Light & Power and Environmental Services Committee
Regular MeetingCulpeper, VA · August 27, 2025
Agenda
Light & Power and Environmental Services
Committee Agenda
Wednesday, August 27, 2025 at 9:30 AM
Economic Development Center, Council Meeting Room
803 South Main Street, Culpeper
Page
1. 1. CALL TO ORDER
By Chairwoman Schmidt
2. PREVIOUS MEETING MINUTES
2.1 For Reference Only - Minutes from July 2025 4-6
Light & Power and Environmental Services Committee - Jul 23 2025 -
Minutes - Html
3. APPROVAL OF AGENDA
Motion to approve or amend the agenda.
4. PUBLIC COMMENTS
Members of the public may address the committee on any item at this time.
Your committee wishes to conduct its business as expeditiously as possible;
therefore, those who wish to speak are requested to sign the Public Forum
Sign-In sheet at the door.
When called, come forward, state your name and address, and speak only
on the subject directly concerning town government.
Each speaker is allowed to speak for an amount of time designated by the
presiding officer.
For groups present, you are requested to have a spokesperson.
Questions should be directed to the presiding officer.
5. ITEMS REFERRED BY COUNCIL OR INDIVIDUAL MEMBERS
Page 1 of 29
6. SPECIAL ITEMS & PRESENTATIONS
7. LIGHT & POWER ITEMS
7.1 Departmental Activities 7
JULY 2025 LP Activities CDH.pdf
7.2 Financial Summary 8 - 11
Copy of LP Financial Summary JULY 2025.pdf JULY 26 TT.pdf
YEARLY REVENUE COMPARISON FY2026.pdf YEARLY VMEA BILLING
FY24 FY2025 FY2026 W-KWH COST.pdf
8. ENVIRONMENTAL SERVICES ITEMS
8.1 Departmental Activities 12 - 15
Environmental Services Monthly Report for July 2025.pdf
8.2 Financial Summary 16 - 17
Environmental Services Monthly Financial Report for July 2025.pdf
8.3 Tap Sales Report 18 - 27
Tap Sales Report.pdf
8.4 R/R Re: FY26 Budget Amendment for Emergency Replacement 28 - 29
of a 1000 kW Generator at the Water Pollution Control Facility
Motion to approve budget transfers totaling $510,013.
8.5 Designation of Consent Agenda Item
9. TOWN & COUNTY INTERACTION COMMITTEE
9.1 Potential Items for Discussion at Next Interaction Committee
Meeting
10. ADJOURNMENT
Adjournment of Meeting
Committee Members:
Janie Schmidt (Chairwoman), Pranas A. Rimeikis, Jon D. Russell & William M. Yowell
Page 2 of 29
Note: Members of the Town Council who are not members of the committee may be in
attendance at the committee meeting. If so, and if a quorum of council is present, then the
meeting will be a special meeting of council in addition to being a committee meeting, pursuant
to the Virginia Freedom of Information Advisory Council Attorney Opinion, AO-03-14. Only
business matters to be considered are the committee’s recommendations to the council unless
specifically noted in this public notice.
Page 3 of 29
07-23-2025 Light & Power and Environmental Services Committee & Special Council
Meeting
9:30 a.m. Economic Development Center, 803 S. Main Street
The purpose of this meeting was to consider Light & Power and Environmental Services
Committee matters; however, members of the Town Council who were not members of the
committee were in attendance and participated in the discussion, resulting in a special meeting
of council.
Committee Members Present: Chairwoman Janie Schmidt, William M. Yowell, Pranas A.
Rimeikis
Committee Members Absent: Jon D. Russell
Also Present: Frank Reaves Jr., Council Member; Christopher D. Hively, Town Manager;
Courtney O. Strawser, Records Management Specialist; Jim Hoy, Public Services Director;
Chris Heggan, Assistant Director of Light & Power; Mike Stover, Director of Light & Power
CALL TO ORDER
Chairwoman Schmidt called the meeting to order at 9:30 a.m.
PREVIOUS MEETING MINUTES
For Reference Only – Minutes from June 2025
There were no changes to the minutes.
APPROVAL OF AGENDA
Mr. Yowell moved, Mr. Rimeikis seconded, approval of the agenda as presented. The motion
carried by voice vote.
PUBLIC COMMENTS – None
ITEMS REFERRED BY COUNCIL OR INDIVIDUAL MEMBERS – None
SPECIAL ITEMS & PRESENTATIONS – None
LIGHT & POWER ITEMS
Departmental Activities – The committee received the report.
Financial Summary – The committee received the report.
Discussion Item: Electric Avenue Sound Study
Mr. Hoy presented the item and shared the results of the June 30, 2025 Light & Power facility
sound study from Polysonics and discuss options for Committee consideration.
Mr. Hoy advised that on June 6, 2025, Polysonics conducted on-site sound measurements at
the Electric Avenue facility. The purpose of the measurements was to assess sound levels from
recently updated machinery and to estimate the sound pressure levels that could affect nearby
residential structures.
He noted this was the first phase of the study, which involved field data collection only. A
second phase, if necessary, would involve analyzing potential mitigation options based on the
phase one results.
A brief discussion ensued.
Page 4 of 29
Light & Power and ES Committee
July 23, 2025 – Page 2 of 3
It was the consensus of the committee to direct staff to proceed with Polysonics in addressing
potential sound mitigation.
ENVIRONMENTAL SERVICES ITEMS
Departmental Activities
Mr. Hoy presented the report and noted that on June 9, the 1,000 kW generator serving the
Biological Nutrient Removal (BNR) process at the Water Pollution Control Facility failed. The
failure was attributed to a disintegrated bearing on the rotor, which had damaged the magnet
responsible for generating electricity. As a result, the generator would need to be replaced.
Caterpillar, the generator rental provider, had recommended replacing the unit due to its age,
the high rental costs, and uncertainty regarding the availability of replacement parts.
Mr. Hoy further reported that staff had began soliciting quotes for a new unit. The lowest quote,
received through Virginia Tech’s Fidelity, totaled $359,000, with an additional $89,000 for
installation.
Mr. Hoy advised due to the emergency nature of the situation, staff had initiated an emergency
purchase and aimed to have the new generator in place by next month.
He stated that a report and recommendation would be presented at the August committee
meeting for consideration.
Mr. Hively provided an update on the National Pollutant Discharge Elimination System (NPDES)
permit renewal, stating that the Department of Environmental Quality (DEQ) had requested the
Town evaluate the Lake Culpeper dam during the August/September timeframe to measure the
amount of seepage occurring beneath the dam. This data would be used to improve the
accuracy of DEQ’s modeling.
Financial Summary – The committee received the report.
Tap Sales Report – The committee received the report.
R/R Re: Approval of Water Services Agreement
Mr. Hively presented the report and recommendation stating staff had been working with
STACK to develop a Reclaimed Water System to provide cooling for the future data center,
thereby reducing the power usage requirements for the facility. Additionally, the reuse of
wastewater effluent is anticipated
to reduce the nutrient and other pollutant loading in the Water Pollution Control Facility effluent
discharged to Mountain Run.
