Engineering Services Committee Meeting
Regular MeetingAugusta, GA · June 13, 2011
Agenda
Engineering Services Committee Commission Chamber- 6/13/2011- 1:10 PM
Meeting
ENGINEERING SERVICES
1. Motion to approve a cost sharing agreement between the Attachments
Augusta Utilities Department and Coel Development Co., Inc.
and Stephen Beazley Builders, Inc.
2. Motion to approve RFQ #11-130: Task Order Program for Attachments
Infrastructure for the City of Augusta - Utilities Department in
the amount of $2,000,000.00 for execution by Contract
Management, Inc.; Blair Construction, Inc., Eagle Utility
Contracting, Inc; and Quality Storm Water Solutions as qualified
and selected contractors.
3. Discuss traffic calming for Highland Avenue. (Requested by Attachments
Commissioner Bowles) (Referred from June 7 Commission
meeting)
4. Consider a request by the Summerville Neighborhood Attachments
Association for a Public Hearing to discuss the placement of
wooden and metal signs with the Summerville logo and
inscription at the following locations: corner of Bourne Pl. and
Milledge Rd.; corner of Henry St. and Highland Ave.; corner of
Highland Ave. and Wrightsboro Rd.; corner of Heard Ave. and
Wrightsboro Rd.; corner of Walton Way and Milledge Rd. (will
also have a State of Georgia historical marker).
5. Approve the awarding of low bid in the amount of $76,495 to Attachments
Graybar Electric for street light poles and fixtures for
replacements/repairs in the Augusta Richmond County urban
areas for a period of one year. Effective upon date of adoption of
this item. The funds are available in the Street Lighting Budget
Account 2760416105414410.
6. Approve a component change for $1,376,987 to the GMP Attachments
(Guaranteed Maximum Price) and existing Purchase Order
(P179109) for purchase and installation of Kitchen Equipment
for the TEE Center under the CM Contract. This does not
increase overall project cost. The revised GMP is $29,276,987.
www.augustaga.gov
Engineering Services Committee Meeting
6/13/2011 1:10 PM
16 Inch Water Main Cost Share Agreement with Coel Dev. and Stephen Beazley Builders
Department: Augusta Utilities Department
Caption: Motion to approve a cost sharing agreement between the Augusta
Utilities Department and Coel Development Co., Inc. and Stephen
Beazley Builders, Inc.
Background: AUD project 10156/Gordon Highway 16" Water Main is in the
final stages of planning and easement acquisition. Coel
Development and Stephen Beazley Builders are in the process of
developing a subdivision to be known as Haynes Station near the
tie-in point of project 10156. This development will require that
the 16" line be constructed as soon as possible.
Analysis: The developers need water extended before AUD would normally
constuct the project; they wish to share the cost to have the portion
that will serve their development constructed immediately. Such
an agreement will benefit both parties by constructing 4,596 linear
feet of 16" pipe, which will become part of Augusta's system, and
providing water to the new subdisivion. The agreement states that
the first 3,000 feet will be a 50/50 split between AUD and
Coel/Beazley, the remaining 1,596 feet will be paid by AUD.
Financial Impact: $244,968.79
Alternatives: Deny the motion to approve a cost sharing agreement between the
Augusta Utilities Department and Coel Development Co., Inc. and
Stephen Beazley Builders, Inc.
Recommendation: Approve the motion to approve a cost sharing agreement between
the Augusta Utilities Department and Coel Development Co., Inc.
and Stephen Beazley Builders, Inc.
