City Council Agendas
Regular MeetingBlue Springs, MO · January 29, 2024
Minutes
CITY OF BLUE SPRINGS, MISSOURI
MINUTES OF COUNCIL WORK SESSION
JANUARY 29, 2024
A Work Session of the City Council of the City of Blue Springs, Missouri, was held on Monday,
January 29, 2024, 6:00 p.m. in the Administrative Training Room of the Blue Springs City Hall,
903 W. Main Street with Mayor Carson Ross presiding.
COUNCILMEMBERS IN Jerry Kaylor Galen Ericson
ATTENDANCE Chris Lievsay Kent Edmondson
Ron Fowler Susan Culpepper
Also present were City Administrator Christine Cates, Assistant to the
City Administrator Sheryl Morgan, and City Clerk Erin Ford.
CALL MEETING TO Mayor Ross called the meeting to order at 6:02 p.m. The City Clerk
ORDER AND confirmed a quorum of the Council was present.
CONFIRMATION OF
QUORUM
2024 STREET Public Works Director Tom Degenhardt and Assistant Director of
MAINTENANCE Public Works Adam Hilgedick presented the 2024 Street Maintenance
PROGRAM Program and addressed questions from Council. A copy of a
presentation with staff's recommendation is attached to these Minutes
and incorporated herein.
2024 INFILL SIDEWALK Public Works Director Tom Degenhardt and Assistant Director of
PROGRAM Public Works Adam Hilgedick presented the 2024 Infill Sidewalk
Program and addressed questions from Council. A copy of a
presentation with staff's recommendation is attached to these Minutes
and incorporated herein .
ADJOURN At 6:42 p.m., there was no further business to come before the
Council, Mayor Ross declared the meeting adjourned .
CITY OF BLUE SPRINGS
ATTEST:
~
Carson Ross, Mayor
Agenda
CITY COUNCIL WORK SESSION
AGENDA
January 29, 2024 - 6:00 p.m.
Administrative Training Room
Blue Springs City Hall
903 W. Main Street
Blue Springs, Missouri
1. Call meeting to order
2. Confirmation of Quorum
3. 2024 Infill Sidewalk Program
4. 2024 Street Maintenance Program
5. Adjourn
Miscellaneous Items
City Council Meeting – Monday, February 5, 6:00 PM
Parks Commission Meeting – Monday, February 6, 6:00 PM
Planning Commission Meeting – Monday, February 12, 6:30 PM
Public Arts Commission Meeting – Wednesday, February 14, 3:30 PM
City Council Meeting – Wednesday, February 21, 6:00 PM
This Agenda was posted at City Hall and on the City’s website on Thursday, January 25, 2024.
Erin Ford, City Clerk
TO: Mayor, Councilmembers, Department Directors, and Press
FROM: Christine Cates
City Administrator
DATE: January 25, 2024
SUBJECT: Agenda Explanations
Item 3 – 2024 Infill Sidewalk Program
Public Works Director, Tom Degenhardt, will present details of the 2024 Infill Sidewalk Program
for Council consideration. Refer to Council Information Form from Public Works Director Tom
Degenhardt for additional information.
Item 4 – 2024 Street Maintenance Program
Public Works Director, Tom Degenhardt, will present details of the 2024 Street Maintenance
Program for Council consideration. Refer to Council Information Form from Public Works Director
Tom Degenhardt for additional information.
Council Work Session Date: January 29, 2024
Agenda Item #: 3
Page 1 of 1
CITY OF BLUE SPRINGS
CITY COUNCIL INFORMATION FORM
DATE SUBMITTED: January 11, 2024
SUBMITTED BY: Tom Degenhardt DEPARTMENT: Public Works
Ordinance Resolution Presentation Public Hearing
Contract Discussion Economic Dev. Other
ISSUE/REQUEST
Public Works Director, Tom Degenhardt, will present details of the 2024 infill sidewalk program
for Council consideration.
BACKGROUND/JUSTIFICATION
Infill Sidewalk ST-44 is budgeted in the amount of $277,200 for the 2024 construction season.
The presentation is designed to provide information to City Council for proposed infill sidewalk
locations.
