Utilities Commission
Regular MeetingBaxter, MN · December 4, 2024
Minutes
UTILITIES COMMISSION MINUTES
Wednesday, December 04, 2024 at 5:30 PM
Baxter City Hall, 13190 Memorywood Drive, Baxter, MN
“A Growing Community”
CALL TO ORDER
The regular meeting of the Baxter Utilities Commission was called to order at 5:30 p.m. by Chairman Rock Yliniemi.
ROLL CALL
Members Present: Commissioner Douglas Stenberg, Jack Christofferson, Chairman Rock Yliniemi and Council
Liaison Mark Cross.
Members Absent: Commissioner John Brenny.
Staff Present: Public Works Director/City Engineer Trevor Walter, Assistant City Engineer Trevor Thompson, and
Public Works Administrative Assistant Mary Haugen.
Other Present: SEH Consulting Engineers Neil Heinonen, Alex Voit, Senior Water Engineer Kevin Young, & Senior
Engineer Water Services Chad Katzenberger, and WiDSETH Consulting Engineer Alex Bitter.
CONSENT AGENDA
1. Approve the Utilities Commission Minutes from November 7, 2024
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve the
Utilities Commission minutes from November 07, 2024. Motion carried unanimously.
BUSINESS ITEMS
2. Recommend Planning and Zoning Commission Approve the Baxter Storage Preliminary and Final Plat
Assistance City Engineer Thompson explained the developer that had initiated the conversation by
submitting the petition to extend sanitary sewer and water to the corner of Inglewood Drive and CSAH
77 has submitted a preliminary and final plat to dedicate the easements over the water main and the
sanitary sewer main.
The plat includes combining three existing metes and bounds lots of records into one outlot. When
the developer is ready to move forward with the development, the property will need to be re-platted.
The plat includes the dedication of the additional 7-feet of right-of-way along Inglewood Drive to meet
the 80-foot right-of-way requirement in the Baxter City Code.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to recommend the
Planning and Zoning Commission approve the Baxter Storage Preliminary and Final Plat. Motion carried
unanimously.
3. Approve the True North Controls Quote in the Not-to-Exceed Amount of $13,000 for Onsite
Communication Controls
12/4/2024 Utilities Commission Minutes Page 2
Public Works Director/City Engineer Walter informed the commission that staff have been battling
poor radio communications associated with various lift stations, it is uncertain to the exact reasoning
of why this is happening. It could be due to poor signal strength, too powerful signal strength,
structural interference (trees, buildings, etc.), deteriorating antennas/cabling at sites, or interference
from the other radio systems among other things. This has been causing staff to receive
communication fails on a regular basis, with the majority of the callouts on nights and weekends.
Mr. Walter stated that the existing MDS radios are antiquated and do not contain onboard diagnostic
tools to help troubleshoot the radio systems. The current telecommunication system is costing the city
a lot in time and wasted resources.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to approve the True
North Controls Quote in the Not-to-Exceed amount of $13,000 for Onsite Communication Controls.
Motion carried unanimously.
4. Whiskey Creek Stormwater Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
5. Approve the J.R. Ferche, Inc. Partial Pay Estimate No. 6 (Final) in the amount of $71,800.77 for the
Whiskey Creek Stormwater Improvements Project, Municipal Project Number 200292
Public Works Director/City Engineer Walter reviewed the J.R. Ferche, Inc. Final Pay Estimate No. 6 in
the amount of $71,800.77. Final Pay Estimate No. 6 includes work completed in the amount of
$4,442.15. The payment includes the cost of unit price work completed during the sixth pay period to
November 21, 2024. This pay estimate includes additional rock stabilization by the bridge abutment
identified during a final site walk through on November 19th, 2024 (paid under the topsoil borrow bid
item) and seeding and stabilization to finish the project. All items are within the contract amount of
$1,353.005.82 approved by Council on March 19, 2024. Additionally, Final Pay Estimate No. 6 includes
releasing the project retainage.
The final punch list items were addressed on November 21, 2024, and it was confirmed that J.R.
Ferche’s portion of the site has reached the recommended stabilization. The removal of the sand pile
will be completed under a separate agreement between J.R. Ferche, Inc. and Good Samaritan, and is
no longer considered part of their contract with the City.
The contractor has submitted IC-134 tax forms at this time and Mr. Walter has no concerns and
recommends approval of the final payment.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to approve the J.R.
Ferche, Inc. Final Pay Estimate No. 6 in the amount of $71,800.77 for the Whiskey Creek Stormwater
Improvements Project. Motion carried unanimously.
6. Whiskey Creek Planting Plans Project Monthly Update
There was no new information or questions from the commission or the public.
7. Approve the MNL, Inc. Partial Pay Estimate No. 2 in the amount of $6,270.00 for the Whiskey Creek
Stormwater Improvements Project, Municipal Project Number 200292
12/4/2024 Utilities Commission Minutes Page 3
Public Works Director/City Engineer Walter reviewed the Partial Pay Estimate No. 2 in the amount of
$6,270.00 for the Whiskey Creek Stormwater Improvements Project Plantings. The payment includes
the cost of unit price work completed from July 26, 2024 to October 8, 2024.
The pay estimate includes 1-year of warranty work. The plantings will be monitored over the course of
the 3-year warranty period and a portion of the remaining budget may be used for additional plantings
to reinforce any locations that may be struggling. The contractor will provide warranty services for
three years following completion of the project.
The project is currently tracking under budget, but it will require maintenance for the next two years.
The remaining budget may be spent on replacement plantings if the need arises. The contingency of
$11,934.23 is budgeted for and is not anticipated to be spent.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve the MNL,
Inc. Partial Pay Estimate No. 2 in the amount of $6,270.00 for the Whiskey Creek Stormwater
Improvements Project. Motion carried unanimously.
8. 2024 Well Rehabilitation Project Update and Summary
Senior Water Engineer Young presented the 2024 Well Rehabilitation Project Summary to the
commission. The presentation covered the well rehabilitation, results, 2025 water demand projects
and recommendations.
Well 3 Rehabilitation (04.12.2024 – 04.25.2024)
Thein began the initial rehabilitation for Well 3 by pulling the pump and associated equipment on April
12. The pre-rehabilitation specific capacity for the well was 12.9 gpm/ft. The well was televised after
flushing and allowing the well to sit stagnant for two days.