Funds are Available
in the Following 511043410-5425110 80310156-5425110
Accounts:
Cover Memo
Item # 1
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Cover Memo
Item # 1
Attachment number 1
Page 1 of 1
Item # 1
Attachment number 2
Page 1 of 1
Item # 1
Attachment number 3
Page 1 of 1
Item # 1
Attachment number 4
Page 1 of 1
Item # 1
Attachment number 5
Page 1 of 1
Item # 1
Attachment number 6
Page 1 of 5
STATE OF GEORGIA)
COUNTY OF RICHMOND) COST SHARING AGREEMENT
THIS Agreement, made the ____ day of _____________, 2011, by and between
COEL DEVELOPMENT CO., INC., a Georgia corporation, and STEPHEN BEAZLEY
BUILDERS, INC., a Georgia corporation, as party of the first part, hereinafter referred to
as “COEL”, and AUGUSTA, GEORGIA, a political subdivision of the State of Georgia,
by and through its Utilities Department, as party of the second part, hereinafter referred
to as “AUGUSTA”:
WITNESSETH
WHEREAS COEL owns certain property described as:
All that lot, or parcel of land, situate, lying and being in Richmond County, Georgia,
119th G.M.D. on the northern right of way of Gordon Highway (U.S. Highway 78) and
containing 196.89 acres, as shown on a plat prepared for Nordahl Development
West, Inc., by Southern Partners, Inc., dated August 11, 2005, said plat being
recorded in the office of the Clerk of the Superior Court of Richmond County,
Georgia, in Book 1, page 1173, reference being hereby made for a more complete
and accurate description as to the metes, courses, bounds and location of said
property. Said property being known in the local tax map and parcel numbering
system as 064-0-008-00-0; and
WHEREAS COEL wishes to construct a subdivision, presently going by the
name of Haynes Station, as approved by the Augusta-Richmond County Planning
Commission on ______________, and the Augusta Commission on
________________; and
WHEREAS it is to the benefit of both parties to construct a water main pipeline,
hereinafter referred to as “water main”, to serve said COEL property; and
NOW THEREFORE, COEL and AUGUSTA hereby enter into the following
agreement:
Item # 1
Attachment number 6
Page 2 of 5
PROJECT SCOPE AND ESTIMATED COST:
COEL will cause a sixteen inch (16) inch ductile iron water main pipeline to be
constructed for a distance of 4,596 linear feet, as shown on Exhibit A, which will be
constructed within the easements purchased by Augusta, Georgia, for the Gordon
Highway 16” Water Main Project.
Said project consists of two (2) sections:
Section 1 will begin at a point on the western boundary line of a tract of land owned by
Fred Sims, Jr., being known under the local Parcel Identification Number as 080-0-001-
00-0, at Station 37+08, and continue under Willhaven Drive, in a westerly direction, for
3,000 feet to Station 67+08, on the same parcel identified previously in this paragraph.
Section 2 will begin at Station 67+08 and continue in a westerly direction, for a distance
of 1,596 feet, to Station 83+04.
COEL conducted a competitive bid, adhering to the guidelines of the Augusta-
Richmond County Procurement Department, for the construction of said water main
pipeline. The lowest bid was submitted by Blair, with the total project cost being
$363,655.22.
AUGUSTA and COEL have agreed to cost share the construction cost for
Section 1, with fifty percent (50%) share being paid by AUGUSTA and a fifty percent
(50%) share being paid by COEL. The construction cost, for this section, is two
hundred thirty seven thousand, three hundred seventy two dollars and eighty six cents
($237,372.86).
Item # 1
Attachment number 6
Page 3 of 5
AUGUSTA has agreed to pay 100 percent (100%) of the construction cost for
Section 2. The cost, for this section, is one hundred twenty six thousand, two hundred
eighty two dollars and thirty six cents ($126,282.36).
STIPULATIONS:
All parties understand and agree that:
1. The above stated construction costs include any and all costs associated with
this project, including, but not limited to surveying, engineering, plats, clearing and
grubbing, construction, materials, acquisition and restoration.
2. The water main shall be constructed consistent with the applicable AUD
(Augusta Utilities Department), AWWA, IFPA codes, Georgia Plumbing codes and any
other standards, regulations and requirements pertinent to water mains.
3. The water main must pass all required and recommended testing. AUD may,
but is not obligated to, monitor the construction of the water main.