FINANCIAL IMPACT
Contractor: N/A
PROJECT TIMELINE
Estimated Start Date Estimated End Date
February 5, 2024 December 31, 2024
OTHER BOARDS & COMMISSIONS ASSIGNED
Name of Board or Commission: N/A
ECONOMIC DEVELOPMENT PROJECT
N/A
LIST OF REFERENCE DOCUMENTS ATTACHED
1. PowerPoint Presentation
REVIEWED BY:
Requesting Director: Budget:
Tom Degenhardt N/A
Legal: City Administrator:
N/A Christine Cates
Rev. 02/14/2023
1/24/2024
2024 Infill Sidewalk
ST‐44
1
$277,200 Funded for FY 2023‐2024
To be used for new sidewalk only, no removal and replacement of sidewalk
Priority:
Safety
Known High‐Traffic Pedestrian Areas
Schools
Businesses
Hotel
Apartment/Multifamily
Missing gaps
2
1
1/24/2024
Recommended Program – $257,156
Street From To Length Cost Note
NW Valley View Road 4503 Valley View Rd West to School sidewalk 1,045' $ 34,736.00 Some grading required
NW Mock AVE The Edison Apartments West to Existing Sidewalk 660' $ 26,400.00 Curb abutting or culvert extension
NE Mock Avenue Field House The Edison Apartments 585' $ 24,400.00 R/W or tree removal
SW Lake Village Boulevard Heartland Church 7 Highway 615' $ 25,140.00
SW Lake Village Boulevard SW Christiansen Drive Heartland Church 145' $ 4,964.00
SW Liggett Road 7 Highway Existing west 320' $ 12,800.00
SW Meadowridge DR Strip mall Apartment entrance 670' $ 22,412.00 Some grading required
NW South Outer Road IBEX Whataburger 355' $ 15,010.00
NW Jefferson ST Welcome Inn Gage Center 360' $ 14,220.00
NW Jefferson ST KC Cannabis Northridge DR 300' $ 12,324.00
SW Moreland School RD Walgreens The Ridge Apartments 280' $ 11,200.00 R/W and some grading
SW Clark RD Clark LN Apartments to the west 260' $ 11,696.00
SW South AVE 5th ST 4th ST 270' $ 9,288.00
NW Primrose 1512 NW Primrose 1513 NW Primrose 150' $ 5,772.00
NW Duncan RD south side Casey's Flex Spaces 70' $ 5,560.00 Utility conflicts.
SW 19th ST Sunset AVE Dollar General Store 125' $ 5,324.00
NW Jefferson ST West of 2001 To existing sidewalk 160' $ 5,120.00
SW 10th ST Green Meadow DR Edgewater 75' $ 3,000.00 NW corner
SW 9th ST Green Meadow DR Edgewater 50' $ 2,000.00 SW corner
SW 8th ST Green Meadow DR Edgewater 48' $ 1,920.00 SW corner
SW 8th ST Green Meadow DR Edgewater 45' $ 1,800.00 NW corner
SW 9th ST Green Meadow DR Edgewater 40' $ 1,600.00 NW corner
2201 NW Sparta Drive 2201 NW Sparta Drive 2201 NW Sparta Drive 15' $ 480.00
3
NW Valley View Rd – 4503 Valley View to School
$34,736 1,045 Linear feet
Some Grading Required
4
2
1/24/2024
NW Mock Ave – Edison Apartments to Existing Sidewalk
$26,400 660 Linear feet
Curb abutting and/or Culvert Extension
5
NW Mock Ave – Field House to Edison Apartments
$24,400 585 Linear feet
Additional R/W or Tree Removal
6
3
1/24/2024
SW Lake Village Blvd – 7 Highway East to Heartland Church
$25,140 615 Linear feet
7
SW Lake Village Blvd – Heartland Church to Christiansen Drive
$4,964 145 Linear feet
8
4
1/24/2024
SW Liggett Road – 7 Highway West to Existing Sidewalk
$12,800 320 Linear feet
9
SW Meadowridge Dr – Strip Mall to Apartment Entrance
$22,412 670 Linear feet
10
5
1/24/2024
NW South Outer Rd – Whataburger to IBEX
$15,010 355 Linear feet
11
NW Jefferson Street – Welcome Inn to Gage Center
$14,220 360 Linear feet
12
6
1/24/2024
NW Jefferson Street – KC Cannabis to Northridge Drive
$12,324 300 Linear feet
13
SW Moreland School Road – Walgreens to The Ridge Apartments
$11,200 280 Linear feet
Additional R/W and Grading
14
7
1/24/2024
SW Clark Road – Clark Lane to Apartment to the West
$11,696 260 Linear feet
15
SW South Avenue – SW 5th Street to SW 4th Street