In February 2025, Council approved an Agreement with STACK to design and construct the
Reclaimed Water System with all costs being paid by STACK. This Agreement referenced the
Water Services Agreement (WSA) to be developed at a later date after a more defined scope
and details of the Reclaimed Water System could be determined.
Since execution of the Agreement, design plans for the Reclaimed Water System have been
developed to the 35% design level, with design ongoing and final design anticipated in 2025. All
costs associated with this design are being paid by STACK.
The WSA has been developed by STACK and the Town to further define the project and to
address reimbursement of all costs by STACK to the Town for the remaining design and
construction costs prior to the system becoming operational. Prior to the system becoming
Page 5 of 29
Light & Power and ES Committee
July 23, 2025 – Page 3 of 3
operation, the Town will develop rates and fees to recover ongoing operations and maintenance
costs associated with the provision of reclaimed water.
The WSA has been reviewed and approved by the Town Attorney as to form.
There is no financial impact associated with executing this agreement. All future design and
construction costs of the reclaimed water system will be paid for by the developer.
It was recommended that Council authorize the Town Manager to execute the Water Services
Agreement with minor changes as may be required and approved by the Town Attorney as to
form.
Mr. Yowell moved, Mr. Rimeikis seconded, approval of the report and recommendation for
submission to council. The motion carried by voice vote.
Designation of Consent Agenda Item – R/R Re: Approval of Water Services Agreement
ADJOURNMENT – The meeting adjourned at 10:13 a.m.
Page 6 of 29
Substations/Generation/Metering
Peak Shaving Summary:
• 5- Generation runs for the month of July.
• Monthly generation credit: $113,014.87.
Activities:
• Normal maintenance completed on all units: checked all fluid levels, checked for any alarm
codes, and cleaned up any dust and oil seepage.
• Continue cross training of L&P personnel on the generator’s operations.
• Performed visual inspection on Fire Extinguisher’s & Eye Stations.
• Continued mapping of electrical system with GIS department.
• Performed monthly DEQ inspection.
Substation:
• Monthly station inspection was completed.
• Cleaned transformer containment pits and Storm Water retention pond.
• Maintained standby batteries in control house.
• Vegetation management.
Distribution
Distribution Activities:
• Completed service disconnects for non-payment.
• Tree trimming was completed in various locations around town.
• Overhead and underground line maintenance, upgrade lines, replacing old infrastructure at
Various locations around Town.
• Continue to maintain equipment and fleet.
• Cleaned and organized material yard and buildings.
• Conducted monthly Construction and Safety meetings within our department.
• Disconnected and reconnected house service for upgrades-various locations.
• Continuing electrical infrastructure at Laurel Park.
• Continuing electrical infrastructure at The Greens.
• Changed a leaking 3 phase transformer at Bingham & Taylor.
• Continuing traffic control upgrades.
• Installed a 5-mva step down transformer at Laurel Park.
• Installed pole & underground for three business’s at 511 N. Main St.
Trouble Calls – Summary:
• 6 - Street lights reported out or malfunctioning, repaired.
• 1 - Street lights reported to Dominion Energy and Rappahannock Electric.
• 1- No Power – (N. West St. & Edmondson St.) – tree on wire-removed tree & quick sleeved
copper.
• 1 – No Power – (1213 Oaklawn) – bad transformer-removed & replaced with a new transformer.
• 1 – No Power – (308 N. Main St.) – broken K-mate-removed K-mate & direct wired to stirrup.
New Services:
• 35 – Residential – 1812 Mulligan Way, 2008, 2009, 2000 Divot Drive, 2701, 2757, 2761, 2769,
2749, 2745, 2741, 2737, 2733,2729, 2765 Apricot Drive, Apts. 102, 103, 104 South Main St.,
117-120, 217-220, 317-320 Lightfoot Apartments, 3230, 3227, 3234 Plum Lane, 3301,3309,
Pecan Lane.
• 2 – Commercial – 605 E. Spencer St., 1400 Lightfoot St. – community building.
Page 7 of 29
FINANCIAL SUMMARY
JULY 2025
LIGHT & POWER FUND
FY26 FY26 FY25
REVENUES MTD YTD YTD
Sale of Power $ 1,704,715 $ 1,704,715 $ 1,596,972
Utility Fees $ 18,609 $ 18,609 $ 15,774
Service Connection Charges $ 27,500 $ 27,500 $ 60,500
Interest Income $ 22,937 $ 22,937 $ 23,525
Sale of Salvage/Surplus $ 529 $ 529 $ 215
Time & Material Charges $ - $ - $ -
Pole Permits & Rental Charges $ 75 $ 75 $ -
Insurance Claims / Recovery $ - $ - $ -
Street Light Recovery $ - $ - $ -
TOTAL REVENUE $ 1,774,365 $ 1,774,365 $ 1,696,986
EXPENDITURES FY26 FY26 FY25
MTD YTD YTD
Purchased Power $ 1,045,245 $ 1,045,245 $ 828,753
Salaries & Benefits $ 278,109 $ 278,109 $ 263,036
Services $ 169,135 $ 169,135 $ 163,208
System Improvements $ 22,990 $ 22,990 $ 177,085
Materials & Supplies $ 9,453 $ 9,453 $ 11,353
Other $ 42,482 $ 42,482 $ 49,814
PILOT $ - $ - $ -
Debt Service $ 40,248 $ 40,248 $ 40,996
TOTAL O&M EXPENDITURES $ 1,607,662 $ 1,607,662 $ 1,534,245
NET SURPLUS (DEFICIT) NOT INCLUDING CAPITAL EXPENSE $ 166,703 $ 166,703 $ 162,741
TOTAL CAPITAL EXPENSE $ 14,197 $ 14,197 $ 10,699
NET SURPLUS (DEFICIT) $ 152,506 $ 152,506 $ 152,042
For informational purposes only - amount of open encumbrances at end of current month $ 209,872
FY26 Begin Bal Net Activites Ending Balance JULY 2025 Activity
L&P CASH & INVESTMENTS $ 9,869,721 $ (165,240) $9,704,481 $ (165,240)
L&P Accounts Receivable $ 1,175,866 $ 53,837 $ 1,229,703 $ 53,837
Outstanding Debt Service Balance $ 1,707,000 $ - $1,707,000 $ -
CONNECTED SERVICES 6063 PURCHASED KWH $0.0875
NEW SERVICES ADDED 37 SOLD KWH $0.1385
Page 8 of 29
TOWN OF CULPEPER - MONTHLY REVENUE REPORT - July 2025
ELECTRIC # CONNECTIONS
#CONNECTIONSSERVICES KWH KW-DEM RKVA CONSUMP TOTAL GROSS REV