4. Any and all estimated cost overruns must have prior written approval of
AUGUSTA, through its Utilities Department (AUD).
5. Any and all additional easements required for this project shall be donated to
AUGUSTA.
6. This agreement is contingent upon the Augusta Commission approval of the
overall project and the Cost Sharing Agreement.
7. If the Augusta Commission does not approve the overall project and Cost
Sharing Agreement, AUGUSTA will be liable for none of the expense associated with
this project and this agreement becomes null and void.
All parties further agree that the contractor will be informed to pay
particular attention to the fence, gate and other improvements located on Parcel
Identification Number 080-0-012-00-0 and Parcel Identification Number 080-0-013-
00-0, both parcels being owned by Dennis P. Faglier. All caution is to be taken to
prevent any damage, or harm, to these improvements.
Item # 1
Attachment number 6
Page 4 of 5
PAYMENT:
Upon the completion of said water main, AUD will perform a final inspection to
determine that said water main has been constructed to all applicable Standards,
Specifications and Codes, and that said water main has passed all required and
recommended testing. If AUD determines that said water main is acceptable to
AUGUSTA, a final inspection report will be forwarded to COEL and COEL will send an
itemized invoice to AUD. Payment to COEL will be made within thirty (30) days of the
receipt of the itemized invoice by AUD.
The terms “COEL” and "AUGUSTA" as used herein shall be deemed to mean their
respective heirs, successors and assigns, and this Agreement shall inure to the benefit of and
be binding upon COEL and AUGUSTA and their respective heirs, successors and assigns.
IN WITNESS WHEREOF, the parties hereto have hereunto set their hands and their
seals on the day and year above first written.
Signed, sealed and delivered in the presence of:
COEL DEVELOPMENT CO., INC.
(owning a 90% interest)
_________________________________ By: ___________________________________
WITNESS
_________________________________ As Its: ________________________
NOTARY PUBLIC
________ County, Georgia Attest: _________________________________
My Commission Expires: _______________
As its: _____________________
(signatures continued on next page)
Item # 1
Attachment number 6
Page 5 of 5
STEPHEN BEAZLEY BUILDERS INC.
(owning a 10% interest)
_________________________________ By: ___________________________________
WITNESS
_________________________________ As Its: ________________________
NOTARY PUBLIC
________ County, Georgia Attest: _________________________________
My Commission Expires: _______________
As its: _____________________
AUGUSTA, GEORGIA
_________________________________ By: ______________________________________
WITNESS David S. Copenhaver
As Its: ____Mayor_____
_________________________________
NOTARY PUBLIC
_____________ County, State of ___________
My Commission Expires: _____________
[NOTARY SEAL]
Attest:
By: ______________________________________
As Its: ________________________________
(SEAL)
Item # 1
Engineering Services Committee Meeting
6/13/2011 1:10 PM
Approve RFQ #11-130: Task Order Program for Infrastructure for the City of Augusta - Utilities
Department in the amount of $2,000.00.00.
Department: Augusta Utilities Department
Caption: Motion to approve RFQ #11-130: Task Order Program for
Infrastructure for the City of Augusta - Utilities Department in the
amount of $2,000,000.00 for execution by Contract Management,
Inc.; Blair Construction, Inc., Eagle Utility Contracting, Inc; and
Quality Storm Water Solutions as qualified and selected
contractors.
Background: The intent of this solicitation is to establish a pool of qualified
contractors from which Augusta Utilities will solicit expedited
bids for work. The types of work anticipated for the Task Order
Program are emergency repairs or smaller construction projects
that require resources beyond those of the Department. Larger
projects would still be bid in the normal fashion. The of the Task
Order Program is to solicit competetive bids from the pool as
projects arise
Analysis: AUD has evaluated Contract Management, Inc.; Blair
Construction, Inc., Eagle Utility Contracting, Inc; and Quality
Storm Water Solutions proposal(s) to participate in the Task Order
Program and has considered the proposal(s) fair and reasonable to
accomplish the task.
