Tri-Town Board of Water Commissioners
Regular MeetingBraintree, MA · April 12, 2016
Minutes
TRI TOWN BOARD
Of Water Commissioners
Braintree, Holbrook, Randolph
Braintree Town Hall
MINUTES
April 12, 2016
PRESENT: Chairman, Joseph Sullivan, Mayor, Town of Braintree; Richard Brewer, Town of
Randolph, Timothy Gordon, Town Administrator, Town of Holbrook.
IN ATTENDANCE: Michael Cimotelli, Flansburgh Architects, Michael Dowhan, Waterman Design,
Vincent Dube, Flansburg Architects, Lou Dutton, Ben Eccord, Ben Fehan, Michael Igo, Aqueous,
Barbara Mello, Steve Stafford, Symmes Mani & McKee Associates, Mike Walsh, Robyn LaFrance,
recording secretary.
Mayor Sullivan opened the meeting at 2:05 pm.
MINUTES: the minutes of the January 27, 2016 meeting were reviewed.
MOTION: by Rich Brewer to accept Minutes of 1/27/16.
SECOND: by Tim Gordon
VOTE: Unanimous
Great Pond Dam Project update: Mike Walsh
Mike Walsh explained that permit applications will be submitted and that permits last for two
years.
Discussed a water survey by MA D.E.P.
Project design documents and permit applications can be done and ready in two weeks.
90% of the design is completed and the new cost estimate is $1.2 million. It was explained that
the original cost estimate was done five years ago.
A grant was received for dam upgrades.
Upper reservoir is poor to fair.
Mike Walsh explained that more design work had to be done to accommodate the fish ladder and
that ultimately raised the cost of the design.
Barbara Mello gave an update on the project cost explaining that it is a combination of a loan and
a cash grant totaling $1,358,911.00. The breakdown for the three communities are:
o Braintree: Total cost: $652,277.28; cash grant for $79,296; and loan for $391,042.08.
o Randolph: Total cost: $502,797; cash grant for $61,124; and loan for $301,428.27.
o Holbrook: Total cost: $203,836.65; cash grant for $24,780; and loan for $122,200.65.
CDM Costs are based on 1. Construction Based Service, 2. Engineering, 3. Design and 4.
Permitting.
Mike Walsh discussed the lifespan of a dam and explained that once it’s armored, it’s built to last
50 to 70 years and will be as good as new. He noted that there is no comparison to a “100 year
storm”.
Construction cost estimate is $1.24 million.
Documents and permits are ready.
1
Bids open in a couple of weeks.
MOTION: By Tim Gordon to move forward on the Great Pond Dam Improvement Project
SECOND: by Rich Brewer
VOTE: Unanimous
Barbara Mello urged the Board to keep in mind that June 30 is a date to be aware of regarding the
grant. Under the terms of the grant, all construction was to be completed and there is a risk of
funds being called back.
Mike Walsh is in need of signatures.
CDM is under contract for the design.
CDM is not under contract for the bid process but can do that.
There was discussion concerning the bid process. It is possible that if CDM does not do the bid
process, it could prolong the process.
Secretary Beaton draft letter:
The Board will mail a letter to Secretary Matthew Beaton as a follow up to the correspondence the
Board sent on 8/3/15 after the Tri Town Board voted to build the new water treatment plant. The
letter will invite him to a site visit and offer to show him the existing water treatment facilities at
the same time.
Mayor Sullivan clarified the background history on the MWRA option and explained that that Tri
Town Board already voted in favor of building the new Tri Town Water Treatment Plant. This
vote was taken in the summer of 2015 and we will look back in the minutes and provide this for
Tim Gordon, Town of Holbrook.
Holbrook School Building update & Presentation: Tim Gordon and visiting architects
At the last Tri Town Board meeting, a new Holbrook Pre K-12 school presentation was made and
they were asked to return with firm numbers on anticipated water consumption for sports field
irrigation.
Michael Cimotelli gave an update on the new Holbrook Pre K-12 school building project. He
explained that 11,800 gallons of water per day would be the water usage needed to properly
irrigate the boys and girls softball fields. He explained that harvesting rain water was explored but
it is not feasible.
The Tri Town firm yield study was explained as being approximately 9.2 million gallons/day and
actual daily use is 7.5 million/day. This is based on the firm yield supply on the hottest day of the
month.
Architects gave a detailed presentation on the new Holbrook Pre K-12 School infrastructure and
the process for the engineered irrigation system. There was a presentation on the turf grass
management field process and it was explained that it will be a draught tolerant field. Irrigation
program management was discussed and an internet based program will be used to operate some
of the features. All of this irrigation system will suspend during rainfall. Expected water usage is
11,800 gallons on the top peak day (example, hottest day in July) and an average of 6,300 gallons
on the average day.
The take-away’s from this presentation are that the Holbrook team has done its due diligence, and
that Water consumption will be a fraction of a fraction of a percent of the annual draw.
2
Questions were asked concerning the use of water on a peak day if residents are not allowed to use
water, and has there been a second engineer to review the numbers.
Lou Dutton corrected the firm yield amounts reporting that it is not 9 million gallons per day.
It was explained that Holbrook does not have a natural resource for water, and a vote was
requested. The primary use will be for high school sports. Mayor Sullivan wants to be helpful
and explained that 7-9 million was a nominal amount.
There was discussion concerning water bans and irrigation.
There was discussion concerning opening the Cochato River and it was explained that the Board
needs D.E.P. approval to open the Cochato River. It was explained that the Tri Town Board
decided to close it and now D.E.P. would need to determine its opening.
MOTION: By Tim Gordon to allow the Holbrook Pre K-12 School Complex to utilize its sprinkler
system to irrigate the boys & girls sports fields.
SECOND: by Rich Brewer
VOTE: Unanimous
Other/Wheelhouse Option - Mayor Sullivan
Mayor Sullivan explained this Braintree issue with SouthField. The purpose would be to install a
pipe and connect SouthField with the North Weymouth/MWRA/Route 3A community.
Information was discussed and provided to the Tri Town Board by Mayor Sullivan and Ron
Mariano.
Other: Action items
Letter to be mailed to Secretary Beaton
Barbara Mello will get documents together for Board
Next meeting date was set for May 5 at 1 pm at Braintree Town Hall.
MOTION: By Mayor Sullivan to adjourn meeting at 3:30 pm.
SECOND: by Tim Gordon
VOTE: Unanimous
Respectfully submitted,
Robyn LaFrance
Recording Secretary
3
Agenda
TRI TOWN BOARD
of Water Commissioners
Braintree, Holbrook, Randolph
Johnson Chambers, Braintree Town Hall
April 12, 2016 | 2:00 pm
AGENDA
1. Minutes of January 27, 2016 meeting
2. Great Pond Dam project
3. Holbrook School Building Team
4. MWRA Update – Wheelhouse Option
5. Secretary Beaton letter
OTHER BUSINESS: As determined by the Chairman
NEXT MEETING DATE:
EXECUTIVE SESSION: