Wastewater Treatment Board
Regular MeetingCortland, NY · June 22, 2015
Minutes
CITY OF CORTLAND
WASTEWATER TREATMENT
FACILITY
Meeting Minutes
Members:
Da te : 6/ 22 /15
Ti me : 5 :30 p m
Chairman John Troy – Present
C on fe r en ce R o om ,
C or t la nd Wa st e wa t e r Vice Chair William Starr – Present
Commissioner Sally Horak – Present
Commissioner Todd Morris – Present
Village of McGraw Mayor Allan Stauber – Present
Bruce Adams, Supt. of Wastewater – Present
Tom McCall, CPWOA President - Absent
Meeting called to order at 5:29 p.m.
Minutes from May 18, 2015, meeting for approval. Bruce Adams made mention of a correction to the
members listing on the first page of his title from Chief Operator to Superintendent of Wastewater.
Motion to approve the minutes and correction from May 18, 2015, meeting by Bill Starr. Seconded by Sally
Horak. UNANIMOUS
Plant Manager’s Report:
Plant Managers Report
for
June 22, 2015
(as written by Chief Adams)
Administration–
Mack Cook and I met with Larsen Engineering and Casella Organics to discuss reapplying for state funding
for a vermicomposting project. We are hoping to include sludge from Virgil and Dryden and at some point
possibly Auburn.
The electrical contractor on the current phase of the upgrade project has been denied for M/WBE status.
They are appealing the decision. If they are unsuccessful in their appeal, it will make it exceedingly difficult
to make the required 20% M/WBE percentage. The contractor is doing their best to make good faith efforts
to source equipment and supply purchases from M/WBE certified businesses. Our equipment supplier was
also counting on using the electrical contractor to satisfy their M/WBE requirements. To date they have not
submitted a contingency plan should the appeal be unsuccessful.
A visit by a DOL inspector revealed our boilers do not have a current inspection. We arranged with the City's
boiler insurance carrier to have them inspected as quickly as possible.
Operations–
Excessive rains have resulted in higher than seasonal flows. This has required putting additional tanks online
than is normal for this time of year. It also creates higher chemical usage for disinfection.
We have had some minor difficulties with both the new chlorine residual and the old dechlor residual
analyzers. These issues have been successfully addressed and no permit violations were incurred.
Maintenance–
Seasonal grounds work including facility-wide weed control.
Project work is on schedule. SBR decanter installation is complete save for grouting in the North basin
mounting plates.
We discovered that parts are no longer available for the aeration system grid. We are cannibalizing the
aeration system out of the East chlorine contact tank in order to do the repairs currently needed. I have
requested a quote for replacing the aeration grids two basins at a time. We will need to budget for this
work over the next several years in order to have a system for which we can obtain replacement parts.
WWAB Minutes 22 June 2015 Page 2 of 4
Performed repairs as necessary on West Final Clarifier.
Bruce Adams
Superintendent of Wastewater
Bruce Adams extended an invitation to the board for a walk through tour of the plant to view the upgrades
that have been made.
Motion to approve the Plant Manager’s Report by Todd Morris. Seconded by Bill Starr. UNANIMOUS
Finance: Financial statements and abstracts dated 5/31/15, and 6/15/15, were submitted for approval.
Motion to approve financial statements and abstracts by Sally Horak. Seconded by Todd Morris.
UNANIMOUS
Sewer Grievance:
A sewer grievance application was submitted by Lois Sellers on 6/15/15, for property located at
5 Yong Street, City of Cortland. Ms. Sellers reported that there was a toilet leak at the property
which was repaired by Halco on 2/6/15. Ms. Sellers further reported that the problem was
exacerbated by pipes freezing underground due to the extreme cold temperatures throughout
the winter. She was advised by her plumber, as well as two other services that came out to the
property to thaw out the pipes, to leave water running constantly to avoid freezing pipes.
Ms. Sellers is requesting relief towards the sewer portion of her billing.
The board reviewed Ms. Seller's application. John Troy stated that the maximum allowable
credit that could possibly be granted was $75.00, based on Ms. Seller's quarterly billing
averages. Sally Horak made the motion to grant the credit.
Motion to approve a credit of $75.00, by Sally Horak. Seconded by Todd Morris. UNANIMOUS
New Business: No new business
Old Business: No old business
John Troy recommended that a walk through tour of the plant be scheduled for the next WWAB meeting on
Monday, July 27, 2015, at 6:00 p.m. John also requested that an invitation be extended to the Common
Council members. A letter of invitation will be sent to the Common Council members by Margie Becker.
WWAB Minutes 22 June 2015 Page 3 of 4
Motion to Adjourn at 5:44 p.m. by Bill Starr. Seconded by Sally Horak. UNANIMOUS
Respectfully submitted by:
City of Cortland WWTF
WWAB Minutes 22 June 2015 Page 4 of 4
Agenda
CITY OF CORTLAND
WASTEWATER TREATMENT
FACILITY
AGENDA
Call to Order
Approval of Previous Meeting Minutes –
Da te : 6/ 22 /15
May 18, 2015
Ti me : 5 :30 p m
Plant Manager’s Report
C on fe r en ce R o om ,
C or t la nd Wa st e wa t e r Finance
Approve Bills
Abstracts dated – 5/31/15 &
6/15/15
Financial Statements
Grievance Applications:
Lois Sellers
Grievance Outcome Letters
New Business
Old Business
Next Advisory Board Meeting – 7/27/15
Adjournment
Get email alerts for Cortland
A daily email when new agendas and minutes are posted.