TYPE BILLED ADDED KWH'S SALES REVENUE REVENUE TAX REVENUES TOTAL PER kWh
Residential (50000) 5260 5234 6,552,664 1,008,379.73 0.00 1,008,379.73 1,008,379.73 0.1539
Small General Serv (51000) 677 663 1,272,872 204,683.62 0.00 204,683.62 204,683.62 0.1608
Med Gen Svc(52000) 88 87 1,373,146 148,910.53 29,583.75 0.00 178,494.28 178,494.28 0.1300
Large Gen Svc(53000) 9 9 1,477,111 74,267.61 55,280.11 111.96 0.00 129,659.68 129,659.68 0.0878
Industrial Power (53100) 1 1 969,600 48,766.88 67,181.86 57.60 116,006.34 116,006.34 0.1196
Time of Use - ON PK (54000) 7 7 249,307 19,573.16 20,846.76 0.00 40,419.92 40,419.92 0.1621
Time of USE - OFF PK (54200) 7 7 379,669 9,676.79 9,676.79 9,676.79 0.0255
Traffic Controls (56200) 14 14 9,952 619.25 619.25 619.25 0.0622
AMR / Consumption Tax (57000) 15,269.83 15,269.83
TOTALS 6063 6022 0 12,284,321 1,514,877.57 172,892.48 169.56 15,269.83 1,687,939.61 1,703,209.44 0.1374
ADJUSTMENTS AND CONSUMPTION TAX CALCULATIONS:
Prior month adjmts: RES
DOM
Adjusted consumption tax
Consumption tax billing recap
0.00 ROUNDING DIFFERENCE
STREET AND YARD LIGHTS # CONNECTIONS TAXABLE TAXABLE
TYPE #CONNECTIONS BILLED MULT TOTAL KWH KWH UNITS RATE REVENUES
LED (56000) 1188 1,187 30 35,610 8,280 276 15.15 17,967.90
TOTAL ST/YD LTS 1188 1,187 35,610 8,280 276 $17,967.90 17,967.90 0.5046
12.96
TOTAL ELECTRIC 12,319,931 15,282.79 1,705,907.51 1,721,177.34 $0.1385
ELECTRIC ADJUSTMENTS: SOLAR (500002) 70 70 26,880 ($2,331.41)
1,703,576.10
Page 9 of 29
YEARLY ELECTRIC SALES REVENUE COMPARISON
FISCAL YEAR 2026 FISCAL YEAR 2025
MONTH REVENUE MONTH REVENUE
DIFFERENCE
JULY $ 1,705,907.51 $ 106,780.84 JULY $ 1,599,126.67
AUGUST $ - AUGUST $ 1,660,871.11
SEPTEMBER $ - $ - SEPTEMBER $ 1,468,112.61
OCTOBER $ - $ - OCTOBER $ 1,098,475.92
NOVEMBER $ - $ - NOVEMBER $ 1,026,775.23
DECEMBER $ - $ - DECEMBER $ 1,087,767.03
JANUARY $ - $ - JANUARY $ 1,262,084.37
FEBRUARY $ - $ - FEBRUARY $ 1,369,201.35
MARCH $ - $ - MARCH $ 1,117,765.15
APRIL $ - $ - APRIL $ 1,060,037.52
MAY $ - $ - MAY $ 1,132,035.87
JUNE $ - JUNE $ 1,274,051.75
YTD TOTAL $ 1,705,907.51 $ 106,780.84 YTD TOTAL $ 15,156,304.58
BUDGET $ 17,809,629.00 BUDGET $ 16,594,817.00
BALANCE $ 16,103,721.49 BALANCE $ 1,438,512.42
Page 10 of 29
YEARLY VMEA BILLING FY24 FY2025 FY2026 W-KWH COST
FISCAL YEAR 2026 EXCESS EXCESS VMEA
MONTH BILLING KWH KW DEMAND CHARGE GEN. CREDIT COST/KWH
JULY $ 1,212,913.74 11,791,495 28,551 $ 113,014.87 $0.10286
AUGUST $ - 0 0 $ -
SEPTEMBER $ - 0 0 $ -
OCTOBER $ - 0 0 $ -
NOVEMBER $ - 0 0 $ -
DECEMBER $ - 0 0 $ -
JANUARY $ - 0 0 $ -
FEBRUARY $ - 0 0 $ -
MARCH $ - 0 0 $ -
APRIL $ - 0 0 $ -
MAY $ - 0 0 $ -
JUNE $ - 0 0 $ -
TOTALS $ 1,212,913.74 11,791,495 28,551.00 0.00 $ - $ 113,014.87 0.10286
BUDGET $ 10,726,137.00
FISCAL YEAR 2025 EXCESS EXCESS VMEA
MONTH BILLING KWH KW DEMAND CHARGE GEN. CREDIT COST/KWH
JULY $ 972,069.94 13,252,460 29,292 $ 15,686.73 $0.07335
AUGUST $ 931,851.19 12,225,459 28,547 $ 10,964.45 $0.07622
SEPTEMBER $ 656,514.95 9,025,747 16,946 $ 6,294.25 $0.07274
OCTOBER $ 652,832.70 8,351,341 17,520 $ 8,176.44 $0.07817
NOVEMBER $ 566,771.72 8,203,123 13,483 $ 7,556.98 $0.06909
DECEMBER $ 667,715.08 9,834,511 16,357 $ 11,271.56 $0.06790
JANUARY $ 747,650.71 11,003,924 20,682 $ 16,529.01 $0.06794
FEBRUARY $ 661,101.05 9,015,460 19,604 $ 8,830.81 $0.07333
MARCH $ 604,404.80 8,301,583 14,799 $ 6,238.23 $0.07281
APRIL $ 790,209.28 8,568,325 22,015 $ 22,627.19 $0.09222
MAY $ 819,645.56 9,314,235 21,645 $ 16,266.72 $0.08800
JUNE $ 1,017,465.35 12,084,400 29,261 $ 149,700.22 $0.08420
TOTALS $ 9,088,232.33 119,180,568 250,151.00 0.00 $ - $ 280,142.59 0.07626
BUDGET $ 9,549,455.00
FISCAL YEAR 2024 EXCESS EXCESS VMEA
MONTH BILLING KWH KW DEMAND CHARGE GEN. CREDIT COST/KWH
JULY $ 1,301,263.98 13,104,828 27,788 $ 13,081.62 $0.09930
AUGUST $ 1,182,250.76 12,097,663 23,567 $ 11,679.93 $0.09773
SEPTEMBER $ 1,029,894.79 9,755,704 28,898 $ 8,598.81 $0.10557
OCTOBER $ 775,466.42 8,010,745 19,853 $ 10,221.72 $0.09680
NOVEMBER $ 713,998.62 8,005,707 16,942 $ 13,542.85 $0.08919
DECEMBER $ 747,946.91 8,938,950 16,395 $ 10,029.17 $0.08367
JANUARY $ 826,043.29 9,729,920 19,463 $ 12,406.60 $0.08490
FEBRUARY $ 706,661.00 8,397,775 15,937 $ 7,809.34 $0.08415
MARCH $ 648,527.74 8,021,621 13,079 $ 7,253.11 $0.08085
APRIL $ 714,112.23 7,970,757 21,351 $ 9,811.19 $0.08959
MAY $ 805,430.62 9,543,258 23,967 $ 14,823.46 $0.08440
JUNE $ 822,476.53 11,801,551 23,022 $ 8,292.77 $0.06969
TOTALS $ 10,274,072.89 115,378,479 250,262.00 0.00 $ - $ 127,550.57 0.08905
BUDGET $ 10,731,000.00
Page 11 of 29
ENVIRONMENTAL SERVICES DEPARTMENT COMMITTEE REPORT
JULY 2025
Water Treatment Plant (WTP) Operations Summary:
Water Plant (4.0 MGD Capacity)
JULY YTD
Raw Water Treated (MG): 51 301
Average Daily Raw Water Flow (MGD): 1.6 1.4
Max Raw Water Flow (MGD): 2.8 2.8
Water Produced (MG): 50 301
Average Daily Finished Flow (MGD): 1.6 1.4
Max Daily Finished Flow (MGD): 2.4 2.4
Bulk Water Sales (MG): 0.81 3.9
Average pH (su): 7.4 7.5
Average Chlorine (mg/L): 2.1 2.1
Average Turbidity (NTU): 0.05 0.05
Max Average Turbidity (NTU): 0.07 0.06
Partnership Turbidity (95%) (NTU): 0.07 0.07
Chandler Street Wells
Well Water Produced (MG): 19 123
Average Daily Water Produced (MGD): 0.62 0.58
Max Daily Flow (MGD) 0.66 0.69
Rockwater Park Well
Well Water Produced (MG): 0.0 1.4
Average Daily Water Produced (MGD): 0.0 0.01
Max Daily Flow (MGD) 0.0 0.16
Nalles Mills Wells
Well Water Produced (MG): 14 77
Average Daily Water Produced (MGD): 0.44 0.36
Max Daily Flow (MGD) 0.55 0.55
Sports Complex Well
Well Water Produced (MG): 0.0 0.0
Average Daily Water Produced (MGD): 0.0 0.0
Max Daily Flow (MGD) 0.0 0.0
Total Well Water Produced (MG): 33 201
Total Water Plant Water Produced (MG): 50 301
TOTAL WATER PRODUCED (MG): 83 502
AVERAGE DAILY WATER PRODUCED (MGD): 2.7 2.4
Page 12 of 29
Distribution Positive Bacteria: 0 0
Safety Incidents: 0 0
Regulatory Violations: 0 0
Notes: Lake Culpeper 10.5 inches below the overflow as of
8/10/25.
