Anderson Redevelopment Commission
Regular MeetingAnderson, IN · May 8, 2014
Minutes
MINUTES
ANDERSON REDEVELOPMENT COMMISSION
May 8, 2014
INVOICES
Mr. Sulc moved to approve the invoices as
PUBLIC MEETING presented. Mr. Royer seconded. Motion passed
4:30 p.m. unanimously; 3 yes, 0 no.
Conference Room #1
120 East 8th Street BUSINESS
Anderson, IN 46016
Jackson Street Streetscape and 14th and Main
MEMBERS PRESENT Streets Historic Beautification Project
Carolyn Scott, Secretary / Treasurer Mr. Winkler stated a study was prepared for the
Joe Royer, Member project. The fountain will be located at 14th & Main
Kevin Sulc, Member Streets. A Redevelopment Plan for downtown was
approved for two projects in 2004 for the historic
MEMBERS ABSENT district for streetscapes, sidewalks, signage, curbs,
Mike Farmer, President and gutter repair and in addition there was the
Justin Puckett, Vice President straightening of the one-way / two-way street
Roger Clark, Non-Voting Member issues. Between the two projects there is
$1,750,000 in the plan. The Jackson Street project
will cost approximately $1,750,000. The fountain
STAFF PRESENT
will cost $20,000. Jackson Street is the main
Greg Winkler, Director
corridor off Dr. Martin Luther King Jr. Blvd. and it is
Michael Frischkorn, Deputy Director
the dividing line between the historic districts. All
Ann Marie Bauer, Attorney
of the area that is being considered for
April Phillips, Financial Specialist
improvements from 8th to 14th Streets is in the
Gary McKinney, Environmental Specialist
historic districts with the exception of two and half
Karen Pettigrew, Small Business Specialist
blocks. The fountain would anchor the end near
the Train Depot. At this point, very little has been
OTHERS PRESENT
done with Downtown in regards to redevelopment
Mike Spyers, City Engineer
projects. The recommendation of the Economic
Pete Heuer, Board of Works Chairman
Development staff would be to go ahead and
Jason Fenwick, City Controller
initiate the projects. There will need to be some
Ken de la Bastide, Herald-Bulletin
modification, but not much.
ROLL CALL AND DECLARATION OF Mr. Spyers explained the fountain will actually cost
QUORUM approximately $88,000 and $20,000 of utility work
Mrs. Scott called the meeting to order at 4:30 p.m. will be donated by the City.
and declared a quorum with three (3) members
present. Mr. Winkler stated the total cost will be $1,840,000.
The plan estimated the cost at $1,750,000;
MINUTES however, to do the project another $90,000 is
Mr. Royer moved to approve the April 7, 2014, estimated to be needed.
minutes as submitted. Mr. Royer seconded. Motion
passed unanimously; 3 yes, 0 no. Mr. Heuer mentioned that all the ADA features will
be updated along the Jackson Street corridor as
part of the project.
Mr. Royer asked how this would be paid.
Mr. Royer moved to proceed with the 14th & Main
Mr. Winkler answered TIF funds. Streets historic beautification project. Mr. Sulc
seconded. Motion passed unanimously; 3 yes, 0
Mr. Sulc asked if the total cost for both projects no.
was $1,800,000.
Mr. Winkler stated the streetscape is estimated at Sesco Agreement: Environmental
$1,750,000 and the fountain is estimated to be Investigation Edgewood Plaza (Dry Cleaners)
$88,000. Mr. McKinney sent the Commission members the
proposal via email. He explained that this is what is
Mr. Sulc asked about the $20,000 donation for the required to get closure on the site and receive a
fountain? “No Further Action” letter from IDEM. His
recommendation is to move forward with this.
Mr. Spyers explained that the City will be donating
in-kind utility work. Mr. Royer moved to approve the Sesco Agreement.
Mr. Sulc seconded. Motion passed unanimously; 3
Mr. Sulc asked if the City would be donating in-kind yes, 0 no.
work for Jackson Street.
Patriot Engineering Contract (Parking
Mr. Spyers stated the design and construction Garage)
inspection will be done in house. The fountain will Mr. Spyers explained this is a contract to do the
be constructed where the former Antique Mall was testing of the concrete work being completed by
located. MK Betts for the parking garage. The estimate
from the consultants is approximately $8,000-
Mr. Sulc thought the project was overdue. The City $10,000 worth of testing over a two to three year
addressed Meridian Street several years ago, but period.
then activity went dormant. It is time to address
Jackson Street. The Train Depot /Ballet Theater is Mr. Sulc stated he saw the hourly rate in the
a historical site. When the old buildings were torn contract, but not a total. Is this the typical way of
down, it changed the whole visual for the area. doing estimates for this type of work.
Highlighting this will add to the aesthetics of the
area and could potentially be a prop for future Mr. Spyers answered yes.
development. The only thing the Commission and
City can do are projects like this. Development Mr. Sulc stated the $8,000-10,000 estimate is based
cannot be forced, but the infrastructure and area on the amount of time necessary for the testing. Is
can be upgraded. There is a definite need in this testing for the entire garage or just the
upgrading and replacing the sidewalks and lighting. foundation? Will an analysis of the condition of the
This has been a part of the plan since 2004. concrete be given?