Financial Impact: The construction funds available for this project are
$2,000,000.00. These funds are available from account
507043490-5425410 / 88886666-5425410
Alternatives: Rejection of this RFQ Contractor Selection would delay the
Utilities Department ability to execute planned and emergency
repairs of the water/sewer infrastructure system throughout
Augusta/Richmond.
Recommendation: Recommend Commission approve RFQ #11-130: Task Order
Program for Infrastructure for the City of Augusta - Utilities
Department in the amount of $2,000.00.00. Cover Memo
Item # 2
Funds are Available
$2,000,000.00 from account 507043490-5425410 / 88886666-
in the Following
5425410
Accounts:
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Cover Memo
Item # 2
Attachment number 1
Page 1 of 1
Item # 2
Attachment number 2
Page 1 of 1
REQUEST FOR QUALIFICATIONS
Request for Qualifications will be received at this office until Tuesday, May 24, 2011 @ 3:00 p.m. for furnishing:
RFQ ITEM #11-130 Task Order Program for Infrastructure for Utilities Department
RFQs will be received by: The Augusta Commission hereinafter referred to as the OWNER at the offices of:
Geri A. Sams, Director
Augusta Procurement Department
530 Greene Street - Room 605
Augusta, Georgia 30901
RFQ documents may be viewed on the Augusta Richmond County web site under the Procurement Department
ARCbid. RFQ documents may be obtained at the office of the Augusta, GA Procurement Department, 530
Greene Street – Room 605, Augusta, GA 30901. A Mandatory Pre-Qualification Meeting will be held on
Friday May 6, 2011 @ 10:00 a.m. in the Procurement Department, 530 Greene Street, Room 605. All
questions must be submitted in writing by email to procbidandcontract@augustaga.gov to the office of
the Procurement Department by Monday, May 9, 2011 @ 5:00 P.M. No bid will be accepted by fax, all
must be received by mail or hand delivered.
The local bidder preference program is applicable to this project. To be approved as a local bidder and
receive bid preference on an eligible local project, the certification statement as a local bidder and all
supporting documents must be submitted to the Procurement Department with your bonafide bid
package.
No RFQ may be withdrawn for a period of 90 days after time has been called on the date of opening.
An invitation for bids shall be issued by the Procurement Office and shall include specifications prepared in
accordance with Article 4 (Product Specifications), and all contractual terms and conditions, applicable to
procurement. All specific requirements contained in the invitation to bid including, but not limited to, the number
of copies needed, the timing of the submission, the required financial data, and any other requirements
designated by the Procurement Department are considered material conditions of the bid which are not
waiveable or modifiable by the Procurement Director. Please mark RFQ number on the outside of the envelope.
Bidders are cautioned that sequestration of RFQ documents through any source other than the office of the
Procurement Department is not advisable. Acquisition of RFQ documents from unauthorized sources places
the bidder at the risk of receiving incomplete or inaccurate information upon which to base his qualifications.
Funding for this project may include federal funds provided by the U. S. Department of Transportation (DOT)
and/or other federal agencies. All DOT funded projects are subject to the requirements of 49 CFR Part 26.
These requirements are mandatory and non-negotiable. Augusta enforces Disadvantage Business Enterprise
(DBE) requirements and/or DBE goals set by Federal and/or State Agencies in accordance with State and
Federal laws. Please be advised that the U. S. District Court for the Southern District of Georgia has entered
on Order enjoining the Race-Based portion of Augusta, Georgia’s DBE Program. Thus, Augusta, Georgia
does not have or operate a DBE, MBE or WBE Program for projects (or portions of projects) having Augusta,
Georgia as the source of funding.
