Castle Rock Water Commission
Regular MeetingCastle Rock, CO · March 22, 2023
Minutes
Todd Warnke, Chair
Bill Leung, Vice Chair
Castle Rock Water Commission
Angie Brown
Meeting Minutes - Final Kathryn Gienger
David Hammelman
Kevin McHugh
Tony Rathbun
Wednesday, March 22, 2023 6:00 PM Castle Rock Water
175 Kellogg Ct., Bldg. 171
Castle Rock, CO 80109
This meeting is open to the public and will be held in a hybrid format in accordance with
Town Council Electronic Participation, Connected, and Hybrid Meeting Policy. The
in-person meeting will be held at 175 Kellogg Ct. Bldg. 171 Castle Rock CO 80104 or this
meeting can be accessed online at:
https://crgov.webex.com/crgov/j.php?MTID=m92cb42571097d1f8b206e0b9132d5aa0
the Meeting password: Mar22WCMtg (62722926 from video systems) or phone in by
calling (720) 650-7664, meeting code #24978923628#. One or more Council members
may also attend this meeting, during which the items listed herein will be discussed.
CALL TO ORDER / ROLL CALL
Present 6 - Chair Todd Warnke, Vice Chair Bill Leung, Angie Brown, Kathryn Gienger, David
Hammelman, and Kevin McHugh
Not Present 1 - Tony Rathbun
Attendance 9 - Jason Gray, Mark Marlowe, Nichol Bussey , Roy Gallea, David Van Dellen, Paul Rementer,
Walt Schwarz, Matt Hayes, and Shantanu Tiwari
COUNCIL UPDATE
Time was allowed for Mayor Gray to share a council update.
COMMISSION COMMENTS
Time was allowed for Commissioner Comments.
ADMINISTRATIVE BUSINESS
WC 2023-028 Approval of the February 28, 2023 Meeting Minutes
Town Council Agenda Date: NA
Angie Brown shared two corrections to the meeting minutes, Rick Schultz
was left off the attendance list and the vote on the meeting minute’s item
reflected an incorrect vote. The vote should have been 6-0-1 (Angie Brown
abstained)
It was moved by Kathryn Gienger and seconded by David Hammelman to approve
the meeting minutes with the added corrections The motion passed 6-0
Yes: 6 - Chair Warnke, Vice Chair Leung, Brown, Gienger, Hammelman, and McHugh
Castle Rock Water Commission Meeting Minutes - Final March 22, 2023
Not Present: 1 - Rathbun
WC 2023-029 Water Commission Appreciation Event
Town Council Agenda Date: NA
Ms. Woodrick shared that the Water Commission Appreciation Event will be
on Friday, April 21, 2023 at the Mill House. Cocktails will be served at 5:30
pm with dinner being served at 6:30 pm. Invitations will be sent via email in
the next day or two.
Mr. Marlowe also let board members know that the Board and Commission
application process will start in April. At this time, the Water Commission
Board will have two open positions and two positions that are up for
reappointment. Applications will be accepted from April 1st - 24th. Interviews
will be held on May 9th. The new board members will begin their terms on
June 1st.
ACTION ITEMS (HIGH PRIORITY / TIME CRITICAL)
WC 2023-030 A Resolution Approving a Construction Contract between
the Town of Castle Rock and Global Underground
Corporation for the East Plum Creek Open Space Well
Facility [Open space north of Plum Creek Water Purification
Facility]
Town Council Agenda Date: April 4, 2023
Mr. Hayes explained that this project is to build the well facility for the wells
that are currently being drilled just north of the Plum Creek Water Purification
Facility (PCWPF). The anticipated production of these wells is 0.7-0.9 million
gallons per day (MGD). The wells will be designed for Aquifer Storage and
Recovery as well. Castle Rock Water (CRW) will be able to send this water to
the Meadows Treatment Facility or to PCWPF. This project will help CRW
meet customer water demands during peak season use.
CRW received four bids. Global Underground was selected as the contractor.
The proposed cost of the project is $2,375,650.01 with a 10% contingency for
a total estimated authorization of $2,613,215.01. The project will begin in May
of 2023 with an estimated completion of December 2023.
Commission Brown asked which aquifer would be used for the aquifer
storage and recovery (ASR)? Mr. Hayes explained it would be the Arapahoe
Basin.
Kevin McHugh moved to recommend to Town Council approval of the Resolution as
presented. Bill Leung seconded the motion. Passed unanimously 6-0.
