Utilities Commission
Regular MeetingBaxter, MN · October 2, 2024
Minutes
UTILITIES COMMISSION MINUTES
Wednesday, October 02, 2024 at 5:30 PM
Baxter City Hall, 13190 Memorywood Drive, Baxter, MN
“A Growing Community”
CALL TO ORDER
The regular meeting of the Baxter Utilities Commission was called to order at 5:32 p.m. by Chairman Rock
Yliniemi.
ROLL CALL
Members Present: Commissioner Douglas Stenberg, Jack Christofferson, John Brenny, Chairman Rock Yliniemi, and
Council Liaison Mark Cross.
Members Absent: None.
Staff Present: Public Works Director/City Engineer Trevor Walter, Assistant City Engineer Trevor Thompson, and
Administrative Assistant Dani Steininger.
Other Present: Bolton & Menk Consulting Engineer Bryan Drown, SEH Consulting Engineers Scott Hedlund, Neil
Heinonen, Aaron Kutz, Alex Voit, Widseth Consulting Engineer Alex Bitter.
CONSENT AGENDA
1. Accept the Utilities Commission Minutes from September 4, 2024
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to approve the Utilities
Commission minutes from September 4, 2024. Motion carried unanimously.
BUSINESS ITEMS
2. Pavement Management Plan - Micro Surfacing Program Review
Bolton & Menk Consulting Engineer Drown gave a status update on the program. This is the first year
that micro-surfacing is being done on mill and overlay or full depth reclamation roads as part of the
Pavement Management Plan.
There is an opportunity to spread out the Pavement Management Plan from an eight-year rotation
to a twelve-year rotation. This attributes to the City’s reconstruction and use of C oil on roads instead
of recycled asphalt pavement. C oil preforms better in colder and hotter temperatures. There is not
as much cracking at year eight and the roads look to have a longer life span.
Discussion:
Chairman Yliniemi inquired if low speeds are harder on roads than high speeds. Mr. Drown said that
the slow turning at driveway causing scuffing, but yes that is true.
Assistant City Engineer Thompson added that Inglewood and Clearwater have no moisture spots
compared to ones present last year. City staff will continue to monitor annually to review the
condition of the roads.
10/2/2024 Utilities Commission Minutes Page 2
Public Works Director/City Engineer Walter added that in the chip sealing areas we start seeing
stripping in year four. Right now, nothing is showing that micro surfacing is doing anything other than
wearing like it is supposed to like a ware course.
Mr. Thompson mentioned that when staff looked at the Pavement Management Plan in 2019 staff
did not know what to expect with the micro surfacing, therefore age limits were put on roads. At
year eight staff was hoping to get a life span of 20 years out of commercial roads and 25 years out of
residential roads. Now with the possibility of a twelve year rotation it could change to become 25
years out of commercial roads, 30 years out of residential roads, and to see where the collector
roads fall. The Pavement Management Plan ties into CIP discussion and budgeting.
3. 2024 Micro Surfacing Project Update
There was no new information or questions from the commission or the public.
4. Approve ASTECH Pay Estimate No. 2 in the amount of $94,028.91 for the 2024 Micro Surfacing
Project
Bolton & Menk Consulting Engineer Drown reviewed ASTECH Partial Pay Estimate No. 2 in the
amount of $94,028.91 for the 2024 Micro Surfacing Project. He notified the commissioners that City
staff will be attending the final walkthrough next Monday, October 7th.
The contractor has earned $601,188.26 to date, which represents 99% of the contract’s value. The
payment includes the cost of unit price work completed through September 13, 2024. In accordance
with the agreement as the project is Substantially Complete the amount retained has been reduced
to 2.5%. The 2.5% retainage equals $15,029.71. The amount retained equals 250% of the shouldering
items which have not been finally accepted. Previous payments to the contractor equal $492,129.64,
which results in a payment of $94,028.91. Mr. Drown has no concerns with Pay Estimate No. 2 and
recommends approval.
MOTION by Commissioner Brenny, seconded by Commissioner Stenberg approve the ASTECH Partial
Pay Estimate No. 2 in the amount of $94,028.91 for the 2024 Micro Surfacing Project. Motion carried
unanimously.
5. Accept the 2024 Water CAMP Report
SEH Consulting Engineer Heinonen reviewed the 2024 Water CAMP Report.
Work related to the 2024 Water System CAMP Update has been initiated. SEH met with City staff,
and they assisted in gathering information for updates made in the last year to the wells, water
treatment plant, water towers, and interconnect building. City staff is still working to gather
information on water mains, hydrants, and plastic tees from record drawings and GIS updates. Once
all information has been received, the cost summary can be completed to assist in City financial
planning. The cost summary should be completed within the next two weeks, pending information
from the City. In 2025 there will be a formal update to keep everything current every year, add new
assets, and make changes to existing assets.
