City Council Workshop
Regular MeetingBlaine, MN · September 12, 2013
Minutes
10801 Town Square Dr.
City of Blaine Blaine MN 55449
Anoka County, Minnesota
Minutes - Final
City Council Workshop
*While this is a public meeting where interested persons are
welcome to attend, it is a work session for Council and staff
to discuss issues before them. It is not for the purpose of
receiving public input.
Thursday, September 12, 2013 6:30 PM Cloverleaf Farm Room A
Meeting Number 13-44
NOTICE OF WORKSHOP MEETING
The meeting was called to order by Mayor Ryan at 6:30 p.m. Quorum
Present.
ALSO PRESENT: Bob Therres, Acting City Manager/Public Services
Manager; Thomas Sweeney, City Attorney; Bryan Schafer, Planning Director;
Joe Huss, Finance Director; Ward Brown, Financial Analyst; Chris Olson,
Police Chief/Safety Services Manager; Jean Keely, City Engineer; Roark
Haver, Communications Technician; Jane Cross, City Clerk; and Recording
Secretary Linda Dahlquist.
Present: 4 - Councilmember Kolb, Mayor Ryan, Councilmember Hovland, and
Councilmember Swanson
Absent: 3 - Councilmember Clark, Councilmember Bourke, and Councilmember
Herbst
1
Bill Goff, MnDOT Metro Districts, Brad Larson, MN Pass, and Bob Benke,
Project Coordinator for 35W Corridor. Mr. Goff gave an overview of the
project, which started in 2009 and involves twelve cities and four counties.
He gave an overview of the project’s four goals and the proposed corridor
four viable alternatives. He gave an overview of the Bus Rapid Transit (BRT)
evaluation and the projected 2030 BRT ridership. He gave an overview of
MnDOT’s five-point vision for a managed lane. He gave an overview of six
points of the implementation plan and a summary of the total corridor
expenditure as of 2011.
Councilmember Swanson commented MnDOT did look at building new
lanes.
Councilmember Kolb arrived at 6:39 p.m.
City of Blaine Page 1
City Council Workshop Minutes - Final September 12, 2013
Mr. Benke stated the next steps will be Phase I, Hwy 36 to Hwy 10. He noted
that this phase is $120,000,000 short in funding. He stated the MnDOT
Commissioner will work on raising funds with the legislature. He commented
the Federal gas tax has not been raised since 1980. He stated “earmarks” may
be brought back. He noted the project is well received by Met Council. He
stated an engineering document would take approximately 18 months in order
to apply for Federal funding.
Mayor Ryan stated the cities to the north are not in favor of managed lanes.
Councilmember Hovland asked what Blaine can do to help the project (i.e.,
lobby legislators). Mr. Benke replied communicating with legislators and the
governor. He stated a meeting will be held with all the northern cities invited
to build support.
Councilmember Swanson stated the project needs funding from the Federal
government like the project on 35W south received. He noted that 610 should
be completed within 5 years.
2 WS 13-52 PROPOSED RECONSTRUCTION OF 125TH AVENUE
FROM RADISSON ROAD THRU HARPERS STREET
INTERSECTION
Sponsors: Keely
Attachments: 125th Avenue Improvements-Location Map.pdf
Acting City Manager/Public Services Manager Therres stated staff met with
Anoka County Highway Department to discuss the City’s proposed 125th
Avenue and Harpers Street intersection improvement project. He stated in the
meeting the County shared their improvement project plans for 125th Avenue
from Radisson Road to Harpers Street in 2016. He stated the discussions led
to the County moving their project timeline forward to 2015 if the City would
take the lead on preliminary engineering and surveying. He noted combining
the projects into one in 2015 would be more efficient and cost effective.
Councilmember Swanson asked if the County has the funding for the project.
Acting City Manager/Public Services Manager Therres replied a joint powers
agreement would be written.
Councilmember Kolb asked how the residents would be impacted by the
project being pushed out. Acting City Manager/Public Services Manager
Therres replied the signal intersection would not be done. He stated the
parking work would be done as planned.
City of Blaine Page 2
City Council Workshop Minutes - Final September 12, 2013
Councilmember Kolb suggested sending letters to the residents to explain the
project delay in detail.
City Engineer Keely stated the County is going to use State Aid funding and
the project is in their capital improvement plan. She noted that the project
would be a 2014/2015 project due to right-of-way issues.
Discussed
3 WS 13-53 PROPOSED 2014 PAVEMENT MANAGEMENT PROGRAM
Sponsors: Keely
Attachments: 2014 pmp location map.pdf
City Engineer Keely stated the Engineering Department has begun the
selection of streets for the 2014 Pavement Management Program. She stated
streets are selected based on condition ratings. She gave an overview of the
program’s plan, which consists of four roads that are Municipal State Aid
Streets (MSAS), various roads for bituminous overlays and 14 roads for
partial reconstructions.
Councilmember Kolb stated she is favor of paving Jefferson. She asked if
turn lanes will be added.
Councilmember Swanson asked when 87th and Hastings would be
reconstructed. City Engineer Keely stated the Council will receive more
detail on the Pavement Management Program to review at the October 10,
2013, Workshop Meeting.
Councilmember Hovland asked about fixing the roads near the airport.
Acting City Manager/Public Services Manager Therres replied Xylite was
repaved, but no further work is planned. He noted the airport does not plan to
expand in the near future. Councilmember Swanson noted the airport did pay
half the cost for Xylite.
Councilmember Hovland asked about street markings on Oak Park Boulevard
near the Library.
Councilmember Swanson stated he has concerns about not putting the asphalt
over the curbing around Aurelia Park.