$9,288 270 Linear feet
16
8
1/24/2024
NW Primrose – 1512 NW Primrose to 1513 NW Primrose
$5,772 150 Linear feet
17
NW Duncan Road – Casey’s to Flex Spaces
$5,560 70 Linear feet
18
9
1/24/2024
SW 19th Street – Dollar General Store to SW Sunset Avenue
$5,324 125 Linear feet
19
NW Jefferson Street – West of 2001 Jefferson to Existing Sidewalk
$5,120 160 Linear feet
20
10
1/24/2024
SW Green Meadow Drive
@ SW 10th Street – NW Corner
$3,000 75 Linear feet
@ SW 9th Street – SW Corner
$2,000 50 Linear feet
@ SW 9th Street – NW Corner
$1,600 40 Linear feet
@ SW 8th Street – SW Corner
$1,920 48 Linear feet
@ SW 8th Street – NW Corner
$1,800 45 Linear feet
21
2201 NW Sparta Drive
$480 15 Linear feet
22
11
1/24/2024
Unfunded
Street From To Length Cost Note
NW Jefferson ST Gage Center 12th ST, up 12th 355' $ 11,684.00 Terrain has considerable slope
NW Jefferson ST 12th ST East of Benton House 1,110' $ 47,640.00 Grading
NW Jefferson ST Guier Fence Saunders RD 610' $ 24,724.00 About 200' of wall
NW Briarwood DR 37th ST East to Sonic 425' $ 17,972.00
NW Jefferson ST Flex Spaces property line Brewery/ Car Repair 75' $ 3,270.00 Steep grade
NW Duncan RD north side 6th ST West to Existing SW 145' $ 6,124.00
NW Shaw PKWY 7 HWY 6th TER 260' $ 11,584.00 About 60' of wall
NW Duncan Road 7 Highway NW 6th Terr 250' $ 10,864.00
NW 51st ST Downing ST North to school sidewalk 605' $ 20,008.00 About 240' of wall
NW Valley View Road 51st Street 55th Street 935' $ 39,344.00 Extreme grade. About 260' of wall
SW Lutrell/ Sunset AVE SE corner 450' $ 18,324.00
SW Sunset AVE West of Price Chopper Driveway 110 $ 4,400.00
SW South AVE 1st Street West to shared driveway 350' $ 11,524.00 Grade issues
SW 8th ST Green Meadow DR Edgewater 80' $ 3,524.00 NE corner
SW 8th ST Green Meadow DR Edgewater 76' $ 3,364.00 SE corner
Totals $ 234,350.00 Total does not include wall or grading
Areas needing engineering to determine cost:
Street From To Length Cost Note
NW Duncan Road NW 6th Terr NW 4th Street Place 743’
NW Duncan Road Flex Spaces NW Westbrooke Drive 1,700’ Unimproved street
SW Walnut Street SW 19th Street Old Mill Park 3,700’ Street project ST‐61
SW Liggett Road SW 22nd Street SW 12th Street 2,670’ Unimproved street
NW Vesper Woods Chapel Rd Fox Hollow Ln 3,300’ Street project ST‐07
NW Pink Hill Road Casey's NW 1st Street 1,500’ Unimproved street
23
NW Duncan Road – NW 4th Place to NW 6th Terrace
Steep Grade, Wall Needed, Driveway Replacements
24
12
1/24/2024
* NW Duncan Road – NW Westbrooke Drive to Flex Spaces
Unimproved Street with Roadside Ditches,
Drainage System Needed
* Councilmember Request
25
* NW Vesper Street – NW Fox Hollow Lane to SW Woods Chapel Road
Unimproved Street with Roadside Ditches,
Drainage System Needed
* Councilmember Request
26
13
1/24/2024
* SW Walnut Street – SW 19th Street to Old Mill Park
Cemetery Wall on South Side, Drainage and
Grading Needed on North Side
* Councilmember Request
27
* NW Pink Hill Road – Casey’s to NW 1st Street
Unimproved Street with Roadside Ditches,
Drainage System Needed
* Councilmember Request
28
14
Council Work Session Date: January 29, 2024
Agenda Item #: 4
Page 1 of 1
CITY OF BLUE SPRINGS
CITY COUNCIL INFORMATION FORM
DATE SUBMITTED: January 11, 2024
SUBMITTED BY: Tom Degenhardt DEPARTMENT: Public Works
Ordinance Resolution Presentation Public Hearing
Contract Discussion Economic Dev. Other
ISSUE/REQUEST
Public Works Director, Tom Degenhardt, will present details of the 2024 Street Maintenance
Program for Council consideration.
