Committee of the Whole
Regular MeetingBrookfield, IL · February 28, 2022
Agenda
Village of Brookfield
Agenda
Committee of the Whole Meeting
Monday, February 28, 2022 @ 7:00 PM
or Immediately Following Village Board Meeting
Edward Barcal Hall 8820 Brookfield Avenue Brookfield,
IL 60513
I. ROLL CALL
II. REGULAR BUSINESS
1. Discussion Concerning Options for Grant Avenue Widening as Part of
the 2022 Street Improvement Project
Committee Item Memo- Grant Ave Widening
2. Eight-Corners Fountain Update
Committee Item Memo-Fountain Update
III. PUBLIC COMMENT
IV. EXECUTIVE SESSION
V. ADJOURNMENT
Page 1 of 16
Committee Item Memo
Meeting Date: February 28, 2022
Staff Contact: Carl Muell, Public Works Director
Department: Public Works
Subject: Discussion Concerning Options for Grant Avenue Widening as Part of the
2022 Street Improvement Project
Background Information:
At its last Committee of the Whole meeting on February 14th, 2022 the Board discussed the
widening of Grant Avenue from Grand Boulevard to Forest Avenue. Following discussion, the
Board requested additional options be presented for the potential widening.
At the January 24 Committee of the Whole meeting, the Board requested that staff hold a
meeting to allow impacted residents of the area to review the options. Staff mailed out notices
to all residents that either live on Grant Avenue, from Grand to Forest, or to residents whose
property was adjacent to Grant, inviting them to participate in an online meeting on February 9
to discuss the project. At this meeting, staff presented various options (summarized below)
and provided its rationale for recommending that Grant be widened to allow for two 11-foot
drive lanes, and two parking lanes on the north and south sides of the street. One resident
participated in the meeting. He was opposed to any widening option, primarily due to its
impact on existing trees, he felt it was not in keeping with the residential nature of the north
side of the street and he did not feel there is a problem with the current street configuration.
Following the last Board meeting, Hancock Engineering created a new Option A, which
consists of two 11' drive thru lanes and 7' designated parking lanes on both sides of Grant
Avenue between Grand Boulevard and Prairie Avenue. An Option B was discussed by the
Board, which included widening Grant Avenue to 29' between Grand Boulevard and Prairie
Avenue. This would allow for two 11' drive thru lanes and a 7' designated parking on the south
side of Grant Avenue. There would continue to be no parking on the north side of Grant
Avenue in Option B. A new Option C was offered which provided for a 15' drive lane, and 7'
dedicated parking lanes for both sides of the street.
In addition to the Options for Grant widening, the Board discussed the potential elimination of
parking spaces on Prairie Avenue at Grant Avenue, to increase sight line distances. The
Village Engineer has reviewed this intersection and is recommending the elimination of 10 total
parking spaces on Prairie in order to improve the sight line for traffic on Grant turning either
north or south onto Prairie.
Page 2 of 16
Staff has provided three options for Board consideration for the widening of Grant Avenue.
These are summarized below:
Option Configuration Benefits Estimated Cost
A Two 7-foot parking Adds 13 new parking $91,500
lanes on both side of spaces to the north
street; Two 11-foot side; safer drive
through-lanes lanes and can
handle more traffic
B 7-foot parking lane Safer drive lanes, $45,000
on southside only; handle more traffic.
two 11-foot through Saves more trees.
lanes
C Two 7-foot parking Adds 13 new parking $40,000
lanes on both sides; spaces; saves
one 15-foot through existing trees
lane
Financial Impact:
Options range from $40,000 to $91,500
Recommendation(s):
It is staff's recommendation for Option A for the widening of Grant Avenue and the elimination
of 10 parking spaces on Prairie Avenue
Attachments:
Grant-Exhibit (Feb 17)-1A
Grant-Exhibit (Feb 17)-1B
Grant-Exhibit (Feb 17)-1C
Grant-Exhibit (Feb 17)-A
Grant-Exhibit (Feb 17)-B
Grant-Exhibit (Feb 17)-C
Grant-Prairie Int Exhibit-A
Grant-Prairie Int Exhibit-B
Page 3 of 16
GRANT AVENUE WIDENING
(GRAND BOULEVARD - PRAIRIE AVENUE)
NORTH SOUTH
R.O.W. R.O.W.
