Planning Commission
Regular MeetingAlta, UT · June 2, 2022
Minutes
MINUTES
ALTA PLANNING COMMISSION MEETING
Thursday, June 2, 2022, 3:00 PM
*Meeting held virtually
Alta Community Center, 10351 E. Highway 210, Alta, Utah
PRESENT: John Nepstad, Chair
Rob Voye
Jeff Niermeyer
David Abraham
Maren Askins
Roger Bourke, Town of Alta Mayor (ex-officio)
STAFF PRESENT: John Guldner, Town Administrator
Chris Cawley, Assistant Town Administrator
Polly Mclean, Legal Counsel
OTHERS: Dave Richards, Alta Ski Area Avalanche Department Director
Mike Maughan, Alta Ski Area General Manager
1. INTRODUCTION, DETERMINATION LETTER READING, AND WELCOME
FROM THE CHAIR
Planning Commission Chair Jon Nepstad opened the meeting at 3:00 PM. Mr. Nepstad described
that the meeting was not taking place at the usual time for monthly Alta Planning Commission
meetings.
2. DISCUSSION AND POSSIBLE ACTION: CONDITIONAL USE PERMIT
APPLICATION FROM ALTA SKI AREA FOR THE INSTALLATION OF
WYSSEN TOWER REMOTE CONTROL AVALANCHE STRUCTURES ON
MOUNT BALDY. MIKE MAUGHAN, DAVE RICHARDS
Planning Commission Chair Jon Nepstad introduced Dave Richards, Alta Ski Area Avalanche
Office Director. Mr. Richards thanked the planning commission for convening a meeting to
consider issuing a conditional use permit for Alta Ski Area to install Wyssen Tower remote
avalanche control systems (RACS) on private lands on Mount Baldy. Mr. Richards stated that the
purpose of the project was to maintain and improve skier safety and to provide an alternative to
the use of artillery to conduct avalanche mitigation at Alta Ski Area. Mr. Richards described that
artillery has been relied upon for avalanche mitigation in Alta since the 1950s, but that the US
Army is requiring Alta Ski Area and other civilian artillery users to discontinue using artillery by
2025.
Mr. Richards acknowledged that Alta Ski Area had studied various alternatives to artillery,
including a small aerial tramway that would deliver avalanche workers and skiers to the top of
Mount Baldy, and the installation of a 22-unit RACS array. Mr. Richards described details of the
Alta Planning Commission Meeting Minutes
June 2, 2022 1
Wyssen Tower proposal: 9 towers would be installed on private lands, and 2 would be installed on
US Forest Service (USFS) lands.
Mr. Richards opined that impacts from installation of the Wyssen Towers would be limited to
noise, and added that current artillery-based avalanche mitigation system was possibly louder than
the Wyssen Towers would end up being. Mr. Richards responded to several components of the
conditional use permit application process, including that various other agencies have provided
approvals under their respective authorities. The Bureau of Alcohol, Tobacco, and Firearms (ATF)
approved 9 Wyssen Towers, but may be asked to approve an additional two towers in the future.
Mr. Nepstad asked Mr. Richards to describe how many artillery targets would be covered by the
proposed Wyssen Towers. Mr. Richards described that 11 Wyssen Towers could affect the
avalanche starting zones associated with 20 individual artillery targets. Mr. Richards described
that Wyssen Towers deliver a significantly larger explosive payload than other methods, which is
part of what would allow Alta Ski Area to reduce target areas on Mt. Baldy. Mr. Nepstad asked
Mr. Richards to describe how Wyssen Towers are maintained and re-charged mid-season, and Mr.
Richards described that Wyssen Tower explosive magazines are picked up by helicopters and
flown to the base area to be restocked with explosives.
Mr. Nepstad asked Mr. Richards whether the Wyssen Towers would disrupt views of the Mount
Baldy Ridgeline. Mr. Richards said that the Wyssen Towers would not disrupt ridgeline views
except from isolated locations such as from directly underneath Mount Baldy in the Ballroom area.
Planning Commission Member Jeff Niermeyer referred to the USFS approval memo for the two
Wyssen Towers proposed on USFS lands, and asked Mr. Richards whether the Wyssen Towers
would foreclose the potential for Alta Ski Area to install an aerial tramway to the top of Mount
Baldy. Mr. Richards responded that since he did not speak for the Alta Ski Area Board of Directors,
he could not definitively confirm that the Wyssen Towers would preclude a tramway to Mount
Baldy. However, Mr. Richards opined that as the Alta Ski Area Avalanche Department Director,
installing Wyssen Towers would render a tramway to Mount Baldy unnecessary. Alta Ski Area
General Manager Mike Maughan described that Alta Ski Area would observe the efficacy of the
Wyssen Towers and may conclude in the future that further mitigation methods, such as an aerial
tramway, would not be necessary.
