Public Safety, Public Works, Planning and Community Development Committee
Regular MeetingCulpeper, VA · November 25, 2025
Agenda
Public Safety, Public Works, Planning &
Community Development Agenda
Tuesday, November 25, 2025 at 9:45 AM
Economic Development Center, Council Meeting Room
803 South Main Street, Culpeper
Page
1. CALL TO ORDER
By Chairman Rimeikis
2. PREVIOUS MEETING MINUTES 4-6
For Reference Only - Minutes from October 2025
10-28-2025 PSPWPCD Committee Special.pdf
3. APPROVAL OF AGENDA
Motion to approve or amend the agenda.
4. PUBLIC COMMENTS
Members of the public may address the committee on matters relevant to town
government at this time.
Those who wish to speak are requested to Sign-In at the door.
State your name and address for the record.
Each speaker shall have three (3) minutes and shall comply with the Citizen
Participation Policy.
For groups present, you are requested to have a spokesperson.
Questions should be directed to the Chair.
5. ITEMS REFERRED BY COUNCIL OR INDIVIDUAL MEMBERS
6. SPECIAL ITEMS & PRESENTATIONS
7. PUBLIC WORKS ITEMS
Page 1 of 35
7.1 Departmental Activities 7-9
Public Works Monthly Report for October 2025.pdf
7.2 R/R Re: Columbia Gas Deed of Easement for Old Brandy Road 10 - 15
Deed of Easement - Columbia Gas TAG 2025.11.03.pdf
Motion to approve.
8. PLANNING & COMMUNITY DEVELOPMENT ITEMS
8.1 Departmental Activities 16 - 20
2025_10_PCD_Departmental Activities.pdf
9. PUBLIC SAFETY ITEMS
9.1 Departmental Activities 21 - 29
10 - October 2025 PSC Report.pdf
9.2 E911 Center Report 30 - 32
OCT 2025 E911 Report.pdf
9.3 Culpeper Volunteer Fire Department Report 33 - 35
CCVFD Report.pdf
Attachment added on November 24 at 12:00pm.
10. TOWN & COUNTY INTERACTION COMMITTEE
10.1 Potential Items for Discussion at Next Interaction Committee
Meeting
11. ADJOURNMENT
Adjournment of Meeting
Committee Members:
Pranas A. Rimeikis (Chairman), Jamie Dyke, Michael T. Olinger & Joe Short
Note: Members of the Town Council who are not members of the committee may be in
attendance at the committee meeting. If so, and if a quorum of council is present, then the
meeting will be a special meeting of council in addition to being a committee meeting, pursuant
to the Virginia Freedom of Information Advisory Council Attorney Opinion, AO-03-14. Only
Page 2 of 35
business matters to be considered are the committee's recommendations to the council unless
specifically noted in this public notice.
Page 3 of 35
10-28-2025 Public Safety, Public Works, Planning & Community Development Committee and Special
Council Meeting
9:45 a.m. Economic Development Center, 803 S. Main Street
The purpose of this meeting was to consider Public Safety, Public Works, Planning and Community
Development Committee matters; however, members of the Town Council who were not members of
the committee were in attendance and participated in the discussion, resulting in a special meeting of
council.
Committee Members Present: Chairman Pranas A. Rimeikis, Jamie Dyke, Michael T. Olinger, Janie
Schmidt (Alternate for Joe Short)
Committee Members Absent: Joe Short
Also Present: Frank Reaves Jr., B. Travis Brown, William Yowell; Council Members; Christopher D. Hively,
Town Manager; Jim Hoy, Director of Public Services; Ashley R. Clatterbuck, Town Clerk; Chief Chris
Settle; Andrew Hopewell, Director of Planning & Community Development; Blake Dodson, Culpeper
County Sheriff’s Office
CALL TO ORDER
Chairman Rimeikis called the meeting to order at 10:05 a.m.
PREVIOUS MEETING MINUTES
For Reference Only – Minutes from September 2025
There were no changes to the minutes.
APPROVAL OF AGENDA
Ms. Schmidt moved, Ms. Dyke seconded, approval of the agenda as presented. The motion carried by
voice vote.
PUBLIC COMMENTS – None
ITEMS REFERRED BY COUNCIL OR INDIVIDUAL MEMBERS – None
SPECIAL ITEMS & PRESENTATIONS
Presentation by Maggie Kardos, Executive Director of PlayDate: A Children's Museum
Maggie Kardos, Executive Director; Lauren Ashoff, President; and Ginny Koontz, Treasurer, provided a
PowerPoint presentation on PlayDate: A Children’s Museum.
Ms. Kardos explained that the museum is an interactive, hands-on space designed to encourage learning
through play, rather than observation alone. She emphasized their mission to inspire a lifelong love of
learning and help children reach their full potential to make a positive impact in the world.
She further noted that play-based learning allows children to learn best through active engagement and
exploration, supporting cognitive, social, and emotional development. She explained that as a children’s
museum, PlayDate promotes STEM education, critical thinking, problem-solving, pretend play,
imagination, and creativity.
Ms. Ashoff explained that PlayDate had been open for a year and has already established a Story of the
Week, Craft of the Week, Science Saturday and Sensory Friendly Hours.
Ms. Koontz reported that, thanks to a generous grant from the Culpeper Wellness Foundation, PlayDate
was able to offer free admission to low-income families. She further noted that the museum had served
Page 4 of 35
PS/PW/PCD Committee
October 28, 2025 – Page 2 of 3
3,645 families through general admission, 329 through Science Saturdays, and 322 through the
scholarship program.
PUBLIC WORKS ITEMS
Departmental Activities
Mr. Hoy presented the report and provided an update on the Route 3/McDevitt Drive roundabout,
noting they anticipated completion in November.
He further noted leaf collection was scheduled for the week after Thanksgiving.
PLANNING & COMMUNITY DEVELOPMENT ITEMS
Departmental Activities – The committee received the report.
For Information Only: UDO Text Amendment for Reasonable Accommodations
Mr. Hopewell presented the item stating it has come to the Town’s attention that there is not currently
a way to grant a reasonable accommodation to the Town’s Unified Development Ordinance (UDO) if the
event that a citizen with a disability is not able to use and enjoy a dwelling or structure within the Town.
The proposed text amendment would create that opportunity for requests to be made related to
specific individuals and specific properties and would provide an avenue to address these requests in
the instance they cannot be accommodated through a Zoning Variance as prescribed in Virginia State
Code § 15.2-2309.2. The proposed amendment would create a process whereby the accommodation
could be requested, identifying the accommodation necessary, the property and the individual needing
the accommodation along with the medical justification for the need for the accommodation. The
request would be evaluated by the Zoning Administrator who would identify the request’s potential
impacts and possible alternatives, as well as if it could be addressed by a variance instead. If not able to
be addressed in any other manner, the reasonable accommodation request will be presented to the
Town Council within 90 days of submission. If granted, the accommodation will be specific to the
individual(s) and the property(ies) involved in the request.
A public hearing would be held at the November 13, 2025 regular council meeting.
No formal action was taken on this item.
Discussion Item: Yowell Meadow Park Lighting and Hours of Operation
Mr. Hopewell presented the item stating Light & Power received a request from a citizen to install a
streetlight in Yowell Meadow Park at the upper bridge near West Asher Street. The citizen noted that
they frequently walk in the area during dark hours and felt unsafe. This was presented to the Town’s
Light & Power and Environmental Services Committee on September 24, 2025. Following a brief
discussion regarding prior trail issues, increased use of parks and trails during dark hours, and the
possibility of re-evaluating the park hours, it was the consensus of the committee for staff to prepare a
discussion item for presentation at the Public Safety, Public Works, Planning & Community Development
Committee.