Work Completed Since Last Meeting:
10/2/2024 Utilities Commission Minutes Page 3
One (1) as-built drawing has been finalized and forwarded to SEH water staff to be included in the
updated spreadsheet. Staff have continued implementing best practices for managing well
drawdown by monitoring the well pumping rates and well levels.
Work to Be Completed:
Staff to compile a list of all 2023 road construction projects to include in the addition of water main
and hydrant data from the associated as-built files, as they are available. This excludes the CSAH 48
Cypress Drive project, as this has been included in the existing spreadsheet.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to accept the 2024
Water CAMP Report. Motion carried unanimously.
6. 2024 Well Rehabilitation Project Update
There was no new information or questions from the commission or the public.
7. Approve the Thein Well Company Change Order No. 2 in the Increased Amount of $7,450.50 for
the 2024 Well Rehabilitation Project
SEH Consulting Engineer Heinonen reviewed Thein Well Company Change Order No. 2 in the
Increased Amount of $7,450.50 for the 2024 Well Rehabilitation Project.
Prior to the rehabilitation work for Well No. 4 commencing, SEH consulted with Johnson Screens
which recommended adding Nu-Well 400 to the chemical mixture specified for the well
rehabilitation. During the rehabilitation of Well No. 4, it was determined that the drop pipe
connecting the submersible pump to the pitless adapter was corroded and had damaged threads,
requiring replacement. Staff approved both changes to keep work progress moving.
Change Order 2 is being presented in the amount of $7,450.50 with no change in contract time for
the use of Nu-Well 400 and replacement of the drop pipe in Well No. 4. Change Order 2 increases the
total contract price from $150,891.00 to $158,341.50. Mr. Heinonen has no concerns with Change
Order No. 2 and recommends approval.
MOTION by Commissioner Christofferson, seconded by Commissioner Brenny to approve the Thein
Well Company Change Order No. 2 in the increased amount of $7,450.50 for the 2024 Well
Rehabilitation Project. Motion carried unanimously.
8. 2024 Well Replacement Exploration
SEH Consulting Engineer/Geologist Kutz gave a presentation explaining the exploration for
replacement wells.
The Existing Wellfield Evaluation Report provided to City Staff on May 1, 2024, recommended the
replacement of two wells in the existing wellfield but with sufficient separation to reduce the
potential of interference and minimize precipitates from forming in the aquifer. On June 18, 2024,
SEH was hired to move forward with exploration of the existing wellfield aquifer for the potential
installation of replacement wells on the eastern side of the water treatment plant parcel.
Task 1 (Completed): Following a bidding process, an Agreement with the low bidder, Traut
Companies, was approved by City Council on August 7, 2024, for services that included the use of
10/2/2024 Utilities Commission Minutes Page 4
sonic drilling techniques to complete two soil borings and installation of two observations wells.
Drilling services oversight and borehole logging will be completed by an SEH geologist to potentially
speed up aquifer assessment and the well design process.
Task 2 (Pending): Based on Traut’s current drilling schedule, drilling activities are scheduled to begin
on September 30 with drilling anticipated to about last 5 to 7 days. Upon completion of the drilling
program consisting of exploratory soil borings, test pumping using temporary screens, and
installation of observations wells, additional services include water quality sampling of the
observation wells and temporary installation of transducers (minimum of two weeks) to allow
remote monitoring to aid in the evaluation of aquifer conditions with current pumping by existing
water supply wells.
Task 3 (Pending): A preliminary report is anticipated for later in October 2024 following completion
of field tasks, and all drilling and laboratory results are available. The final report will be presented to
the Utilities Commission in November.
The first test well location has been completed. It is called MW-1 (Monitoring Well-1) and located is
in the back NE area in the storage yard at the Baxter Public Works Facility. The second EB-2/MW-2
(Exploration Boring) location was a following up boring after the first one was completed. This one is
located south of MW-1.
MW-1 is a good test well as it hit bedrock at 137 ft. bgs. While EB-2/MW-2 hit bedrock at 122 ft. bgs.,
and this is not a viable option to be a monitoring well. At 85’ the ground material transitions to tight
compacted clay and cobble that does not let water pass through. It is believed that a possible glacial
till ridge has been formed South of MW-1 this is separating the out washed sand and making the
ground harder sooner.
There are two more areas that may have possible monitoring wells. The first is NE of MW-1 across
Jasperwood Drive on City property, now called EB/MW-3. The second is in the SE corner at the
Mapleton and Jasperwood roundabout. It has been verified that these locations do not have utilities
in the area.
Discussion:
Commissioner Brenny asked Mr. Kutz why they did not do a pump test and Mr. Kutz said that you
don’t want to do it unnecessarily because every pump test costs $6,600.00, each drilling costs
$9,000.00 and that can add up fast if you start doing more boring and drilling in multiple
unresearched areas.