Wastewater Pollution Control Facility (WPCF) Operations Summary:
Wastewater Plant (6.0 MGD Capacity)
JULY YTD
Average Daily Flow (MGD): 3.6 3.4
Max Daily Flow (MGD): 5.8 6.8
Total Flow (MG) 113 719
Rainfall (in): 7.2 26.5
Centrifuged output (MGD): 0.65 4.6
Centrifuged output (dry metric tons): 68 386
Septage received (gal): 153350 906720
Bio-solids land applied (wet tons): 240 1728
Average pH (su): 7.4 7.3
Minimum DO (mg/L): 7.8 7.8
Average TSS (mg/L) (QL=1): <QL <QL
Average BOD (mg/L) (Dec – May) (QL=2): --- <QL
Average CBOD (mg/L) (Jun – Nov) (QL=2): <QL <QL
Average Ammonia (mg/L) (QL=0.20): --- <QL
Average TKN (mg/L) (QL=0.50): <QL 0.64
Average Total Nitrogen (mg/L): 0.71 1.0
Average Total Phosphorus (mg/L): 0.025 0.034
Wastewater discharge violations 0 0
Overflows and Bypasses 0 0
Pre-Treatment Violations: 0 0
WTP Maintenance Summary:
Completed installation and start up on new carbon feeder
Completed cleaning and inspection of the pressure reducing valves
Installed new clear well level transmitter
Completed all backflow certifications
WPCF Maintenance Summary:
Installed new sodium bicarbonate system in the sludge basement
Installed new muffin monster flow meter
Serviced all pump stations
Completed monthly PMs
Page 13 of 29
Completed all backflow certifications
Water Distribution Summary:
Cleared/cut utility right of ways and easements
Tied in water service to the water fountain at Heritage Park
Relocated water service at Northridge Estates
Exercised water valves in the Downtown area
Completed UDF in the Downtown Area
Repaired fire hydrant at Old Brandy Road and Brandy Knoll Court
Replaced water meter box and backflow device at 406 Clay Street
Updated water meter components at Bingham & Taylor office addition
Replaced fire hydrant at Sycamore Park Elementary School
Repaired water main break on Old Brandy Road on July 14th
Repaired water main break on First Street on July 14th
Repaired water main break on Old Brandy Road on July 15th
Repaired water main break on First Street on July 28th
Repaired water main break on First Street on July 29th
Replaced/reprogrammed AMR MTU’s, billing reads, disconnects, etc.
Wastewater Collection Summary:
Cleared/cut utility right of ways and easements
Sewer jetted troubled areas
Adjusted utility manholes on Old Rixeyville Road, Water’s Place, South East Street, and East
Culpeper Street
Installed sanitary sewer tap at Blue Ridge & Chandler Intersection
Projects Summary:
Water Pollution Control Facility (WPCF) Digester and Headworks Project
WW Associates has completed construction plans and a project manual for the WPCF digester and headworks
project. Staff compiled this information into a bid package and worked with Town procurement to advertise an
invitation to bid for construction of this project on May 25, 2022. A pre-bid meeting was held on June 15, 2022,
with prospective bidders. Construction bids were opened at 2 pm, Thursday, July 14, 2022. Based on the bids
received, Council awarded MEB the project construction contract at their September 13, 2022, meeting. A pre-
construction meeting with MEB was held on November 10, 2022, with a notice to proceed issued on December 1,
2022. The new Alfa Laval centrifuge was delivered on February 10, 2023 and MEB has been on site multiple
times completing pre-construction surveys. In June 2023, MEB continued mobilization and completed demolition
of the RAS pump station and secondary clarifiers to accommodate retrofit of new aerobic digester equipment in
existing basins. From July 2023 through June 2024, MEB continued retrofit of the former secondary clarifiers for
conversion to new aerobic digesters, installed yard piping, converted primary clarifier valves and initiated scope
of work for installing new centrifuge. Two new headworks screens were installed and placed into service in
February 2024. Three new blowers were installed for supplying the new aerobic digesters in April 2024. The
new motor control center and programmable logic control cabinet for the new centrifuge were installed in the
biosolids building in May 2024. The new centrifuge was installed in May 2025. Acceptance testing for the new
centrifuge has been completed and the 30 day trial run of new unit has commenced. Installation of groundwater
dewatering system for the aerobic digesters has been completed and is operating.
Drought Response
Completed distribution system connection for TOC X2A in March 2025—awaiting installation of fluoridation
system and VDH sanitary inspection.
Completed bore and jack installation of raw water line for well TOC X4B in February 2025.
Page 14 of 29
Finalizing the installation of TOC X2A groundwater well treatment controls to prepare for startup following VDH
Office of Drinking Water sanitary inspection.