Presently, Town Code Sec. 15-2. reads,
a. No person shall go upon or remain on any part of the town park areas between one (1) hour
after sunset and one (1) hour before sunrise except upon special permission from the town
manager and subject to such restrictions and conditions that may be imposed by him.
b. A violation of this section is punishable as a class 1 misdemeanor.
Page 5 of 35
PS/PW/PCD Committee
October 28, 2025 – Page 3 of 3
The matter for discussion of the committee is whether there is a desire to accommodate additional
activities in the park during hours of darkness. This could be accomplished by changing the park hours. If
there is a desire to permit activity beyond the current hours, is there a desire to provide lighting for
parts of the trail and/or park to better allow the activity? If there is a desire for additional lighting, in
response to the citizen request, Town Light & Power provided an initial estimate of approximately
$2,000 for the installation of one light at the bridge. Following a more thorough examination of the site,
it is estimated that one light on the East side of the walking bridge would have a cost of $4,722.26,
alternatively, one light could be installed on the East side along with three on the West side for
$12,093.36.
The matter was presented to the Town’s Parks & Recreation Committee on October 27, 2025 and they
recommended a light not be installed and the hours of operation not be adjusted.
No formal action was taken on this item.
PUBLIC SAFETY ITEMS
Departmental Activities – The committee received the report.
E911 Center Report – The committee received the report.
Culpeper Volunteer Fire Department Report – The committee received the report.
TOWN & COUNTY INTERACTION COMMITTEE
Follow-up Discussion from the September 26, 2025 Meeting
Mr. Hively presented a slideshow summarizing the Courthouse Renovation Project.
Discussion ensued.
It was the consensus of the committee for Mr. Hively to send a letter to the County Administrator giving
the following comments:
• The request for a Traffic Impact Analysis and Economic Impact Analysis.
• The Economic Impact Analysis should include feedback from CRI and the downtown business
community.
• Eliminate the East Spencer / East Cameron Street Structured Parking from further discussion.
• Further develop the Blue Ridge Avenue / West Street Structured Parking. This should include
moving the structure further away from Blue Ridge Avenue creating a vegetative buffer and to
acquire a portion of the back yards of the two adjoining properties that affront West Street to
allow the structured parking to be located closer to West Street and also allowing a pedestrian
bridge walkway from the top floor of the structure to Blue Ridge Avenue and possibly a second
vehicle across from the West Cameron Street parking lot to the top of the parking structure.
• Renovation of the courthouse should include architectural features which complement the
surrounding structures in the downtown.
Potential Items for Discussion at Next Interaction Committee Meeting
Chairman Rimeikis requested to add a discussion item regarding the status of the Joint Planning
Advisory Committee.
ADJOURNMENT
The meeting adjourned at 10:55 a.m.
Page 6 of 35
October 2025
Streets
The following routine maintenance operations were performed: asphalt pavement and patching;
ditch, culvert and catch basin cleaning; street sweeping; curb and gutter cleaning; ROW mowing
and trimming operations to include embankments, medians, and roadway edges.
Supported scheduled community special events with signs, traffic control and refuse collection as
needed.
Conducted refuse and debris removal from roadways, medians, parking lots, medians, catch basins,
drop inlets and culverts.
Verified inventory of road salt and sand sheds for upcoming winter season.
Public Works and Special Projects
The following routine operations were performed: daily inspections, ROW permits, Miss Utility
tickets, locate tickets, mapping utilities with GIS, AMR Service orders, MTU reprogramming and
replacement, installation and repair of meters, hydrants and registers, record management, plan
review, reviewing video of utilities, set up and take down of work zones and working with
contractors in locating additional utilities.
Continued landscaping, installation of signs, and worked with other departments to complete
facilities at Heritage Park.
Performed various inspections, plan review and testing of Laurel Park, Kite Acres, Williams Mill,
Parkside, The Greens, Lifepoint Church, Sheetz, Germanna Hwy. roundabout, and Community pool.
Preconstruction meetings held with inspectors and contractors to review sites. Continued
reviewing plans for construction of future projects.
Continued development of groundwater well sites.
Relocated water meter service for the widening of E. Spencer St.
Installed water/sewer taps at Wayland Rd. and Saunders St.; repaired water main break on
Elizabeth St.
Traffic Engineering
Performed routine sign maintenance inspections (retro reflectivity, damage etc.).
Page 1|3
Public Works
M o n t h l y R ePage
p o r t7 of 35
General Properties
The following routine maintenance operations were performed throughout facilities: electrical
repairs, and other general building repairs and updates.
Continued renovations at Town Hall to include updates to facilities in Treasurers office.
Motor Pool
Routine preventive maintenance operations were performed throughout the fleet, as necessary
(light replacements, oil changes, inspections, wiper blade replacements, exhaust work, brake/rotor
replacements etc.). Continued preparation and maintenance of seasonal equipment before and
after weather events.
Additional repairs completed:
322 – Brush Truck – Installed brine tank
325 – Dump Truck – Replaced faulty clutch switch with new
336 – Trash Truck - Replaced faulty belt and spring on grabber arm
371 – Loader – Rebuilt locking cylinder and replaced curb finders on snowblade
861 – Backhoe – Replaced hydraulic line and quick coupler on boom
Began preparations for snow equipment
Cemetery
The following routine maintenance operations were performed: collecting limbs and plastic
flowers, pruning trees, trimming bushes, grade roadways, cleanup stock and spoil piles, filling,
leveling and seeding graves. Provided necessary services for interments and repairs of existing
graves as needed.
Continued mowing operations; weed eating, clean up maintenance building and control of exterior
vegetative overgrowth.
Parks & Recreation
The following routine maintenance operations were performed for parks: inspected flags and
replaced as needed, litter control, mowing and trimming, cleanup of planter beds, around trees,
parking lots and play areas and maintenance of ball fields.
Developed new path through wooded area at RWP for Frisbee golf course.
Page 2|3
Public Works
M o n t h l y R ePage
p o r t8 of 35
Personnel
Staff completed required Safe Personnel training.
Staff currently working to complete required Arctic Wolf Cybersecurity Awareness training.
Construction Inspectors are currently studying DEQ Storm Water and Erosion for certification.
Amy Jeffries and April Aylor attended the VAGARA Records Retention Conference.
Public Works welcomed DaeQuon Butler to our team as a new equipment operator.
Ethan Pullen attended a regional VA 811 Seminar.
Gene Scott and Shelly Plaster attended the Roadway Management Conference.
Upcoming Activities
Continue to support the development of Heritage Park.
Continue to support community special events as scheduled.
Continue preparations for leaf collection.
Continue preparations for snow and ice operations.
Continue the E. Spencer St. widening project.
Page 3|3
Public Works
M o n t h l y R ePage
p o r t9 of 35
Agenda Item Summary
Committee:
Public Works Committee
Title:
R/R Re: Columbia Gas Deed of Easement for Old Brandy Road
Background:
Due to a mandated requirement to replace an existing pipeline, Columbia Gas is requesting a 15-foot
easement on Town Parcel 41-93 to construct and maintain a new gas line. The easement will last 40 years
and gives Columbia Gas the right to build, operate, and repair their line, with full responsibility for restoring
any disturbed areas.