Chairman Yliniemi inquired if clay would start to pull through screens and affecting the ability of
water well with these clay particles and resulting in issues. Mr. Kutz said that over time you would
pull some particles out of the well, but you could do maintenance to prevent that.
Council Liaison Cross asked if there is any advantage to getting over the possible glacial till ridge and
getting into another confinement of water. Kutz said they looked into it and in their initial report
there is not any city owned property on the south side of the Mapleton Road.
Commissioner Brenny asked Mr. Kutz where the majority of water comes from the top or bottom of
the water table. Mr. Kutz informed him that the water gets pulled in from the bottom.
10/2/2024 Utilities Commission Minutes Page 5
9. Approve the Traut Companies Change Order No. 1 in the increased amount of $23,492.50 for
additional Well Exploration Services related to the 2024 Well Replacement Exploration
SEH Consulting Engineers Kutz and Heinonen reviewed the Traut Companies Change Order No. 1 in
the increased amount of $23,492.50 for additional Well Exploration Services related to the 2024 Well
Replacement Exploration.
During drilling exploration, a layer of unexpected clay material was encountered in one of the test
well locations. The Consultant and City Staff agreed that this location would not be desirable for a
production well. An alternate location was reviewed, and this Change Order includes the cost to drill
an additional test well and to provide an additional monitoring well.
Mr. Heinonen has no concerns with Change Order No. 2 and recommends approval.
Public Works Director/City Engineer Walter noted that on the financial implication that there will be
additional engineering fees. There will be a contract amendment coming and it is estimated at about
$8,000.00. The amount will actually be $31,492.50 total budget amendment that will be coming.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve the Traut
Companies Change Order No. 1 in the increased amount of $23,492.50 for additional Well
Exploration Services related to the 2024 Well Replacement Exploration.
10. 2023 Commercial and Residential Full Depth Reclamation and Quiet Zone Improvements Project –
Monthly Update
SEH Consulting Engineer Voit informed the commissioners that the meeting with MnDOT and DNR is
scheduled for Thursday, October 10th.
11. Approve the Anderson Brothers Construction Company of Brainerd, LLC Partial Pay Estimate No. 11
in the amount of $99,923.35 for the 2023 Commercial and Residential Full Depth Reclamation and
Quiet Zone Improvements Project
SEH Consulting Engineer Voit reviewed Anderson Brothers Construction Company of Brainerd, LLC
Partial Pay Estimate No. 11 in the amount of $99,923.35 for the 2023 Commercial and Residential
Full Depth Reclamation and Quiet Zone Improvements Project.
Application for Payment No. 11 is for storm sewer lining related to Change Order #5 and concrete
median work on the Quiet Zone portion of the project related to Change Order #9. Project retainage
is being held at 1%. Mr. Voit has no concerns with the Partial Pay Estimate No. 11 and recommends
approval.
Public Works Director/City Engineer Walter asked Mr. Voit if this project will be completed by
December 31st, 2024. Mr. Voit said there is a chance, they are held up by some signage and mailbox
supports.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve the
Anderson Brothers Construction Company of Brainerd, LLC Partial Pay Estimate No. 11 in the amount
of $99,923.35 for the 2023 Commercial and Residential Full Depth Reclamation and Quiet Zone
Improvements Project. Motion carried unanimously.
12. 2024 South Forestview Improvements Project Monthly Update
10/2/2024 Utilities Commission Minutes Page 6
There was no new information or questions from the commission or the public.
13. Approve the RL Larson Excavating, Inc. Change Order No. 6 in the increased amount of $19,162.66
for the 2024 South Forestview Improvements Project, Municipal Project No. 4138
SEH Consulting Engineer Hedlund reviewed RL Larson Excavating, Inc. Change Order No. 6 in the
increased amount of $19,162.66 for the 2024 South Forestview Improvements Project.
Added Work Items of Change Order No. 6:
Stump removal in various areas of the project utilizing a different method than included
with the contractor’s bid. This change order includes labor and material for the requested
method of stump removal.
Clearing and grubbing operations along the pedestrian trail corridor.
Additional mobilization charge for turf restoration .
Additional grading on a pedestrian trail along Riverwood Road to meet running slope
constraints per the Americans with Disabilities Act (ADA).
Additional grading and topsoil placement outside of project limits in order to meet
requirements of the general storm water permit.
Modifications to contract quantities and additional varieties of plants. This has saved
$18,000.00 in project costs.
During review of contract completion dates it was evident that sufficient time was not
provided for the Contractor to complete turf restoration following wear course paving.
The original final competition date of June 13th, 2025 has been pushed to July 11th, 2025.
City staff requested that topsoil remain lower over the winter months adjacent to
roadway edges and additional cautionary signage be installed.
Mr. Hedlund has no concerns with Change Order No. 6 and recommends approval.
