Wastewater Treatment Board
Regular MeetingCortland, NY · April 28, 2014
Minutes
CITY OF CORTLAND
WASTEWATER TREATMENT
FACILITY
Meeting Minutes
Members:
Da te : 4/ 28 /14
Ti me : 5 :30 p m
Chairman John Troy – Present
C on fe r en ce R o om ,
C or t la nd Wa st e wa t e r Vice Chair William Starr – Present
Commissioner Sally Horak – Present
Commissioner Todd Morris – Present
Commissioner Paul Lorenzo – Present
Village of McGraw Mayor Allan Stauber – Present
Village of Homer Trustee Michael Berry – Absent
Bruce Adams, Chief Operator – Present
Tom McCall, CPWOA President – Absent
Meeting called to order at 5:30 p.m.
Minutes from March 24, 2014, meeting for approval.
Motion to approve the minutes from March 24, 2014, meeting by Sally Horak. Seconded by Paul Lorenzo.
UNANIMOUS
Plant Manager’s Report:
Plant Managers Report
for
April 28, 2014
(as written by Chief Adams)
Administration–
Byrne’s expected start-up of test operations has slipped to the second or third week of May due to issues with
their pretreatment installation.
We are still negotiating with Byrne on a put-or-pay agreement for whey acceptance. We are very near a mutually
acceptable contract.
I met with the County and Barton & Loguidice to review their data on ash leachate. The data presented, though
preliminary, was reassuring in that it appears the ash leachate would pose no issues for the POTW.
The City and County had a separate meeting to discuss logistics and finances of monetizing the sludge and
leachate disposal. No decisions were made at the meeting.
Marietta has started discharging pretreated wastewater to the City’s sanitary sewer. They report the pretreatment
equipment is working very well. We will soon begin negotiating a labor-only contract to operate and maintain
their pretreatment system for them.
We are in what I hope are the final steps in closing the EFC bonding for the upgrade project. Significant delays in
getting DEC to sign off on the Environmental Review has put the whole process behind. We will need to renew
the Bond Anticipation Note to get us to what is now expected to be a July or August bond closing. This may cause
problems with the amount of work that is able to be completed this building season, but it can’t be helped.
Operations-
We’ve begun Spring clean-up activities around the plant grounds.
Cleaned Aeration basins 3 and 4 as well as the East final clarifier.
Installed hook-up for receiving whey in the GBT holding tank. This is a temporary measure until we complete
installation of MBR treatment equipment in whey holding tank.
The GBT continues to work very well. We have arrived at a routine of operating the GBT for about two hours
each weekday, followed by pumping primary sludge into the holding tank.
Maintenance-
Worked on restoring the old Perth gas recirculation mixers to operation. The North one is functioning, the South
one had a catastrophic failure. We will not invest the $10,000 minimum it would take to make it work but instead
try to use the belt press feed pump to effect some mixing until the new mixing system is installed.
Serviced all groundskeeping equipment in preparation for summer work.
Began installing wiring for automated valves to be used in moving sludge from the primary clarifiers and SBRs to
the GBT holding tank.
WWAB Minutes 28 April 2014 Page 2 of 6
Started installing replacement atmosphere monitoring equipment in screening building.
Bruce Adams
Chief Operator
John Troy added that he was able to sit in on the Barton & Loguidice meeting with Bruce Adams and was very
impressed with what they were able to do, not only with the data on the ash leachate; but they also did a
comparison of other facilities that had the MSW base with ash on top. John further reported that the numbers
looked very good with nothing to alarm anyone.
Bruce Adams reported to the board that the Wastewater Plant has joined the Energy Curtailment Systems.
This program is coordinated through the New York Independent System Operator to save on energy usage by
lessening the power load on the grid, which has a heavy usage during the summer. The Wastewater plant will
switch to generator use for a short amount of time during the summer season which begins in May. A
monetary incentive is offered through this program.
Motion to approve the Plant Manager’s Report by Bill Starr. Seconded by Paul Lorenzo. UNANIMOUS
Finance: Financial statements and abstracts dated 3/31/14 and 4/15/14, were submitted for approval.
Motion to approve financial statements and abstracts by Paul Lorenzo. Seconded by Sally Horak.