The Town may continue to use the area as long as it does not conflict with the gas line. No structures may
be placed in the easement.
If the Town or VDOT later needs the line moved, Columbia Gas must relocate it at their expense. If the area
becomes a public road, the easement will end unless allowed under Columbia Gas’s franchise.
At the end of the easement, Columbia Gas must remove its facilities or abandon them in place, which then
become Town property.
State law requires the Town to advertise and receive bids for the easement at the Council meeting. If any
additional bids are received, staff will review them and provide recommendations to Council. Council may
also make such other investigations as it sees fit. Council will have the following options: (1) reject all the
bids and make no awards, (2) grant the easement to the highest bidder, or (3) by a recorded vote of the
majority of the members elected to the Council reject a higher bidder and accept a lower bid from a
responsible bidder if, in its opinion, some reason affecting the interest of the Town makes it advisable to
do so. With option (3), the reason would have to be expressed in the form of the approval.
The proposed deed of easement for your consideration has been reviewed and approved by the Town
Attorney as to form.
Page 10 of 35
Financial Impact:
All construction, relocation, restoration, removal, and maintenance costs are the responsibility of Columbia
Gas. No direct financial burden to the Town is anticipated.
Recommendation:
That Council accepts the bid for granting of the deed of easement and right of way to Columbia Gas of
Virginia to construct and maintain a gas line for a period of forty (40) years from the date of execution and
authorizes the Town Manager to execute the document.
Page 11 of 35
Parcel ID#: 41 93
RW
JO # 24-0382100, 24-0381913
DEED OF EASEMENT AND RIGHT OF WAY
THIS DEED OF EASEMENT AND RIGHT OF WAY granted this ____ day of
______________, 2025, by and between THE TOWN OF CULPEPER, VIRGINIA, a municipal
corporation, hereinafter called the "Grantor," and COLUMBIA GAS OF VIRGINIA, INC., a
Virginia corporation, having a mailing address at 1809 Coyote Drive, Chester, Virginia 23836,
hereinafter called the "Grantee,"
W I T N E S S E T H:
That for and in consideration of the sum of One Dollar ($1.00), the receipt and sufficiency of
which is hereby acknowledged, before entry is made to construct the same, the Grantor hereby grants
and conveys to the Grantee, its successors and assigns, for a period of forty (40) years from the date
of execution of this Deed of Easement and Right of Way, an easement and right of way to construct,
operate, maintain, replace, repair, upgrade, remove or abandon in place pipelines and appurtenant
equipment, together with valves, service connections and lateral connections for transporting gas with
associated products, or other substances that can be transported through pipelines, and appurtenant
facilities including, but not limited to, cathodic protection, and to perform pre-construction work or
activities, over and through that portion of the property of Grantor identified as “15’ WIDE GAS
PIPELINE EASEMENT” on Drawing Number V47-280-25 (“Easement Area”), attached hereto,
made a part hereof, and recorded herewith. Being across a portion of a parcel of property owned by
Grantor situate in the Town of Culpeper, Virginia, that is more particularly described as:
All that certain lot or parcel of land together with all improvements thereon
located and being in the County of Culpeper, Virginia, described by metes and bounds
in the Deed from Brandy Road Properties, L.L.C., to The Town of Culpeper dated
April 14, 2023, and recorded April 14, 2023, as Instrument No. 230001462, among
the land records of Culpeper County, Virginia, containing 5.616 acres of land, more
or less, and known as Parcel Identification Number 41-93;
And being a portion of the same property conveyed to Brandy Road
Properties, L.L.C., by Deed from Sheilda H. Breeden, individually and Sheilda H.
Breeden, Trustee of the Amy Sue Breeden and Mary Kate Breeden Testamentary
Trust, dated January 15, 2002, recorded January 17, 2002 at Instrument No.
020000472, among the land records of Culpeper County, Virginia.
Prepared By: 1
Columbia Gas of Virginia, Inc.
Page 12 of 35
The easement and right of way herein granted (the "Easement") shall be subject to the
following further conditions:
1. The Grantee shall have the right to trim, cut, and remove trees, shrubbery, fences,
structures, or other obstructions or facilities on or over the Easement that are deemed by it in its
discretion to interfere with the proper and efficient construction, operation, and maintenance of the
Easement; provided, however, that following completion of construction or repair, the Grantee shall
at its own expense restore, as nearly as possible, the property to its original condition, such restoration
including the re-pavement of the roadway, backfilling of trenches, replacement of fences, and the
reseeding or resodding of lawns, but not the replacement of structures, trees, bushes, undergrowth or
other facilities located within the Easement.
2. The Grantor reserves the right to make any use of the Easement which may not be
inconsistent with the rights herein conveyed or interfere with the use of said Easement by the Grantee
for the purposes named; provided, however, that the Grantor shall not erect any building, or other
structure, excepting a vehicular entrance, driveway or fence, on the Easement without obtaining prior
written approval of the Grantee.
3. Should Grantor at any time deem it necessary to relocate for Grantor’s sole
convenience all or a portion of the Easement and/or the pipelines or appurtenant facilities, Grantee at
its sole cost shall relocate pipelines and/or appurtenant facilities to a mutually agreed upon location
to be provided by the Grantor. If the relocation of the pipeline or appurtenant facilities is outside of
the Easement Area, for no consideration, Grantor shall grant unto Grantee such replacement easement
and right of way as may be reasonably necessary to affect such relocation.
4. If in the future it is decided by the Grantor that the Easement Area is to be dedicated
to public use for public road purposes this Easement and Right of Way shall terminate, and the
Grantee shall execute a Release of Easement terminating all of the Grantee’s rights and interest
hereunder to the Grantor. If the Grantee has a valid franchise agreement with the Town of Culpeper
at the time of the dedication to public use for public road purposes under this provision and relocation
of the utilities is not required by the Virginia Department of Transportation (VDOT) as part of any
road improvement project, the Grantee shall be eligible to apply for a permit under their franchise to
allow their pipeline and appurtenant facilities to remain in place. If relocation of the pipeline or
appurtenant facilities is required by VDOT, Grantee at its sole cost shall relocate pipelines and/or
appurtenant facilities to either (a) a mutually agreed upon location within the public road subject to a
2
Page 13 of 35
permit issued under Grantee’s franchise or (b) if the relocation of the pipeline or appurtenant facilities
is required by VDOT to be outside of the road, for no consideration, Grantor shall grant unto Grantee
such replacement easement and right of way as may be reasonably necessary to affect such relocation.
5. If Grantee obtains a permit to allow the pipeline and appurtenant facilities to remain
on the Grantor’s property under a franchise with Grantor, the terms of the franchise and permit shall
govern the rights and obligations of the parties from that point forward and this Easement shall
terminate. Except when termination occurs on the basis of the issuance of the aforementioned permit,
upon termination of the Easement the Grantee shall either (a) at its expense, remove from the
Easement Area and the land of the Grantor all pipelines, cables, poles, equipment of any kind, and
other personal property of the Grantee or used by it in or on the Easement Area or (b) abandon such
pipelines and appurtenant facilities in place and without any compensation paid to the Grantee such
property shall become the property of the Grantor.
6. Pursuant to Code of Virginia § 15.2-2100.B, this Easement is only granted for a term
of forty (40) years.
The rights, privileges and terms contained herein shall extend to and be binding upon Grantor
and Grantee and their respective representatives, heirs, successors and assigns.