Public Works Director/City Engineer Walter stated that the change in completion date should have
been added to the motion since it is a contract amendment as well.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve the RL
Larson Excavating, Inc. Change Order No. 6 in the increased amount of $19,162.66 for the 2024 South
Forestview Improvements Project pending the final completion date be changed from June 13th,
2025 to July 11th, 2025.
14. Approve RL Larson Excavating, Inc Partial Pay Estimate No. 6 in the amount of $698,703.87 for the
2024 South Forestview Area Improvements Project, Municipal Project No. 4138
SEH Consulting Engineer Hedlund reviewed RL Larson Excavating, Inc Partial Pay Estimate No. 6 in the
amount of $698,703.87 for the 2024 South Forestview Area Improvements Project.
Partial Pay Estimate No. 6 is for work completed through September 13, 2024. The work included
with this payment is for excavation, embankment, roadway and driveway paving, concrete flat work,
mailboxes, turf establishment, and utility construction items.
The Contractor has earned $4,859,686.62 to date, which represents approximately 79.4% of the
contract value. Per the contract, 5% is being retained. The summary below notes the amount due
and the amount compensated with previous payments.
10/2/2024 Utilities Commission Minutes Page 7
Summary:
Gross Amount Due: $4,859,686.62
Less 5% Retainage: $242,984.33
Amount Eligible for Payment to Date: $4,616,702.29
Less Previous Payments: $3,917,998.42
Amount Due with Application for Payment No. 6 $698,703.87
Mr. Hedlund has no concerns with Partial Pay Estimate No. 6 and recommends approval. He added
that currently 79% of the work is completed.
MOTION by Commissioner Christofferson, seconded by Commissioner Brenny to approve the RL
Larson Excavating, Inc. Partial Pay Estimate No. 6 in the amount of $698,703.87 for the 2024 South
Forestview Area Improvements Project.
15. 2024 Mill & Overlay and Full Depth Reclamation Improvements Project Monthly Update
Widseth Consulting Engineer Bitter informed the commissioners the final walkthroughs are taking
place and everything is almost done.
16. Approve the Knife River Corporation – North Central Change Order No. 5 in the Increased Amount
of $27,290.39 for the 2024 Mill & Overlay and Full Depth Reclamation Improvements Project,
Municipal Project Number 4424
Widseth Consulting Engineer Bitter reviewed the Knife River Corporation – North Central Change
Order No. 5 in the Increased Amount of $27,290.39 for the 2024 Mill & Overlay and Full Depth
Reclamation Improvements Project.
Change Order No. 5 includes:
1. During construction, it was found that four storm sewer structures were leaking at the
seam of the structure and the lid. In order to replace the seals at this joint, the contractor
needed to be able to lift the lids off. The existing lids did not have the lift points. The cost
associated with this item is the contractor installing lift points on the existing lids and the
materials to seal the joint.
2. During the sub cut on the Edgewood Drive, it was found that the water table was near the
final subgrade elevation. This is a significant impact on the strength of the roadway. Road
fabric was installed to help improve the strength of the road and the cost associated with this
item if the materials and installation of the fabric.
3. At the start of the project, it was estimated that $50,000 could possibly be spent on
irrigation sprinkler repair. This number has been exceeded as the contractor continues to
make repairs on the system. The Change Order includes $14,511.00 over the updated $52,870
allowance so far. Each month, as repairs are being made, we will continue to update the
budget with a change order. An estimated cost for additional sprinkler repair is taken into
account for the remaining contingencies.
The $27,290.39 change order increases the total contract price from $3,938,520.31 to $3,965,810.70.
The overall project budget is $5,030,467.01 which was set at the assessment hearing. Widseth
updates the project budget with each pay estimate. With the projected overruns and underruns,
10/2/2024 Utilities Commission Minutes Page 8
there are no remaining contingencies in the project budget. This is based on a change order that are
currently being reviewed. Estimated costs have been inserted into the final budget but we will not
have a final cost in the final budget until the final negotiations have been completed. This also does
not include the possible increase in the engineering contract or additional turf establishment in 2025.
Mr. Bitter has no concerns with Change Order No. 5 and recommends approval.
Discussion:
Mr. Bitter stated that the contractor for the project was being careful regarding sprinklers. Mr. Bitter
and the contractor had many conversations about how they are going about exposing sprinklers, and
which ones were hit and need to be repaired. There will be another item in the next change order
requesting more sprinkler repair refunds and that it hopefully should be the last one.
Commissioner Christofferson asked Mr. Bitter if before starting the project couldn’t the owners of
property in the construction area mark their irrigation system prior to this project?
Mr. Bitter said they do ask, and a lot of times it happens, but sometimes things still get hit or
damaged from trying to dig them up. Knife River is careful about irrigations systems, it is the
subcontractors that are less careful. The plan could be to possibly do something in the future to
minimize those damages and make the repairs incidental to work adjacent, but the cost is going to be
there either way with that option.
