Airport Authority
Regular MeetingAthens-Clarke County, GA · April 25, 2023
Minutes
Athens Ben Epps Airport Authority Meeting
April 25, 2023, 3:00PM
Minutes
Live Stream on ACCGOV YouTube Channel
https://youtube.com/live/87dV5ClG1Wc?feature=share
In attendance: Mike Mathews, Grant Tribble, Diane Napier, Keith Sanders, Jeff Benjamin, Craig Westwood, Davin Welter,
Niki Jones, Andrew Bolin (RS&H)
Apologies: David Asman
Note-taker: Davin Welter
1) Chair Update and announcements: Mr. Tribble welcomed the participants and previewed the agenda.
2) March Meeting Minutes: The March minutes were approved as submitted, per unanimous vote. Mr.
Sanders moved and Mr. Benjamin seconded to approve the minutes.
3) Airport Manager Reports
a) Financial & Operations Report: Mr. Mathews reported that our financials continue to look good.
Corporate traffic has been strong and other revenues and expenses have been in line for the month.
Coca-Cola has taken over our vending services and they are providing free water for now for our
customers with a cooler in the pilot’s lounge and by the door going out to the flight line.
b) Capital Improvement Project Updates: Mr. Mathews reported that the 2-20 Runway project began
on April 10. He said that E.R. Snell is working strong on the lighting and underdrain components
of the project. Wet dirt has been an issue and needs to dry out before they can put it in the safety
area. Unfortunately, an old sewer line was hit and that has been an issue but Mr. Mathews is
working with ACC Public Utilities to resolve the issue. Lastly, RS&H is redesigning and rebidding
the Taxiway Alpha project. A work authorization is into the Mayor and Commission for that work
and they will vote on it on May 2. Mr. Mathews is hoping that it will take 3 months for the redesign
and for the bidding. Mr. Welter is working on quotes for the self-serve unit. Mr. Mathews reported
that Titan will share the cost on the self-serve project. GDOT came to us with some funding for a
fencing project. AHN will have to pay 25% of the project. GDOT has $495,000 and the total project
will be $660,000. He reported that he has an agenda item for this project and the Mayor and
Commission will vote on it on the May 2 meeting. Mr. Mathews wants to give priority to the area
where we took out the farm fencing for the ROFA project. This will be phase 1 of the fencing
projects. Mr. Tribble asked about the new control tower. Mr. Mathews said that the planning
meeting for the new tower went well. The virtual view started at 60 ft and then 80 ft and then 120
ft. It is important to be able to see over all the buildings and see all portions of both runways. The
most likely spot for the location is next to the parking lot. Mr. Mathews said that we need to offer
something that will work because we need the tower. He said that in 6 months we should know
where it will be located. Mr. Mathews reported that AHN will need to do environmental assessment
and will need to tear down Sonny’s hanger. Construction for the tower will start in 2024. Mr.
Sanders asked if he had any concerns about the tower project. Mr. Mathews responded that he is
concerned about taking away future parking but that it will be easy to build a parking garage. Mr.
Westwood said he was surprised that the south side of the airport location was disregarded. Mr.
Mathews said that the VOR was a concern as was the access to the tower in that location.
c) Marketing & Outreach: Mr. Mathews could not think of anything major at this time during March.
4) Old Business
a) Strategic Plan Update: Mr. Welter reported about the changes to the strategic plan previously
approved by the Authority. The changes are primarily minor and provides more clear language
for the general public. Mr. Tribble explained the process that essentially took what the authority
approved and sent it to the ACC Manager’s Office. They added some language and added a
sixth goal. Dr. Napier asked about the 3 “To Be Determined” classifications in Goal 4. Mr.
Welter said that he would update those three. Mr. Westwood moved and Dr. Napier seconded to
approve the strategic plan as presented with the update of the three TBDs in Goal 4. The plan was
unanimously approved.
5) New Business
a) None
6) Standing Committees: Issues & Updates
a) Business/Finance: Mr. Sanders had no report.
b) Operating: Mr. Asman was not present and had no report.
c) Air Service Development/Marketing: Mr. Mathews reported that Mead and Hunt has gotten the
latest data that they will use to update the market study and because of that it will be another couple
of months before that study is complete. Once this is complete, Mr. Mathews will present the
market study to the Authority and to the Air Services Development Committee. Mr. Westwood
asked how far back the data will go. Mr. Mathews responded that he did not think that the data will
include the COVID years.
7) Other Business:
a) Mr. Jones said that he had no updates from ACC but expressed appreciation to the Authority
for their work on the Strategic Plan.
b) Dr. Napier reported that the current Lexington Highway projects will roll into the 2023
projects because of the overlap between the two. She said that this opens up a lot of
possibilities including a revival of the plan to build a trail around the airport to provide
connectivity between Satterfield Park and the Firefly Trail.
c) The next meeting will be held on May 23, 2023, 3-5 p.m., in the conference room in the Flight
Center Building.
8) Adjourn: 3:41 PM Mr. Benjamin moved and Mr. Westwood seconded that the Authority meeting be
adjourned and the vote to adjourn was unanimous.
Minutes Approved, DATE:
Grant Tribble, Authority Chair
Davin Welter________________________
Agenda
Agenda
Athens Ben Epps Airport Authority Meeting
Tuesday, April 25, 2023, 3-5pm
In-person Meeting: Flight Center Conference Room
1. Chair Update: Opening remarks and agenda preview.
2. Minutes: March Meeting Minutes: Review & Approval
3. Airport Manager Reports
a. Financial & Operations Report
b. Capital Improvement Project Updates
c. Marketing & Outreach Activities
4. Old Business
a. Strategic Plan Update
5. New Business: None
6. Standing Committees: Issues & Updates
a. Business/Finance:
b. Operating:
c. Air Service Development/Marketing
7. Other Business:
a. Next meeting: Tuesday May 23, 2023
8. Adjourn