NOTICE TO LANDOWNER: You are conveying rights to a public service corporation. A
public service corporation may have the right to obtain some or all of these rights through exercise of
eminent domain. To the extent that any of the rights being conveyed are not subject to eminent
domain, you have the right to choose not to convey those rights and you could not be compelled to
do so. You have the right to negotiate compensation for any rights that you are voluntarily conveying.
[Signatures on the following page]
Prepared By: 3
Columbia Gas of Virginia, Inc.
Page 14 of 35
WITNESS the following signatures and seal this ____ day of ________________, 2025.
GRANTOR: THE TOWN OF CULPEPER,
VIRGINIA, a municipal corporation
By: _______________________________ (SEAL)
Christopher D. Hively, Town Manager
COMMONWEALTH OF VIRGINIA
COUNTY OF CULPEPER, to-wit:
The foregoing instrument was acknowledged before me this _____ day of
_________________, 2025 by Christopher D. Hively, Town Manager of THE TOWN OF
CULPEPER, VIRGINIA, a municipal corporation, on behalf of the corporation.
________________________________________________
(Notary Signature)
My commission expires the ______ day of _____________, 20____.
Notary Registration No.: ____________________________
Approved as to form:
_________________________
Town Attorney
4
Page 15 of 35
Planning & Community Development Departmental Report
October, 2025
Planning Commission Activities
The Planning Commission held their Regular Meeting on October 21, 2025 and considered the
following:
• Public Hearing – Text Amendment: Staff presented a Text Amendment to Town Code
Chapter 27 to provide a mechanism for consideration of a request for a reasonable
accommodation in accordance with provisions of state and federal fair housing laws or the
Americans with Disabilities Act of 1990 (42 U.S.C. § 12131 et seq.), as applicable.
Discussion ensued. The Commission voted to forward to Town Council with a
recommendation for approval.
The Planning Commission held their Work Session on October 30, 2025.
• Comprehensive Plan Update: Discussion ensued regarding Mr. Fitzsimmons findings that
he compiled of Comp Plans from other localities within the State as well as core
components of the vision and various other aspects of the Comp Plan.
• The Commission voted to cancel the regularly scheduled November and December work
sessions and combine them for a December 4th work session.
Joint Board of Zoning Appeals Activities
The Joint Board of Zoning Appeals did not hold their Regular Meeting in October 2025.
Public Transportation Board Activities
The Public Transportation Board held its Regular Meeting on October 23, 2025 and considered
the following:
• Ridership Report: Mr. Socha discussed the monthly ridership. Mr. Socha pointed out the
overall number is up from last year but the Express Route had a dip in ridership. Mr. Socha
discussed the Stevensburg/Brandy Station Hybrid fixed route.
• Private Property Easements: The Board discussed the requirements for the private property
easements. Mr. Thompson will work with Town staff to ensure the proper language is
included in the easement language.
• Bus Shelter at Heritage Park: The Board discussed the proposed shelter for the bus stop at
Heritage Park. The Board unanimously voted for a 6’x12’ Barrel Vault Roof shelter.
• Discussion regarding amendment to the agenda format or possible bylaw change: The
Board discussed the flow of the agenda per the bylaws. Staff presented a couple of options
for the format of the agenda. The Board discussed other possible changes to the bylaws.
The Board agreed to review the bylaws to see if there are any other changes to the bylaws
that may be required.
• The Board held a discussion regarding the bus shelter/stop at Commerce Street. The Board
voiced their strong concerns about not having a shelter or bench at the Commerce Street
bus stop. Ms. Puryear stated she would bring the Board’s concern back to Town staff to
discuss options available for the site.
Page 16 of 35
Architectural Review Board Activities
The Architectural Review Board held its Regular Meeting on October 22, 2025 and considered the
following:
• COF-6057-2025: The Board approved a request by Wortman Properties, LLC, owner, to
replace the roof at 115 South West Street.
• COF-6066-2025: The Board approved, with conditions, a request by Charles Ramey, on
behalf of the owner, Myron John Buchele, et ux, to replace the previously removed
chimney at 206 East Spencer Street.
• COF-6070-2025: The Board approved, with conditions, a request by Galina Futekova, on
behalf of the owners, Krassimir Ianev et al and EBW Properties LLC, to add a new exterior
door at 128 and 118 North Main Street.
• Historic District Flyers: The Board discussed the 2025 Historic District Flyers. Every year
the Board mails flyers to all property owners in the Historic District. The flyers contain
general information about the district, the application process, and where to find more
information.
Parking Authority Activities
The Parking Authority did not hold held its Regular Meeting on October 15, 2025 due to not having
a quorum.
Parks and Recreation Commission Activities
The Parks and Recreation Commission held their Regular Meeting on October 27, 2025 to consider
the following:
• The Commission discussed streetlights at Yowell Meadow Park. The Commission voiced
concerns about adding lights to the park, as it would change the hours of operation of the
park. The Commission voted to recommend denial of the request for lights at Yowell
Meadow Park.
• The Commission discussed Disc Golf Course at Rockwater Park. The Commission voted
on a caution sign for the path for Disc Golf.
• The Commission discussed Guidebook/Best Practices.
• Comprehensive Plan Update for Parks & Recreation Section: the commission discussed
the updated update to the Comprehensive Plan.
Property Complaints – Enforcement Actions – (October 2025)
The following properties are scheduled for Town Action:
• 2018 Orange Road-Vegetation
• 1322 High Street- Vegetation Encroachment on Street
• 402 Monticello- Vegetation
• 633 Fourth Street- Safety Nuisance
Property Enforcement Totals (October 2025)
Zoning/Town Code Complaints:
• Courtesy/Violation Notices (New): (13)
Page 17 of 35
VA. Maintenance Code (September 2025)
• 402 East Spencer Street (Damaged Roof)-Ongoing
• 102 North West Street (Structure Fire)-Permits Issued
• 106 North West Street (Structure Fire)-Permits Issued
• 1700 Magnolia Circle (Interior Flooding)-Ongoing
• 138 North Main Street (Fire/Water Damage)- Ongoing
• 800A/800B Third Street (Fire/Water Damage)-Under Construction
• 201-209 East Davis Street (Fire/Water Damage)-Ongoing
• 1010/1012 South Main (Utility Suspension/ Lack of Sanitary Plumbing System)-Ongoing
Fire Code (Egress) Inspections – Town Ordinance O-2015-011 (October 2025)
• 137 South Main- Addressing Deficiency
Zoning Ordinance Update
Staff worked with Duncan Associates and Codametrics on an overhaul to the Zoning and
Subdivision Ordinance. An Advisory Committee was selected by Town Council to lead the
overhaul effort and provide guidance to Town staff and the consultant team.
The full draft has been shared with the public to start 2025. A joint work session with the Planning
Commission and Town Council was held on January 28, 2025 and Planning Commission public
hearings were held on March 18 and April 15, 2025. The Town Council public hearings were held
on May 13, 2025 and June 10, 2025. A special Town Council meeting was held on July 11, 2025
for Town Council to share their perspectives with staff for the development of a final version of
the Unified Development Ordinance. The Ordinance had public hearings before the Planning
Commission on August 19, 2025 and Town Council on September 9, 2025. The Unified
Development Ordinance was adopted by the Town Council on October 14, 2025. It is currently in
effect and its full implementation is currently underway.
