Borough Council
Regular MeetingCollegeville, PA · April 7, 2021
Minutes
COLLEGEVILLE BOROUGH COUNCIL
ZOOM MEETING MINUTES
APRIL 7, 2021
The meeting was called to order at 7PM by Council President Cathy Kernen
ROLL CALL: President Cathy Kernen, Pro Tem Gary Hoffmann, Council Member Marion McKinney,
Council Member Craig Farr, Council Member Valarie Beckius, Council Member Kathy Costello and Mayor
Aidsand Wright-Riggins. VP Shannon Spencer was not present.
ALSO IN ATTENDANCE: Solicitor Dan Grieser, Engineer David Leh, Police Chief Bart Bucher and Borough
Manager Tamara Twardowski.
MOTION to approve the minutes from the March meeting by Ms. McKinney with a second by Mr.
Hoffmann
MOTION carries 6-0
Ms. Kernen introduced Chris Canavan to discuss final approval for the Land Development plan known as
Freeland Square. Mr. Canavan advised that one final waiver has been requested and recommended for
approval by the Planning Commission regarding plantings close to the underground utilities. Barriers
will be laid to ensure the roots of the trees will not disrupt the utilities. Mr. Farr asked how this works.
Mr. Canavan explained that the burlap barriers merely encourage the roots to grow in a different
direction and that this is a common practice. Mr. Grieser advised that public comment be allowed
before approval is granted by Council.
Brian Fox 104 W Third Ave: Mr. Fox wanted to be assured that before demolition, the environmental
testing is complete.
Mr. Canavan advised that both Phase I and II are complete. He noted that the demolition of a site this
large is heavily regulated by the state. He assured everyone that the safety fence is up, the asbestos is
being properly taken care of and that the construction vehicles will be directed on to Main Street and
not W Third Ave.
MOTION to approve the final conditional land development for Freeland Square by Ms. McKinney with a
second by Ms. Beckius
MOTION carries 6-0
PUBLIC COMMENT:
Aileen Johnson, Director of PV Library reported that the library is now open twenty-eight hours per
week and still has curbside pickup for those who want it. She noted that the Norristown Library now has
a new Director, Karen D’Angelo. All programs will continue to be online through the summer.
Public Comment closed.
TREASURE’S REPORT: Ms. Twardowski noted that the full report is available at the office and asked for
approval of disbursement included payroll, Ach payments, and checks #4793-4857 totaling
$188,874.14. She reported that transfer taxes are up $40K from last year (mostly due to the WB Homes
purchase of the Rees property closing), earned income taxes are up approximately $20K over last year
and that we are about $10K over budget on snow removal. Ms. Twardowski also made note of funds of
$500K that may be made available from the government to the Borough under the American Rescue
Plan. She explained that there are very specific guidelines for how this money can be used and that,
unfortunately, it cannot be used for roads or bridges. She will continue to update council on the ever
changing guidelines and will work to best utilize the funds to benefit the borough.
MOTION to approve the Treasure’s report and checks my Ms. McKinney with a second by Mr.
Hoffmann.
MOTION carries 6-0
BUSINESS DEVELOPMENT: Ms. Kernen shared a presentation that was a part of the latest BDC meeting.
She highlighted the following points:
Core Development will start creating density at the 5th Ave & Main St corner
Work is needed on the other side of Main St between Fourth & Fifth Avenues
Begin looking at which college owned properties can be leased to businesses now
Focus on helping recruit good destination businesses as anchors, such as the Key Bank building
Consideration of Clamer Hall as a town center
Flowers on Main St
The RAP Grant application was completed under the wire. We are considering what the funds
can be used for to best benefit the Borough; as in expanding our meeting space and a
renovation to Borough Hall should we receive the grant.
She and Robert Botti wrote articles regarding the future of the Perkiomen Bridge Hotel, taking
opposing sides as to whether the building should be saved. Mr. Botti’s article said that the
building is too far gone and that it would take too much money to fix for anyone to ever see a
profit from doing so. Ms. Kernen took the side of saving the building no matter the cost because
it dates back eleven generations, and that once the history is destroyed, it cannot be replaced.
She noted that she spoke with the owner at length and that he appreciates any help with
fundraising. The purpose of the opposing articles was to get feedback from the community.
Ms. Kernen is reaching out to the Montgomery County Historical Society for assistance. She is
also working on a new historic building ordinance with our solicitor to maintain the quaint look
of our Main St.