Mrs. Bauer explained the projects have already Mr. Royer asked if cost was part of the overall
been added to the plan so just a motion to proceed estimate.
would be needed.
Mr. Sulc asked if Mr. Spyers
Mrs. Scott asked Mr. Spyers if the curb from 8th Mr. Spyers answered that the cost was part of the
Street turning south onto Meridian Street could be overall estimate. The testing is for the new concrete
addressed. This has nothing to do with this project, to ensure it is up to standards. Testing is needed
but it is a hazard. for these types of projects. MK Betts is planning on
starting work on Monday. They are interested in
A minor discussion was held on this issue. completing the project over a two year period as
opposed to a three year period if this is agreeable
Mr. Sulc moved to proceed with the Jackson Street to the Commission.
Streetscape project. Mr. Royer seconded. Motion
passed unanimously; 3 yes, 0 no.
Anderson Redevelopment Commission: May 8, 2014 Page 2
Mr. Winkler asked if it would reduce contractor Avenue. They are still working on access
costs and provide a bit of a savings. agreements and easements. There may be a
couple of properties that they are unable to get
Mr. Spyers answered yes. agreements on, but if that happens, they will work
around it.
Mr. Sulc moved to approve the contract with Patriot
Engineering. Mr. Royer seconded. Motion passed
unanimously; 3 yes, 0 no.
Hy-Tech Machining
UPDATES Mr. Winkler mentioned he is continuing
conversations with the property owner.
60th Street
Mr. Spyers stated he met with Stoops. They Scatterfield Park Improvements
seemed agreeable to the design of the roadway Mr. Spyers stated Municipal Light and Power should
through their property. There are three other begin putting their lines through and then remove
properties that will need to be acquired. The the existing poles within the next couple of weeks.
appraisals are being completed. Rayl Engineering The concern is getting the traffic signalize
should have everything ready to go to bid by mid- energized.
June for the storm and sanitary sewer portion of
the project. Also, in June there will be a contract 67TH Street
for the redesign of the road through the Stoops Mr. Spyers explained the City offered the
property for Rayl Engineering. He is currently opportunity for a Public Hearing. The consultants
talking with Ivy Tech for them to run the storm stated there were no comments or requests for
sewer up to their property and ways to “de-water” future public hearings. The environmental packet
their property. If it is cost efficient then we would will be submitted to INDOT and to the Federal
like to have them run the storm sewer to the Highway Administration (FTA) for their approval
property. within the next 30 days. After approval, they will
begin the purchase of right of way.
EPA: GM Properties
Mr. McKinney explained the sampling has been Parking Garage
completed and sent to USEPA. USEPA has all the Mr. Spyers stated that MK Betts requested that the
information they need to make a decision as to project be completed within two years as opposed
what they will propose as a final clean-up measure to three years as originally planned. This may save
for the property. approximately $20,000-$30,000. This would bring
the total project cost to about $800,000.
EDA Project
Mr. Spyers stated the contractors are burying the Mr. Winkler asked for an estimate.
lime to stabilize the roadway. They are still waiting
on AT&T to move lines on 29th Street. The traffic MISCELLANEOUS
light has been temporarily reset. He is working with
the contractors to get electricity over to it because
Municipal Light and Power is getting ready to pull ADJOURNMENT
their lines. Mr. Sulc moved to adjourn. Mr. Royer seconded.
Meeting adjourned at 5:00 p.m.
Greater Edgewood Plaza Redevelopment
Mr. McKinney stated all the asphalt has been
removed from the parking lot. There is a meeting
Monday to discuss how to proceed with the fill dirt
and such items as grass, wild flowers, etc. The
former Taco Bell, which was one of the three
buildings slated for demolition, has been has been
razed. The sidewalk project is continuing. The goal
is install a sidewalk from Brentwood Drive to Raible
Anderson Redevelopment Commission: May 8, 2014 Page 3
Agenda
AGENDA
ANDERSON REDEVELOPMENT COMMISSION
May 8, 2014
PUBLIC MEETING ROLL CALL & DECLARATION OF
4:30 p.m. QUOROM
Conference Room #1
120 East 8th Street MINUTES
Anderson, IN 46016 April 7, 2014
MEMBERS
Mike Farmer, President INVOICES
Justin Puckett, Vice President
Carolyn Scott, Secretary / Treasurer BUSINESS
Joe Royer, Member Jackson Street Streetscape and 14th &
Kevin Sulc, Member Main Streets Historic Beautification
Roger Clark, Board of Public Works Project
Representative (non-voting)
Sesco Agreement: Environmental
STAFF Investigation Edgewood Plaza (former dry
Ann Marie Bauer, Attorney cleaner)
Greg Winkler, Director of Corporate Sales
and Economic Development Patriot Engineering Contract (Parking
Garage)
Michael Frischkorn, Deputy Director
April Phillips, Specialist
UPDATES
60th Street
EPA: GM Properties
EDA Project
Greater Edgewood Plaza Redevelopment
Hy-Tech Machining
Scatterfield Park Improvements
67th Street
Parking Garage
MISCELLANEOUS
ADJOURNMENT