Public Works Director/City Engineer Walter discussed that in the future it could be added to the
contract that the City pays labor hours to dig up and layout irrigation systems from the very
beginning before curb work. It is tough to do this because between different managers of stores not
knowing the irrigation system to new homeowners that are not familiar because they did not put
them in initially.
Mr. Bitter said for previous projects they give a general estimated allowance for irrigation repairs and
complete the repairs as the project continues. This estimated number is hard to come up with
because all irrigation system can be different, and it is encouraged to have them in the road right-of-
way to keep everything in the City consistent.
Assistant City Engineer Thompson asked Mr. Bitter how many commercial irrigation systems and how
many residential irrigations systems there are for this project. Mr. Bitter did not have the information
on hand. Mr. Walter said it would be nice to have in the future for bidding allowances.
Commissioner Christofferson asked where the fabric portion of this project is laid down in the layers
of material.
Mr. Bitter said it goes native material (subgrade of sand), fabric, reclaim material, and then final
pavement. This fabric helps bridge soft material with being saturated and it helps keep the
separation from sand and reclaim. So as the water table raises and lowers you don’t have the sand
and reclaim together which can lower its strength.
Mr. Walter mentioned that another change order should be prepared for payment for pumping
stormwater ponds in the area.
10/2/2024 Utilities Commission Minutes Page 9
Mr. Bitter continued that he needs to get the final invoice from Pratt’s Affordable Excavating for the
temporary pumping down of the stormwater ponds. This was done to help lower the water table
down for construction purposes.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to approve the Knife
River Corporation – North Central Change Order No. 5 in the Increased Amount of $27,290.39 for the
2024 Mill & Overlay and Full Depth Reclamation Improvements Project.
17. Approve the Knife River Corporation – North Central Partial Pay Estimate No. 5 in the amount of
$777,280.94 for the 2024 Mill & Overlay and Full Depth Reclamation Improvements Project,
Municipal Project Number 4424
Widseth Consulting Engineer Bitter reviewed the Knife River Corporation – North Central Partial Pay
Estimate No. 5 in the amount of $777,280.94 for the 2024 Mill & Overlay and Full Depth Reclamation
Improvements Project.
The Contractor has earned $3,063,336.24 to date which represents 77.2% contract value. In
accordance with the agreement, 5% of the revised contract value ($198,290.53) is being retained
which results in a total payment of $777,280.94. Mr. Bitter has no concerns with Partial Pay Estimate
No. 5 and recommends approval. The
Mr. Bitter informed the Utilities Commission and City staff present that the retainage is for some
final paving and turf establishment. He continued that there are a few spots in paved areas where
they noticed the final rubber tire roller is picking up some of the pavement because of the C oil that
makes it really soft and sticky, so a rubber tire tends to pick up in some spots. The contractor will be
back to come and smooth out those areas.
MOTION by Commissioner Brenny, seconded by Commissioner Christofferson to approve the Knife
River Corporation – North Central Partial Pay Estimate No. 5 in the amount of $777,280.94 for the
2024 Mill & Overlay and Full Depth Reclamation Improvements Project.
18. 2025 Commercial Full Depth Reclamation Improvements Project, Municipal Project 4425 Monthly
Project Update
Widseth Consulting Engineer Bitter gave a presentation and reviewed the 2025 Commercial Full
Depth Reclamation Improvements Project. The project was put on a brief hold to allow City staff time
to review the residential projects for the CIP. The decision was made to push the residential M&O
and FDR roads back 1 year and the commercial project will stay on schedule. The residential roads for
the 2025 project will be moving to 2026. The commercial roadways will be the only remaining project
areas for the 2025 project. Widseth has finished updating the Feasibility Report to only include the
Commercial Roadways. Since the project is only including commercial roads and there will not be
able to mill & overlay, the project title is being updated. With updating the project title, it was
thought to update the previous Resolution ordering the Report. A Resolution is also being proposed
to receive the report and order the Improvement Hearing. The Improvement Hearing is tentatively
scheduled for November 7th of 2024. The total estimated project costs is $3,160,898.73 and the total
City cost summary is $787,425.25 (25%).
Discussion:
Public Works Director/City Engineer Walter asked Mr. Voit if catch basins will be rehabbed with new
castings.
10/2/2024 Utilities Commission Minutes Page 10
Mr. Bitter responded that all updates will be done along with select curb removal, as there are many
catch basins that have sunken in. Curb will be replaced 10’-15’ on each side with new castings except
for Lake Forest Drive. Lake Forest Drive has different, none City standard castings that will be
replaced with new ones, but retain the same different style.
Mr. Walter questioned if sanitary sewer repair costs are included and Mr. Bitter said they are in the
project costs, but it needs to be reviewed if it is an assessable cost or not.
Chairman Yliniemi inquired if the ground is unstable. Mr. Bitter said the water table is high and the
main issue they will be facing in the project.