66' R.O.W.
5' 7.5' 39' B/C TO B/C 7.5' 5'
S/W PARKWAY PARKWAY S/W
11' 11'
THRU LANE THRU LANE
Jeep
9933 EHE
7' 7'
PARKING PARKING
LANE LANE
DESIGN OPTION A
1. PROVIDES ADDITIONAL 13 PARKING SPACES ON NORTH SIDE OF GRANT AVENUE (CURRENTLY PARKING IS NOT ALLOWED ON THE NORTH SIDE).
2. RESULTS IN 2 - 11' WIDE DEDICATED THROUGH LANES.
3. 23 NEW TREES PROPOSED TO BE PLANTED AT A MORE UNIFORM SPACING. THIS IS AN INCREASE OF 6 NEW TREES FROM EXISTING CONDITIONS.
4. ESTIMATED INCREASE IN COST = $91,500.
Page 4 of 16
W:\Projects_by_Village\Brookfield\12521275 - 2022 Street Improvements\Site\Grant-Exhibit (Feb 17).dwg
GRANT AVENUE WIDENING
(GRAND BOULEVARD - PRAIRIE AVENUE)
NORTH SOUTH
R.O.W. R.O.W.
66' R.O.W.
5' 14.5' 32' B/C-B/C 7.5' 5'
S/W PARKWAY PARKWAY S/W
11' 11'
THRU LANE THRU LANE
7'
PARKING
LANE
DESIGN OPTION B
1. NO INCREASE IN AVAILABLE PARKING.
2. RESULTS IN 2 - 11' WIDE DEDICATED THROUGH LANES.
3. 5 EXISTING TREES TO BE REMOVED, 10 NEW TREES PROPOSED TO BE INSTALLED.
4. ESTIMATED INCREASE IN COST = $45,000.
Page 5 of 16
W:\Projects_by_Village\Brookfield\12521275 - 2022 Street Improvements\Site\Grant-Exhibit (Feb 17).dwg
GRANT AVENUE WIDENING
(GRAND BOULEVARD - PRAIRIE AVENUE)
NORTH SOUTH
R.O.W. R.O.W.
66' R.O.W.
5' 11' 32' B/C TO B/C 11' 5'
S/W PARKWAY PARKWAY S/W
15'
THRU LANE
Jeep
9933 EHE
7' 7'
PARKING PARKING
LANE LANE
DESIGN OPTION C
1. PROVIDES ADDITIONAL 13 PARKING SPACES ON NORTH SIDE OF GRANT AVENUE (CURRENTLY PARKING IS NOT ALLOWED ON THE NORTH SIDE).
2. RESULTS IN 1 - 15' WIDE SHARED THROUGH LANE.
3. NO IMPACT ON EXISTING TREES.
4. ESTIMATED INCREASE IN COST = $40,000.
Page 6 of 16
W:\Projects_by_Village\Brookfield\12521275 - 2022 Street Improvements\Site\Grant-Exhibit (Feb 17).dwg
GRANT AVENUE WIDENING
DESIGN OPTION A - 7' WIDENING ON BOTH SIDES
VERNON AVENUE AVENUE
AVENUE
GRANT AVENUE GRANT AVENUE GRANT AVENUE
7'
11'
25'
11'
7'
FOREST
G
B RA
PRAIRIE
O N
U D
LE
V
A
R
D
1. PROVIDES ADDITIONAL 13 PARKING SPACES ON NORTH SIDE OF GRANT AVENUE (CURRENTLY PARKING IS NOT ALLOWED ON THE NORTH SIDE).
2. RESULTS IN 2 - 11' WIDE DEDICATED THROUGH LANES.
3. 23 NEW TREES PROPOSED TO BE PLANTED AT A MORE UNIFORM SPACING. THIS IS AN INCREASE OF 6 NEW TREES FROM EXISTING CONDITIONS.