SMART SCALE Transportation Projects
Round 3: The traffic circle at McDevitt Drive and Route 3 has been funded and is being managed
by VDOT. Construction is currently under way. The project is anticipated to be substantially
completed by December of 2025.
Round 5: Staff worked with VDOT and submitted revised applications for funding of a roundabout
at the intersection of Fredericksburg Road (Route 3/522) and Orange Road (Business 15) as well
as sidewalk improvements along Orange Road and Old Brandy Road. All three projects were
recommended for funding by VDOT staff and were approved by the Commonwealth
Transportation Board at their June, 2023 meeting. Preliminary engineering on the three projects
was slated to begin in December 2024.
Round 6: Staff submitted four projects to VDOT for the pre-application stage evaluation for the
current round of grants. These include two roundabouts on US Business 15 (Brandy Road) at the
intersection with Ira Hoffman Lane ($20,941,407) and the Walmart/Dominion Square entrance
($17,542,802), along with bicycle and pedestrian accommodations and crosswalks along US
Page 18 of 35
Business 15 ($33,490,471), and finally a roundabout at the intersection of Germanna
Highway/Madison Road/South Main Street ($18,304,357). The Commonwealth Transportation
Board approved the roundabout at the intersection of Ira Hoffman Lane and US Business 15 at
their May, 2025 meeting. VDOT is rolling this project into a bundle with the Round 5 projects.
Round 7: Staff is preparing to work with VDOT on at least two new submissions for a roundabout
on US Business 15 (Brandy Road) at the Walmart/Dominion Square entrance along with bicycle
and pedestrian accommodations and crosswalks along US Business 15. Staff will be working to
try and provide some value engineering to the applications to improve their competitiveness.
Culpeper Community Pool
The County has awarded two separate contracts for the pool facility – one related to the buildings
and site work and one related to the pool and splash pad facilities. At this time, the plan is for the
pool to be constructed by the Fall of 2025 and operational by May of 2026. This would meet the
requirements of the funding agreement with the Town.
GIS Activities
Utilities: Town GIS Technician continues to work closely with utility field crews to update the
Town water, sewer, and electric maps – over 580 edits to features were completed this month,
including new electric mapped in Laurel Park and town wide water/sewer map corrections.
IT: Town GIS computer software and equipment upgrades were started, including Windows
1011 and Zscaler (VPN) to Secure Access, along with one smartphone replacement; additional
GIS core users’ & ArcGIS Server software upgrades will continue over the next few months.
Personnel: Town GIS Coordinator and GIS Analyst participated in the annual Virginia GIS
Conference (GeoCon2025) hosted by VAMLIS in Harrisonburg this month – two full days of
networking and training sessions, including both Local Government and Women in GIS forums.
Online GIS: WebGIS public online site was updated in October, including the newly adopted
zoning changes. Town GIS Analyst was kept busy with web application modifications and
restorations after the recent ESRI ArcGIS Online (AGOL) software update and AWS East Coast
Server downtime issues; in addition to all the PCD web app development mentioned below.
REQUESTS:
Planning: GIS continues to provide plat review comments and map/data products, as requested.
Nearly 50 new base map data changes were completed in GIS & MUNIS records this month,
as well as zoning code changes for all parcels in Town GIS datasets.
Completed all mapping zoning changes associated with UDO adoption: updated AGOL Hub
site, maps/apps, WebGIS, layer symbology changes, Town website links; also provided
spreadsheet data to Town’s IT Database and Management Analysts for Property Master
Import to MUNIS and Culpeper County for updating their Assessor and Permitting systems.
PCD Dashboard landing page of AGOL apps created and demo’d for internal Planning staff,
including new Building Use Type editor app and PCD Viewer app (to replace ArcMap).
Page 19 of 35
Treasurer: Compiled utility & road asset features number & length statistics for annual report
Town Clerk: Odd Fellows lots georeferenced into Fairview Cemetery GIS admin map for review
Registrar: Town GIS staff assisted with numerous address verification requests for new voters
Terms:
AGOL: ArcGIS Online – ESRI’s cloud-based GIS website for hosting our GIS resources
PCD: Planning & Community Development (Planning, Zoning & GIS) Town department
Page 20 of 35
Culpeper Police Department
October 2025 Monthly Activities Report
Calls for Service Summary
July – September 2025 YTD 2025 July – September 2024 YTD 2024
Calls for Service 4,074 12,471 4,958 12,884
Officer Initiated 2,899 6,675 2,068 6,255
Direct/Extra Patrols 5,542 16,226 4,398 12,749
Admin 22 66 40 148
Totals 12,537 35,438 11,464 31,842
Calls for Service
5,542
6,000
4,958
5,000 4,398
4,074
4,000
2,899
3,000 2,068
2,000
1,000 40
22
0
Calls for Service Officer Initiated Direct/Extra Admin
Patrols
Jul - Sept 2025 Jul - Sept 2024
Selected Offense Crime Summary
July – September 2025 YTD 2025 July – September 2024 YTD 2024
Aggravated Assaults 5 12 3 14
Arson 0 0 0 0
B&E/Burglaries 1 3 3 10
Domestics 53 165 55 188
Forcible Rape 0 1 1 1
Homicides 0 0 1 1
Larcenies 66 235 93 238
Motor Vehicle Thefts 3 8 6 21
Robberies 1 1 1 5
Totals 129 425 163 478
1
Page 21 of 35
Property Summary
July – September 2025 YTD 2025 July – September 2024 YTD 2024
Estimated $ of
$231,445.35 $688,799.80 $168,543.87 $2,461,249.09
Property Stolen
Estimated $ of
$45,335.56 $56,294.83 $53,875.20 $192,408.11
Property Recovered
Arrests – All
July – September 2025 YTD 2025 July – September 2024 YTD 2024
Adults 266 791 317 907
Juveniles 3 21 10 23
Totals 269 812 327 930
Arrests
400 317 327
266 269
300
200
100
3 10
0
Adult Juvenile Totals
Jul - Sept 2025 Jul - Sept 2024
Traffic Summary
July – September 2025 YTD 2025 July – September 2024 YTD 2024
Total Crashes 59 172 60 190
Crashes w/Pedestrians 2 5 2 7
Crash Related Summons 31 132 40 135
Hit & Run 44 108 31 103
Personal Injuries 27 85 29 71
Fatalities 0 0 0 0
2
Page 22 of 35
Traffic Summons Issued
July – September 2025 666
YTD 2025 1,741
July – September 2024 538
YTD 2024 1,698
Traffic Summonses Issued
2000 1,741 1,698
1500
1000 666
538
500
0
Jul - Sept 2025 Jul - Sept 2024 YTD 2025 YTD 2024
Parking Summary
July – September 2025 YTD 2025 July – September 2024 YTD 2024
Parking Tickets Issued –
79 239 58 227
Authority Lots
Parking Tickets Issued – On
585 1,237 586 920
Street
Totals 664 1,476 644 1,147
Parking Summary
800 664 644
585 586
600
400
200 79 58
0
Parking On Street Total
Authority Lots
Jul - Sept 2025 Jul - Sept 2024
*All Statistics are current as of October 17, 2025.*
3
Page 23 of 35
Significant Department Activities
• On October 17th, Sergeant A. Caruso, Sergeant W. Hickman and Master Police Officer J Smith attended
the KinderCare Trunk or Treat.
• On October 18th, members of the department assisted with the Culpeper Renaissance Inc. Hop n Hog.