UNANIMOUS
Sewer Grievance:
A sewer grievance was received from Reese W. Weyant on 4/04/14, for property located at 10
Glyndon Avenue, City of Cortland. Mr. Weyant reported that on January 3, 2014, his boiler
broke causing water to leak onto his cellar floor. He further reported that in order to maintain
heat in his residence, he had to remove the water every two hours using his shop vac, dumping
the water onto his driveway. This process continued daily until he replaced his boiler with a
new one on January 10, 2014. Mr. Weyant stated that the daily volume of water dumped was
approximately 5 gallons. He is seeking credit towards the sewer portion of his bill.
The grievance was reviewed by the board and a motion to deny was made by Bill Starr, as
there appeared to have been no change in his current sewer bill in comparison to past quarterly
billings. The denial was supported by the board with a recommendation that Mr. Weyant may
submit another sewer grievance if his future sewer billings show an increase.
Motion to deny Mr. Weyant's grievance by Bill Starr. Seconded by Todd Morris. UNANIMOUS
Sewer Grievance:
Gerald Riker submitted a sewer grievance application on 4/08/14, for property located at 1
Holley Terrace, City of Cortland. Mr. Riker stated that a leak from a disconnect pipe was found
WWAB Minutes 28 April 2014 Page 3 of 6
in the basement of the property, somehow connected to the property next door on Pleasant
Avenue at one time. Due to the cold temperatures, this pipe may have been compromised. He
further reported that the valve was shut off and he capped off the pipe that goes outside
underground. The leak was detected on 3/27/14, and repaired on 3/28/14. Mr. Riker is
requesting an adjustment on the sewer portion of his bill.
After reviewing the grievance application and information submitted by Mr. Riker, Bill Starr
made a recommendation that the grievance be tabled until the next board meeting on May 19,
2014, to obtain additional information. The board is requesting clarification on which quarter
Mr. Riker is aggrieving, which was not noted on the application. The current billing from the
past three quarters showed a gradual increase, especially from the 4th quarter (2013) to the
present quarter. Paul Lorenzo made a recommendation to obtain a history of previous quarterly
sewer billing totals to better assess the normal average billing per quarter. Margie Becker will
obtain this information from Stephanie Mattice at the Water Department.
Motion to table Mr. Riker's grievance by Bill Starr. Seconded by Todd Morris. UNANIMOUS
Sewer Grievance:
A sewer grievance application was submitted by Dolores Heller on 4/09/14, for property located
at 26 Charles Street, City of Cortland. Mrs. Heller reported that she cannot afford to pay her bill
for the first quarter and stated that three men from the Water Department came out to the
residence and checked the water meter on 3/28/14, and the problem is unresolved.
A report was received from the Water Department regarding this property detailing a
chronology of interactions with Ms. Heller, who was notified on 12/16/13, with a blue card from
the Water Department advising her of an increase in water usage. After processing meter
readings taken on 3/11/14, it was noted that the units of water used were high at 197. Mrs.
Heller was notified via telephone by Margaret Noble (Water Dept), on 3/12/14, of the high use
at her property, in which she was displeased and had advised Margaret that this had happened
before.
Mrs. Heller has had a plumber come out to her property several times at the recommendation
of the Water Department to inspect the property and see if they could locate the source of
possible leaks, which they were unable to find anything. The Water Department offered to
come out to the property and inspect the meter due to Mrs. Heller's concern that it was faulty.
The meter was checked and found to be working properly. Mrs. Heller also sought assistance
via email with her Alderman, Carlos Ferrer, on finding a solution to this problem. Alderman
Ferrer has been in contact with the Water Department personnel working to assist Mrs. Heller.
On 4/02/14, a reading was taken at the property which showed that 14 units were used in 25
days. The read indicated that the water used since the last reading on 3/11/14, was back to
"normal" when compared to the 2nd quarter reading of 2013.
On 4/28/14, Mrs. Heller came into the office and dropped off additional information regarding
her grievance. Mrs. Heller is seeking relief on the sewer portion of her bill.
The board reviewed the grievance and additional information submitted both from Mrs. Heller
and from the Water Department. A recommendation was made by Paul Lorenzo to deny the
grievance due to water already having been processed through the system and no problems
found. It was also noted that the current meter readings submitted were normal. The board
WWAB Minutes 28 April 2014 Page 4 of 6
supported the recommendation for a denial with an understanding to Mrs. Heller that she may
submit another grievance if a problem is found.