Mechanical cleaning was then completed with the wire brush and the casing was bailed. The following
day, chemical cleaning began with the addition of 70 gallons of Nu-Well 120/Nu-Well 310. The next
morning, the pH was at 4, therefore, Thein added another 28 gallons of Nu-Well 120/Nu-Well 310 to
bring the pH back down to 3.
Surging was completed and the well was pumped to remove the chemical and return the water to a
normal pH. Performance pumping took place on April 19 and the specific capacity was calculated to be
16 gpm/ft pumping at 600 gpm, representing a 20% increase in specific capacity.
On April 22, Thein televised prior to chlorinating the well and pumping to waste. The pumping
equipment was replaced, and the well was put back in service following receipt of bacteria testing
results on April 25. Thein replaced 42 feet of drop pipe in Well 3 due to concerns over pitting and
corrosion on the pipe.
Since the rehabilitation was not able to return Well 3 to it’s 2023 inspection specific capacity, the City
asked SEH to review the results with Thein and evaluate whether a second rehabilitation would be
beneficial. Well 1 required back-to-back rehabilitations in 2011 to return its capacity to near design
conditions.
Well 2 Rehabilitation (04.25.2024 – 05.06.2024)
12/4/2024 Utilities Commission Minutes Page 4
Following the rehabilitation of Well 3, Thein began pulling pump and equipment from Well 2 on April
25. The pre-rehabilitation specific capacity for the well was 19.8 gpm/ft. The well was flushed and
allowed to sit stagnant for two days before televising.
Well 2 was televised on April 29 before mechanical cleaning by wire brushing was completed.
Televising for this well showed a similar state of the screen as Well 3, with minimal build up visible on
the screen. The following day, Thein jetted the well for 8 hours, at which point, the specific capacity
plateaued so jetting was stopped. After jetting was complete, 70 gallons of Nu-Well 120/Nu-Well 310
chemical was added to Well 2 for the initial chemical treatment on May 1. When the pH was verified
the next day, it had remained below 2, therefore, additional chemical was not added. Surging was
completed and the well was pumped to remove the chemical and return the water to a normal pH.
On May 2, Thein completed performance pumping of the well until there was no more improvement
in specific capacity. The final specific capacity was 21.0 gpm/ft, an approximately 6% increase from the
initial specific capacity of 19.8 gpm/ft. On May 6, Thein televised prior to chlorinating the well and
pumping to waste. Pumping equipment was replaced and the well was put back in service following
receipt of bacteria testing results on May 7.
Well 3 Additional Rehabilitation (6.7.2024 – 6.19.2024)
Since the initial Well 3 rehabilitation was not able to restore the specific capacity to January 2023
values, the City decided to conduct a second rehabilitation utilizing WaterSafe AR for the chemical
treatment. Thein Well previously used WaterSafe AR successfully in Baxter and other cities so it was
decided to use it for the second rehabilitation instead of the Johnson Screens Nu-Well chemicals in an
attempt to further increase the Well 3 specific capacity. The starting specific capacity for this
rehabilitation was 16.0 gpm/ft.
The Well 3 pump equipment was pulled and jetting began on June 10. Thein continued to jet at
approximately 175 gpm and monitor specific capacity. On June 11, chemical treatment began with the
addition of 180 gallons of WaterSafe AR to the well. Surging began and continued the following day,
while the chemical mixture was left in the well overnight. At the conclusion of the second day of
surging, chlorine and acetic acid were added to the well and left overnight for disinfection. On June 19,
Thein removed the surge block and began pumping the well and chlorine to waste, followed by
collecting bacteria testing samples. Pumping equipment was replaced and the well was put back in
service following receipt of bacteria testing results.
The final specific capacity for Well 3 was 18 gpm/ft, resulting in a 13% increase in specific capacity for
this rehabilitation and a total of nearly 40% increase in specific capacity between both rehabilitations.
Following the rehabilitation of Wells 2 and 3, the City decided to delay the rehabilitation of Wells 1 and
4 until the fall of 2024.
Well 4 Rehabilitation (09.09.2024 – 09.16.2024)
After the Well 3 rehabilitation was complete in June 2024, SEH reached out to Johnson Screens for a
recommendation to improve the rehabilitation results. Johnson Screens recommend adding Nu-Well
400 to the chemical solution used for cleaning. Nu-Well 400 is a dispersant chemical which is designed
to increase the chemical penetration into the aquifer formation to improve the cleaning process.
Thein began the rehabilitation of Well 4 by pulling the pump and equipment on September 9. The
initial specific capacity for the well was 13.8 gpm/ft. The well was televised the following day. Thein
then began jetting and pumping to loosen material on the screen. On September 11, Thein added 20
12/4/2024 Utilities Commission Minutes Page 5
gallons of Nu-Well 310, 50 gallons of Nu-Well 120, and 1 gallon of Nu-Well 400 to the well to react
overnight. The following day, Thein began surging and continued throughout the day.
The pH in the well remained adequately low overnight and additional chemical did not need to be
added. Thein continued surging throughout the following day. Thein started and stopped pumping to
“burp” any extra chemical out. The post-rehabilitation specific capacity was 21.1 gpm/ft at a pumping
rate of 590 gpm. Thein then put chlorine in the well for disinfection over the weekend. Thein televised
on September 16 and collected bacteria samples for analysis. Bacteriological testing results were
received on September 18 before the well was put online.
When the drop pipe was removed from Well 4 it was found to have corrosion pitting and was
recommended to be replaced. All the drop pipe was replaced. Thein left the abandoned well drop pipe
for Well 4 per the City’s request.
Well 1 Rehabilitation (09.23.2024 – 09.30.2024)
Thein began pulling the pump and equipment from Well 1 on September 23. The initial specific capacity
for the well was 18.9 gpm/ft with the well being pumped at 270 gpm. The well was televised the next
day, followed by jetting and pumping to loosen material on the screen. On September 24, Thein added
20 gallons of Nu-Well 310, 50 gallons of Nu-Well 120, and 1 gallon of Nu-Well 400 to the well to react
overnight. The following day, Thein began surging and continued throughout the day.
