PUBLIC MEETING Mr. Puckett moved to approve the July 5, 2016,
4:30 p.m. minutes as received. Mrs. Scott seconded.
ED Conference Room #1 Motion passed unanimously; 3 yes, 0 no.
120 East 8th Street
Anderson, IN 46016 BUSINESS
MEMBERS PRESENT INDOT Reimbursement Agreement
Kevin Sulc, President Mr. Spyers explained this is for the paving
Justin Puckett, Secretary work on Scatterfield Road associated with the
Carolyn Scott, Member Purdue / 27th Street project. The Commission
would pay Milestone Construction for the work
MEMBERS ABSENT and then be reimbursed by INDOT. The total
Joe Royer, Vice President amount to be reimbursed is $160,000.
Michael Collette, Member
Mr. Sulc mentioned the agreement was sent to
STAFF PRESENT the members via email. He asked if the Board
Ann Marie Bauer, Attorney of Public Works (BPW) approved the
Greg Winkler, Director agreement.
Michael Frischkorn, Deputy Director
April Phillips, Financial Specialist Mr. Spyers answered yes.
Gary McKinney, Environmental/Brownfield
Specialist Mr. Puckett moved to approve the INDOT
agreement. Mrs. Scott seconded. Motion
OTHERS PRESENT passed unanimously; 3 yes, 0 no.
Abby Gerhart, City Controller’s Office
Ken da la Bastide, Herald-Bulletin CSX Agreement: Scatterfield West
Mike Spyers, City Engineer Mr. Spyers explained this is for the work to be
Thomas Tijerina, EPIC Initiatives completed at the grade crossing for the
Marc Scharnowkse Purdue/27th Street project. The agreement is
Bill and Pam Farmen in the amount of $48,959 of which a deposit of
Floyd Burroughs $9,350 has already been paid towards the PE
portion of it. The amount due is $39,609.
ROLL CALL AND DECLARATION OF
QUORUM Mr. Sulc asked if the Board of Public Works
Mr. Sulc called the meeting to order at (BPW) approved the agreement.
4:30 p.m. and declared a quorum with three (3)
members present. Mr. Spyers answered yes.
MINUTES Mrs. Scott moved to approve the INDOT
agreement. Mr. Puckett seconded. Motion
passed unanimously; 3 yes, 0 no.
then the building could be utilized as part of
FINANCIALS the agreement.
Mr. Puckett moved to approve the financial
reports as presented. Mrs. Scott seconded. Mrs. Bauer stated the RFP process must be
Motion passed unanimously; 3 yes, 0 no. followed.
A discussion was held regarding the RFP
INVOICES process.
Mrs. Scott moved to approve the invoices as
submitted. Mr. Puckett seconded. Motion A discussion was held on the area within the
passed unanimously; 3 yes, 0 no. TIF district and possible expansion.
UPDATES Mr. Scharnowkse asked if there was a strategic
plan for the west side area.
EPA: GM Properties
Mr. McKinney stated the proposals have been Mr. Winkler answered yes, mainly for the
received and reviewed. Negotiations have Nichol and Raible Avenue area.
started with the lowest bidder. The hope is to
begin construction on the ERH system by Purdue/Flagship Makers Space Facility (P3)
October. Work will begin within the next few Mr. Winkler stated the project is on schedule.
weeks to remove an underground storage tank.
Scatterfield West Redevelopment
Greater Edgewood Plaza Redevelopment There was no additional information to report.
Mr. McKinney explained UST removal and
excavation of contaminated soil has been Italpollina
completed at the former Baxter Pest Control Mr. Winkler stated groundbreaking will be
property. The final report has not yet been take place on August 10, 2016, at 2:00 p.m.
received. Monitor well sampling will be need
to be conducted for a period of time. NTN
Mr. Winkler thought permanent electrification
Mr. Winkler mentioned there were two took place today. There is another opportunity
opportunities for redevelopment in the area for associated with NTN to be discussed in the
commercial and residential use. The near future.
commercial entity would be able to do the
acquisition, clean-up, demolition, and Mr. Spyers stated water and sewer has been
construction in the area around Nichol and installed up to NTN, but has not been
Raible Avenues. There is interest in using the connected yet. The design-build for the booster
southern two-thirds of the property the station should take place the first part of
Commission owns for residential, leaving the October.
northern one-third closer to Nichol Avenue for
future commercial uses. Parking Garage
Mr. Sulc stated that nobody from the BPW was
Mrs. Scott asked about the interim use of in attendance to give a report. He requested
Baxter Pest Control. Mrs. Bauer mention to the BPW that the
Commission is still waiting on a report.
Mrs. Bauer explained that it could not be done
without going through the entire RFP process. 67th Street
Mr. Spyers stated he is waiting on the final
Mr. Winkler asked if Mr. Tijerina could be billing from the consultant and the utility
hired as a consultant for a nominal fee and reimbursement.
Anderson Redevelopment Commission: August 2, 2016 Page 2
MISCELLANEOUS
Mrs. Scott wanted to verify that the Wigwam
group asked for money and the Commission
declined.
Mr. Sulc explained he offered the Wigwam
group the opportunity to present a proposal to
the Commission and if they wanted to go
further than they needed to work with the
administration. Nothing has been brought to
the Commission from the Mayor or staff.
ADJOURNMENT
Mr. Puckett moved to adjourn the meeting.
Meeting adjourned at 5:02 p.m.
Anderson Redevelopment Commission: August 2, 2016 Page 3
Agenda
AGENDA
ANDERSON REDEVELOPMENT COMMISSION
August 2, 2016
ROLL CALL AND DECLARATION OF
PUBLIC MEETING QUORUM
4:30 p.m.
Conference Room #1 MINUTES
120 East 8th Street July 5, 2016
Anderson, IN 46016
BUSINESS
MEMBERS INDOT Reimbursement Agreement
Kevin Sulc, President
Joe Royer, Vice President CSX Agreement: Scatterfield West
Justin Puckett, Secretary
Michael Collette, Member FINANCIALS
Carolyn Scott, Member
INVOICES
STAFF
Ann Marie Bauer, Attorney UPDATES
Greg Winkler, Economic Development Director EPA: GM Properties
Michael Frischkorn, Deputy Director Greater Edgewood Plaza Redevelopment
April Phillips, Specialist Purdue/Flagship Makers Space Facility
Scatterfield West Redevelopment
Gary McKinney, Environmental/Brownfield Italpollina
Specialist NTN
Parking Garage
67th Street
MISCELLANEOUS
ADJOURNMENT