Conservation Commission
Regular MeetingChicopee, MA · February 5, 2025
Minutes
CITY OF CHICOPEE
CONSERVATION COMMISSION
Minutes of Meeting
February 5, 2025
Pursuant to Mass. General Law Ch. 131, Section 40 and the Chicopee Wetland Ordinance Ch. 272, the Chicopee Conservation
Commission held a public hearing on Wednesday, February 5, 2025 at 6:15 PM in the RiverMills Senior Center, Classroom
30, First Floor, 5 West Main St., Chicopee, MA 01013
Celeste Donovan opened the meeting at 6:18 PM and announced that the meeting was being recorded.
Conservation Commission attendance:
Member Present Absent Excused
Celeste Donovan X
Charles Payne X
Meghan Balakier X
Richard Valcourt X
Bianca Thomas X
Barbara Chamberlain X
Sharon Balcom X
Planning/Conservation Staff attendance:
Member Present Absent Excused
Lee Pouliot, Director X
James Dawson, Development Manager X
Nick Kiser, Associate Planner X
Patrick Collins, Assistant Planner X
Item 1: Request for Certificate of Compliance. On August 7, 2024 the Commission approved an Order of Conditions (NOI 24-
004) for upgrades to existing utility ROW. Soil borings within Bordering Vegetated Wetland. Buffer Zone and Terrace Escarpment
(TE) Soils in preparation for structure replacements. The work has been completed, and the area has been stabilized. Location: 363
Prospect St., Chicopee, MA Applicant: David Askew, NSTAR Electrical Co. DBA Eversource Energy Service Co., 107 Selden St.,
Berlin, CT 06037
Notes: John Furman of VHB, and Applicant David Askew were in attendance to present the request to the Commission. Mr. Furman
presented photos from the January 15, 2025 site visit with Staff. Staff was satisfied that the site was stabilzed to the best it could be
considering the winter season. Erosion control jute mats were in place and the service roads were very well constructed with crushed
stone and underlayment of fabric to prevent the stone from becoming compacted into the soil. Staff recommended approval of the
Certificate of Compliance which closes out the first phase of the project and enables the Applicant to submit an NOI for the next
phase.
Motion to approve and issue the Certificate of Compliance was made by Charles Payne and seconded by Richard Valcourt. Vote was
6-0 to approve and issue the Certificate of Compliance.
Member Approve Deny Table Abstain
Celeste Donovan X
Charles Payne X
Meghan Balakier X
Richard Valcourt X
Barbara Chamberlain X
Sharon Balcom X
Item 2: Minutes from December 4, 2024
Motion to approve with noted corrections was made by Barbara Chamberlain and seconded by Sharon Balcom. Vote was 6-0 to
approve with the noted corrections.
Member Approve Deny Table Abstain
Celeste Donovan X
Charles Payne X
Meghan Balakier X
Richard Valcourt X
Barbara Chamberlain X
Sharon Balcom X
Item 3: Sign Bills – There were no bills to sign.
Item 4: Upcoming Projects/Discussion/Communications
• Implementation of fines for Enforcement Orders 23-E002 and 23-E003 on McKinstry Avenue. Enforcement Orders
were issued by the Commission in September 2023. To date we are not aware of any progress toward resolving the
Enforcement Orders.
Notes: Ryan Nelson of R. Levesque Associates presented an update on the status of the Enforcement Orders that were issued in 2023.
R. Levesque has been retained by both landowners and recipients of the Enforcement Orders (Gramntad, LLC and R. Ducharme, Inc.).
Mr. Nelson explained that Gramntad, LLC had applied for a zone change on their property to eliminate a split-zoned property and
allow for full Industrial use of the entire property. He explained that once the zone change had been obtained the Applicant would be
able to pull back from the TE Soils and buffer zone on the property. Mr. Nelson also noted that an NOI was being prepared in
response to the conditions of the Enforcement Orders. The Commission has reiterated that the property owners must cease and desist
all activity within the TE soils and respective buffer zone areas on the site or possibly face fines. The Commission also requested a
site visit to determine if any erosion was occurring within the TE soils areas of their buffer zones. The Commission tabled discussion
on this issue until March 5, 2025 at which time they expect another update as to compliance with the Enforcement Order and a site
visit will have occurred. The Commission noted that the ONLY exception from the Cease and Desist would be allowance of the new
access road to be utilized.
Motion to table discussion on the issue to March 5, 2025 was made by Charles Payne and seconded by Richard Valcourt. Vote was 6-
0 to table the discussion to March 5, 2025.
Member Approve Deny Table Abstain
Celeste Donovan X
Charles Payne X
Meghan Balakier X
Richard Valcourt X
Barbara Chamberlain X
Sharon Balcom X
Item 5: Adjournment – Next meeting is scheduled for February 19, 2025.
Motion to adjourn was made by Barbara Chamberlain and seconded by Sharon Balcom. Vote was 6-0 to adjourn.
Member Approve Deny Continue Abstain
Celeste Donovan X
Charles Payne X
Meghan Balakier X
Richard Valcourt X
Barbara Chamberlain X
Sharon Balcom X
Meeting adjourned at 7:20 PM.
Agenda
CITY OF CHICOPEE - CONSERVATION COMMISSION
274 Front Street, Chicopee, MA 01013
(413) 594-1515
PUBLIC HEARING AGENDA
February 5, 2025
Pursuant to Mass. General Law Ch. 131, Section 40 and the Chicopee Wetland Ordinance Ch. 272, the
Chicopee Conservation Commission will hold a public hearing on Wednesday, February 5, 2025 at 6:15 PM at
the RiverMills Senior Center, Classroom 30, First Floor, 5 West Main St., Chicopee, MA. to discuss the
following:
Chairperson please announce meeting is being recorded and inform public if they are recording the meeting
they must disclose they are recording and provide their name and address for the record.
Item 1: Request for Certificate of Compliance. On August 7, 2024 the Commission approved an Order of
Conditions (NOI 24-004) for upgrades to existing utility ROW. Soil borings within Bordering Vegetated Wetland. Buffer Zone
and Terrace Escarpment (TE) Soils in preparation for structure replacements. The work has been completed, and the area has been
stabilized. Location: 363 Prospect St., Chicopee, MA Applicant: David Askew, NSTAR Electrical Co. DBA Eversource Energy
Service Co., 107 Selden St., Berlin, CT 06037
Item 2: Minutes from December 4, 2024
Item 3: Sign Bills
Item 4: Upcoming Projects/Discussion/Communications
• Implementation of fines for Enforcement Orders 23-E002 and 23-E003 on McKinstry Avenue.
Enforcement Orders were issued by the Commission in September 2023. To date we are not aware of any
progress toward resolving the Enforcement Orders.
Item 5: Adjournment – Next meeting is scheduled for February 19, 2025