Mr. Niermeyer asked Mr. Richards to clarify how many towers the ski area planned to install in
2022. Mr. Richards confirmed that Alta Ski Area would install 5 towers east of the summit of
Mount Baldy in 2022, 4 towers on the west side of Baldy in 2023, and would consider whether to
install an additional 2 towers later in the future.
Mr. Niermeyer asked Mr. Richards whether Alta Ski Area had considered refinishing the towers
to cause them to blend in to the landscape. Mr. Richards described that there are products available
to dull the reflective nature of the galvanized steel surface of the towers.
Mr. Niermeyer asked Mr. Richards whether the ATF approval covered all the towers proposed for
installation on private land, and Mr. Richards confirmed that this was the case.
Alta Planning Commission Meeting Minutes
June 2, 2022 2
Mr. Maughan asked Mr. Richards to describe the phasing of various RACS installation projects in
Little Cottonwood Canyon. Mr. Richards described that with the US Army’s decision to end
civilian use of military artillery, numerous avalanche mitigation operations were seeking to
develop alternatives to artillery prior to the US Army’s deadline. Hence, Snowbird, Alta, and the
Utah Department of Transportation were planning to tightly sequence respective projects during
2022, 2023, and 2024 so that each entity will be prepared when the US Army deadline to stop
using artillery came to pass.
Planning Commission Member Dave Abraham asked Mr. Richards to address the map included in
the meeting exhibits, and Mr. Richards described which of the Wyssen Tower installations
indicated on the map it was actively pursuing, and which were tentative. Mr. Abraham asked
whether Alta Ski Area would install tower extensions described in the Wyssen Tower specification
sheets, and Mr. Richards stated that the ski area did not plan to install tower extensions.
Planning Commission Member Maren Askins and Mr. Richards discussed the location of the
tentative Wyssen Tower installations. Ms. Askins asked Mr. Richards whether the Wyssen Towers
would be less impactful on the landscape or the environment than using artillery or other
alternatives. Mr. Richards opined that the Wyssen Towers would be less impactful than a tramway
and observed that the explosives deployed by the Wyssen Towers would leave a “powder burn”
of black or brown explosive residue on the snow surface. Mr. Neirmeyer asked whether the towers
would mitigate the problem of unexploded ordinance being left on the slope, and Mr. Nepstad
pointed out that artillery rounds exploded into fragments of metal that remained on the landscape.
Mr. Richards stated that there would be much less unexploded ordinance associated with the
Wyssen Towers,
Mr. Niermeyer asked Mr. Richards how much Wyssen Towers cost, and Mr. Richards described
that towers cost $220,000 installed, each. Mr. Richards opined that it was well worth the cost of
installation given how much safer Wyssen Towers are for avalanche workers and the public than
artillery.
Mayor Roger Bourke asked Mr. Richards why Alta Ski Area was breaking the installation up into
two phases, and how Alta Ski Area determined where to install the towers on Mt. Baldy. Mr.
Richards described that the Wyssen Tower installer was working with Alta and Snowbird, and that
Alta and Snowbird were on the same timeline to respond to the US Army’s order to stop using
artillery. Additionally, the ski area preferred to break up the total expense associated with the
Wyssen Tower project over two years. Mr. Richards described the ski area’s process to determine
the most effective locations to install Wyssen Towers, which involved the use of ArcGIS-based
software to study the terrain on Mount Baldy, in-person evaluation of the proposed installation
sites, and historical knowledge of avalanche activity on Mount Baldy.
Mr. Nepstad recommended that the planning commission approve Alta Ski Area’s application for
a conditional use permit to install Wyssen Towers on Mount Baldy. Mr. Niermeyer introduced
a motion to approve granting a conditional use permit for the eight Wyssen Towers on Alta
Ski Lifts’ private property, as requested in their letter dated May 23 rd, 2022, subject to the
following conditions: that all requirements in the USFS decision letter dated January 2022,
and all requirements in the ATF approval letter dated March 3rd, 2021 be incorporated as
Alta Planning Commission Meeting Minutes
June 2, 2022 3
conditions in the conditional use permit granted by the Town of Alta, also including the
foundation plans as provided by the tower manufacturer. Mr. Nepstad asked Mr. Niermeyer
to clarify how many towers he intended to refer to in his motion, and Mr. Niermeyer stated he was
referring to 8 towers. Mr. Niermeyer opined that he hoped the Wyssen Towers would eliminate
the need to install a tram to Mount Baldy in the future. Mr. Abraham seconded Mr. Niemeyer’s
motion, and the motion was passed with unanimous consent of the planning commission.