The pH of the water in the well remained at an acceptable level so no additional chemical was added
and Thein continued to surge on September 26. The next day, Thein installed the pump and pumped
to determine the specific capacity. Thein recorded the final specific capacity at 22.2 gpm/ft being
pumped at 633 gpm. On September 30, Thein completed post-televising of the well and collected
bacteria testing samples. The well was placed in service upon receipt of bacteria testing results on
October 2. After the wells were placed back in service, Thein assisted with identifying the depth of the
well level transducers.
Summary of Rehabilitation Results
Flow:
When the wells were drilled the well pumps were capable of individually producing more than 700
gpm, which was not advised. In 2013, the well pumps were replaced to target a flow rate of 700 gpm.
During the 2023 well inspection by Thein Well, all pumps could produce about 700 gpm before the
historically high-water demand experienced during the summer of 2023 required all four (4) wells to
run at the same time for the first time since the wells were drilled.
The maximum flow rate from each well, with all four (4) wells running for a short period of time, was
tested on November 21, 2024, after the 2024 rehabilitation work was complete. Only Well 3 was
capable of pumping more than 600 gpm to the Water Treatment Plant. The total pumping capacity
from the well pumps is nearly 500 gpm less than the 2013 design flow rates.
Reduced pumping rates are often correlated to clogged well screens, pump or motor issues, declining
water levels, or changing aquifer conditions. Knowing the wells screens are not clogged after
rehabilitation, the reduced flows can be correlated to the lower pumping water levels. It is also possible
that the pump impellers are experiencing some wear and are no longer able to pump at their original
capacity or that the aquifer conditions changed outside of the radius that can be reached by the typical
well rehabilitation methods used.
Specific Capacity:
12/4/2024 Utilities Commission Minutes Page 6
Specific capacity is the volume of water that can be pumped from a well per foot of decreased water
level during pumping, measured in gallons per minute of foot of drawdown (gpm/ft). It is often tracked
to use as an indicator of well condition. The 2024 well rehabilitation efforts increased the specific
capacity of each well when compared to the pre-rehabilitation specific capacities with improvements
ranging from 6% to 53%, as presented in Table 2. However, none of the wells had the specific capacity
restored to their March 2023 levels. The specific capacities were restored to 52-60% of the March
2023 specific capacities.
2025 Water Demand Projections:
Mr. Young stated that it is important to look ahead to 2025 and begin to plan for the possibility of high
summer demands like those experienced in 2023 to determine if the wells will be able to meet the
City’s water demand.
Based on the projected 2025 water demands, the City may need to purchase up to roughly 600,000
gallons per day (420 gpm) from Brainerd to meet the average summer day (ASD) demands if the well
field is only able to sustainably produce 1,800 gpm over 18 hours per day. If the well field is able to
sustain 2,300 gpm the City would likely keep up with demands on an average day. However, up to
1,000,000 gallons per day (700 gpm) may need to be purchased on an intermittent basis to meet
maximum summer day (MSD) demands. The volume of supplemental water that may be needed will
depend on well/pumping conditions, weather (which impacts water demand), and operational
limitations of the interconnect.
During the summer of 2024, Brainerd Public Utilities (BPU) requested that Baxter purchase a consistent
volume of water to reduce the stress on their system. The City of Baxter currently charges $3.68/1,000
gallons while BPU charges $4.10/1,000 gallons for commercial customers.
If the minimum flow of 300 gpm was purchased from BPU consistently throughout the summer, it
would cost the City about $27,600 more than customers would be charged for the water. For
comparison, the average cost of the well rehabilitations completed in 2024 was nearly $32,000 per
well, not including engineering, meaning the added cost of purchasing supplemental water from
Brainerd is estimated to be less than the cost to rehabilitate one well.
Recommendations:
Operate multiple wells at lower flow rates to reduce the drawdown in the well field. For
example, rather than pumping two (2) wells at 700 gpm each to produce 1,400 gpm the City
could use three (3) wells each pumping about 465 gpm to keep the water level in the wells
higher. Pumping from a higher water surface elevation in the aquifer also reduces the amount
of electricity used to pump the water. SEH recommends targeting a pumping water level of
less than about 60’ across the well field, consistent with the summer 2024 recommendations.
This recommendation is not a hard limit, as operators need to balance water production and
pumping water level. If pumping levels begin to follow a dropping trend as demands pick up,
water may need to be purchased from Brainerd.
o The maximum pumping level for the wells is about 80’ to maintain a required column of
water over top of the pump without breaking suction. However, as the pumping level
drops below 60’ it is anticipated that the formation in the vicinity of the well will foul at an
increased rate like it did in 2023, so there may be diminishing returns from dropping the
pumping level below 60’ to not purchase water from Brainerd.
Replace pumps for Wells 1 and 4 to achieve up to 700 gpm from each well. The existing well
pumps are no longer capable of producing 700 gpm as they were designed. This is likely due
to a combination of lower pumping water levels or pump/impeller wear. Prior to the filter
12/4/2024 Utilities Commission Minutes Page 7
rehabilitation project when variable frequency drives (VFDs) were installed, the City relied on
pump impellers being trimmed to target a desired flow. Now that VFDs are in place, the City
has more flexibility to operate the wells at varying flow rates and dial the VFD speed back to
reduce the flow rate as aquifer conditions require.
o It is recommended that the City’s future well field operation strategy consist of primarily
operating existing Wells 1 and 4 with the proposed Wells 5 and 6 to maximize pump
spacing and reduce interference between the wells. In this case Wells 1 and 4 would still
be relied on to produce up to 700 gpm. When Wells 2 and 3 are used it would be
recommended to pump Wells 1 and 3 or Wells 2 and 4, again to minimize interference
between the wells. Wells 5 and 6 would be allowed to pump with either previous
combination or with Wells 2 or 3. Assuming Wells 5 and 6 are constructed with a 700-gpm
capacity, this would not require Wells 2 and 3 to produce 700-gpm in the short-term.
o SEH recommends purchasing new pumps for Wells 1 and 4 so they are able to pump 700
gpm to the WTP, but dial the speed setting back during lower demand periods or as aquifer
conditions require to reduce stress on the aquifer.
o Thein has indicated that the lead time for new pumps matching the existing pump
model would be about 5-6 weeks after the pump is ordered. The lead time could be
reduced to about 4 weeks if a different pump manufacturer was selected.
o Thein reported that it will be cheaper to install new pumps than to pull the pumps,
replace the impellers, and then reinstall them. It is estimated that each new pump will cost
about $15,000.