19. Adopt Resolution No. 2024-XXX Ordering Preparation of Report for the 2025 Commercial Full
Depth Reclamation Improvements Project Municipal Project No. 4425
Widseth Consulting Engineer Bitter reviewed Resolution No. 2024-XXX Ordering Preparation of
Report for the 2025 Commercial Full Depth Reclamation Improvements Project.
The City is planning improvements to the roadway corridors listed below in 2025. In accordance with
the Minn. Stat. 429.031, a feasibility report must be prepared outlining the following:
Whether the project is necessary
Estimated project costs and proposed funding sources
Whether the project is cost effective
Other information as necessary for council consideration
The proposed project areas are as follows; Audubon Way, Edgewood Drive (North of Novotny Road
to CSAH 77), Lake Forest Road and Whispering Woods Lane (west of Pearl Drive extending 175’ to the
east).
Mr. Bitter recommends adoption of Resolution No. 2024-XXX Ordering Preparation of Report for the
2025 Commercial Full Depth Reclamation Improvements Project.
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to adopt Resolution No.
2024-XXX Ordering Preparation of Report for the 2025 Commercial Full Depth Reclamation
Improvements Project.
20. Adopt Resolution No. 2024-XXX Receiving Revised Feasibility Report and Calling the Improvement
Hearing for the 2025 Commercial Full Depth Reclamation Improvements Project Municipal Project
No. 4425
Widseth Consulting Engineer Bitter reviewed Resolution No. 2024-XXX Receiving Revised Feasibility
Report and Calling the Improvement Hearing for the 2025 Commercial Full Depth Reclamation
Improvements Project.
Roadways and Projects Reviewed in this Report Include:
Audubon Way
Edgewood Drive (north of Novotny Road)
Lake Forest Road
Whispering Woods Lane (west of Pearl Drive extending 175’ to the east)
10/2/2024 Utilities Commission Minutes Page 11
The report reviews existing conditions, proposes feasible improvements, estimates project costs,
discusses project implementation, and presents conclusions and recommendations for the project
areas as required by the Minnesota Chapter 429 assessment process.
The report will be utilized to prepare for the Improvement Hearing scheduled for 6:00 pm on
November 7, 2024.
Mr. Bitter recommends adoption of Resolution No. 2024-XXX Receiving Revised Feasibility Report
and Calling the Improvement Hearing for the 2025 Commercial Full Depth Reclamation
Improvements Project.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to adopt Resolution
No. 2024-XXX Receiving Revised Feasibility Report and Calling the Improvement Hearing for the 2025
Commercial Full Depth Reclamation Improvements Project.
21. Approve the Widseth Agreement for Professional Engineering Services in the Not to Exceed
Amount of $9,950 for the 2028 Olivewood Drive, Jadewood Drive and Jewelwood Drive Area
Improvements Feasibility Report
Widseth Consulting Engineer Bitter reviewed the Widseth Agreement for Professional Engineering
Services in the Not to Exceed Amount of $9,950 for the 2028 Olivewood Drive, Jadewood Drive and
Jewelwood Drive Area Improvements Feasibility Report.
Proposed improvements include gravity sanitary sewer, water distribution and rural roadway
reconstruction.
Project Areas:
Olivewood Drive
Deerwood Road from Olivewood Drive to 600’ east
Woida Road from 200’ west of Jewelwood Drive to Inglewood Drive
Jewelwood Drive from Jadewood Drive to Woida Road
Jadewood Drive
The above-referenced improvements are scheduled for completion in 2028 as part of the 2024 –
2033 Capital Improvements Plan. Widseth assisted the City with the original Feasibility Reports,
which were completed in September 2006 and 2007.
This Report will combine the projects and build on prior completed work to determine estimated
project costs and assessments for the project based on current practice. The Report will be suitable
for use in a future Minnesota Chapter 429 assessment project with updates closer to project
initialization.
Public Works Director/City Engineer Walter added that the last report was done in 2005. The policy
has changed, so staff are trying to complete the CIP of what the City costs are vs what is assess vs
water costs, sewer costs, street costs, and storm water costs. Staff’s goal is to get it everything
covered in order to put the CIP together to have the CIP in front of City Council by late winter or as
early as January or February for more discussion that needs to happen.
MOTION by Commissioner Chrisofferson, seconded by Commissioner Stenberg to approve the
Widseth Agreement for Professional Engineering Services in the Not to Exceed Amount of $9,950 for
10/2/2024 Utilities Commission Minutes Page 12
the 2028 Olivewood Drive, Jadewood Drive and Jewelwood Drive Area Improvements Feasibility
Report.
22. Approve the Widseth Agreement for Professional Engineering Services in the Not to Exceed
Amount of $8,500 for the 2030 Welton Road Area Improvements Feasibility Report
Public Works Director/City Engineer Walter reviewed the Widseth Agreement for Professional
Engineering Services in the Not to Exceed Amount of $8,500 for the 2030 Welton Road Area
Improvements Feasibility Report.
