City Council Workshop
Regular MeetingBlaine, MN · March 16, 2017
Minutes
Blaine City Hall
City of Blaine 10801 Town Sq Dr NE
Blaine, MN 55449
Anoka County, Minnesota
Minutes - Final
City Council Workshop
Thursday, March 16, 2017 6:30 PM Cloverleaf Farm Room A
NOTICE OF WORKSHOP MEETING
1 Call to Order
The meeting was called to order by Mayor Ryan at 6:30 p.m.
2 Roll Call
Quorum Present.
ALSO PRESENT: City Manager Clark Arneson; Planning and Community
Development Director Bryan Schafer; Finance Director Joe Huss; Police
Chief/Safety Services Manager Chris Olson; Public Services Manager Bob
Therres; City Engineer Jean Keely; City Attorney Andy Pratt;
Communications Technician Roark Haver; Senior Engineering Technician
Jason Sundeen; and City Clerk Catherine Sorensen.
Present: 6 - Councilmember Hovland, Councilmember Clark, Councilmember King,
Councilmember Garvais, Mayor Ryan, and Councilmember Swanson
Absent: 1 - Councilmember Jeppson
3 New Business
3-1 WS 17-17 DISCUSS HAM LAKE REQUEST FOR WATER CONNECTION
Public Services Manager Therres stated the City of Ham Lake has requested
that two properties in Ham Lake be allowed to connect to water main from the
City of Blaine. One of the properties has an existing building and one is
vacant. The request is being made to primarily provide fire protection to the
properties. Not having city water requires a more expensive fire suppression
method be use. It was noted the City of Blaine has similar water connection
agreements with most of the cities that we share boundaries with. With our
existing agreements, however, the properties served are directly adjacent to
the boundary. Only one of the Ham Lake properties is directly adjacent, the
other is a few hundred feet away.
Councilmember Garvais questioned where the closest lines were for the Ham
Lake municipal water system. Public Services Manager Therres reported the
City of Ham Lake does not have a municipal water system.
City of Blaine Page 1
City Council Workshop Minutes - Final March 16, 2017
Councilmember Hovland asked who would pay the expense of installing the
requested water lines. Public Services Manager Therres indicated staff has
not held this conversation yet. Further discussion ensued regarding how to
collect on outstanding utility bills.
Councilmember Swanson did not believe the line extension should cost the
residents of Blaine anything. He inquired if the City had enough water
capacity to cover the proposed project. Public Services Manager Therres
stated the City did currently have enough capacity for the project.
Councilmember Swanson questioned who would be responsible for
maintaining these water lines. Public Services Manager Therres commented
the lines could remain the City’s responsibility or be made private. He
explained this would have to be negotiated with the applicant.
Councilmember King stated he did not object to the project but did not want
to see the expense put on Blaine taxpayers.
Council consensus was to direct staff to discuss the expense of the project
with the properties owners in Ham Lake and for staff to report back to the
City Council.
Discussed
3-3 WS 17-19 CONTRACT LANGUAGE FOR CONSTRUCTION PROJECTS
City Engineer Keely stated Council expressed concern over the City’s contract
specifications after the 2016 construction season and asked for a Workshop
item to discuss. Two issues that Council raised were the quality of top soil on
the Hastings Street project and the heavy rain event that lifted sanitary sewer
cover plates in the street and allowed storm water to enter adjacent basements.
City Engineer Keely explained the City’s current specifications for top soil are
based on Minnesota Department of Transportation (MNDOT) standard
specifications. The Engineering staff has discussed the materials delivered to
our construction sites this last season. On the 91st Avenue project, the top
soil delivered was 1% short on organic material and on the Hastings Street
project Councilmember Swanson reported that a neighbor found debris in the
topsoil. Staff is recommending a modification to our current specifications
that will require the addition of compost if native top soil is reused. If top soil
is going to be brought to the project from another location, a sample must be
approved by the Engineering Department prior to delivery. The imported top
soil will be required to meet MNDOT specifications for boulevard top soil
which should be more acceptable to adjacent property owners. The
specifications will emphasize the need to have the material screened before
placement.
City of Blaine Page 2
City Council Workshop Minutes - Final March 16, 2017
City Engineer Keely reported the City’s current specifications require the
contractor to protect work, property and persons. On the Hastings Street
project, the contractor had left the road bed low after removal of the existing
pavement and water main construction. The contractor had not yet started to
place aggregate material in the street. The sanitary sewer manhole covers had
been removed and temporary metal plates covered the manholes. There was a
heavy storm that filled the street with water that entered the sanitary sewer
system and then entered some of the adjacent basements. To try to prevent
another occurrence of this event, the Engineering Department is
recommending an addition to our specifications that requires all sanitary
sewer manholes be sealed water tight during construction. Both changes to
the specifications may result in additional bid cost, but will have a positive
impact to future projects.