Drill additional production wells to relieve the stress on the existing well field. SEH is currently
under design on proposed Wells 5 and 6. It is anticipated that the wells will be drilled during
the summer of 2025, but it is unlikely that they will be able to pump water to the WTP until
the end of the summer high demand period.
Monitor specific capacity. If the individual well specific capacities drop to the Well
Rehabilitation Trigger Specific Capacity, the well(s) should be rehabilitated. The Well
Rehabilitation Trigger Specific Capacity is based on the specific capacity dropping 20% from
the 2024 post-rehabilitation level.
Discuss wholesale water rates with Brainerd Public Utilities. While the volume of water that
may be required to supplement flows from Baxter’s wells can’t be quantified to an exact
number, it could be up to 85 million gallons during the summer of 2025. Similar to 2021 when
the City purchased all of its water from Brainerd when the WTP was offline for filter
reconstruction, the City should discuss water rates with BPU prior to summer demands picking
up. Also, it may be beneficial to install a modulating flow control valve at the interconnect if
supplemental flows less than 300 gpm would be sufficient to meet the City’s water demand.
Mr. Young did note that the City was awarded a $50,000 grant from Sourcewell for rehabilitation of
Well Nos. 1 & 4. Mr. Walter mentioned the City will reach out to Sourcewell to see if any grant
opportunities are available for purchasing pumps and motors for Wells 1 and 4.
The commission held an extensive discussion on the original drilling of the well, pumping of the wells
and capacity. Mr. Young stated that he was seeking action on requesting quotes for replacing the pump
at Well No. 1 and Well No. 4. Consensus of the commission was to request quotes for Well No. 1 and
Well No. 4 and return with this information at the January meeting.
9. Approve the Thein Well Company Final Pay Application No. 1 in the amount of $158,341.50 for the
2024 Well Rehabilitation Project
12/4/2024 Utilities Commission Minutes Page 8
SEH Senior Water Engineer Young reviewed the Thein Well Company Final Pay Application No. 1 in the
amount of $158,341.50 for the 2024 Well Rehabilitation Project. This is the first and final pay
application to be submitted by Thein Wells and this payment will close out the project.
Mr. Young stated that Thein Well Company completed the rehabilitation work on September 30, 2024
and submitted the required project closeout documentation. Mr. Young had no concerns with Final
Pay Application No. 1 and recommends approval.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to approve the Thein
Well Company Final Pay Application No. 1 in the amount of $158,341.50 for the 2024 Well
Rehabilitation Project. Motion carried unanimously.
10. 2024 Well Replacement Exploration Monthly Update
SEH Consulting Engineer Heinonen stated that a preliminary report is anticipated to be completed
during December 2024 following completion of field tasks and pending all soil and laboratory testing
results being available. The final report is anticipated to be presented to the Utilities Commission in
January.
11. Approve SEH Fee Amendment No. 1 in the Not To Exceed Amount of $27,600.00 for additional
engineering services related to the 2024 Well Replacement Exploration project
SEH Consulting Engineer Heinonen reviewed Fee Amendment No. 1 in the Not To Exceed Amount of
$27,600.00 for Additional Engineering Services Related to the 2024 Well Replacement Exploration
Project.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve the SEH
Fee Amendment No. 1 in the Not To Exceed Amount of $27,600.00 for Additional Engineering Services
Related to the 2024 Well Replacement Exploration Project. Motion carried unanimously.
12. Water Supply Improvements Project – Wells 5 & 6 Monthly Update
SEH Consulting Engineer Heinonen stated that bidding documents will be prepared for presentation to
the Utilities Commission to obtain approval to advertise for bidding at the January 8, 2025 Utilities
Commission meeting.
13. Accept Water System Planning and Hydraulic Model Report
SEH Senior Engineer Water Services Katzenburger reviewed presented the Water System Planning and
Hydraulic Model Report. The report addressed the following items:
Water Model Update – Calibrate water model and utilize the model to demonstrate present
and future scenarios to assist City planning efforts.
Water Demand Analysis and Projections – Model water demand projections based on
population projects and predicted future land use.
Trunk Highway 210/371 Trunk Water Main Changes – Utilize the model to recommend
improvements to maintain desired system operations as major changes are expected at the
intersection of trunk highways 210 and 371.
Ultimate Water System Planning – Provide system recommendations to enhance system
performance and plan for adequate infrastructure growth to accommodate the projected
growth.
12/4/2024 Utilities Commission Minutes Page 9
Mr. Katzenburger explained that one of the first uses of the updated model was to evaluate the
necessary water main rerouting changes for pipe that will be impacted by the pending Hwy 371/210
interchange project. The model was used to evaluate various alternatives for relocating the water
main. The conclusion of the evaluation determined that a large portion of the conflicting main could
be removed from service with minimal hydraulic impacts, provided the prescribed water main looping
occurs along the proposed alignment when Fairview Road is connected to Excelsior Road. This
evaluation provided valuable insight in that much of the impacted main does not need to be re-routed
and re-installed, saving utility costs. The evaluation proved that 2,700 LF of decommissioned water
main could be replaced in function by the installation of the 600 LF of water main proposed with the
Fairview Road extension.
In addition to evaluation the TH 371/210 interchange water main, an overall water system evaluation
was conducted with numerous water model simulations. These simulations allow for system pressure
and fire flow to be evaluated across the entire system. One area of interest is the West side of the City
where industrial growth is a potential. Currently the available fire flow in this area is limited. The model
was used to evaluate potential improvements including a new elevated water storage tank and/or a
trunk water main (previously defined in the ultimate water system planning map. The analysis
concluded that the proposed looped trunk main would have a positive impact on available fire flow,
meeting flow goals for the area. While this area is still the preferred location for the next elevated
storage tank, the installation of the trunk main loop will bolster fire protection capabilities in the near
term.
Public Works Director/City Engineer Walter inquired on the cost to update the report every couple of
years. Mr. Katzenburger stated an estimated $5,000.00 - $10,000.00.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to accept the SEH
Water System Planning and Hydraulic Model Report. Motion carried unanimously.