O = dissolved oxygen TSS = total suspended solids
BOD = biological oxygen demand; CBOD = chemical biological oxygen demand
TKN = total Kjeldahl nitrogen BNR = biological nutrient removal
MTU = meter transmitting unit RAS = return activated sludge
WAS = waste activated sludge PM = preventive maintenance
IPS = intermediate pump station UDF = unidirectional flushing
VFD = variable frequency drive
Page 15 of 29
FINANCIAL SUMMARY
Jul-25
WATER FUND
REVENUES FY26 FY26 FY25
MTD YTD YTD
Metered Sales $ 382,917 $ 382,917 $ 388,205
Utility Fees $ 22,161 $ 22,161 $ 11,941
Utility Charges $ 3,046 $ 3,046 $ 2,562
Revenues from Use of Money $ 20,065 $ 20,065 $ 22,382
Miscellaneous $ 3,541 $ 3,541 $ 5,179
TOTAL O&M REVENUE $ 431,729 $ 431,729 $ 430,270
Tap Fee & Misc Capital Revenue $ 128,500 $ 128,500 $ 84,500
CARES Act Funding / ARPA Funds $ - $ - $ -
TOTAL CAPITAL REVENUE $ 128,500 $ 128,500 $ 84,500
TOTAL REVENUE $ 560,229 $ 560,229 $ 514,770
EXPENDITURES Water Treatment Water Distribution Water Fund
Dept. 3700 Dept. 3800 TOTAL
FY26 FY26 FY26 FY26 FY26 FY26 FY25
MTD YTD MTD YTD MTD YTD YTD
Personnel $ 135,307 $ 135,307 $ 111,505 $ 111,505 $ 246,812 $ 246,812 $ 220,443
Services $ 100,236 $ 100,236 $ 3,729 $ 3,729 $ 103,966 $ 103,966 $ 101,524
Other Charges $ 63,019 $ 63,019 $ 4,430 $ 4,430 $ 67,449 $ 67,449 $ 68,762
Miscellaneous $ 2,543 $ 2,543 $ 24,309 $ 24,309 $ 26,852 $ 26,852 $ 24,628
Materials / Supplies $ 87,837 $ 87,837 $ 7,222 $ 7,222 $ 95,059 $ 95,059 $ 99,416
Capital Outlays $ - $ - $ 110,064 $ 110,064 $ 110,064 $ 110,064 $ 20,644
CARES Act / ARPA Expenses $ - $ - $ -
PILOT $ 12,600 $ 12,600 $ 12,011
Debt Service $ - $ - $ -
TOTAL O&M EXPENSES $ 388,943 $ 388,943 $ 261,259 $ 261,259 $ 662,802 $ 662,802 $ 547,427
NET SURPLUS (DEFICIT) EXCLUDING CAPITAL PROJECTS $ (102,573) $ (102,573) $ (32,658)
TOTAL CAPITAL PROJECTS EXPENSE $ 6,847 $ 6,847 $ 75,122
NET SURPLUS (DEFICIT) $ (109,420) $ (109,420) $ (107,780)
FY26 Begin Bal Net Activities Ending Balance July 2026 Activity
WATER CASH & CASH INVESTMENTS $ 8,633,768 $ (42,239) $ 8,591,529 $ (42,239)
Water Accounts Receivable $ 324,517 $ (38,407) $ 286,110 $ (38,407)
Outstanding Debt Service Balance $ 4,678,000 $ - $ 4,678,000 $ -
Encumbrance/Req - Operational $ 410,894 $ - $ 410,894 $ -
Encumbrance/Req - Capital $ - $ - $ - $ -
Page 16 of 29
FINANCIAL SUMMARY
Jul-25
WASTEWATER FUND
REVENUES FY26 FY26 FY25
MTD YTD YTD
Metered Sales $ 460,870 $ 460,870 $ 457,719
Utility Fees $ 27,726 $ 27,726 $ 22,568
Utility Charges $ 6,524 $ 6,524 $ 2,562
Revenues from Use of Money $ 23,927 $ 23,927 $ 21,917
Miscellaneous $ 3,589 $ 3,589 $ -
TOTAL O&M REVENUES $ 522,636 $ 522,636 $ 504,765
Tap Fee & Misc Capital Revenue $ 165,000 $ 165,000 $ 130,000
CARES Act Funding / ARPA Funds $ - $ - $ -
TOTAL CAPITAL REVENUE $ 165,000 $ 165,000 $ 130,000
TOTAL REVENUE $ 687,636 $ 687,636 $ 634,765
EXPENDITURES WW Treatment WW Collection Wastewater Fund
Dept. 4700 Dept. 4800 TOTAL
FY26 FY26 FY26 FY26 FY26 FY26 FY25
MTD YTD MTD YTD MTD YTD YTD
Personnel $ 228,176 $ 228,176 $ 61,493 $ 61,493 $ 289,669 $ 289,669 $ 274,609
Services $ 113,241 $ 113,241 $ 1,290 $ 1,290 $ 114,531 $ 114,531 $ 125,878
Other Charges $ 48,969 $ 48,969 $ 6,739 $ 6,739 $ 55,708 $ 55,708 $ 79,846
Miscellaneous $ 4,883 $ 4,883 $ - $ - $ 4,883 $ 4,883 $ 2,294
Materials / Supplies $ 76,263 $ 76,263 $ 5,963 $ 5,963 $ 82,227 $ 82,227 $ 31,044
Capital Outlays $ - $ - $ 627 $ 627 $ 627 $ 627 $ 106,160
CARES Act / ARPA Expenses $ - $ - $ -
PILOT $ 14,505 $ 14,505 $ 14,116
Debt Service $ - $ - $ -
TOTAL O&M EXPENSES $ 471,532 $ 471,532 $ 76,113 $ 76,113 562,150 $ 562,150 $ 633,948
NET SURPLUS (DEFICIT) - NOT INCLUDING CAPITAL PROJECTS $ 125,486 $ 125,486 $ 817
*Note: These amounts to be partially offset by ARPA proceeds on a quarterly basis.