Castle Rock Water Commission Meeting Minutes - Final March 22, 2023
Yes: 6 - Chair Warnke, Vice Chair Leung, Brown, Gienger, Hammelman, and McHugh
Not Present: 1 - Rathbun
WC 2023-031 A Resolution Approving a Construction Contract between
the Town of Castle Rock and RME Ltd., LLC dba Elite
Surface Infrastructure for the Prestwick Water Rehab Project
[W. Prestwick Way]
Town Council Agenda Date: April 4, 2023
Mr. Hayes explained that this project is a rehabilitation project that is located
in the southern part of the Plum Creek neighborhood. This pipe was laid in the
1980’s and CRW has had to make several repairs of the pipe in recent years.
This project will replace 2,241 feet of 8 inch main, 9 gate valves, 5 fire
hydrants, as well as replace service lines between the main and curb stop
and repair the road that will be disturbed by this project.
CRW received four bids. Elite Surface Infrastructure (ESI) was selected as
the contractor. The proposed cost of the project is $1,095,135 plus a 10%
contingency for a total estimated budget of $1,204,648. The project is
scheduled to begin in May 2023 with a planned completion date of
September 2023.
Commissioner Brown asked what the material of the pipe currently is? Mr.
Hayes explained that it is ductile iron pipe that was not wrapped to protect it
from corrosion.
Commissioner Hammelman asked what the impact will be on the residents?
Mr. Hayes explained that the disruption of water to homes should be minimal.
The water will only need to be disrupted when the connections from the main
to the curb stop are made.
Commissioner McHugh asked what happens if the line from the curb stop to
the home is not in good condition? Mr. Hayes explained that the customer
would be responsible for any repairs to that portion of the service line.
Commissioner Warnke asked what the life span of a pipe should be, is this a
normal timeframe, will CR residents being seeing more replacement projects
in the future? Staff answered, 40 to 50 years so yes, and yes residents will
see more of these projects in the future.
Bill Leung moved to recommend to Town Council approval of the Resolution as
presented. David Hammelman seconded the motion. Passed unanimously 6-0.
Yes: 6 - Chair Warnke, Vice Chair Leung, Brown, Gienger, Hammelman, and McHugh
Not Present: 1 - Rathbun
Castle Rock Water Commission Meeting Minutes - Final March 22, 2023
WC 2023-032 A Resolution Approving a Construction Contract between
the Town of Castle Rock and XXXX to provide construction
services for Castle Rock Reservoir No. 2 (CRR2) and Castle
Rock Reservoir No. 1 (CRR1) [Sedalia, CO]
Town Council Agenda Date: April 4, 2023
Mr. Tiwari shared that CRW has an existing reservoir out in the Sedalia area.
The current reservoir holds 240 acre feet (AF). The purpose of this project is
to build a second reservoir that will hold 790 AF. Once the second reservoir is
built the first reservoir will be expanded to hold 550 AF.
CRW received five bids for this project. HEI was selected as the contractor
for this project. The proposed cost for this project is $26,490,159.04 with a
10% contingency for a total estimated authorization of $29,139,174.94.
Commissioner Warnke asked why there was such a large difference between
HEI’s bid and the next lowest bid? Is there any concern that something was
missed? Staff explained that HEI built the first reservoir so they were very
familiar with the site. They are also a local contractor with significant currently
available equipment. Based on meetings with the design engineer and HEI,
staff does not have any concerns at this point that something was missed.
Commissioner Gienger asked how the other reservoirs they have done
compare to this project? Mr. Tiwari stated that most are the size of reservoir 1
or smaller.
Kevin McHugh moved to recommend to Town Council approval of the Resolution as
presented. Angie Brown seconded the motion. Passed unanimously 6-0.
Yes: 6 - Chair Warnke, Vice Chair Leung, Brown, Gienger, Hammelman, and McHugh
Not Present: 1 - Rathbun
WC 2023-033 A Resolution Waiving Formal Written Bidding Requirements
on the Basis of a Sole Source and Approving a Professional
Services Agreement to provide construction support
services for the Castle Rock Reservoir No. 2 (CRR2) and
Castle Rock Reservoir No. 1 (CRR1) [5219 Rio Grande Ave,
Sedalia, CO 80135]
Town Council Agenda Date: April 4, 2023
Mr. Tiwari explained that W.W. Wheeler has been the design engineer for the
Castle Rock Reservoir No. 1 & No. 2 project. This agreement is to have them
continue as support through the construction project. Their services will
include construction supervision, materials testing, review of submittals,
handling of requests for information (RFI’s) and change orders.
Castle Rock Water Commission Meeting Minutes - Final March 22, 2023
The proposed cost for this service is $2,111,200 with a 5% contingency for a
total estimated authorization of $2,216,760.