14. 2024 South Forestview Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
15. Approve the RL Larson Excavating, Inc. Change Order No. 7 in the increased amount of $17,015.82
for the 2024 South Forestview Improvements Project, Municipal Project No. 4138
SEH Consulting Engineer Heinonen reviewed the RL Larson Excavating, Inc. Change Order No. 7 in the
increased amount of $17,015.82 for the 2024 South Forestview Area Improvements Project.
The change order includes the following items:
Part 1: During initial startup and testing, the new weather warning siren was found not to be
communicating properly with the City and County’s emergency system. The Engineer and City
requested that the contractor and subcontractor coordinate with the company that completes
programming for the storm sirens within the County’s system. This work was considered extra
work related to the project.
Part 2: As part of the construction process for installation of the lift station control panel and
associated wiring, an initial site meeting was held with staff from the Minnesota Department
of Labor and Industry (MnDLI) to review installation procedures and code compliance.
Following this meeting, a MnDLI inspection was completed on a different lift station project in
the city which resulted in necessary modifications to conduit placement and vent piping
12/4/2024 Utilities Commission Minutes Page 10
clearance. Upon further review of the recent inspection and continued conversations with the
MnDLI Inspector, it was determined that modifications to conduit and vent piping at Lift
Stations 25 and 26 would be required to pass the formal electrical inspection. Subsequently,
the Contractor modified the conduit layout and returned the original vent pipe to the
manufacturer to add a section of piping to make it taller.
Part 3: During construction, the support brackets approved for the lift station piping were
lagging for delivery, so the City requested alternate more readily available brackets to allow
the startup to occur sooner than the contract required. This Change Order includes material
cost for the alternate brackets. The original brackets ordered for the project will be delivered
to the City and included in their inventory for future use.
Part 4: During construction of the trailhead area near the southernmost limit of Forestview
Drive, City Staff requested that fill material be imported to build a slight berm between the
trail and the paved cul-de-sac area to enhance the visual barrier between the end of the cul-
de-sac and Highway 371.
Part 5: After initial construction of the barricades, the City noted their preference for
aluminum barricade panels. The project specifications did not require aluminum panels for the
permanent barricades.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to approve the RL
Larson Excavating, Inc. Change Order No. 7 in the amount of $17,015.82 for the 2024 South Forestview
Area Improvements Project. Motion carried unanimously.
16. Approve RL Larson Excavating, Inc Partial Pay Estimate No. 8 in the amount of $52,827.76 for the
2024 South Forestview Area Improvements Project, Municipal Project No. 4138
SEH Consulting Engineer Heinonen reviewed the RL Larson Excavating, Inc Partial Pay Estimate No. 8
in the amount of $52,827.76 for the 2024 South Forestview Area Improvements Project.
The contractor has earned $5,802,290.46 to date, which represents 94.5% of the contract value. The
retainage is being withheld in the amount of 5% as per the contract.
Mr. Heinonen has no concerns with the Partial Pay Estimate No. 8 and recommends approval.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve the RL
Larson Excavating, Inc. Partial Pay Estimate No. 8 in the amount of $52,827.76 for the 2024 South
Forestview Area Improvements Project. Motion carried unanimously.
17. 2023 Commercial and Residential Full Depth Reclamation and Quiet Zone Improvements Project
Monthly Update
SEH Consulting Engineer Voit informed the commission that the signs that were approved with Change
Order No. 10 and are expected to be installed on Monday, December 9th.
18. Approve the Anderson Brothers Construction Partial Pay Estimate No. 12 in the amount of
$20,234.18 for the 2023 Commercial and Residential Full Depth Reclamation and Quiet Zone
Improvements Project
SEH Consulting Engineer Voit reviewed the Anderson Brothers Construction Partial Pay Estimate No.
12 in the amount of $20,234.18 for the 2023 Commercial and Residential Full Depth Reclamation and
Quiet Zone Improvements Project.
12/4/2024 Utilities Commission Minutes Page 11
Mr. Voit has no concerns with the Partial Pay Estimate No. 12 and recommends approval.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve the
Anderson Brothers Construction Partial Pay Estimate No. 12 in the amount of $20,234.18 for the 2023
Commercial and Residential Full Depth Reclamation and Quiet Zone Improvements Project. Motion
carried unanimously.
19. 2023 Knollwood Drive Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
20. Approve the Knife River Corporation – North Central Final Pay Estimate No. 9 in the amount of
$38,330.17 and amend the project budget in the increased amount of $5,657.73 from $2,376,379.07
to $2,382,036.80 for the 2023 Knollwood Drive Improvements Project, Municipal Project Number
4132
WiDSETH Consulting Engineer Bitter reviewed the Knife River Corporation – North Central Final Pay
Estimate No. 9 in the amount of $38,330.17 and requested to amend the project budget in the
increased amount of $5,657.73 from $2,376,379.07 to $2,382,036.80 for the 2023 Knollwood Drive
Improvements Project.
The payment includes the remaining cost of unit price work completed on the project and releasing
the remaining retainage. In January of 2024, the budget was amended to be $2,376,379.07. With the
final pay estimate, the final project cost is $2,382,036.80. This results in the project being over the
originally approved budget set when adopting the assessment roll by $169,195.54. A couple of the
reasons the project is over budget is listed below:
Excavation Special (Pond Excavation) – Additional excavation was required in the stormwater
ponds located on the Forestview Middle School site to bring the bottom of the ponds 6” below
the end of stormwater inlet apron.
Common Labor, Skid loader, and Street Sweeping - These items are included in the quantities
to pay for miscellaneous construction and clean up items. The quantities exceeded planned
quantity because they were used to compensate the Contractor for assistance with private
utility company relocation efforts.
Bituminous Driveway Replacement - Additional driveway replacement was necessary to
address grading and drainage issues. These driveways were removed further back than
planned to address these issues. 6” Concrete Walk, Truncated Domes and Signage– Additional
trail/pedestrian crossings were added after the project was bid to provide pedestrian
connectivity to intersecting streets on the west side of Knollwood Drive.
Turf Establishment - Project cost saving measures were implemented during the project which
included removing sodding item and replacing it with seeding and an organic matrix. This was
a significant savings, but anticipated quantities were exceeded due to slightly larger seeding
areas than estimated in the stormwater ponds and slightly wider seeding areas for the
roadway construction with the private utility relocations.