Proposed improvements include installation of gravity sanitary sewer, water distribution and rural
roadway reconstruction. The improvements are scheduled for completion in 2030 as part of the
2024-2033 Capital Improvements Plan.
Project Areas:
Welton Road from Clearwater Road to 650’ north of Ashley Road
Ashley Road
Baywood Road
Black Oak Road
Springwood Drive
Mr. Walter recommends approval of the Widseth Agreement for Professional Engineering Services in
the Not to Exceed Amount of $8,500 for the 2030 Welton Road Area Improvements Feasibility
Report.
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to approve the Widseth
Agreement for Professional Engineering Services in the Not to Exceed Amount of $8,500 for the 2030
Welton Road Area Improvements Feasibility Report.
23. Adopt Resolution 2024-XXX to Enter into the Cooperative Construction Agreement with MnDOT
and City of Baxter and Crow Wing County for SP 1805-81
Assistant City Engineer Thompson reviewed the Resolution 2024-XXX to Enter into the Cooperative
Construction Agreement with MnDOT and City of Baxter and Crow Wing County for SP 1805-81.
MnDOT will perform grading, bituminous surfacing, ADA improvements, signal, lighting, and TMS
construction and other associated construction upon, along, and adjacent to Trunk Highway 210
from 1,400 feet west of Timberwood Drive to 520 feet west of Baxter Drive.
MnDOT is seeking approval from the City on the ‘State of Minnesota Department of Transportation
and City of Baxter and Crow Wing County Cooperative Construction Agreement”. According to the
agreement, there are no construction cost responsibilities for the City however there will be
maintenance responsibilities. The maintenance responsibilities are not changing from what is
currently in place.
The City will have financial implications associated with the maintenance of the lighting (2 more
streetlights), sidewalk (trail) and signal at CSAH 48. However, there are no immediate financial
implications.
10/2/2024 Utilities Commission Minutes Page 13
Mr. Thompson recommends adoption of Resolution 2024-XXX to Enter into the Cooperative
Construction Agreement with MnDOT and City of Baxter and Crow Wing County for SP 1805-81.
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to adopt Resolution 2024-
XXX to Enter into the Cooperative Construction Agreement with MnDOT and City of Baxter and Crow
Wing County for SP 1805-81.
INFORMATIONAL ITEMS
24. 2022 Trunk Highway 210 & Inglewood Drive Railway Crossing Improvements Project Update - City
of Baxter - Municipal Project No. 4121
There was no new information or questions from the commission or the public.
25. 2023 Cypress Drive and Douglas Fir Drive Improvements project – Monthly Update
There was no new information or questions from the commission or the public.
26. Camping World Site Redevelopment Traffic Impact Study - Monthly Update
There was no new information or questions from the commission or the public.
27. Whiskey Creek Stormwater Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
28. Whiskey Creek Planting Plans Project Monthly Update
There was no new information or questions from the commission or the public.
29. 2024 Water System Hydraulic Model Update and Water System 20-Year Use Projections Project
There was no new information or questions from the commission or the public.
30. 2024 Preliminary Aquifer Evaluation Monthly Update
There was no new information or questions from the commission or the public.
31. Project Timber Wolf Project Monthly Update
There was no new information or questions from the commission or the public.
32. 2023 Knollwood Drive Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
33. 2025 Design Road & TH 371 Stormwater Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
34. 2026 Mill & Overlay, Full Depth Reclamation and Reconstruction Improvements, Project Monthly
Update
10/2/2024 Utilities Commission Minutes Page 14
There was no new information or questions from the commission or the public.
35. 2023 Novotny Road Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
36. 2022 Full Depth Reclamation and Reconstruction Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
37. Baxter 20-Year Public Works Facility Assessment Project Monthly Update
There was no new information or questions from the commission or the public.
38. 2023 Whiskey Creek Pedestrian Bridge Inspection Project Monthly Update
There was no new information or questions from the commission or the public.
39. Eagle Drive Area Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
40. Assist City Staff with Assessing the Holiday Station Store Contamination at Excelsior and Hwy 371
Project Monthly Update
There was no new information or questions from the commission or the public.
41. Wellhead Protection Plan Part II Project Monthly Update
There was no new information or questions from the commission or the public.
ADJOURN
MOTION by Commissioner Stenberg, seconded by Commissioner Brenny to adjourn at 6:53 p.m. Motion carried
unanimously.