Mr. Nepstad suggested that the planning commission should seek an update on the effectiveness
of the Wyssen Towers and possibly take an in-person tour to observe the Towers. Assistant Town
Administrator Chris Cawley asked Mr. Niermeyer to forward a transcript of his motion for
inclusion in the meeting minutes.
Mr. Guldner thanked the planning commission for working through the ski area’s conditional use
permit application, and thanked Mr. Richards and Mr. Maughan for their presentation to the
commission. Mr. Guldner described that after the commission’s approval of a conditional use
permit, the Alta Town Council would need to grant a variance to Alta Ski Area for construction
on slopes over 30% in steepness.
Mayor Bourke asked Mr. Richards when Alta Ski Area planned to begin construction, and Mr.
Richards reported that the projected start date of June 20 had been postponed due to slower-than-
anticipated snowmelt.
3. DATE OF NEXT MEETING
Planning Commission Chair Jon Nepstad asked whether the plan to convene a social event was
still in the works. Mr. Bourke opined that he’d like to hold such an event, although Mr. Nepstad
reported he would be out of town on the regular date for a June planning commission meeting.
Alta Ski Area General Manager Mike Maughan asked Mr. Nepstad whether the commission had
questions about Alta Ski Area summer plans, and Mr. Nepstad thanked Mr. Maughan for reporting
to the commission in detail at the commission’s April 26 meeting. Mayor Bourke asked Mr.
Maughan about the project to replace the Sunnyside Chairlift. Mr. Maughan reported that weather
had delayed removal of the existing lift, and supply chain issues were creating concerns about
whether Alta Ski Area would receive all the parts of the new lift in time for ski season. Mr.
Maughan described that the ski area may need to run the Albion Lift at the beginning of the season
if work on the new left was ongoing at that time. Mr. Maughan described that the ski area would
begin a master plan update focused on responding to climate change and managing demand for
access to Alta. Mr. Maughan added the process could address UDOT’s imminent decision to
pursue a major transportation project through the Little Cottonwood Canyon Environmental
Impact Statement.
Alta Ski Area Avalanche Department Director Dave Richards excused himself from the meeting
and thanked the planning commission for taking action to grant a conditional use permit.
4. MOTION TO ADJOURN
Alta Planning Commission Meeting Minutes
June 2, 2022 4
Planning Commission Member Jeff Niermeyer moved to adjourn the meeting. Planning
Commission Member Maren Askins seconded the motion, and the motion was carried with
unanimous consent of the commission.
Minutes Approved on July 18, 2023.
_________________________
Chris Cawley, Interim Town Manager
Alta Planning Commission Meeting Minutes
June 2, 2022 5
Agenda
ALTA PLANNING COMMISSION
Thursday June 2, 2022
1:00PM
THIS WILL BE A VIRTUAL MEETING
This meeting will be an electronic meeting without an anchor location pursuant to Planning
Commission Chair Jon Nepstad’s May 27th, 2022, determination:
https://townofalta.com/wp-content/uploads/2022/05/2022-5-26-Determination-Letter-Remote-
Location-.pdf
Attendees can watch the meeting on YouTube via a link that will be posted on the Town’s
website at the start of the meeting here:
https://townofalta.com/town-government/planning-commission/agendas-minutes/
1) Introduction, electronic meeting determination, and welcome from the
Chair.
2) Discussion and possible action: Conditional use permit application from
Alta Ski Area for the installation of Wyssen Tower Remote Control
Avalanche Structures on Mount Baldy. Mike Maughan, Dave Richards.
3) Motion to adjourn.
Alta Town Council members are invited to the meeting; as such there may be a quorum of the Town Council.
Reasonable accommodations (including auxiliary communicative aids and services) for individuals with disabilities may be provided
upon receipt of a request with three (3) working days’ notice. For assistance, please call the Alta Town Office at 801.363.5105
Get email alerts for Alta
A daily email when new agendas and minutes are posted.