Hydrant & Valve Replacement – There were hydrants that could not be fully restored as
specified in the contract, so City staff elected to replace those hydrants to keep them
operational.
Televising & Jetting Sanitary & Storm Sewer – This item was not included in the original project
budget and has become a standard practice by the City to jet and televise before and after a
project.
12/4/2024 Utilities Commission Minutes Page 12
Engineering Fee Amendment – there were additional services completing the stormwater
pond cleaning and restoration work on the Forestview Middle School site. The Council
approved the fee amendment on October 17, 2023.
Mr. Bitter had no concerns with Final Pay Estimate No. 9 and recommends approval.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to approve the Knife
River Corporation – North Central Final Pay Estimate No. 9 in the amount of $38,330.17 and requested
to amend the project budget in the increased amount of $5,657.73 from $2,376,379.07 to
$2,382,036.80 for the 2023 Knollwood Drive Improvements Project. Motion carried unanimously.
21. 2024 CSAH 77 Utility Improvements Project Monthly Project Update, Municipal Project No. 4118
There was no new information or questions from the commission or the public.
22. Approve the Pratt’s Affordable Excavating, Inc. Change Order No. 1 in the increased amount of
$4,656.70 for the CSAH 77 Utility Improvements Project, Municipal Project Number 4118
WiDSETH Consulting Engineer Bitter reviewed the Pratt’s Affordable Excavating, Inc. Change Order No.
1 in the increased amount of $4,656.70 for the CSAH 77 Utility Improvements Project.
The change order includes the following item:
Hydrant extensions used to adjust hydrant to the proper grade.
Mr. Bitter had no concerns with Change Order No. 1 and recommends approval.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve Pratt’s
Affordable Excavating, Inc. Change Order No. 1 in the increased amount of $4,656.70 for the CSAH 77
Utility Improvements Project. Motion carried unanimously.
23. Approve Pratt’s Affordable Excavating, Inc. Partial Pay Estimate No. 2 in the amount of $79,864.86
for the 2024 CSAH 77 Utility Improvements Project, Municipal Project 4118
WiDSETH Consulting Engineer Bitter reviewed Pratt’s Affordable Excavating, Inc. Partial Pay Estimate
No. 2 in the amount of $79,864.86 for the 2024 CSAH 77 Utility Improvements Project.
The contractor has earned $483,372.10 which represents 87% of the contract value. In accordance
with the contract documents, retainage is being withheld in the amount of 5% of the contract value or
$27,785.50. The results in a payment of $79,864.86.
Mr. Bitter had no concerns with Partial Payment No. 2 and recommends approval.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve Pratt’s
Affordable Excavating, Inc. Partial Pay Estimate No. 2 in the amount of $79,864.86 for the 2024 CSAH
77 Utility Improvements Project. Motion carried unanimously.
24. Approve the Widseth Proposal for Professional Construction and Post Construction Services in the
Not to Exceed Amount of $83,320.00 for the 2024 CSAH 77 Utility Improvements Project, Municipal
Project 4118
12/4/2024 Utilities Commission Minutes Page 13
WiDSETH Consulting Engineer Bitter reviewed the Widseth Proposal for Professional Construction and
Post Construction Services in the Not to Exceed Amount of $83,320.00 for the 2024 CSAH 77 Utility
Improvements Project. The cost for the construction related service was included in the overall project
budget and assessed to the benefiting property owners.
The proposed Scope of Services is as follows:
Construction Staking
WIDSETH proposes to provide construction staking and field survey services associated with the
proposed construction. Specific tasks included with this Proposal are:
Establish vertical and horizontal control in the Project Area.
Generate staking files for the design elements shown in the plans.
Provide construction staking for removals, sanitary sewer, forcemain and watermain –
staked one (1) time.
Document staked point locations and elevations.
Provide contractor with construction staking information.
Construction Administration
WIDSETH proposes to provide construction administration services associated with construction of
the proposed improvements and coordination with the contract documents. Specific tasks included
with this Proposal are:
Coordinate execution of the contract documents.
Coordinate and attend a pre-construction conference.
Prepare project website updates.
Review contractor material submittals and shop drawings for compliance with the plans and
specifications.
Coordinate and conduct weekly construction meetings.
Project status reports and required City Council RCA’s.
SWPPP monitoring.
Preparation of contractor payment requests – up to four (4) payment requests.
Review and preparation of change orders and work directives – up to four (4) change orders.
Serve as the liaison between City, Contractor, and the Public.
Review project status, pay estimates and change orders with Utilities Commission and City
Council.
Deliverables: Electronic PDF copies of meeting agendas and minutes, pay estimates and
change orders with accompanying City Council RCA’s and pertinent project correspondence.
Construction Observation
WIDSETH proposes to provide construction observation services to document conformance to the
contract documents. Specific tasks included with this Proposal are:
Provide part-time field observation of the following items:
o Traffic control.
o Erosion control.
o Removals.
o Gravity sanitary sewer.
o Forcemain.
o Watermain.
o Restoration and project clean up.
Provide full-time field observation of the following items:
12/4/2024 Utilities Commission Minutes Page 14
o City utility modifications.
o Storm sewer.
o Concrete curb & gutter and flatwork.
o Bituminous roadway and driveways.
Observe and document testing procedures and results.
Document daily work activities for conformance to the plans and specifications.
Measure and document bid items for payment.
Assist the City with the final walkthrough and project closeout.
Deliverables: Electronic PDF copies of daily construction records, Item Record Accounts,
and
other pertinent project documentation.
Construction Materials Testing
WIDSETH proposes to sub-contract with Braun Intertec Corporation to complete required City
construction testing in accordance with City requirements and the MnDOT Schedule of Materials
Control. Items typically included with this task include:
Coordination and scheduling of Braun Intertec construction testing.
Completion of required soils testing.
Preparation of construction testing compliance documentation.
Deliverables: Construction materials testing compliance documentation in electronic PDF
format.