BACKGROUND/JUSTIFICATION
Street Maintenance Program ST-06 is budgeted in the amount of $2.02 million for the 2024
construction season. The presentation is designed to provide background of the state of the
system and the process used to select streets for the upcoming program information to the City
Council.
FINANCIAL IMPACT
Contractor: N/A
PROJECT TIMELINE
Estimated Start Date Estimated End Date
February 21, 2024 October 1, 2024
OTHER BOARDS & COMMISSIONS ASSIGNED
Name of Board or Commission: N/A
ECONOMIC DEVELOPMENT PROJECT
N/A
LIST OF REFERENCE DOCUMENTS ATTACHED
1. PowerPoint Presentation for 2024 Street Maintenance Program
REVIEWED BY:
Requesting Director: Budget:
Tom Degenhardt N/A
Legal: City Administrator:
N/A Christine Cates
Rev. 02/14/2023
1/24/2024
2024 Pavement Management Program
ST‐06
1
City Maintains approximately 261 Centerline Miles (CL) of Streets (Equivalent)
8.8 CL Miles of Arterial Streets (3.4%)
106.5 CL Miles of Collector Street (40.8%)
145.7 CL Miles of Local Streets (55.8%)
MoDOT Maintains:
Interstate I‐70
US Highway 7
US Highway 40
Jackson County/Blue Springs 2000 Maintenance Agreement
Maintenance versus Capital Improvements
2
1
1/24/2024
New Street Miles Added by Year (CL)
2018 – 5.77 Miles
2019 – 0.95 Miles
2020 – 3.93 Miles
2021 – 1.50 Miles
2022 – 2.59 Miles
2023 – 2.04 Miles
3
Street Rating System:
In 2016 the City contracted with Stantec Inc. to systematically
drive and rate every segment of roadway in the City and calculate
a Pavement Quality Index (PQI) and Pavement Condition Index (PCI) for each segment.
The PQI and PCI are tools for programming streets and not the final determination for the
program.
Each segment is rated on a scale from 0.0 to 100.0 and grouped as shown below:
0 to 19.9 – Failed
20 to 39.9 – Poor
40 to 69.9 – Fair
70 to 100 – Good
Historical average PCI data:
2016 – 59.5
2019 – 53.2
2023 – 52.6
4
2
1/24/2024
Current PCI Condition:
Failed – 11.5 Miles ( 4.4%)
Poor – 90.3 Miles (34.6%)
Fair – 87.0 Miles (33.3%)
Good – 72.2 Miles (27.7%)
5
Street Rating System:
SW 12th Street between
SW Chicago and SW South Ave
PCI=10.2 (Failed)
Last Overlayed in 2012
6
3
1/24/2024
Street Rating System:
SE Lake Village Blvd. between
Brandywine and Washington
PCI=19.4 (Failed)
Last Overlayed in 2012
7
Street Rating System:
SW Emerald Creek Pl between
Pine Creek Ct and
Crystal Creek Pl
PCI=31.3 (Poor)
Built in 1992
8
4
1/24/2024
Street Rating System:
SW South Ave between
SW 6th St and SW 6th Terr
PCI=50.0 (Fair)
Last Overlayed in 2015
9
Street Rating System:
SW Liggett Rd between
7 Hwy and SW 8th Terr
PCI=70.0 (Good)
Last Overlayed in 2017
10
5
1/24/2024
Street Rating System:
SE Moreland School Rd between
7 Hwy and ADP
PCI=100.0 (Good)
Last Overlayed in 2023
2013
11
Eleven Year History:
12
6
1/24/2024
History:
Overlay CL Miles per year:
2009 – 24.0 Miles (9.2%) 2017 – 11.8 Miles (4.5%)
2010 – 18.0 Miles (6.9%) 2018 – No Program
2011 – 19.0 Miles (7.3%) 2019 – 7.7 Miles (3.0%)