TOTAL CAPITAL PROJECTS $ 216,529 $ 216,529 $ 292,801
NET SURPLUS (DEFICIT) $ (91,044) $ (91,044) $ (291,984)
FY26 Begin Bal Net Activities Ending Balance July 2026 Activity
WASTEWATER CASH & CASH INVESTMENTS $ 10,295,682 $ (38,604) $ 10,257,078 $ (38,604)
Wastewater Accounts Receivable $ 476,355 $ (43,325) $ 433,030 $ (43,325)
Outstanding Debt Service Balance $ 10,175,000 $ - $ 10,175,000 $ -
Encumbrance/Req - Operational $ 1,271,924 $ - $ 1,271,924 $ -
Encumbrance/Req - Capital $ (216,529) $ - $ (216,529) $ -
Page 17 of 29
Water and Wastewater Tap Information
Number Number of
FY25-26 Name of Develpment or of Water Amount Wastewater County
Month Applicant Location Meter Size Taps Due Taps Amount Due (Y/N)
W - 1.5 in
Jul Lifepoint Church 15064 Success Dr S - 1 in. 1 $ 37,500 1 $ 20,000 Y
614 Second St
Just Getting By LLC 616 Second St 5/8 2 $ 13,000 2 $ 20,000 N
SAB Investments LLC 151 Saunders St 5/8 0 $ - 1 $ 5,000 N
NVR/Ryan Homes Willow Shade Lane Lot 8 5/8 1 $ 6,500 1 $ 10,000 Y
Laurel Park Phase 1B2
Lots 162-163, 167, 170,
NVR/Ryan Homes 172 5/8 5 $ 32,500 5 $ 50,000 N
NVR/Ryan Homes Kite Acres Lot 29 5/8 1 $ 6,500 1 $ 10,000 Y
DRB Homes Lincoln Circle Pl Lots 11 5/8 1 $ 6,500 1 $ 10,000 Y
DRB Homes Northern View Rd Lot 21 5/8 1 $ 6,500 1 $ 10,000 Y
Williams Mill - Lots 35,
Shea Homes LP 39, 100 5/8 3 $ 19,500 3 $ 30,000 Y
Sub Total 15 $ 128,500 16 $ 165,000
Grand Total 15 $ 128,500 16 $ 165,000
NOTES
July 2025 - Lifepoint Church purchased additional water tap capacity for irrigation
July 2025 - Suanders St already has perviously established water service
1 8/6/2025
Page 18 of 29
FISCAL YEAR SUMMARIES
Fiscal Year Water Wastewater
25-26 Taps Amount Due Taps Amount Due
July Total 15 $ 128,500 15 $ 160,000
August Total
September Total
October Total
November Total
December Total
January Total
February Total
March Total
April Total
May Total
June Total
Fiscal Year 15 $ 128,500 15 $ 160,000
Fiscal Year Water Wastewater
24-25 Taps Amount Due Taps Amount Due
July Total 13 $ 84,500 13 $ 130,000
August Total 61 $ 396,500 61 $ 610,000
September Total 1 $ 3,250 2 $ 15,000
October Total 51 $ 362,500 51 $ 560,000
November Total 11 $ 71,500 12 $ 120,000
December Total 17 $ 179,000 18 $ 290,000
January Total 10 $ 65,000 11 $ 105,000
February Total 5 $ 29,250 4 $ 35,000
March Total 19 $ 123,500 19 $ 190,000
April Total 24 $ 156,000 24 $ 240,000
May Total 29 $ 188,500 29 $ 290,000
June Total 41 $ 266,500 41 $ 410,000
Fiscal Year 282 $ 1,926,000 285 $ 2,995,000
Fiscal Year Water Wastewater
23-24 Taps Amount Due Taps Amount Due
July Total 10 $ 65,000 10 $ 100,000
August Total 24 $ 156,000 24 $ 240,000
September Total 7 $ 42,250 6 $ 55,000
October Total 8 $ 60,500 8 $ 90,250
November Total 15 $ 97,500 15 $ 150,000
Page 19 of 29
December Total 43 $ 279,500 42 $ 420,000
January Total 7 $ 45,500 7 $ 70,000
February Total 17 $ 110,500 17 $ 170,000
March Total 3 $ 16,250 4 $ 30,000
April Total 17 $ 110,500 17 $ 170,000
May Total 6 $ 35,750 6 $ 55,000
June Total 10 $ 65,000 12 $ 110,000
Fiscal Year 167 $ 1,084,250 168 $ 1,660,250
Fiscal Year Water Wastewater
22-23 Taps Amount Due Taps Amount Due
July Total 1 $ 3,250 1 $ 5,000
August Total 1 $ 6,500 2 $ 22,500
September Total 0 $ 46,000 0 $ 40,500
October Total 5 $ 29,250 5 $ 45,000
November Total 2 $ 13,000 1 $ 10,000
December Total 15 $ 91,000 15 $ 140,000
January Total 2 $ 13,150 2 $ 17,500
February Total 6 $ 39,000 6 $ 60,000
March Total 35 $ 227,500 35 $ 350,000
April Total 0 $ - 0 $ -
May Total 5 $ 32,500 5 $ 50,000
June Total 2 $ 9,750 2 $ 15,000
Fiscal Year 74 $ 510,900 74 $ 755,500
Fiscal Year Water Wastewater
21-22 Taps Amount Due Taps Amount Due
July Total 7 $ 45,500 8 $ 80,000
August Total 3 $ 19,500 3 $ 30,000
September Total 3 $ 19,500 3 $ 30,000
October Total 6 $ 56,000 8 $ 95,500
November Total 7 $ 45,500 7 $ 70,000
December Total 8 $ 52,000 8 $ 80,000
January Total 24 $ 120,250 24 $ 185,000
February Total 8 $ 52,000 8 $ 80,000
March Total 12 $ 78,000 12 $ 120,000
April Total 13 $ 61,750 3 $ 30,000
May Total 2 $ 13,000 2 $ 20,000
June Total 12 $ 71,500 7 $ 60,000
Fiscal Year 105 $ 634,500 93 $ 880,500
Fiscal Year Water Wastewater
20-21 Taps Amount Due Taps Amount Due
July Total 8 $ 75,500 9 $ 115,500
August Total 17 $ 107,250 17 $ 165,000
September Total 4 $ 26,000 4 $ 40,000
October Total 2 $ 13,000 2 $ 20,000
November Total 7 $ 42,250 7 $ 65,000
December Total 6 $ 39,000 6 $ 60,000
January Total 2 $ 13,000 2 $ 20,000
Page 20 of 29
February Total 2 $ 13,000 2 $ 20,000
March Total 1 $ 6,500 1 $ 10,000
April Total 0 $ - 1 $ 5,000
May Total 14 $ 45,500 15 $ 75,000
June Total 1 $ 6,500 1 $ 10,000
Fiscal Year 64 $ 387,500 67 $ 605,500
Page 21 of 29
Fiscal Year Water Wastewater
19-20 Taps Amount Due Taps Amount Due
July Total 7 $ 45,500 7 $ 70,000
August Total 5 $ 41,000 5 $ 60,250
September Total 5 $ 56,000 5 $ 70,000
October Total 7 $ 69,000 7 $ 100,500
November Total 3 $ 19,500 3 $ 30,000
December Total 3 $ 19,500 3 $ 30,000
January Total 11 $ 87,000 9 $ 100,250
February Total 9 $ 58,500 9 $ 90,000
March Total 11 $ 71,500 11 $ 110,000
April Total 9 $ 58,500 9 $ 90,000
May Total 36 $ 130,150 35 $ 185,000
June Total 9 $ 58,500 9 $ 90,000
Fiscal Year 115 $ 714,650 112 $ 1,026,000
Fiscal Year Water Wastewater
18-19 Taps Amount Due Taps Amount Due
July Total 10 $ 73,500 10 $ 110,250
August Total 11 $ 71,500 11 $ 110,000
September Total 8 $ 52,000 8 $ 80,000
October Total 14 $ 114,500 13 $ 160,500
November Total 11 $ 71,500 12 $ 115,000
December Total 6 $ 39,000 6 $ 60,000
January Total 5 $ 32,500 6 $ 55,000