GERI A. SAMS, Procurement Director
Publish:
Augusta Chronicle April 14, 21, 28, May 5, 2011
Metro Courier April 20, 2011
cc: Tameka Allen Interim Deputy Administrator
Tom Wiedmeier Augusta Utilities
Drew Goins Augusta Utilities
Jerry Delaughter Augusta Utilities
Merle Wilkie Augusta Utilities
Item # 2
Attachment number 3
Page 1 of 1
RFQ Item #11-130
Task Order Program for Infrastructure
for the City of Augusta - Utilities Department
RFQ Due: Tuesday, May 24, 2011 @ 3:00 p.m.
VENDORS Attachment B Original 8 Copies
Blair Construction, Inc.
PO Box 770 Yes Yes Yes
Evans, GA 30809
Contract Management, Inc.
1827 Killingsworth Yes Yes Yes
Augusta, GA 30904
Eagle Utility Contracting, Inc.
1350 Branch Road Yes Yes Yes
Bishop, GA 30627
Quality Storm Water Solutions
P.O. Box 1847 Yes Yes Yes
Evans, GA 30809
Item # 2
Page 1 of 1
Attachment number 4
Page 1 of 1
Item # 2
Attachment number 5
Page 1 of 1
Cumulative Evaluation Sheet - RFQ Item #11-130
Task Order Program for Infrastructure
for the City of Augusta - Utilities Department
Blair Construction, Contract Eagle Utility Quality Storm Water
Inc. Management, Inc. Contracting, Inc. Solutions
PO Box 770 1827 Killingsworth 1350 Branch Road P.O. Box 1847
Evans, GA 30809 Augusta, GA 30904 Bishop, GA 30627 Evans, GA 30809
Evaluation Criteria PTS
20.7 16.7 18.3 15.0
1. Firm’s experience in utility
construction 25
2. Firm’s experience with AUD
projects, infrastructure & 20.7 15.0 18.3 11.7
specifications 25
20.7 16.7 19.0 15.0
3. Capacity/Ability to respond 25
4. Ability to meet liability 25.0 25.0 25.0 25.0
insurance & specified bonding
requirements 25
Total 87.0 73.3 80.7 66.7
100
Comments:
Item # 2
Attachment number 6
Page 1 of 2
Item # 2
Attachment number 6
Page 2 of 2
Item # 2
Attachment number 7
Page 1 of 4
Item # 2
Attachment number 7
Page 2 of 4
Item # 2
Attachment number 7
Page 3 of 4
Item # 2
Attachment number 7
Page 4 of 4
Item # 2
Engineering Services Committee Meeting
6/13/2011 1:10 PM
Highland Avenue Traffic Calming
Department: Clerk of Commission
Caption: Discuss traffic calming for Highland Avenue. (Requested by
Commissioner Bowles) (Referred from June 7 Commission
meeting)
Background:
Analysis:
Financial Impact:
Alternatives:
Recommendation:
Funds are Available
in the Following
Accounts:
REVIEWED AND APPROVED BY:
Cover Memo
Item # 3
Engineering Services Committee Meeting
6/13/2011 1:10 PM
Monument-Marker request - Summerville Neighborhood Signs
Department: Planning Commission
Caption: Consider a request by the Summerville Neighborhood Association
for a Public Hearing to discuss the placement of wooden and
metal signs with the Summerville logo and inscription at the
following locations: corner of Bourne Pl. and Milledge Rd.;
corner of Henry St. and Highland Ave.; corner of Highland Ave.
and Wrightsboro Rd.; corner of Heard Ave. and Wrightsboro Rd.;
corner of Walton Way and Milledge Rd. (will also have a State of
Georgia historical marker).
Background:
Analysis: Placement of signs must be approved by Traffic Engineering
Dept. before installation
Financial Impact: No cost to the City
Alternatives: Allow the signs on City right-of-way or deny the signs.
Recommendation: Allow the signs
Funds are Available
in the Following
Accounts:
REVIEWED AND APPROVED BY:
Clerk of Commission
Cover Memo
Item # 4
Engineering Services Committee Meeting
6/13/2011 1:10 PM
Street lighting award 2011
Department: Engineering/Traffic
Caption: Approve the awarding of low bid in the amount of $76,495 to
Graybar Electric for street light poles and fixtures for
replacements/repairs in the Augusta Richmond County urban
areas for a period of one year. Effective upon date of adoption of
this item. The funds are available in the Street Lighting Budget
Account 2760416105414410.