Angie Brown moved to recommend to Town Council approval of the Resolution as
presented. Kathryn Gienger seconded the motion. Passed unanimously 6-0.
Yes: 6 - Chair Warnke, Vice Chair Leung, Brown, Gienger, Hammelman, and McHugh
Not Present: 1 - Rathbun
WC 2023-034 A Resolution Approving a Professional Services Agreement
between the Town of Castle Rock and Burns & McDonnell
for the Pinery Water Pipeline Project [Along Castle Oaks Drive
in the northwest part of the Town]
Town Council Agenda Date: April 4, 2023
Mr. Tiwari explained that this item is for the design of a pipeline that will move
water from the Pinery into CRW’s supply. The Town will receive between 0.25
and 1.0 MGD of water from the Pinery, that is originally from the Cherry Creek
Project Water Authority (CCPWA).
CRW received two bids for this project. Burns & McDonnell was selected as
the design engineer. The proposed cost for the design phase is $805,043,
plus a 10% contingency for a total estimated authorization of $885,547.
Commissioner Brown asked if there would be an impact to the residents in
that area? Mr. Tiwari explained that most of the work will be done on Town
property. The only other area is land that is in a trust and staff will work with
them.
Commissioner Leung asked why the water from the Pinery is different than
the water in Castle Rocks system? Staff explained the differences in
aesthetic quality and the resulting impacts that can have.
Bill Leung moved to recommend to Town Council approval of the Resolution as
presented. Kevin McHugh seconded the motion. Passed unanimously 5-0-1 (Kathryn
Gienger abstained).
Yes: 5 - Chair Warnke, Vice Chair Leung, Brown, Hammelman, and McHugh
Not Present: 1 - Rathbun
Abstain: 1 - Gienger
WC 2023-035 A Resolution Approving a Services Agreement between the
Town of Castle Rock and Burns & McConnell Engineering to
complete the Design Phase Engineering Services for
Castle Rock Water Commission Meeting Minutes - Final March 22, 2023
PCWPF Expansion Project [1929 Liggett Rd. Castle Rock, CO
80109] DRAFT
Town Council Agenda Date: April 18, 2023
Mr. Schwarz shared that CRW is ready to begin the next phase of the Plum
Creek Water Purification Facility Expansion. This item is to design the next
expansion which will increase the facility capacity from 6 MGD to 12 MGD.
The additions will include an additional pretreatment train, raw water feed
tanks, additional granular activated carbon (GAC) filtration, ozone treatment
and improved solids handling. A new larger generator will also be added.
This agreement will also stipulate that the contractor will be selected and
added to the team once the design has been 30% completed. This will allow
the contractor to lend their expertise in what will and will not work as well.
The RFP was issued to five engineering firms and CRW receive one
proposal. Burns & McDonnell was selected as the design engineer. The
proposed cost of the project is $2,388,880 with a 5% contingency for a total
estimated cost of $2,508,324. The design schedule is April 2023 to May
2024 with the RFP for the contractor to be issued in Fall 2023. The estimated
completion of the project will be the end of 2026.
Commissioner Gienger asked if all of the facilities have generators? Mr.
Schwarz explained that yes they all do with the exception of Founders Water
Treatment Plant.
Commissioner McHugh asked if this will help give CRW some breathing
room prior to Dawson Trails coming on-line? Staff answered that this will help
provide a wider margin of supply especially during irrigation season.
Kevin McHugh moved to recommend to Town Council approval of the Resolution as
presented. Angie Brown seconded the motion. Passed unanimously 6-0
Yes: 6 - Chair Warnke, Vice Chair Leung, Brown, Gienger, Hammelman, and McHugh
Not Present: 1 - Rathbun
DIRECTOR FOLLOW-UP AND INFORMATIONAL / UPDATE ITEMS
WC 2023-036 2022-2023 Budget Recap
Town Council Agenda Date: NA
Mr. Rementer shared a presentation on multiple topics related to finances. He
shared that building permits are down which will impact CIP projects planned
for 2023 and beyond. He also shared that staff is looking at energy costs and
will be working on ways to be more efficient.
Ms. Bussey was happy to share an update on the progress for the new AMI
project, how the Financial Hardship program is going and how many
Castle Rock Water Commission Meeting Minutes - Final March 22, 2023
customers have signed up for the new on-line bill pay portal (Silverblaze).