Post–Construction Services
WIDSETH will complete post–construction services in accordance with City requirements. Specific
tasks included with this Proposal are:
Complete record drawing survey of new or gravity sanitary sewer, forcemain and water
pipes, structures, and appurtenances. Record drawing survey for signs will be completed
using City equipment
Re-establish removed or disturbed property boundary markers
Preparation of property boundary Certificate of Survey
Preparation of “Record Drawing” document
Deliverables: Electronic PDF of record drawing documents and property boundary
Certificate of Survey for re-establishment of initially found property markers
WiDSETH proposes to perform these services for the Not To Exceed amount of $83,320.00.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve the
Widseth Proposal for Professional Construction and Post Construction Services in the Not to Exceed
Amount of $83,320.00 for the 2024 CSAH 77 Utility Improvements Project. Motion carried
unanimously.
25. 2024 Mill & Overlay and Full Depth Reclamation Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
26. Approve the Knife River Corporation – North Central Partial Pay Estimate No. 7 in the amount of
$140,078.19 for the 2024 Mill & Overlay and Full Depth Reclamation Improvements Project,
Municipal Project Number 4424
12/4/2024 Utilities Commission Minutes Page 15
WiDSETH Consulting Engineer Bitter reviewed the Knife River Corporation – North Central Partial Pay
Estimate No. 7 in the amount of $140,078.19 for the 2024 Mill & Overlay and Full Depth Reclamation
Improvements Project.
The contractor has earned $3,574,715.36 which represents 88.6% of the contract value. The payment
includes $39,237.13 of unit price work completed during this pay period along with $100,841.06 of
retainage being released. The retainage is being reduced from 5% to 2.5%, there will be enough
retainage left to address any turf issues and outstanding items in the spring.
Mr. Bitter had no concerns with Partial Payment No. 7 and recommends approval.
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to approve the Knife
River Corporation – North Central Partial Pay Estimate No. 7 in the amount of $140,078.19 for the 2024
Mill & Overlay and Full Depth Reclamation Improvements Project, Municipal Project Number 4424.
Motion carried unanimously.
27. 2025 Design Road & TH 371 Stormwater Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
28. Adopt Resolution No. 2024-096 Ordering Preparation of Report for the 2025 Design Road & TH 371
Stormwater Improvements Project Municipal Project No. 4315
WiDSETH Consulting Engineer Bitter informed that Widseth has been working with MNDOT to get the
required items submitted for the project and update the project schedule. The only remaining items
to complete are the easement documents and discussions with the property owners.
Mr. Bitter stated that an updated resolution is also being brought forward to order the preparation of
the feasibility report. The report was originally ordered by City Council as part of the 2022 Baxter Street
Improvements Project on October 19, 2021; however, Design Road was pulled from the 2022 project.
This allowed for additional time to coordinate with MNDOT on improvements related to the 210/371
Interchange Project. Since the project scope significantly changed it was appropriate to bring a new
RCA and Resolution forward ordering the Preparation of the Report.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg adopt Resolution No.
2024-096 Ordering Preparation of Report for the 2025 Design Road & TH 371 Stormwater
Improvements Project Municipal Project No. 4315. Motion carried unanimously.
29. Lift Station 13 Reconstruction Project Monthly Update
There was no new information or questions from the commission or the public.
30. Approve the Anderson Brothers Construction Change Order No. 4 in the increased amount of
$2,887.50 and Increase the Project Budget $2,887.50 from $266,290.30 to $269,177.80 for the Lift
Station No. 13 Reconstruction Project
WiDSETH Consulting Engineer Bitter reviewed the Anderson Brothers Construction Change Order No.
4 in the amount of $2,887.50 and increase the project budget from $266,290.30 to $269,177.80 for
the Lift Station No. 13 Reconstruction Project.
Change Order No. 4 addresses the following items:
12/4/2024 Utilities Commission Minutes Page 16
Repairing groundwater leaks through the wet well concrete walls.
3 pipe penetrations and a joint were sealed and repaired.
Mr. Bitter explained the Change Order revises the construction contract from $195,061.05 to
$197,948.55 and will require a contract amendment. The project budget prior to this change order was
$266,290.30. With this change order the project budget will need to be increased to $269,177.80.
Mr. Bitter had no concerns with Change Order No. 4 and recommends approval.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to approve the
Anderson Brothers Construction Change Order No. 4 in the increased amount of $2,887.50 and
increase the project budget $2,887.50 from $266,290.30 to $269,177.80 for the Lift Station No. 13
Reconstruction Project. Motion carried unanimously.
31. Approve the Anderson Brothers Construction Partial Pay Estimate 4 (Final) in the amount of
$3,887.50 for the Lift Station No. 13 Reconstruction Project
WiDSETH Consulting Engineer Bitter reviewed the Anderson Brothers Construction Final Pay Estimate
No. 4 in the amount of $3,887.50 for the Lift Station No. 13 Reconstruction Project.
Mr. Bitter stated the final pay estimate includes payment for Change Order 4 and release of remaining
retainage. Mr. Bitter had no concerns with Final Payment Estimate No. 4 and recommends approval.
MOTION by Commissioner Christofferson, seconded by Commissioner Stenberg to approve the
Anderson Brothers Construction Partial Pay Estimate 4 (Final) in the amount of $3,887.50 for the Lift
Station No. 13 Reconstruction project. Motion carried unanimously.
INFORMATIONAL ITEMS
32. 2022 Full Depth Reclamation and Reconstruction Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
33. 2023 Novotny Road Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
34. 2025 Commercial Full Depth Reclamation Improvements Project Monthly Update, Municipal Project
4425
There was no new information or questions from the commission or the public.
35. 2026 Mill & Overlay, Full Depth Reclamation and Reconstruction Improvements Project Monthly
Update
There was no new information or questions from the commission or the public.
36. Baxter 20-Year Public Works Facility Assessment Project Monthly Update
There was no new information or questions from the commission or the public.
37. Clearwater Road Development Traffic Review Monthly Update
12/4/2024 Utilities Commission Minutes Page 17
There was no new information or questions from the commission or the public.
38. Eagle Drive Area Improvements Project Monthly Update
There was no new information or questions from the commission or the public.
39. Holiday Station Store Contamination Monthly Update
There was no new information or questions from the commission or the public.
40. Lift Station No. 15 Reconstruction Project Monthly Update
There was no new information or questions from the commission or the public.
41. Project Timber Wolf Project Monthly Update
There was no new information or questions from the commission or the public.