4. ESTIMATED INCREASE IN COST = $91,500.
Page 7 of 16 W:\Projects_by_Village\Brookfield\12521275 - 2022 Street Improvements\Site\Grant-Exhibit (Feb 17).dwg
GRANT AVENUE WIDENING
DESIGN OPTION B - 7' WIDENING ON SOUTH SIDE
VERNON AVENUE AVENUE
AVENUE
GRANT AVENUE GRANT AVENUE GRANT AVENUE
11'
25'
11'
7'
FOREST
G
B RA
PRAIRIE
O N
U D
LE
V
A
R
D
1. NO INCREASE IN AVAILABLE PARKING.
2. RESULTS IN 2 - 11' WIDE DEDICATED THROUGH LANES.
3. 5 EXISTING TREES TO BE REMOVED, 10 NEW TREES PROPOSED TO BE INSTALLED.
4. ESTIMATED INCREASE IN COST = $45,000.
Page 8 of 16
W:\Projects_by_Village\Brookfield\12521275 - 2022 Street Improvements\Site\Grant-Exhibit (Feb 17).dwg
GRANT AVENUE WIDENING
DESIGN OPTION C - 15' SHARED THROUGH LANE
VERNON AVENUE AVENUE
AVENUE
GRANT AVENUE GRANT AVENUE GRANT AVENUE
7'
15' 25'
7'
FOREST
G
B RA
PRAIRIE
O N
U D
LE
V
A
R
D
1. PROVIDES ADDITIONAL 13 PARKING SPACES ON NORTH SIDE OF GRANT AVENUE (CURRENTLY PARKING IS NOT ALLOWED ON THE NORTH SIDE).
2. RESULTS IN 1 - 15' WIDE SHARED THROUGH LANE.
3. NO IMPACT ON EXISTING TREES.
4. ESTIMATED INCREASE IN COST = $40,000.
Page 9 of 16
W:\Projects_by_Village\Brookfield\12521275 - 2022 Street Improvements\Site\Grant-Exhibit (Feb 17).dwg
GRANT AVENUE WIDENING
(GRAND BOULEVARD - PRAIRIE AVENUE)
SIGHT TRIANGLE ANALYSIS
IDOT REQUIREMENT
AVENUE
PRAIRIE AVENUE
GRANT
Page 10 of 16
GRANT AVENUE WIDENING
(GRAND BOULEVARD - PRAIRIE AVENUE)
RECOMMENDED IMPROVEMENTS
AVENUE
IDOT REQUIREMENT LOSE 4 SPOTS IDOT REQUIREMENT LOSE 9 SPOTS
RECOMMENDED IMPROVEMENT LOSE 1 SPOT RECOMMENDED IMPROVEMENT LOSE 3 SPOTS
PRAIRIE AVENUE
IDOT REQUIREMENT LOSE 9 SPOTS IDOT REQUIREMENT LOSE 6 SPOTS
GRANT
RECOMMENDED IMPROVEMENT LOSE 3 SPOTS RECOMMENDED IMPROVEMENT LOSE 3 SPOTS
TOTAL FOR ALL 4 LEGS
OF INTERSECTION
IDOT REQUIREMENT LOSE 28 SPOTS
Page 11 of 16
RECOMMENDED IMPROVEMENT LOSE 10 SPOTS
Committee Item Memo
Meeting Date: February 28, 2022
Staff Contact: Carl Muell, Public Works Director
Department: Public Works
Subject: Eight-Corners Fountain Update
Background Information:
Staff has been working to replace the fountain at Eight-Corners for several years now. Design
details were discussed over a two-year period, and funds were included in the 2021 budget for
construction. Shortly after the Board directed staff to move forward with the project, the Village
was informed by the State that we were going to receive $250,000 in State grant funding
towards the project. Since this funding would pay for roughly half the project, Village staff
began to work with the State to comply with the requirements they place on use of these funds.
As a summary:
Bids for the Veteran’s Circle Improvements Project were advertised in July 2021.