Motion to deny Mrs. Heller's grievance by Paul Lorenzo. Seconded by Todd Morris. UNANIMOUS
Sewer Grievance:
Sharon Guingo submitted a sewer grievance application on 4/03/14, for her property located at
38 Pearl Street, City of Cortland. Ms. Guingo reports that while staying with family due to poor
health and other personal reasons, a broken pipe was discovered on her property on 3/14/14.
The water was then shut off at the curb. Ms. Guingo further stated that she was unaware of
the broken pipe and due to financial difficulties, was unable to have this repaired. She has since
found a repairman that will assist her. She is seeking relief towards the sewer portion of her
bill.
The board made a decision to table the grievance until the next board meeting on 5/19/14, in
order to obtain additional information and clarification from Ms. Guingo. Bill Starr made a
request for more specific details on the broken pipe. Paul Lorenzo asked for clarification on
where she was staying during this time, if local or out of state. Paul further requested that a
statement be obtained from Ms. Guingo's repairman on all of the details regarding the broken
pipe and repairs. Todd Morris also added a request if Ms. Guingo had made any provision for
someone to check the property in her absence. This additional information request will be sent
to Ms. Guingo by Margie Becker for clarification and a possible decision at the next board
meeting.
Sally Horak made a request for Margie Becker to check with the Water Department regarding
any mechanisms in place that will allow property owner's to make payments on their bills.
Margie Becker will contact the Water Department and discuss their payment policies and report
to the board at the next board meeting. Margie Becker had informed the board that the Water
Department now has a Water Board which was recently initiated. Paul Lorenzo asked if Ms.
Guingo had filed a grievance with the Water Board, which Margie Becker will check on this and
report back to the board.
Motion to table Ms. Guingo's grievance by Bill Starr. Seconded by Paul Lorenzo. UNANIMOUS
Sewer Grievance:
Ann Rongo submitted a sewer grievance application on 4/05/14, for property located at 192
Central Avenue. Mrs. Rongo reports that a leak to the main water line on the property was
detected on 3/03/14, and was repaired on 3/04/14, by Romer & Sons Plumbing. Mrs. Rongo is
requesting an adjustment to the sewer portion of her bill.
After review of the grievance by the board, a recommendation was made by Paul Lorenzo to
issue a credit of $26.00.
Motion to approve a credit of $26.00 to Mrs. Rongo by Paul Lorenzo. Seconded by Bill Starr.
UNANIMOUS
WWAB Minutes 28 April 2014 Page 5 of 6
Sewer Grievance:
A sewer grievance application was received from Kathleen Paino on 4/12/14, for her property
located at 37 North Church Street, City of Cortland. Ms. Paino had submitted a prior grievance
in January 2014, for the 4th quarter, in which a running toilet was discovered and water was
been turned off to the toilet at that time. The board had denied her grievance as the water
had already processed through the system. Ms. Paino is seeking relief towards the sewer
portion of her bill on the 1st quarter of 2014.
Mrs. Paino's grievance was reviewed by the board and a motion to deny was made by Paul
Lorenzo and supported by the board, based on water having already been processed through
the system.
Motion to deny Mrs. Paino's grievance by Paul Lorenzo. Seconded by Sally Horak. UNANIMOUS
New Business: No new business.
Old Business: No old business.
Motion to Adjourn at 6:20 p.m by Todd Morris. Seconded by Paul Lorenzo. UNANIMOUS
Respectfully submitted by:
City of Cortland WWTF
WWAB Minutes 28 April 2014 Page 6 of 6
Agenda
CITY OF CORTLAND
WASTEWATER TREATMENT
FACILITY
AGENDA
Call to Order
Approval of Previous Meeting Minutes –
Da te : 4/ 28 /14
March 24, 2014
Ti me : 5 :30 p m
Plant Manager’s Report
C on fe r en ce R o om ,
C or t la nd Wa st e wa t e r Finance
Approve Bills
Abstracts dated – 3/31/14 &
4/15/14
Financial Statements
Grievance Applications
Reese W. Weyant
Gerald Riker
Dolores Heller
Sharyn Guingo
Ann Rongo
Kathleen Paino
New Business
Old Business
Next Advisory Board Meeting – 5/19/14