42. Holiday Station Store Contamination Monthly Update
There was no new information or questions from the commission or the public.
43. Wellhead Protection Plan Part II Project Monthly Update
There was no new information or questions from the commission or the public.
ADJOURN
MOTION by Commissioner Stenberg, seconded by Commissioner Christofferson to adjourn the meeting at 7:45 p.m.
Motion unanimously approved.
Approved by: Respectfully submitted:
_______________________ ___________________________
Rock Yliniemi Mary Haugen
Chair Administrative Assistant
Agenda
UTILITIES COMMISSION AGENDA
Wednesday, December 04, 2024 at 5:30 PM
Baxter City Hall, 13190 Memorywood Drive, Baxter, MN
“A Growing Community”
CALL TO ORDER
ROLL CALL
CONSENT AGENDA
1. Approve the Utilities Commission Minutes from November 7, 2024
BUSINESS ITEMS
2. Recommend Planning and Zoning Commission Approve the Baxter Storage Preliminary and Final Plat
3. Approve the True North Controls Quote in the Not-to-Exceed Amount of $13,000 for Onsite
Communication Controls
4. Whiskey Creek Stormwater Improvements Project Monthly Update
5. Approve the J.R. Ferche, Inc. Final Pay Estimate No. 6 in the amount of $71,800.77, contingent upon
receiving IC-134 tax forms for the Whiskey Creek Stormwater Improvements Project, Municipal
Project Number 200292
6. Whiskey Creek Planting Plans Project Monthly Update
7. Approve the MNL, Inc. Partial Pay Estimate No. 2 in the amount of $6,270.00 for the Whiskey Creek
Stormwater Improvements Project, Municipal Project Number 200292
8. 2024 Well Rehabilitation Project Update and Summary
9. Approve the Thein Well Company Final Pay Application 1 in the amount of $158,341.50 for the 2024
Well Rehabilitation Project
10. 2024 Well Replacement Exploration Monthly Update
11. Approve SEH Fee Amendment No. 1 in the Not To Exceed Amount of $27,600.00 for additional
engineering services related to the 2024 Well Replacement Exploration project
12. 2024 Water System Hydraulic Model Update and Water System 20-Year Use Projections Project
13. Water Supply Improvements Project – Wells 5 & 6 Monthly Update
14. Accept Water System Planning and Hydraulic Model Report
15. 2024 South Forestview Improvements Project Monthly Update
16. Approve the RL Larson Excavating, Inc. Change Order No. 7 in the increased amount of $17,015.82
for the 2024 South Forestview Improvements Project, Municipal Project No. 4138
12/4/2024 Utilities Commission Agenda Page 2
17. Approve RL Larson Excavating, Inc Partial Pay Estimate No. 8 in the amount of $52,827.76 for the
2024 South Forestview Area Improvements Project, Municipal Project No. 4138
18. 2023 Commercial and Residential Full Depth Reclamation and Quiet Zone Improvements Project
Monthly Update
19. Approve the Anderson Brothers Construction Partial Pay Estimate No. 12 in the amount of
$20,234.18 for the 2023 Commercial and Residential Full Depth Reclamation and Quiet Zone
Improvements Project
20. 2023 Knollwood Drive Improvements Project Monthly Update
21. Approve the Knife River Corporation – North Central Final Pay Estimate No. 9 in the amount of
$38,330.17 and amend the project budget in the increased amount of $5,657.73 from $2,376,379.07
to $2,382,036.80 for the 2023 Knollwood Drive Improvements Project, Municipal Project Number
4132
22. 2024 CSAH 77 Utility Improvements Project Monthly Project Update, Municipal Project No. 4118
23. Approve the Pratt’s Affordable Excavating, Inc. Change Order 1 in the increased amount of $4,656.70
for the CSAH 77 Utility Improvements Project, Municipal Project Number 4118
24. Approve Pratt’s Affordable Excavating, Inc. Partial Pay Estimate No. 2 in the amount of $79,864.86
for the 2024 CSAH 77 Utility Improvements Project, Municipal Project 4118
25. Approve the Widseth Proposal for Professional Construction and Post Construction Services in the
Not to Exceed Amount of $83,320.00 for the 2024 CSAH 77 Utility Improvements Project, Municipal
Project 4118
26. 2024 Mill & Overlay and Full Depth Reclamation Improvements Project Monthly Update
27. Approve the Knife River Corporation – North Central Partial Pay Estimate No. 7 in the amount of
$140,078.19 for the 2024 Mill & Overlay and Full Depth Reclamation Improvements Project,
Municipal Project Number 4424
28. 2025 Design Road & TH 371 Stormwater Improvements Project Monthly Update
29. Adopt Resolution No. 2024-096 Ordering Preparation of Report for the 2025 Design Road & TH 371
Stormwater Improvements Project Municipal Project No. 4315
30. Lift Station 13 Reconstruction Project Monthly Update
31. Approve the Anderson Brothers Construction Change Order No. 4 in the increased amount of
$2,887.50 and Increase the Project Budget $2,887.50 from $266,290.30 to $269,177.80 for the Lift
Station No. 13 Reconstruction Project
32. Approve the Anderson Brothers Construction Partial Pay Estimate 4 (Final) in the amount of
$3,887.50 for the Lift Station No. 13 Reconstruction project
INFORMATIONAL ITEMS
33. 2022 Full Depth Reclamation and Reconstruction Improvements Project Monthly Update
12/4/2024 Utilities Commission Agenda Page 3
34. 2023 Novotny Road Improvements Project Monthly Update
35. 2025 Commercial Full Depth Reclamation Improvements Project Monthly Update, Municipal Project
4425
36. 2026 Mill & Overlay, Full Depth Reclamation and Reconstruction Improvements Project Monthly
Update
37. Baxter 20-Year Public Works Facility Assessment Project Monthly Update
38. Clearwater Road Development Traffic Review Monthly Update
39. Eagle Drive Area Improvements Project Monthly Update
40. Holiday Station Store Contamination Monthly Update
41. Lift Station No. 15 Reconstruction Project Monthly Update
42. Project Timber Wolf Project Monthly Update
43. Holiday Station Store Contamination Monthly Update
44. Wellhead Protection Plan Part II Project Monthly Update
ADJOURN