• On October 18th, Lieutenant A. Banks, Sergeant W. Hickman, and Master Police Officer J Smith
attended Children’s Day at the Park.
• On October 18th, Sergeant A. Caruso attended the Reva Volunteer Fire Department Open House
• On October 18th and 19th, members of the department assisted with 2 political rallies in town.
• On October 21st, Sergeant A. Caruso attended the Culpeper Christmas Parade meeting.
• On October 21st, Lieutenant A. Banks attended the Culpeper Renaissance Inc. Finance and Organization
Committee meeting via zoom.
• On October 21st, members of the department attended the Annual Domestic Violence Candle Light
Vigil.
• On October 21st – 23rd, Detective Master Police Officer R. Brooking instructed the Basic Crime Scene
Course to recruits at the Central Shenandoah Criminal Justice Training Academy.
• On October 23rd, Lieutenant A. Banks attended the Culpeper Reissuance Inc. Board of Directors
meeting via zoom.
• On October 23rd, members of the department attended the Community Helpers event at Yowell
Elementary.
• On October 23rd, Lieutenant A. Banks attended the Virginia Regional Transit meeting via zoom.
• On October 24th, Detective Lieutenant R. McKnight and Detective Sergeant N. McGuckin assisted with
the Basic Communications Class Scenarios at Central Shenandoah Criminal Justice Training Academy.
• On October 24th, Lieutenant A. Banks, Sergeant A. Caruso, Master Police Officer J Smith and Master
Police Officer C. Frazier attended the Moonlight Candy Hunt at the Culpeper Sports Complex.
• On October 25th, Lieutenant A. Banks, Sergeant A. Caruso and Master Police Officer J Smith assisted
the DEA Drug Take Back.
• On October 25th, Lieutenant A. Banks, Sergeant A. Caruso and Master Police Officer J Smith attended
the Trunk or Treat event at Path Recreation and Fitness Center.
• On October 25th, Lieutenant A. Banks, Sergeant A. Caruso, Master Police Officer J Smith and Master
Police Officer C. Frazier assisted with the Culpeper Renaissance Inc. Movie Night at the Depot.
• On October 25th, Sergeant W. Hickman attended Culpeper 250th Celebration events at Yowell Meadow
Park.
• October 2nd, Lieutenant A. Banks and Sergeant A. Caruso attended the Open Door Baptist Church
Harvest Festival
• On October 26th, Lieutenant A. Banks and Master Police Officer J Smith assisted with the Pet Costume
Parade downtown.
• On October 27th – 30th, Detective Master Police Officer R. Brooking attended Chaplain training in
Asheville, North Carolina.
• On October 27th, Lieutenant A. Banks, Sergeant A. Caruso and Master Police Officer J Smith attended
the Chick-fil-a Trunk or Treat.
• On October 28th, members of the department assisted in escorting Retired Master Police Officer M.
Grant to Found and Sons Funeral Home after he passed away.
• On October 29th, Lieutenant A. Banks and Master Police Officer J. Smith attended the Sycamore Park
Elementary Trunk or Treat.
• On October 29th, Detective Master Police Officers M. Hays and V Grimes and Detective K. Payne
attended Sex Crimes Investigations in Middletown, Virginia.
• On October 31st, Chief C. Settle, Deputy Chief N. White and other members of the department assisted
and attended Halloween events around town.
4
Page 24 of 35
• On November 1st, Lieutenant A. Banks, Sergeant A. Caruso, Sergeant W. Hickman, Master Police
Officer J Smith and Master Police Officer C. Frazier assisted with the Culpeper Renaissance Inc.
Haunted Hustle 5K at Yowell Meadow Park.
• On November 1st, Lieutenant A. Banks, Sergeant A. Caruso, Sergeant W. Hickman, Master Police
Officer J Smith and Master Police Officer C. Frazier attended the Hometown Heroes event at Tractor
Supply Company.
• On November 3rd – 6th, Detective Lieutenant R. McKnight assisted the Fredericksburg Police
Department with their promotional process.
• On November 5th, members of the department attended and assisted with the funeral of Retired Master
Police Officer M. Grant.
• On November 6th, Lieutenant A. Banks, Sergeant A. Caruso, Master Police Officer J Smith and Master
Police Officer C. Frazier attended the Community Helpers event at Sycamore Park Elementary.
• On November 7th, Lieutenant A. Banks, Sergeant A. Caruso, Master Police Officer J Smith and Master
Police Officer N. Yarosis attended the Community Helpers event at A. G. Richardson Elementary.
• On November 12th, Chief C. Settle, Deputy Chief N. White, Captain K. Tooley and other members of
the department attended the Veterans Day Service at the American Legion Hall.
• On November 12th, Detective Master Police Officer 1st Class T. Sisk and Master Police Officer J. Smith
attended the Red/Blue project meeting.
• On November 12th – 14th, Detective Master Police Officer V. Grimes attended the Crimes Against
Children Conference in Virginia Beach, Virginia.
• On November 13th, Master Police Officer J. Smith attended the Town of Culpeper Safety Committee
meeting.
• On November 13th, Chief C. Settle, Deputy Chief N. White, and Lieutenant A. Banks attended the
Culpeper Christmas Parade Meeting.
Heroin Update: Reporting from 5 counties in the task force region there has been 22 documented heroin
overdoses of which 5 have resulted in death so far in the 2025 calendar year.
• For the calendar year 2018 there were 156 documented heroin overdoses in which 26 resulted in death.
• For the calendar year 2019 there were 77 documented heroin overdoses in which 17 resulted in death.
• For the calendar year 2020 there were 148 documented heroin overdoses in which 14 resulted in death.
• For the calendar year 2021 there were 159 documented heroin overdoses in which 34 resulted in death.
• For the calendar year 2022 there were 125 documented heroin overdoses in which 19 resulted in death.
• For the calendar year 2023 there were 91 documented heroin overdoses in which 10 resulted in death.
• For the calendar year 2024 there were 60 documented heroin overdoses in which 13 resulted in death.
Overdoses and Overdose Deaths
200 159
156 148
150 125
91
100 77
60
26 34
50 17 14 19 10 13
0
2018 2019 2020 2021 2022 2023 2024
Overdoses Deaths
5
Page 25 of 35
Upcoming Events
• 11/19 – 11/21 – CTEC Presentation for 5th grade students
• 11/23 – CRI Downtown Open House and Tree Lighting
• 11/27 – Thanksgiving/Turkey Trot 5k
• 12/6 – Blue/Red Project at Walmart
• 12/7 – Christmas Parade
• 12/13 – Wreaths Across America event
• 12/18 – Culpeper Rehab Jingle Bell Bash
PERSONNEL UPDATE
• Authorized Sworn Personnel: 51, Current Sworn Personnel: 48
There are currently 3 applicants in the background phase. Once this is completed, they will join the
department.
The department held its Promotional Ceremony and Awards Banquet on October 23rd at Germanna
Community. Members of the department were honored for training achievements, service awards, and
promotions!
Members of the drone team have begun passing their Part 107 flight tests. The entire team is required
to pass this exam.
• Authorized Civilian Personnel: 9, Current Civilian Personnel: 9
COMMUNITY RESOURCE ACTIVITIES
• Mental Health Co-Responder
Currently, there are no co-responders assigned to the department. Chief C. Settle is still working with
Encompass to get the program back on track.
• Joint Neighborhood Watch Meeting
The next meeting is scheduled December 18th at 7 p.m. The guest speaker and topic will be
decided in the upcoming weeks.