Background: This is for replacement poles.
Analysis: Award of Bid.
Financial Impact: Adequate funds are available and expenditure of this amount will
leave $23,505. which is sufficient for any emergencies that may
arise before the end of the year.
Alternatives: Approve the awarding of low bid in the amount of $76,495. To
Graybar Electric for street light poles and fixtures for
replacements/repairs in the Augusta Richmond County Urban
areas for a period of one year. Effective upon date of adoption of
this item. The funds are available in the Street Lighting Budget
Account No. 2760416105414410.
Recommendation: Approve alternative.
Funds are Available
in the Following 2760416105414410.
Accounts:
REVIEWED AND APPROVED BY:
Finance.
Procurement. Cover Memo
Item # 5
Law.
Administrator.
Clerk of Commission
Cover Memo
Item # 5
Attachment number 1
Page 1 of 1
Invitation To Bid
Sealed bids will be received at this office until 11:00 a.m. Friday, May 13, 2011 for furnishing:
Bid Item #11-122 Street Lighting Poles & Fixtures for Traffic Engineering Department
Bids will be received by Augusta, GA Commission hereinafter referred to as the OWNER at the offices of:
Geri A. Sams
Procurement Department
530 Greene Street - Room 605
Augusta, Georgia 30901
706-821-2422
Bid documents may be viewed on the Augusta Richmond County web site under the Procurement Department
ARCbid. Bid documents may be obtained at the office of the Augusta, GA Procurement Department, 530
Greene Street – Room 605, Augusta, GA 30901. Documents may be examined during regular business
hours at the offices of Augusta, GA Procurement Department. All questions must be submitted in writing
by fax to 706 821-2811 or by email to procbidandcontract@augustaga.gov to the office of the
Procurement Department by Monday, April 25, 2011 @ 5:00 P.M. No bid will be accepted by fax, all
must be received by mail or hand delivered.
The local bidder preference program is applicable to this project. To be approved as a local bidder
and receive bid preference on an eligible local project, the certification statement as a local bidder and
all supporting documents must be submitted to the Procurement Department with your bonafide bid
package.
No Bid may be withdrawn for a period of 90 days after time has been called on the date of opening.
An invitation for bids shall be issued by the Procurement Office and shall include specifications prepared in
accordance with Article 4 (Product Specifications), and all contractual terms and conditions, applicable to the
procurement. All specific requirements contained in the invitation to bid including, but not limited to, the
number of copies needed, the timing of the submission, the required financial data, and any other
requirements designated by the Procurement Department are considered material conditions of the bid which
are not waiveable or modifiable by the Procurement Director. Please mark BID number on the outside of the
envelope.
Bidders are cautioned that sequestration of BID documents through any source other than the office of the
Procurement Department is not advisable. Acquisition of BID documents from unauthorized sources placed
the bidder at the risk of receiving incomplete or inaccurate information upon which to base his qualifications.
Funding for this project may include federal funds provided by the U. S. Department of Transportation
(DOT) and/or other federal agencies. All DOT funded projects are subject to the requirements of 49
CFR Part 26. These requirements are mandatory and non-negotiable. Augusta enforces Disadvantage
Business Enterprise (DBE) requirements and/or DBE goals set by Federal and/or State Agencies in
accordance with State and Federal laws. Please be advised that the U. S. District Court for the
Southern District of Georgia has entered on Order enjoining the Race-Based portion of Augusta,
Georgia’s DBE Program. Thus, Augusta, Georgia does not have or operate a DBE, MBE or WBE
Program for projects (or portions of projects) having Augusta, Georgia as the source of funding.