Approximately two weeks prior to advertising for bids, the Village received notice that it was to
receive $250,000 in grant funds towards the project that would be administered by the
Department of Commerce and Economic Opportunity (DCEO). Village staff worked diligently
with DCEO staff to incorporate any grant-related requirements in the bidding documents. The
most notable of these requirements was the requirement for Disadvantaged Business
Enterprise (DBE) participation in the project. Although DCEO staff could not provide the exact
DBE participation percentage at that time, they recommended that the Village use the typical
DBE percentage used by Cook County which is 34%. DCEO determines the DBE participation
individually for each project and felt that using the Cook County DBE participation percentage
would be conservative.
A contract was awarded to Integral Construction for the project by the Village Board at the
August 23, 2021 Board meeting in the amount of $641,200.00. At this same Board meeting,
Change Order No. 1 was also approved which included certain credits provided by the
contractor and elimination of two items of work which will be performed by Public Works
personnel. This Change Order reduced the total contract amount to $598,080.00.
Since August 2021, staff has submitted the documentation required by DCEO and has been
attempting to have DCEO approve the documentation and determine the MBE participation
requirements for the project. During staff’s most recent conversation with DCEO on February
7th, they indicated that several items remained to be reviewed and they anticipated it would be
approximately 8 – 12 weeks before the Village would receive the DBE participation
Page 12 of 16
percentages. DCEO indicated that typical DBE participation percentages have ranged from 20
– 24% on recent projects. Once these DBE participation percentages are received, the
contractor will submit their Utilization Plan for review by DCEO. It should be noted that the
contractor’s Utilization Plan submitted with the bid included 9.5% DBE participation. Staff
anticipates that DCEO will require the contractor to either increase their DBE participation or
provide documentation of their Good Faith Effort (demonstrate they solicited proposals from
many DBE contractors, etc.). The final approval of the DBE participation can be a “back and
forth” process and it is difficult to estimate the exact amount of time it will take. Staff
anticipates a range of 4 – 8 weeks. Once the DBE participation plan and all other grant
requirements have been satisfied, the Village can proceed with the work and anticipate
receiving the funding from DCEO.
The following is staff’s estimated schedule for the remaining items to be completed.
Receive DBE participation requirements: April 18.
Receive approval of DBE Utilization Plan: May 30
Begin construction: June, 2022
Complete construction: September, 2022
The Village always has the option of moving forward with the project without utilizing the State
funding. Funds are available in the Eight-Corners Tax Increment Financing District to cover
this project. During a recent meeting with DCEO, staff inquired whether our $250,000 grant
could be utilized by the Village for another project, but the DCEO did not feel that was an
option. Staff recommends we continue to follow the State's process until May, 2022. If, at that
point, we are no closer to final approval by the State, we can bring this issue back to the
Board's attention and assess options for moving forward with the construction.
Financial Impact:
The financial impact would be $348,080.00 with the grant or $598,080.00 without the grant.
Recommendation(s):
Continue to follow the State's review process
Attachments:
2 CFR 200 Procurement - 2-7-22 from DCEO Accountability Office
Page 13 of 16
Procurement
Summary
All grants are required to follow procurement standards that are outlined in 2 CFR 200.317
through 2 CFR 200.327 (https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-
200/subpart-D/subject-group-ECFR45ddd4419ad436d). This document will help guide your
organization to establish an organization procurement policy and help your organization remain
in compliance with procurement standards. Noncompliance with procurement standards may
result in the return of funds to the agency.
How to Comply
1. All Grantees must have and use documented procurement procedures that are
consistent with 2 CFR 200.317 through 327, which is summarized in this document.
2. All procurement processes must be documented.
3. The Illinois Department of Commerce & Economic Opportunity may ask for the
procurement policy and backup documentation as part of a grant monitoring review.
Summary of Procurement Methods
1. Micro-purchase
2. Small purchase
3. Sealed bids
4. Proposals
5. Noncompetitive procurement
Micro-purchases
The purchase cannot exceed the micro-purchase threshold, which is defined in the
Federal Acquisition Regulations as $10,000 (confirm this, as the threshold may change
by the federal government).
As a Grantee, you may establish a threshold higher than the micro-purchase threshold,
but you must:
o Qualify as a low-risk auditee, in accordance with 2 CFR 200.520 for the most
recent audit;
o Perform an annual internal institutional risk assessment to identify, mitigate and
manage financial risks; or,
o For public institutions, a higher threshold consistent with State law.