Approved by: Respectfully Submitted,
_____________________________ _____________________________
Rock Yliniemi Dani Steininger
Chairman Administrative Assistant
Agenda
UTILITIES COMMISSION AGENDA
Wednesday, October 02, 2024 at 5:30 PM
Baxter City Hall, 13190 Memorywood Drive, Baxter, MN
“A Growing Community”
CALL TO ORDER
ROLL CALL
CONSENT AGENDA
1. Accept the Utilities Commission Minutes from September 4, 2024
BUSINESS ITEMS
2. Pavement Management Plan - Micro Surfacing Program Review
3. 2024 Micro Surfacing Project Update
4. Approve ASTECH Pay Estimate No. 2 in the amount of $94,028.91 for the 2024 Micro Surfacing
Project
5. Accept the 2024 Water CAMP Report
6. 2024 Well Rehabilitation Project Update
7. Approve the Thein Well Company Change Order No. 2 in the Increased Amount of $7,450.50 for the
2024 Well Rehabilitation Project
8. 2024 Well Replacement Exploration
9. Approve the Traut Companies Change Order No. 1 in the increased amount of $23,492.50 for
additional Well Exploration Services related to the 2024 Well Replacement Exploration
10. 2023 Commercial and Residential Full Depth Reclamation and Quiet Zone Improvements project –
Monthly Update
11. Approve the Anderson Brothers Construction Company of Brainerd, LLC Partial Pay Estimate No. 11
in the amount of $99,923.35 for the 2023 Commercial and Residential Full Depth Reclamation and
Quiet Zone Improvements Project
12. 2024 South Forestview Improvements Project Monthly Update
13. Approve the RL Larson Excavating, Inc. Change Order No. 6 in the increased amount of $19,162.66
for the 2024 South Forestview Improvements Project, Municipal Project No. 4138
14. Approve RL Larson Excavating, Inc Partial Pay Estimate No. 6 in the amount of $698,703.87 for the
2024 South Forestview Area Improvements Project, Municipal Project No. 4138
15. 2024 Mill & Overlay and Full Depth Reclamation Improvements Project Monthly Update
10/2/2024 Utilities Commission Agenda Page 2
16. Approve the Knife River Corporation – North Central Change Order No. 5 in the Increased Amount of
$27,290.39 for the 2024 Mill & Overlay and Full Depth Reclamation Improvements Project, Municipal
Project Number 4424
17. Approve the Knife River Corporation – North Central Partial Pay Estimate No. 5 in the amount of
$777,280.94 for the 2024 Mill & Overlay and Full Depth Reclamation Improvements Project,
Municipal Project Number 4424
18. 2025 Commercial Full Depth Reclamation Improvements Project, Municipal Project 4425 Monthly
Project Update
19. Adopt Resolution No. 2024-XXX Ordering Preparation of Report for the 2025 Commercial Full Depth
Reclamation Improvements Project Municipal Project No. 4425
20. Adopt Resolution No. 2024-XXX Receiving Revised Feasibility Report and Calling the Improvement
Hearing for the 2025 Commercial Full Depth Reclamation Improvements Project Municipal Project
No. 4425
21. Approve the Widseth Agreement for Professional Engineering Services in the Not to Exceed Amount
of $9,950 for the 2028 Olivewood Drive, Jadewood Drive and Jewelwood Drive Area Improvements
Feasibility Report
22. Approve the Widseth Agreement for Professional Engineering Services in the Not to Exceed Amount
of $8,500 for the 2030 Welton Road Area Improvements Feasibility Report
23. Adopt Resolution 2024-XXX to Enter into the Cooperative Construction Agreement with MnDOT and
City of Baxter and Crow Wing County for SP 1805-81
INFORMATIONAL ITEMS
24. 2022 Trunk Highway 210 & Inglewood Drive Railway Crossing Improvements Project Update - City of
Baxter - Municipal Project No. 4121
25. 2023 Cypress Drive and Douglas Fir Drive Improvements project – Monthly Update
26. Camping World Site Redevelopment Traffic Impact Study - Monthly Update
27. Whiskey Creek Stormwater Improvements Project Monthly Update
28. Whiskey Creek Planting Plans Project Monthly Update
29. 2024 Water System Hydraulic Model Update and Water System 20-Year Use Projections Project
30. 2024 Preliminary Aquifer Evaluation Monthly Update
31. Project Timber Wolf Project Monthly Update
32. 2023 Knollwood Drive Improvements Project Monthly Update
33. 2025 Design Road & TH 371 Stormwater Improvements Project Monthly Update
10/2/2024 Utilities Commission Agenda Page 3
34. 2026 Mill & Overlay, Full Depth Reclamation and Reconstruction Improvements, Project Monthly
Update
35. 2023 Novotny Road Improvements Project Monthly Update
36. 2022 Full Depth Reclamation and Reconstruction Improvements Project Monthly Update
37. Baxter 20-Year Public Works Facility Assessment Project Monthly Update
38. 2023 Whiskey Creek Pedestrian Bridge Inspection Project Monthly Update
39. Eagle Drive Area Improvements Project Monthly Update
40. Assist City Staff with Assessing the Holiday Station Store Contamination at Excelsior and Hwy 371
Project Monthly Update
41. Wellhead Protection Plan Part II Project Monthly Update
ADJOURN