February Total 12 $ 78,000 12 $ 120,000
March Total 12 $ 78,000 12 $ 120,000
April Total 15 $ 97,500 15 $ 150,000
May Total 7 $ 45,500 7 $ 70,000
June Total 9 $ 61,900 10 $ 97,500
Fiscal Year 120 $ 815,400 122 $ 1,248,250
Fiscal Year Water Wastewater
17-18 Taps Amount Due Taps Amount Due
July Total 12 $ 78,000 12 $ 120,000
August Total 15 $ 97,500 15 $ 150,000
September Total 5 $ 32,500 5 $ 50,000
October Total 13 $ 84,500 13 $ 400,500
November Total 10 $ 103,500 10 $ 150,750
December Total 10 $ 65,000 9 $ 90,000
January Total 14 $ 91,000 14 $ 140,000
EVHS Press Boxes 14 $ 91,000 14 $ 140,000
March Total 22 $ 143,000 22 $ 220,000
April Total 8 $ 52,000 8 $ 80,000
May Total 21 $ 139,906 20 $ 200,000
June Total 8 $ 52,000 8 $ 80,000
Fiscal Year 152 $ 1,029,906 150 $ 1,821,250
Page 22 of 29
Fiscal Year Water Wastewater
16-17 Taps Amount Due Taps Amount Due
July Total 6 $ 44,250 5 $ 60,250
August Total 1 $ 6,500 1 $ 10,000
September Total 2 $ 13,000 2 $ 20,000
October Total 3 $ 19,500 3 $ 30,000
November Total 6 $ 39,000 6 $ 60,000
December Total 3 $ 19,500 4 $ 40,000
January Total 9 $ 58,500 10 $ 95,000
February Total 5 $ 37,750 3 $ 30,000
March Total 139 $ 474,500 139 $ 730,000
April Total 5 $ 32,500 5 $ 50,000
May Total 6 $ 39,000 5 $ 50,000
June Total 9 $ 75,500 9 $ 110,500
Fiscal Year Total 194 $ 859,500 192 $ 1,285,750
Fiscal Year Water Wastewater
15-16 Taps Amount Due Taps Amount Due
July Total 12 $ 78,000 12 $ 120,000
August Total 16 $ 104,000 16 $ 160,000
September Total 16 $ 104,000 16 $ 160,000
October Total 12 $ 78,000 12 $ 120,000
November Total 3 $ 19,500 3 $ 30,000
December Total 14 $ 91,000 14 $ 140,000
January Total 11 $ 71,500 11 $ 110,000
February Total 10 $ 65,000 10 $ 100,000
March Total 18 $ 113,750 17 $ 170,000
April Total 6 $ 39,000 5 $ 50,000
May Total 12 $ 78,000 12 $ 120,000
June Total 10 $ 75,218 11 $ 112,500
Fiscal Year Total 140 $ 916,968 139 $ 1,392,500
14-15 Taps Amount Due Taps Amount Due
July Total 7 $ 48,906 7 $ 72,500
August Total 10 $ 65,000 10 $ 95,000
September Total 13 $ 84,500 13 $ 130,000
October Total 8 $ 52,000 8 $ 80,000
November Total 3 $ 19,500 5 $ 40,000
December Total 9 $ 52,000 9 $ 80,000
January Total 9 $ 58,500 8 $ 80,000
February Total 4 $ 34,500 4 $ 50,250
March Total 8 $ 52,000 8 $ 80,000
April Total 12 $ 78,000 13 $ 125,000
May Total 13 $ 89,750 11 $ 110,000
June Total 10 $ 65,000 10 $ 100,000
Fiscal Year Total 106 $ 699,656 106 $ 1,042,750
Page 23 of 29
Fiscal Year Water Wastewater
13-14 Taps Amount Due Taps Amount Due
July Total 4 $ 26,000 5 $ 45,000
August Total 9 $ 58,500 9 $ 90,000
September Total 8 $ 52,000 8 $ 80,000
October Total 8 $ 60,500 9 $ 95,250
November Total 17 $ 119,156 16 $ 172,750
December Total 9 $ 58,500 9 $ 90,000
January Total 7 $ 45,500 7 $ 70,000
February Total 6 $ 39,000 7 $ 65,000
March Total 24 $ 156,000 23 $ 230,000
April Total 13 $ 84,500 13 $ 130,000
May Total 20 $ 130,000 20 $ 200,000
June Total 8 $ 52,000 8 $ 80,000
Fiscal Year 133 $ 881,656 134 $ 1,348,000
Fiscal Year Water Wastewater
12-13 Taps Amount Due Taps Amount Due
July Total 5 $ 32,500 5 $ 50,000
August Total 7 $ 45,500 7 $ 70,000
September Total 8 $ 45,500 6 $ 60,000
October Total 5 $ 32,500 6 $ 55,000
November Total 11 $ 71,500 11 $ 110,000
December Total 4 $ 26,000 4 $ 40,000
January Total 7 $ 45,500 7 $ 70,000
February Total 4 $ 34,500 3 $ 45,000
March Total 14 $ 91,000 14 $ 140,000
April Total 11 $ 71,500 11 $ 110,000
May Total 19 $ 123,500 21 $ 200,000
June Total 3 $ 19,500 4 $ 35,000
Fiscal Year Total 98 $ 639,000 99 $ 985,000
Fiscal Year Water Wastewater
11-12 Taps Amount Due Taps Amount Due
July Total 4 $ 32,500 3 $ 40,000
August Total 12 $ 78,000 12 $ 120,000
September Total 9 $ 58,500 9 $ 90,000
October Total 8 $ 52,000 8 $ 80,000
November Total 4 $ 26,000 4 $ 40,000
December Total 4 $ 26,000 5 $ 45,000
January Total 3 $ 19,500 3 $ 30,000
February Total 9 $ 58,500 9 $ 90,000
March Total 7 $ 45,500 8 $ 75,000
April Total 6 $ 39,000 6 $ 60,000
May Total 26 $ 169,000 26 $ 260,000
June Total 7 $ 45,500 7 $ 70,000
Fiscal Year Total 99 $ 650,000 100 $ 1,000,000
Page 24 of 29
Fiscal Year Water Wastewater
10-11 Taps Amount Due Taps Amount Due
July Total 3 $ 26,000 3 $ 40,000
August Total 3 $ 26,000 3 $ 40,000
Septenber Total 2 $ 13,000 2 $ 20,000
October Total 0 $ - 0 $ -
November Total 5 $ 29,250 4 $ 40,000
December Total 7 $ 58,500 7 $ 90,000
January Total 4 $ 32,500 4 $ 50,000
February Total 13 $ 97,500 13 $ 150,000
March Total 2 $ 13,000 2 $ 20,000
April Total 6 $ 42,250 6 $ 65,000
May Total 10 $ 110,432 8 $ 90,028
June Total 11 $ 71,500 11 $ 110,000
Fiscal Year Total 66 $ 519,932 63 $ 715,028
Fiscal Year Water Wastewater
09-10 Taps Amount Due Taps Amount Due
July Total 1 $ 9,750 1 $ 15,000
August Total 3 $ 29,250 3 $ 45,000
September Total 0 $ - 0 $ -
October Total 2 $ 13,000 2 $ 20,000
November Total 0 $ - 0 $ -
December Total 4 $ 39,000 4 $ 60,000
January Total 1 $ 6,500 1 $ 10,000
February Total 2 $ 13,000 2 $ 20,000
March Total 8 $ 55,250 8 $ 85,000
April Total 3 $ 19,500 3 $ 30,000
May Total 3 $ 19,500 3 $ 30,000
June Total 7 $ 48,750 8 $ 90,000
Fiscal Year Total 34 $ 253,500 35 $ 405,000
Fiscal Year Water Wastewater
08-09 Taps Amount Due Taps Amount Due
July Total 1 $ 6,500 1 $ 10,000
August Total 2 $ 13,000 1 $ 15,000
September Total 1 $ 6,500 1 $ 10,000
October Total -7 $ (45,500) -7 $ (70,000)
November Total 0 $ - 0 $ -
December Total 0 $ - 0 $ -
January Total 1 $ 6,500 2 $ 15,000
February Total 0 $ - 0 $ -
March Total 0 $ - 0 $ -
April Total 6 $ 39,000 7 $ 70,000