Councilmember Swanson suggested language be added to the contract that
states if a road drainage is below “X” amount of inches, the contractor will
have pumps available to move the water offsite.
Councilmember King asked how much more it would cost the City to have
the soil screened. City Engineer Keely estimated this would not be any more
than 5%. She reported the City would learn more after bidding the 2017
projects.
Councilmember Hovland questioned if the soil would be screened onsite or
prior to being brought to the City. City Engineer Keely anticipated staff
would address this issue during the 2017 improvement projects.
Council consensus was to direct staff to proceed in amending the language as
presented and as amended above.
Councilmember Clark arrived at 6:55 p.m.
Discussed
3-2 WS 17-18 BLAINE WETLAND SANCTUARY
Public Services Manager Therres stated during open forum at the January 19,
2017 City Council meeting, residents expressed concern over the wetland
sanctuary project and removal of trees. A neighborhood meeting was held on
February 8, 2017 for residents to raise their concerns to the City Council and
Natural Resource Conservation Board. Staff reviewed a list of concerns that
have been brought to the City from residents in preparation for the upcoming
neighborhood meeting on March 29, 2017.
Councilmember Hovland questioned how the City would be able to keep
four-wheelers out of the wetland sanctuary. Public Services Manager Therres
City of Blaine Page 3
City Council Workshop Minutes - Final March 16, 2017
stated staff was proposing that a gated fence and landscaping berm be
installed in order to block off access to recreational vehicles.
Further discussion ensued regarding the access point into the wetland
sanctuary.
Councilmember Clark suggested some sort of signage be posted at the gate
entrance.
Councilmember Hovland supported this recommendation and asked that a
sign be posted that reads “No Recreational Vehicles Allowed”. He asked that
staff be ready to address questions regarding access and how often the
wetland sanctuary will be accessed by City staff. In addition, staff should be
prepared to answer questions regarding what type of maintenance would be
conducted.
Councilmember Clark questioned what it would cost the City to have the site
surveyed. He thought this may benefit the City and improve trust with the
surrounding homeowners. City Engineer Keely estimated this would cost the
City $3,000. She reported a survey was completed by the City in November
prior to the contractor completing any work.
Councilmember Garvais suggested the City explain to the homeowners the
process the City followed to survey the site noting that markers were put in
place and no trees were taken within 10 or 15 feet of these lines.
Councilmember Hovland recommended the Council consider how to create a
buffer between the homes and the wetland sanctuary. Public Services
Manager Therres reported the contractor has provided the City with a list of
wetland tolerant trees and shrubs.
Mayor Ryan questioned how much it would cost the City to provide a buffer
around the access point. Public Services Manager Therres estimated this
would cost the City $50,000 and would be an additional $50,000 to provide
screening behind the homes.
Councilmember Clark supported the Council providing a buffer between the
homes and the wetland sanctuary.
Mayor Ryan agreed.
Councilmember Hovland looked forward to addressing this further with the
neighbors.
Mayor Ryan anticipated that once the wetland sanctuary was thriving, the
property values around this amenity would increase.
City of Blaine Page 4
City Council Workshop Minutes - Final March 16, 2017
Councilmember Swanson suggested the shrubs that are planted be butterfly
and bee friendly. He asked if the City had been in contact with the University
of Minnesota regarding the opportunities that would be available within the
wetland sanctuary. Public Services Manager Therres indicated staff has been
in contact with the University of Minnesota and they were excited about the
potential learning opportunities that would be available in the near future.
Discussed
Other
None.
ADJOURN
The Workshop was adjourned at 7:21 p.m.
Adjourned
City of Blaine Page 5
Agenda
Blaine City Hall
City of Blaine 10801 Town Sq Dr NE
Blaine, MN 55449
Anoka County, Minnesota
Meeting Agenda - Final
City Council Workshop
Thursday, March 16, 2017 6:30 PM Cloverleaf Farm Room A
NOTICE OF WORKSHOP MEETING
In accordance with the provisions of Section 3.01 of the Blaine City Charter, a Council
Workshop meeting is scheduled for the following purpose:
1 Call to Order
2 Roll Call
3 New Business
3-1 WS 17-17 DISCUSS HAM LAKE REQUEST FOR WATER CONNECTION
Sponsors: Therres
Attachments: Request Letter.pdf
Map.pdf
3-2 WS 17-18 BLAINE WETLAND SANCTUARY
Sponsors: Therres
Attachments: Wetland Overview map.pdf
3-3 WS 17-19 CONTRACT LANGUAGE FOR CONSTRUCTION PROJECTS
ADJOURN
City of Blaine Page 1 Printed on 3/13/2017