• Community Policing
The Culpeper County Drug Court continues to meet each Tuesday. Detective Lieutenant R. McKnight
is the department liaison.
On August 5th, the department launched its Blue Envelope Program. This initiative is to better enhance
interactions between first responders and citizens with Autism, intellectual developmental disorders,
and neurocognitive disorders. Persons wanting to enroll or receive additional information about the
program may contact the department via the non-emergency number or blueenvelope@culpeperva.gov.
• School Watch
o Floyd T. Binns Middle School –Sergeant A. Caruso
o Sycamore Park Elementary School – Lieutenant A. Banks
o Yowell Elementary School – Master Police Officer J. Cole
6
Page 26 of 35
o Farmington Elementary School – Master Police Officer J. Smith
o Epiphany Catholic School – Rotating
o Culpeper Christian School – Master Police Officer J. Smith
o Headstart – Master Police Officer J. Smith
o Keys Academy – Sergeant A. Caruso
• Neighborhood Watch Program
Neighborhood Watch Area CPD Liaison
Belle Court Sergeant A. Moran
Belle Parc Master Police Officer S. Yeiser
Cardinal View Officer A. Parker
Culpeper Commons Officer E. Sweet
Depot District Officer J. Yenchak
Dog Hill Officer A. Rustick
Elizabeth Crossing Officer L. Altman
Franklin Meadows Sergeant E. Grant
Garr Avenue Sergeant W. Hickman
Highpoint K9 Master Police Officer D. Cole
Highview Master Police Officer K. Argueta
Kings Manor Officer K. Payne
Lakeview Sergeant J. Cole
Madison Grove Sergeant C. Campbell
Magnolia Greens Master Police Officer J. Smith
Meadows Officer A. Sain
Mountain Brook (Kingsbrook) Officer N. Yarosis
Pelham’s Reach Officer C. Kesler
Picadilly Circus Officer D. Danks
South East Street Master Police Officer J. Davis
South West Street Master Police Officer A. Cooper
Southridge Master Police Officer A. Otey
Stonechase Officer Z. Wadas
Westbrooke K9 Master Police Officer M. Barone
Willowshade Master Police Officer M. Satterfield
Business Watch Area Liaison
Culpeper Colonnade Detective Master Police Officer M. Hays
Dominion Square Detective Master Police Officer, 1st Class T. Sisk
Downtown/Davis Street K9 Sergeant M. Haymaker/ Master Police Officer
S. Frazier
Meadowbrook Shopping Center Vacant
Southgate Shopping Center Detective Master Police Officer M. Hays
Town Square Shopping Center Detective Sergeant N. McGuckin
The Neighborhood and Business Liaisons continue to make contact with the watch leaders and members
on a regular basis while monitoring the issues or concerns within the watch group area. The following watch
areas reported concerns or issues during the month of October.
Belle Court – Sergeant A. Moran received complaints suspicious persons and drinking in public. Sergeant
A. Moran plans to increase his extra and foot patrols in this area to combat the issue.
7
Page 27 of 35
Highpoint – Master Police Officer D. Cole received complaints of parking violations and juveniles playing
in the roadways. He plans to increase his extra and foot patrols in this area to combat the issue.
• Committees and Organizations
o Culpeper Police Department Peer Support Team (Members – Lieutenant B. Jenkins, Master Police
Officer A. Cooper, Master Police Officer/K-9 D. Cole, Officer D. Danks)
In early October, the Peer Support Team was notified that retired Master Police Officer Mike
Grant had been placed in hospice care, with his children providing for his needs. A team member
was assigned as the primary liaison to the family to offer ongoing support. On October 22nd, the
Peer Support Team coordinated a 1st Responder Parade for retired MPO Mike Grant. The event
drew strong participation from the Culpeper Police Department, the Culpeper County Sheriff’s
Office motor units, the Chesterfield Police Department, and Greene County Sheriff’s Office
motor units, who came together to honor Grant’s lifetime of community service. On November
4th and 5th, members of the Peer Support Team and other officers served as casket guards for
retired MPO Mike Grant during family night and funeral services. The Peer Support Team
continues to monitor the wellness of all CPD employees, providing support and resources as
needed.
o Culpeper Teen Empowerment (Liaison – Master Police Officer J. Smith)
This month’s meeting was canceled. The next meeting is scheduled for December 16th.
o Healthy Culpeper (Liaison – Master Police Officer J. Smith)
Master Police Officer J. Smith attended the Healthy Culpeper meeting on November 12th via
Zoom. The guest speaker for this meeting Laura Hoover, Director of Communications and Grants
at Culpeper County Public Schools. Laura provided an update of the first half of the school year.
o Culpeper Livable Aging Communities (CLAC) (Liaison – Master Police Officer J. Smith)
This meeting was not attended this month.
o Aging Together (Liaison – Master Police Officer J. Smith)
This meeting was not attended this month.
o Culpeper TRIAD (Liaison – Master Police Officer J. Smith)
This month’s meeting is scheduled for November 17th.
o Culpeper Law Enforcement Explorers (Advisors – Master Police Officer J. Cole, Master Police
Officer S. Yeiser, K9 Master Police Officer D. Cole, Officer A. Parker, Detective K. Payne, Officer
C. Kesler, and Officer N. Yarosis)
On September 16th the Explorers learned about Human Trafficking, its myths and misconceptions,
indicators, and how to help victims. On October 7th, Deputy Chief N. White gave a presentation to
the Explorers about his experiences as a criminal attorney, and how his legal training supports his
law enforcement career. On October 21st the Explorers attended the Annual Domestic Violence
Candle Light Vigil hosted by SAFE (Services to Abused Families) in support of the Culpeper
County Domestic Violence and Sexual Assault Task Force. The Explorers did not participate in
any Halloween events. The Explorers did not meet on November 4th in observance of the Election
Day holiday. The next Explorer meeting will be on November 18th.
8
Page 28 of 35
o Domestic Violence Task Force (Liaison – TBD)
o Re-Entry Committee (Liaison – Master Police Officer J. Cole)
Master Police Officer J. Cole attended meetings ono August 20th and September 3rd. The next
Resource Fair is scheduled for October 18th.
EQUIPMENT UPDATE
The department has received all of the new vehicles from FY26. The department’s new critical incident
response vehicle is scheduled to be delivered in the upcoming weeks. The department received its new
Harley Davidson Motorcycle from Americans 911 Foundations on October 30th.
9
Page 29 of 35
Culpeper County Sheriff’s Office
Timothy W. Chilton, Sheriff
14023 PUBLIC SAFETY COURT CULPEPER , VA 22701
OFFICE : 540-727-7520 JAIL: 540-727-3434 RECORDS : 540-727-3400
E-911 Communications: 540-727-7900
Culpeper County Sheriff’s Office
Communications Division – Monthly Report
October 2025
Personnel Update
Staffing levels adjusted slightly during October. The division currently maintains 22 full-time
employees, 2 part-time employees, and 2 employees in training. We experienced one resignation,
involving an employee who separated from the division while still in Field Training.
Recruitment efforts remain active, with four candidates currently in the background investigation
phase. Additionally, the Communications Manager position has been formally advertised and
will remain open until November 21, 2025.
The division continues to emphasize retention, professional development, and structured hiring
to ensure stable coverage, leadership presence, and operational continuity across all shifts.