Discussed
4 WS 13-54 PROPOSED RECONSTRUCTION OF FLOWERFIELD
City of Blaine Page 3
City Council Workshop Minutes - Final September 12, 2013
ROAD AND RESTWOOD ROAD WITH THE CITY OF
LEXINGTON
Sponsors: Keely
Attachments: Location Map.pdf
City Engineer Keely stated the City of Lexington has expressed a desire to do
a joint project with the City of Blaine to reconstruct Flowerfield Road from
Naples Street to Lexington Avenue and Restwood Road from Naples Street to
Lake Drive in 2014 or 2015. She stated Flowerfield should be broken into
two projects. She proposes going ahead with the Flowerfield work east of
Lake Drive in 2014 and the rest in 2015.
Councilmember Swanson commented he has received complaints about
Flowerfield Road. Mayor Ryan commented Lexington plans to split the
project costs - City will cover 70% and assess 30%.
Councilmember Hovland asked about the City of Lexington moving utilities
from a Blaine resident’s yard on Flowerfield. He noted that the residents on
Flowerfield are sensitive to the City doing work in the area.
Discussed
5 WS 13-55 2014 PROPOSED SPECIAL REVENUE FUNDS BUDGET
Sponsors: Huss
Attachments: 2014 Proposed Charitable Gambling Fund Budget
Finance Director Huss gave an overview of the preliminary budgets for the
Cable Television Fund and the Charitable Gambling Fund. He stated the
funding source for the Cable Television Fund is comprised from franchise
fees and subscribers’ fees. He stated the net cable franchise fees are projected
to increase for 2014. He noted the proposed capital/equipment upgrade cost
for 2014 is estimated to be higher due to aging equipment
replacements/upgrades.
Councilmember Hovland asked if the reserve balance continues to grow and
not be used. Councilmember Swanson replied renewal of the franchise will
be expensive and the reserve fund will have to cover the cost.
Councilmember Swanson noted the building will be paid off in 2017 and
one-year advance payment is kept in the reserve fund.
Finance Director Huss stated the funding source for the Charitable Gambling
Fund is comprised from four active organizations’ proceeds of 10% of their
City of Blaine Page 4
City Council Workshop Minutes - Final September 12, 2013
net profits from charitable gambling operations. He noted the proposed
charitable contributions for 2014 is projected to be lower than 2013.
Councilmember Hovland would like a workshop on the City’s 50th
anniversary event. Mayor Ryan stated the committee is working on a letter.
He noted the celebration would be a year-long celebration. Council had
discussion on taking an active role on planning the 50th anniversary.
Councilmembers Hovland and Kolb are interested in participating in the
planning. Council had discussion on the celebration committee.
Finance Director Huss proposed increasing funds to the Alexandra House and
funding the Historical Society. He asked about funding Beyond the Yellow
Ribbon for 2014.
Councilmember Kolb suggested funding a small amount to the Creating
Communities organization. She noted the City used to support them in the
past.
Councilmember Swanson suggested looking into using the tourism funds and
grants for funding the 50th anniversary celebration.
Discussed
Mayor Ryan requested the Police Department and City Engineer to give an
update on the Aspen Lake Road issue to the October 10, 2013, Workshop.
City Engineer Keely replied a letter was mailed on August 8, 2013, to the
active builders in The Lakes requesting all vehicles use the parkways to access
construction sites.
Councilmember Kolb asked if there are any traffic counts and noise issues
around the new Wal-Mart. She noted she is not aware of any issues.
Councilmember Swanson asked for a status on the striping on the roundabout.
City Engineer Keely replied people are driving over the striping. Council
discussion on pedestrians crossing in a roundabout.
ADJOURN
The Workshop adjourned at 8:33 p.m.
City of Blaine Page 5
Agenda
10801 Town Square Dr.
City of Blaine Blaine MN 55449
Anoka County, Minnesota
Meeting Agenda - Final
City Council Workshop
*While this is a public meeting where interested persons are
welcome to attend, it is a work session for Council and staff to
discuss issues before them. It is not for the purpose of
receiving public input.
Thursday, September 12, 2013 6:30 PM Cloverleaf Farm Room A
Meeting Number 13-44
NOTICE OF WORKSHOP MEETING
In accordance with the provisions of Section 3.01 of the Blaine City Charter, a Council
Workshop meeting is scheduled for Thursday, September 12, 2013 at 6:30 p.m., at
Blaine City Hall, Cloverleaf Farm Room, 10801 Town Square Drive, Blaine, MN for the
following purpose:
1 I-35W NORTH MANAGED LANES STUDY
2 WS 13-52 PROPOSED RECONSTRUCTION OF 125TH AVENUE FROM
RADISSON ROAD THRU HARPERS STREET INTERSECTION
Sponsors: Keely
Attachments: 125th Avenue Improvements-Location Map.pdf
3 WS 13-53 PROPOSED 2014 PAVEMENT MANAGEMENT PROGRAM
Sponsors: Keely
Attachments: 2014 pmp location map.pdf
4 WS 13-54 PROPOSED RECONSTRUCTION OF FLOWERFIELD ROAD AND
RESTWOOD ROAD WITH THE CITY OF LEXINGTON
Sponsors: Keely
Attachments: Location Map.pdf
5 WS 13-55 2014 PROPOSED SPECIAL REVENUE FUNDS BUDGET
Sponsors: Huss
Attachments: Charitable Gambling Fund Bud 2014.pdf
2014 CTV fund.pdf
ADJOURN
City of Blaine Page 1 Printed on 9/9/2013
Get email alerts for Blaine
A daily email when new agendas and minutes are posted.