2012 – 18.0 Miles (6.9%) 2020 – 8.0 Miles (3.1%)
2013 – 13.5 Miles (5.2%) 2021 – 9.4 Miles (3.6%)
2014 – No Program 2022 – 13.0 Miles (5.0%)
2015 – 14.0 Miles (5.4%) 2023 – 6.0 Miles (2.3%)
2016 – 10.5 Miles (4.0%) 2024 – 4.0 Miles (1.5%)*
66.2% = 15 Year Total
* Not final until bid opening and budget verified
13
Patching: Curb and Sidewalk :
14
7
1/24/2024
Historical Program Cost:
Year Program Amount Cost/Ton Concrete Patching CL Mile Cost/CL Mile
2017 $2,295,605.76 *$54.65 $675,734.05 (29.4%) $239,797.33 (10.4%) 11.83 $194,049.51
2018
2019 $2,334,779.81 *$58.40 $762,279.75 (32.6%) $335,303.57 (14.4%) 7.71 $302,824.88
2020 $2,888,026.08 *$63.35 $747,468.55 (25.9%) $954,477.94 (33.0%) 8.01 $360,552.57
2021 $3,690,024.26 *$64.15 $1,025,185.65 (27.8%) $1,364,959.65 (37.0%) 9.38 $393,392.78
2022 $6,416,133.33 *$68.80 $1,264,178.90 (19.7%) $3,030,484.56 (47.2%) 13.02 $492,790.58
2023 $3,107,325.50 *$84.27 $687,369.42 (22.1%) $1,145,743.36 (36.9%) 5.97 $520,490.03
2024 $2,020,000.00 *$86.14 $530,000.00 (26.2%) $520,000.00 (25.7%) 4.00 $505,000.00
* Unit bid cost, adjusted by asphalt indexing
15
*2024 Street Program:
Street Name From To Ave PCI
SW Colbern RD 7 HWY City Limits 34.5
SE Adams Dairy PKWY 40 HWY AA 53.6
SE/NE Sunnyside School RD R D Mize RD Bent Tree DR 33.1
NE Jefferson ST East of ADP East of 20th ST 45.3
SW 10th ST Stonecreek DR Shadow Creek CT 18.3
SW Twincreek CT Twincreek PL CDS S 16.2
SW Twincreek PL Emerald Creek PL CDS W 25.7
SW Pinecreek CT Emerald Creek PL CDS W 26.5
SW Crystal Creek PL Emerald Creek PL CDS W 31.2
SW Emerald Creek PL Stonecreek DR CDS S 29.4
SW Shadow Brook DR Woods Chapel RD Shadow Glen DR 17.2
SW/NW 27th ST Walnut ST Vesper ST 11.8
Program Average PCI 27.7
* List not final until bid opening and budget verified
16
8
1/24/2024
2024 Program Schedule:
January 29, 2024 – Overlay Bid Advertisement
February 14, 2024 – Overlay Pre‐Bid Meeting
February 21, 2024 – Overlay Bid Opening
April 1, 2024 – Bid Recommendation to City Council
April 18, 2024 – Notice To Proceed
August 30, 2024 – Construction Complete
17
Future Street Program(s):
Optimal Treatment Cycle Minimal Treatment Cycle
System Treatment CL Miles System Treatment CL Miles
Classification CL Miles Cycle (Yrs) Per Year Treatment Cost Classification CL Miles Cycle (Yrs) Per Year Treatment Cost
Arterial 8.8 7 1.26 * Mill/Overlay $628,571 Arterial 8.8 12 0.73 * Mill/Overlay $366,667
Collector 106.5 10 10.65 * Mill/Overlay $5,325,000 Collector 106.5 15 7.10 * Mill/Overlay $3,550,000
Residential 145.7 15 9.71 * Mill/Overlay $4,856,667 Residential 145.7 25 5.83 * Mill/Overlay $2,914,000
Total * Mill/Overlay $10,810,238 Total * Mill/Overlay $6,830,667
Residential 5‐6 Post 9.71 ** Microsurface $776,800 Residential 5‐6 Post 5.83 ** Microsurface $466,400
Yearly Program $11,587,038 Yearly Program $7,297,067
Does not include yearly inflation Does not include yearly inflation
* Based on $500,000 per CL Mile
** Based on $ 80,000 per CL Mile
18
9