Mr. Grieser noted that he is making revisions to the ordinance, will take those to the Planning
Commission and then back to Council for approval. He also said that he is working on the zoning overlay
for both sides of Main St between Fourth & Fifth Avenues to make the zoning the same.
COMMUNICATIONS: Ms. Spencer noted that the newsletter now has 635 subscribers and the April
edition will go out this week.
CPVRPC: Ms. Beckius reported that the committee worked on the post cards, brochures and the
interactive map for the trail map. She noted that storm water was a big discussion as many municipalities
are concerned. The next meeting is scheduled for April 19.
CTMA & PUBLIC WORKS: Ms. McKinney said the CTMA meeting was brief. They paid bills and discussed
where to invest funds. She & Mr. Farr agreed that annuities are risky and they are not willing to risk ANY
of the public’s money. Ms. McKinney wholeheartedly agreed that they need to be responsible stewards
of the funds. Mr. Hoffmann asked if there are restrictions for where funds are to be invested. Mr. Grieser
said there are less than some may think and he will provide more information to the committee.
LPVRSA: Ms. Stagliano provided the following April report:
Approved 15 EDU's capacity Rights Agreements
Release of 20 EDU's Chapter 94 letters
Completed Sludge Storage Tank Mixer project
Middle Perkiomen Creek Interceptor Project progress:
Final Completion date: May10, 2022 (Originally June 3, 2021) many issues, flooding, Eagles, etc.
moved that completion date further out.
Project Duration: 1088 days
Project Duration to date: 636 days
% Complete: 58.5%
Contract Amount: (Original $39,481,777.00) $40,122,832,55
Work Completed to date: $18,268,645,55
Percentage: 45.5%
Contractor updated schedule, indicated they will work 50% of Saturdays to meet contract
completion date. Contractor experienced 11 delay days due to weather in Jan/Feb as result of
snow, flooding and winter weather.
LPVRSA Board is reviewing Allan Myers' claims concerning flooding damage in August and
November.
Annual Average daily Flow:
Actual: 9.3 MGD (Million Gallon Daily)
Permit: 14.25 MGD
Final design of emergency power generator in progress.
Numerous maintenance and repairs to the plant were performed.
If you should have any questions, please do not hesitate to contact me.
PARKS: Ms. Costello reported that she and her group of volunteers (council members, St Eleanor’s CYO
teams and residents) have been working to clean up trash, sticks and trees at our three community parks.
PERSONNEL: No report
PLANNING COMMISSION: Ms. Twardowski reported that the last meeting focused on two projects.
They recommended approval of the WB Homes project Freeland Square which council granted this
evening. The second, was a sketch plan submitted by the owners of the Collegeville Car Wash. They
are hoping to expand their business to the vacant property they own next door. There are some zoning
issues that need to be dealt with: it’s a non-conforming use, the amount of impervious surface and that
fact it is located in a flood plain. The Planning Commission had no issue with the “use” of the business
and suggested the owner move forward with getting a variance. The PC will meet again in April to
discuss ordinances being worked on by the solicitor.
STREETS, ROADS & PUBLIC SAFETY: Mr. Farr said they had a very busy meeting that covered
several topics. The first was the sink hole that developed next to McDonald’s. Because the sink hole
was due to damage from the installment of the water line, Public Works department covered the cost of
and handled the repair. However, this repair brought up a discussion of the brick crosswalks on Main
Street and how the repairs are very expensive and that going forward, perhaps bricks not be used since
they are expensive and less durable. Ms. Kernen noted that when the repaving begins on Main Street,
Penn DOT will not replace roadway with anything decorative and that we should consider just having the
brick crosswalks milled and overlayed with asphalt and then paint the crosswalks. The next issue that
came up was the No Parking at 3rd Ave & Chestnut St. It is now set up that there is no parking on the
side of the street across from Freeland Square. WB Homes has requested that this be swapped during
construction so there would be no parking on their side for safety reasons. Ms. Twardowski believes this
can be done during this time without changing the ordinance as long as it gets switched back post
construction. Mr. Farr noted that letters were sent to all residents of Park Avenue as well as all the
streets off Park and only 5 responses came in that all were in favor of the speed pillows. He hopes to find
a way to reach out to more residents for feedback and to also look into traffic counts and how this project
could possibly divert traffic to other streets. He said he is welcoming representatives from Montgomery
County Planning for their input to the information he has collected. He reported that the Fire Safety
Inspection has begun and will be an effective program. Mr. Farr has asked Ms. Twardowski to research
adopting a rental property inspection. He also noted that he is working with Joe Hastings on a survey of
all the drains in the borough. He feels this will be a big issue around budget time because there needs to
be a maintenance plan going forward. The drains cost approximately $1500 each. Mr. Farr said they
also discussed the best way to get the word out to residents that homeowners are responsible for the
maintenance and repair of their sidewalks.