Micro-purchases may be awarded without soliciting competitive price or rate quotations if
your organization considers the price to be reasonable.
Page 14 of 16
Small Purchases
Small Purchases are for purchases that do not exceed the Simplified Acquisition
Threshold of $250,000 (confirm this, as the threshold may change by the federal
government).
Your organization is responsible for following the established procurement policy of your
organization that describes the small purchase procedures, which includes, but not
limited to:
o Outreach methods
o Acceptable number of responses
o Review methods
Sealed Bids Purchases
Sealed Bids Purchases may be used when the value of the procurement exceeds the
Simplified Acquisition Threshold of $250,000 (confirm this, as the threshold may change
by the federal government).
This method includes a public solicitation and a firm fixed-price contract (lump sum or
unit price) is awarded to the bidder that conforms with the terms and conditions of the
invitation for bids, is the lowest in price.
The following should be present for a sealed bid:
o A complete, adequate and realistic specification or purchase description is
available;
o Two or more responsible bidders are willing and able to compete effectively for
the business; and
o The procurement lends itself to a firm fixed price contract and the selection of the
successful bidder can be made principally on the basis of price.
If sealed bids are used, the following requirements apply:
o Bids must be solicited from an adequate number of qualified sources, providing
them sufficient response time prior to the date set for opening the bids, for local,
and tribal governments, the invitation must be publicly advertised;
o The invitation for bids, which will include any specifications and pertinent
attachments, must define the items or services in order for the bidder to properly
respond;
o All bids will be opened at the time and place prescribed in the invitation for bids,
and for local and tribal governments, the bids must be opened publicly;
o A firm fixed price contract award will be made in writing to the lowest responsive
and responsible bidder. Where specified in bidding documents, factors such as
discounts, transportation cost, and life cycle costs must be considered in
determining which bid is lowest. Payment discounts will only be used to
determine the low bid when prior experience indicates that such discounts are
usually taken advantage of; and
o Any or all bids may be rejected if there is a sound documented reason.
Proposals
Proposals may be used when the value of the procurement exceeds the Simplified
Acquisition Threshold of $250,000 (threshold may change by the federal government).
Proposals are generally used when conditions are not appropriate for the use of sealed
bids (typically when there are unique skills required).
Page 15 of 16
Requests for proposals (RFPs) must be publicized and identify all evaluation factors and
their relative importance. Proposals must be solicited from an adequate number of
qualified offerors. Any response to publicized requests for proposals must be considered
to the maximum extent practical;
There must be written methods for conducting technical evaluations of the proposals
received and making selections;
Contracts must be awarded to the responsible offeror whose proposal is most
advantageous to your organization, which price and other factors considered; and
Your organization may use competitive proposal procedures for qualifications-based
procurement of architectural/engineering (A/E) professional services whereby offeror's
qualifications are evaluated, and the most qualified offeror is selected, subject to
negotiation of fair and reasonable compensation. The method, where price is not used
as a selection factor, can only be used in procurement of A/E professional services. It
cannot be used to purchase other types of services though A/E firms that are a potential
source to perform the proposed effort.
Noncompetitive Procurement
Noncompetitive procurement may be used if one or more of the following circumstances
apply. All decisions on pursuing a noncompetitive procurement must be documented.
o The acquisition of property or services, the aggregate dollar amount of which
does not exceed the micro-purchase threshold
o The item is available only from a single source;
o The public exigency or emergency for the requirement will not permit a delay
resulting from publicizing a competitive solicitation;
o The Illinois Department of Commerce & Economic Opportunity expressly
authorizes a noncompetitive procurement in response to a written request from
the non-Federal entity; or
o After solicitation of a number of sources, competition is determined inadequate.
Tips to Remain in Compliance
Read 2 CFR 200.317 through 2 CFR 200.327 to understand Procurement Standards -
https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200/subpart-D/subject-
group-ECFR45ddd4419ad436d
Create a documented procurement policy that uses 2 CFR 200.317 through 2 CFR
200.327 as minimum requirements.
Avoid conflicts of interest and related-party transactions by following your organization
policy and saving documentation.
If you have any questions, reach out to your grant manager for assistance.
Page 16 of 16