Training & Development
The Communications Division continued its regular monthly training modules, ensuring that
personnel remain proficient and aligned with operational requirements.
Field Training remained active throughout the month. Two trainees are currently progressing
through the Field Training Program, while one trainee successfully completed Field Training and
has been released as an ECS-I. This contributes to increased shift strength and improved
workload balance.
Technology/Equipment Update
During October, the division identified an issue with the NICE recording software involving
radio traffic overlapping and recording over itself. At no point was audio at risk due to the
system’s built-in redundancy, which functioned exactly as intended.
The root cause appears to be settings-related rather than a hardware problem. The team is
working closely with the vendor to correct the configuration, with resolution expected within two
weeks. Recording performance will continue to be monitored closely.
Page 30 of 35
Culpeper County Sheriff’s Office
Timothy W. Chilton, Sheriff
14023 PUBLIC SAFETY COURT CULPEPER , VA 22701
OFFICE : 540-727-7520 JAIL: 540-727-3434 RECORDS : 540-727-3400
E-911 Communications: 540-727-7900
Generator/UPS Update
- Generator: Passed all weekly tests with no issues.
- UPS System: Functioned properly throughout the month.
September 2025 Call Statistics
Culpeper County Sheriff’s Office (CSO): 4,249
Culpeper Police Department (CPD): 4,769
Culpeper County Volunteer Fire & Rescue Association (CCVFRA): 704
E-911 Handled Calls: 58
Animal Control (ACO): 165
Phone & Text Activity
• 911 Calls: 2110
• Administrative Line Calls: 9830
• Text-to-911 Messages: 2244
• Total Incoming Contacts: 12184
FOIA Requests – October 2025
The Communications Division processed 16 FOIA requests during October. These included
requests for audio recordings, CAD data, and other dispatch-related documentation. All
responses were completed within statutory deadlines, with no extensions required.
Quality Assurance / Quality Improvement (QA/QI)
The QA/QI program continued to expand during October. A total of 15 calls were randomly
selected and reviewed, demonstrating over 99% accuracy across multiple evaluation categories.
Page 31 of 35
Culpeper County Sheriff’s Office
Timothy W. Chilton, Sheriff
14023 PUBLIC SAFETY COURT CULPEPER , VA 22701
OFFICE : 540-727-7520 JAIL: 540-727-3434 RECORDS : 540-727-3400
E-911 Communications: 540-727-7900
The number of monthly reviews will continue to increase as the program grows in scope. The
division anticipates the QA/QI program will be fully implemented and operating at full capacity
by January 2026.
Conclusion
October reflected steady progress across all operational areas within the Communications
Division. Preparations are underway for our December all-hands meeting, which occurs twice
annually and serves as an opportunity to align expectations, share updates, and reinforce
organizational culture.
The division continues to prioritize the expansion of peer support initiatives, supporting staff
wellness and resilience. Additionally, the ongoing growth of the QA/QI program remains a
central focus as we enhance performance standards, strengthen service delivery, and promote
consistent excellence across all call types.
Thank you to the entire team for your continued dedication, professionalism, and commitment to
serving the citizens of Culpeper County.
Page 32 of 35
Culpeper Town Public Safety Committee Notes
24 November 2025
Culpeper County Volunteer Fire Department – Call History
10/28/2025 – 11/24/2025
Total Calls 56 -4
Monthly Meetings 2 +1
Other Fire Department Meetings 14 +8
Monthly Drills 1 0
Training Events 9 -15
Public Education Events 3 -3
Station Duty 18 -3
Total Time Logged 245:02 hours -105.46 hours
Activity Log
28 Oct Culpeper Chamber Board of Directors Meeting
28 Oct Culpeper County Schools Safety Division Meeting
30 Oct Sycamore Park Touch-a-Truck – Pre-School
26 Oct Town/County Interaction Committee
30 Oct Downtown Halloween Event
2 Nov Bi-Monthly Chief’s Meeting
6 Nov 111th Annual Chamber Meeting and Banquet
8 Nov Testing of FF1 HMAO – Practical Test Evaluator
10 Nov Town of Culpeper TRC Meeting
11 Nov Zoom Meeting with Bowman – Jameson Crossing
11 Nov CCVFD Monthly Board Meeting
12 Nov Firefighter 2 State Test – Winchester Career Academy
13 Nov CCVFD Monthly General Membership Meeting
14 Nov Active Shooter Tabletop Training Exercise
15 Nov First Due Dashboard Design Discussion
17 Nov The Culpeper – Hazard Vulnerability Assessment
Tool/Emergency Preparedness Plan Review
17 Nov CCVFRA Monthly Board Meeting
17 Nov Phone Meeting (2) with Bowman – Jameson Crossing
18 Nov Culpeper Chamber Board of Directors Meeting
Page 33 of 35
Culpeper Town Public Safety Committee Notes
24 November 2025
18 Nov Phone Meeting with Bowman – Jameson Crossing
19 Nov CTEC Open House – 5th Grade Field Trip
19 Nov Phone Meeting with Bowman – Jameson Crossing
20 Nov CTEC Open House – 5th Grade Field Trip
20 Nov Phone Meeting with Bowman – Jameson Crossing
21 Nov CTEC Open House – 5th Grade Field Trip
21 Nov Phone Meeting with Bowman – Jameson Crossing
22 Nov CTEC FF1 Practical Training – Louisa County Burn Bldg.
24 Nov First Due Dashboard Hardware Review/Requirements
Multiple Town of Culpeper TRC Meeting – Several emails/phone calls
for Ladder Truck navigation in and around Jameson Crossing
development.
Knox Box Installations WIP
1) 201 Waters Place – Update keys, add additional Knox Box
for commercial side, update maps
2) 421 James Madison Highway - CCPS School Board Office –
Walk through, pre-plan, recommend Knox Box location
3) 14115 Lovers Lane – Culpeper Business Center – location
selection for Knox Box.
4) CCPS Knox Box keys are still on order by CCPS for Fire
Department Access.
5) Willow Shade – 101 & 1-2 Duke Street, discussions ongoing.
Request for a KNOX Box and additional pre-planning of the
buildings.
Training The Training Facility Committee has held multiple interactions
this month to work with FGM Architects on the conceptual
drawing of placing all the training structures and components
on the property that CCPS is allowing us to use. We have
engaged with a Civil Engineering firm to assist with storm water
management, the stream that runs through the property, for the
best utilization and cost effectiveness of the property.
Page 34 of 35
Culpeper Town Public Safety Committee Notes
24 November 2025
Update: Received updated quote on works required by Civil
Engineering Firm – Kimly-Horn. Working with the county to
decipher the report.
Five structures have been offered for Firefighter training.
Notable Fire Responses reports during this month are noted below:
31 Oct. – 14392 Kimber Lane– Furnace fire
03 Nov. – 10095 Montelago Ln – Vehicle into house – Shoring to
prevent structure collapse
06 Nov. – 14215 Eggbornsville Road - House Fire
09 Nov. – 559 James Madison Hwy – Deep fryer fire/Natural Gas leak
12 Nov. – 2500 Summerville Road – 5-acre woods/grassland fire
16 Nov. – Cedar Grove Road – 9-acre woods/grassland fire
22 Nov. – 517 Sperryville Pike – House fire (room and contents)
Inspections 2 follow-up meetings in October and 1 in November, with TJ
Maxx for inspections of the Fire Alarm System due to non-
compliance. Still open.
Submitted by Charles “Jr.” Perryman