ADMINISTRATIVE REPORTS:
ENGINEER: Mr. Leh reported that bids went out for this year’s paving project and that seven bids were
received. The lowest bid was from Innovative Construction and was for $74,392.45 for paving only and
$85,570.45 for paving and speed pillows. The contractor is amenable to the location of the speed pillows
being confirmed at a later time.
MOTION to approve the paving bid to Innovative Construction with the speed pillow portion to be
amended at a future time by Ms. McKinney with a second by Ms. Beckius
MOTION carries 6-0
Mr. Leh asked for a MOTION to approve the second and final escrow release for Royal Farms in the
amount of $59,015.39 with the condition of legal & engineering fees pad and an eighteen month
maintenance bond
MOTION to approve the final escrow release to Royal Farms by Ms. McKinney with a second by Mr.
Hoffmann
MOTION carries 6-0
Mr. Leh noted that they are still working on verbiage with Royal Farm’s attorneys for the covenant that will
ensure that Royal Farms will maintain the storm drains.
Mr. Leh asked for a MOTION to approve the escrow release for the 339-341 Main St parking lot project.
The release is for $21,681.00 and a maintenance bond will be provided.
MOTION to approve the escrow release for 339-341 Main St by Mr. Farr with a second by Ms. McKinney
MOTION carries 6-0
SOLICITOR: Mr. Grieser asked for permission to draft an update to the property maintenance ordinance
to incorporate adoption of the International Property Maintenance Code.
MOTION to approve the drafting and advertising of updated property maintenance ordinance by Ms.
McKinney with a second by Ms. Beckius.
MOTION carries 6-0
MANAGER: Ms. Twardowski reported that the fire inspections are going well and that our inspector has
completed most of the Collegeville Shopping Center. She noted that the Montgomery County Borough’s
Association is resuming their meetings and is hosting their first since last year on April 22 at 7PM via
ZOOM for anyone that would like to attend. Ms. Twardowski collected information from our energy
provider and got prices for 20% clean, which is the government standard, 50% renewable, 75% and
100%. She said that any of these options will save us money, but that the prices escalate daily. Her
recommendation is to approve the five year rate tonight so that she can sign the agreement tomorrow.
Mr. Hoffmann reported that if we opted for the 100% renewable option, the borough would still save $500
per year and that is his preference.
MOTION to approve locking in the 100% renewable energy rate for five years by Ms. McKinney with a
second by Mr. Hoffmann
MOTION carries 6-0
POLICE: Chief Bucher noted that his report is available at the office and is open to any questions. He
advised that the Drug Take Back Day is scheduled for Saturday, April 24 from 10AM to 2PM at Borough
Hall. He expressed his appreciation for the work that Ms. Twardowski is doing and also how well the
Public Safety Committee is doing under the leadership of Mr. Farr.
Mr. Farr expressed his hope that people will attend and bring their concerns to the Public Safety meeting
as they have much more time to delve into issues. Much more so than at the Council Meeting which has
so many issues to cover. The Chief also commented that he thinks that Mr. Yardoumian is doing a great
job with the fire inspections. This new initiative will make everyone safer.
FIRE CO: No report
TRAPPE AMBULANCE: No report
MAYOR: The Mayor joined with the Chief in expressing his appreciation for how well all the committees
and staff are working together to make Collegeville such a great place to live! He thanked the Rotary for
their generous gift of the bike Fixit Station and showed some photos of where it will be placed at the
trailhead near DaVinci’s.
MOTION to approve the Committee and Administrative reports by Ms. McKinney with a second by Mr.
Hoffmann
MOTION carries 6-0
PUBLIC COMMENT:
Brian Fox 104 W 3rd Ave: Mr. Fox expressed concern about the amount of baseballs that fly out and hit
cars and homes on Third Ave. He asked if there were any plans to extend the back stop. There was
discussion about how to address the issue.
MEETING ADJOURNED 8:44PM
Get email alerts for Collegeville