WC 2023-037 A Resolution Approving a Variance Pursuant to Chapter
9.16.010.E of the Castle Rock Municipal Code for Nighttime
Construction Activities Related to the Tank 18 Blue Zone
Main Project [Located at the intersection of Castle Oaks Drive
and Pleasant View Drive]
Town Council Agenda Date: March 21, 2023
Mr. Marlowe explained that this item was approved at the March 21st Town
Council meeting and is just an informational update.
WC 2023-038 Upcoming Town Council Items
Town Council Agenda Date: NA
This is a standing item that will be used to share information about projects
that are being worked on at the time of the meeting but that staff doesn’t have
information ready yet.
Mr. Marlowe shared that April is Water Conservation Month and that Town
Council will be making a Proclamation at the April 4th meeting.
COMMISSIONER MEETING COMMENTS
Time was allowed for Commissioner Comments.
Agenda
Todd Warnke, Chair
Castle Rock Water Commission Bill Leung, Vice Chair
Angie Brown
Agenda - Final Kathryn Gienger
David Hammelman
Kevin McHugh
Tony Rathbun
Wednesday, March 22, 2023 6:00 PM Castle Rock Water
175 Kellogg Ct., Bldg. 171
Castle Rock, CO 80109
This meeting is open to the public and will be held in a hybrid format in accordance with
Town Council Electronic Participation, Connected, and Hybrid Meeting Policy. The
in-person meeting will be held at 175 Kellogg Ct. Bldg. 171 Castle Rock CO 80104 or this
meeting can be accessed online at:
https://crgov.webex.com/crgov/j.php?MTID=m92cb42571097d1f8b206e0b9132d5aa0
the Meeting password: Mar22WCMtg (62722926 from video systems) or phone in by
calling (720) 650-7664, meeting code #24978923628#. One or more Council members
may also attend this meeting, during which the items listed herein will be discussed.
6:00 pm CALL TO ORDER / ROLL CALL
COUNCIL UPDATE
COMMISSION COMMENTS
ADMINISTRATIVE BUSINESS
1. WC 2023-028 Approval of the February 28, 2023 Water Commission Meeting
Attachments: Attachment A: Feb Mtg Minutes
2. WC 2023-029 Water Commission Appreciation Event
ACTION ITEMS (HIGH PRIORITY / TIME CRITICAL)
3. WC 2023-030 A Resolution Approving a Construction Contract between the Town of
Castle Rock and Global Underground Corporation for the East Plum Creek
Open Space Well Facility [Open space north of Plum Creek Water
Purification Facility]
Attachments: Attachment B: Site Map
4. WC 2023-031 A Resolution Approving a Construction Contract between the Town of
Castle Rock and RME Ltd., LLC dba Elite Surface Infrastructure for the
Prestwick Water Rehab Project [W. Prestwick Way]
Attachments: Attachment B: Location Map
Castle Rock Water Commission Agenda - Final March 22, 2023
5. WC 2023-032 A Resolution Approving a Construction Contract between the Town of
Castle Rock and XXXX to provide construction services for Castle Rock
Reservoir No. 2 (CRR2) and Castle Rock Reservoir No. 1 (CRR1) [Sedalia,
CO]
Attachments: Attachment B: Location Map
6. WC 2023-033 A Resolution Waiving Formal Written Bidding Requirements on the Basis of
a Sole Source and Approving a Professional Services Agreement to
provide construction support services for the Castle Rock Reservoir No. 2
(CRR2) and Castle Rock Reservoir No. 1(CRR1) [5219 Rio Grande Ave,
Sedalia, CO 80135]
Attachments: Attachment B: Location Map
Attachment C: Sole Source
7. WC 2023-034 A Resolution Approving a Professional Services Agreement between the
Town of Castle Rock and Burns & McDonnell for the Pinery Water Pipeline
Project [Along Castle Oaks Drive in the northwest part of the Town]
Attachments: Attachment B: Location Map
8. WC 2023-035 A Resolution Approving a Services Agreement between Town of Castle
Rock and Burns & McDonnell Engineering Company to complete Design
Phase Engineering Services for PCWPF Expansion Project [1929 Liggett
Rd. Castle Rock, CO 80109]
DIRECTOR FOLLOW-UP AND INFORMATIONAL / UPDATE ITEMS
9. WC 2023-036 2022-2023 Budget Recap
10. WC 2023-037 A Resolution Approving a Variance Pursuant to Chapter 9.16.070.E of the
Castle Rock Municipal Code for Nighttime Construction Activities Related to
the Tank 18 Blue Zone Main Project [Located at the intersection of Castle
Oaks Drive and Pleasant View Drive]
Attachments: Attachment A: Staff Report
11. WC 2023-038 Upcoming Town Council Items