May Total 2 $ 13,000 1 $ 15,000
June Total 1 $ 61,840 1 $ 66,760
Fiscal Year Total 7 $ 100,840 7 $ 131,760
Page 25 of 29
Fiscal Year Water Wastewater
07-08 Taps Amount Due Taps Amount Due
July Total 4 $ 35,750 5 $ 60,000
August Total 14 $ 100,750 14 $ 155,000
September Total 4 $ 47,486 6 $ 61,904
October Total 46 $ 326,670 47 $ 498,380
November Total 3 $ 22,750 4 $ 40,000
December Total 3 $ 19,500 4 $ 40,000
January Total 1 $ (14,670) 1 $ (8,380)
February Total -29 $ (177,710) -29 $ (273,400)
March Total 4 $ 41,618 4 $ 58,352
April Total 4 $ 26,000 5 $ 55,000
May Total 0 $ - 0 $ -
June Total 1 $ 6,500 1 $ 10,000
Fiscal Year 55 $ 434,644 62 $ 696,856
Fiscal Year Water Wastewater
06-07 Taps Amount Due Taps Amount Due
July Total 28 $ 187,750 29 $ 286,500
August Total 30 $ 223,302 30 $ 335,028
September Total 12 $ 99,802 12 $ 148,028
October Total 44 $ 308,750 44 $ 475,000
November Total 14 $ 188,944 14 $ 249,306
December Total 10 $ 77,684 10 $ 116,676
January Total 10 $ 96,236 10 $ 118,704
February Total 10 $ 65,000 10 $ 100,000
March Total 17 $ 120,250 17 $ 185,000
April Total 27 $ 234,722 27 $ 338,408
May Total 39 $ 296,472 40 $ 451,704
June Total 20 $ 159,250 20 $ 236,000
Fiscal Year 261 $ 2,058,162 263 $ 3,040,354
Fiscal Year Water Wastewater
05-06 Taps Amount Due Taps Amount Due
July Total 36 $ 187,500 36 $ 262,500
August Total 49 $ 261,605 49 $ 366,505
September Total 35 $ 256,209 35 $ 347,061
October Total 21 $ 117,500 22 $ 171,500
November Total 46 $ 252,500 46 $ 353,500
December Total 29 $ 130,000 29 $ 161,000
January Total 79 $ 469,130 77 $ 621,380
February Total 13 $ 75,000 14 $ 112,000
March Total 56 $ 415,075 56 $ 552,155
April Total 39 $ 212,500 39 $ 297,500
May Total 61 $ 329,105 62 $ 468,005
June Total 42 $ 235,000 42 $ 329,000
Fiscal Year 506 $ 2,941,124 507 $ 4,042,106
Page 26 of 29
Fiscal Year Water Wastewater
04-05 Taps Amount Due Taps Amount Due
July Total 32 $ 160,000 24 $ 168,000
August Total 40 $ 163,760 23 $ 161,000
September Total 55 $ 275,000 43 $ 301,000
October Total 74 $ 294,500 47 $ 329,000
November Total 37 $ 185,000 37 $ 259,000
December Total 12 $ 60,000 7 $ 49,000
January Total 31 $ 155,000 32 $ 224,000
February Total 12 $ 60,000 12 $ 84,000
March Total 79 $ 408,552 77 $ 552,028
April Total 63 $ 316,605 63 $ 443,505
May Total 48 $ 272,104 47 $ 362,056
June Total 70 $ 262,368 68 $ 363,352
Fiscal Year 553 $ 2,612,889 480 $ 3,295,941
Fiscal Year Water Wastewater
03-04 Taps Amount Due Taps Amount Due
July Total 0 $ - 1 $ 5,000
August Total 10 $ 104,570 9 $ 76,725
September Total 10 $ 65,286 10 $ 75,714
October Total 19 $ 95,000 20 $ 100,000
November Total 22 $ 110,000 22 $ 110,000
December Total 26 $ 130,000 26 $ 130,000
January Total 32 $ 168,210 12 $ 155,000
February Total 15 $ 76,605 84 $ 424,505
March Total 64 $ 460,916 56 $ 432,724
April Total 93 $ 433,240 71 $ 385,000
May Total 46 $ 230,000 47 $ 269,000
June Total 32 $ 160,000 27 $ 189,000
Fiscal Year 369 $ 2,033,827 385 $ 2,352,668
Fiscal Year Water Wastewater
02-03 Taps Amount Due Taps Amount Due
July Total 14 $ 37,240 13 $ 49,920
August Total 16 $ 42,560 16 $ 61,440
September Total 13 $ 37,240 12 $ 46,080
October Total 9 $ 23,940 9 $ 34,560
November Total 16 $ 42,560 17 $ 65,280
December Total 77 $ 204,820 79 $ 303,360
January Total 224 $ 595,840 225 $ 864,000
February Total 72 $ 196,200 73 $ 282,640
March Total 0 $ - 0 $ -
April Total 2 $ 17,368 1 $ 5,000
May Total 0 $ - 0 $ -
June Total 3 $ 15,000 4 $ 20,000
Fiscal Year 446 $ 1,212,768 449 $ 1,732,280
Page 27 of 29
Agenda Item Summary
Committee:
Light & Power and Environmental Services Committee
Title:
FY2026 Budget Amendment for Emergency Replacement of a 1000 kW Generator at the Water
Pollution Control Facility
Background:
On June 7, 2025, a 1000 kW emergency generator serving the Biological Nutrient Removal (BNR)
process at the Water Pollution Control Facility malfunctioned and was damaged beyond repair. This
emergency generator is a DEQ permit requirement and critical for sustaining plant operations.
Town staff responded to this emergency with contract electrical services and rental of a mobile 1000
kW generator. The cost for mobile generator rental with Carter CAT for two months was $61,712.80
and was charged to the Wastewater Treatment department budget.
Additionally, Town staff solicited quotes for replacing the failed 1000 kW generator and determined
the lowest cost provider was Fidelity Engineering Corp at a cost of $448,300. An emergency PO was
issued to purchase the new generator and was charged to the Wastewater Treatment department
budget.
These expenses were unanticipated during the development of the FY2026 Wastewater Fund budget
and will exceed available budget funds for this fiscal year. Staff recommends increases to the
Wastewater Treatment department budget to cover these items.
Financial Impact:
The total financial impact is an increase to the Wastewater Treatment department budget in the
amount of $510,013, with funds to be transferred from the Wastewater Fund reserves.
Recommendation:
Page 28 of 29
That Town Council approves a transfer of $510,013 from Wastewater Fund reserves to increase
Wastewater Treatment budget expense line 40094700-53201, equipment rental in the amount of
$61,713 and to increase Wastewater Treatment budget expense line 40094700-77200, machinery &
equipment in the amount of $448,300 to cover the FY2026 budget overage resulting from the
emergency costs of replacing the Water Pollution Control Facility’s 1000 kW generator.
Page 29 of 29