be opened by
the Board at a regular meeting to be held on 4/22/25 at 1:30 pm and that each bidder be required
to present with the bid a deposit in the amount equal to 5% of the total bid in a bid bond or
certified check, conditioned upon entering into the contract if the bid is accepted and for the
performance of the same.
Adopted by the following vote:
Stetson
Shahinfar
Magee
Zeoli
Affirmative 5 Negative 0