GERI A. SAMS, Procurement Director
Publish:
Augusta Chronicle March 31, April 7, 14, 21, 2011
Metro Courier April 6, 2011
cc: Tameka Allen Interim Deputy Administrator
Abie Ladson Engineering Department
Steve Cassell Traffic Engineering
Charles Gifford Traffic Engineering
Item # 5
Bid Item #11-122
Street Lighting Poles & Fixtures
For the City of Augusta - Engineering-Traffic Engineering Department
Bid Opening Date: Friday, May 13, 2011 at 11:00 a.m.
Consolidated
Hagemeyer Graybar E. Sam Jones
Electrical
1730 Barton 3222 Mike Padgett 3316 Sandpiper Velocity Electical Equipment
Distributors Blue Sky Lighting
Chapel Rd. Hwy Lane Construction Company
Vendors: 1244 Gordon Pk 4086 Quinn Drive
Augusta, GA Augusta, GA Augusta, GA 3000 Pucketts Mill 1431 Marvin Griffin
Augusta, GA Evans, GA 30809
30909 30906 30907 Buford, GA 30519 Augusta, GA 30906
30901
Incomplete
Attachment B Yes Yes
No E-verify #
No. 1 (TS-3)
Delivery 8-10 Weeks 8-12 Weeks
Non-
Bid Price $1,041.00 $1,017.00
Compliant
No. 2 (TS-4)
Delivery 8-10 Weeks 8-12 Weeks
Non-
Bid Price $835.00 $818.00
Compliant
Attachment number 2
Item # 5
Page 1 of 1
Page 1 of 1
Attachment number 3
Page 1 of 1
Item # 5
Attachment number 4
Page 1 of 3
Item # 5
Attachment number 4
Page 2 of 3
Item # 5
Attachment number 4
Page 3 of 3
Item # 5
Engineering Services Committee Meeting
6/13/2011 1:10 PM
TEE Center - Increase GMP for Kitchen Equip
Department: Recreation Parks and Facilities - Facilities Manager
Caption: Approve a component change for $1,376,987 to the GMP
(Guaranteed Maximum Price) and existing Purchase Order
(P179109) for purchase and installation of Kitchen Equipment for
the TEE Center under the CM Contract. This does not increase
overall project cost. The revised GMP is $29,276,987.
Background: R.W. Allen, LLC (RWA) was selected under RFQ 10-039 as the
TEE Center project’s Construction Manager at Risk by the
Augusta Commission on January 19, 2010. A purchase order was
issued to R.W. Allen, LLC on April 20, 2010 for the amount of
their general conditions, construction fee and pre-construction fee.
R.W. Allen submitted the Kitchen Equipment scope for bids,
receiving a total of five responses. Norvell Fixture & Equipment
Company, a local firm, was the low bidder.
Analysis: The proposed monetary modification is required for Kitchen
Equipment inclusion into the Construction Manager’s GMP.
Funds will be transferred from the Fixture Furniture and
Equipment (FF&E) budget into the GMP.
Financial Impact: There is no financial impact to the overall project cost. Funds are
being transferred from the FF&E budget.
Alternatives: 1. Approve a component change for $1,376,987 to the GMP and
existing Purchase Order (P179109) for purchase and installation
of Kitchen Equipment for the TEE Center under the CM Contract.
This does not increase overall project cost. The revised GMP is
$29,276,987. 2. Disapproving the Purchase Order increase will
delay construction schedule.
Recommendation: #1. Approve a component change for $1,376,987 to the GMP and
existing Purchase Order (P179109) for purchase and installation
of Kitchen Equipment for the TEE Center under the CM Contract.
This does not increase overall project cost. The revised GMP is
$29,276,987. Cover Memo
Item # 6
Funds are Available FUNDS ARE AVAILABLE IN ACCOUNT: TEE Center: GL –
in the Following 325-05-1130; JL – 206351102 GL - 361-06-1120 Object Code:
Accounts: 5413130
REVIEWED AND APPROVED BY:
Finance.
Procurement.
Law.
Administrator.
Clerk of Commission
Cover Memo