3. PRESENTATION BY VIRGINIA TECH CENTER FOR ECONOMIC AND COMMUNITY 2
ENGAGEMENT (VT CECE) ON CULPEPER COUNTY COURTHOUSE
Culpeper Courthouse Pre-Meeting Workshop Packet_V3.pdf
Clerk Note: Attachment added on 4/24/26 at 10:22am.
4. ADJOURNMENT
Adjournment of Meeting
Page 1 of 70
Joint Special Board of Supervisors and Town Council
Meeting
April 30th, 2026
Goal: The goal of this meeting is to provide a clear overview of the courthouse scenarios,
including key considerations, stakeholder input, and insights from comparable case
studies, to ensure all participants have a shared baseline understanding.
The session will also facilitate a discussion to gather perspectives, address questions,
and identify remaining information needs. This discussion is intended to inform future
analysis and decision-making, while helping to educate participants on the advantages
and challenges associated with each scenario.
Agenda
Welcome & Project Overview; Ashley Crouse, VT CECE
[10 •minutes]
Opening remarks and participant introductions
• Overview of meeting purpose and expectations
• Study scope, process, and key inputs to date
Courthouse Needs & Moseley Study Findings; Paul Howard, Culpeper County
[20 minutes]
• Summary of current facility and key constraints
• Implications for site design, layout, and project options
• Discussion and Q&A
o Does this algin with your understanding?
o What is most important to consider?
o Where do you see the biggest challenges?
Evaluation Framework & Case Study Insights; Ashley Crouse & John Provo, VT CECE &
John Accordino, VCU
[20 minutes]
• Overview of evaluation criteria
• Key takeaways from comparable communities
• Implications for courthouse location, design, and community impact
The Virginia Tech Center for Economic and Community Engagement
Page 2 of 70
• Discussion and Q&A
o Do these feel like the right factors to consider?
o What feels most relevant to Culpeper?
o Is there anything missing?
----------------------------------------------Intermission ---------------------------------------------------
Stakeholder Feedback; Ashley Crouse & John Provo, VT CECE & John Accordino, VCU
[20 minutes]
• Summary of stakeholder perspectives across scenarios
• Key themes, areas of alignment, and concerns
• Discussion and Q&A
o What stands out most?
o Where do you agree or disagree?
Wrap-up Discussion & Next Steps; Ashley Crouse, VT CECE
[10 minutes]
• Summary of key themes, reactions, and perspectives shared
• Identification of key considerations and potential risks
• Discussion of questions and remaining information needs
Session Expectations
To ensure a productive and respectful conversation, we ask participants to:
• Engage with an open mind and consider multiple perspectives
• Focus on the information presented and the trade-offs across scenarios
• Share input constructively and allow space for all voices
• Help keep the discussion focused on key considerations and priorities
The Virginia Tech Center for Economic and Community Engagement
Page 3 of 70
Culpeper Courthouse Scenario Workshop
Pre-Meeting Reflection Questions
Reflection questions are included to help you think through the key issues, trade-offs, and
priorities in advance of our discussion. Taking a few minutes to review and consider these
questions will ensure we can use our time together more effectively, focusing on
meaningful dialogue, areas of alignment, and key decisions rather than background
information. Your input will help ground the conversation and support a more productive
and informed discussion.
1. What are the top 2–3 factors that should drive this decision?
2. Which trade-offs feel most acceptable? Which feel most concerning?
3. What is the biggest risk or concern you have about this decision?
4. What key information do you feel is still missing?
The Virginia Tech Center for Economic and Community Engagement
Page 4 of 70
Culpeper Courthouse Scenarios Overview
This document provides an overview of the three courthouse scenarios being considered.
1. Expand the existing courthouse at its original historic downtown site
2. Relocate the courthouse outside the historic downtown core but within the Town of
Culpeper
3. Relocate the courthouse to a site elsewhere in Culpeper County
This document is intended to help stakeholders understand what each scenario means in practical
terms, highlight the key benefits and challenges of each option, and support a more informed and
productive discussion during the workshop.
This is not a recommendation, but rather a tool to help clarify choices. All scenarios have been
evaluated using consistent criteria, including access and convenience, facility performance and
long-term needs, cost considerations, community and economic impacts, feasibility and
implementation, and civic identity and historic role.
Page 5 of 70
Scenario A: Expand at the Existing Downtown Site
The courthouse remains in its current downtown location and is improved over time by expanding
and upgrading the facility in stages. This could include renovating the existing building, adding new
space nearby, or using a combination of buildings that function together to meet long-term needs.
Benefits Challenges
Maintains downtown access and walkability Limited space may constrain design and long-
term growth
Preserves the courthouse’s role as a civic Construction could be complex and disruptive
and historic anchor
Supports existing downtown businesses May be harder to fully meet modern security and
and activity operational needs
Avoids the need to fully relocate court Typically, more expensive per square foot due to
operations site limitations
Maintains downtown access and walkability
Scenario B: Relocate Within the Town (Outside Downtown Core)
A new courthouse is built somewhere else in the Town of Culpeper, outside the historic downtown
area. The specific location is undetermined at this time.
Benefits Challenges
Allows for a modern, purpose-built facility Loss of courthouse as a downtown activity anchor
Improves parking and vehicle access Potential impact on local businesses and foot
traffic
More flexibility to meet long-term space and Requires a clear plan for reusing the existing
security needs courthouse site
Potentially more efficient to operate over Outcomes depend heavily on where the new site
time is located
Scenario C: Relocate to Culpeper County
The courthouse moves to a new site outside the Town, somewhere in Culpeper County. The specific
location is undetermined at this time.
Benefits Challenges
Provides the most flexibility for a long-term Increased reliance on driving (less walkability)
solution
Fewer physical constraints ensures easier to Highest risk of reducing downtown activity
design for security, expansion, and
efficiency
Potentially more predictable construction Requires significant investment or reuse planning
and operating costs for the current site
Represents a larger shift in civic presence and
identity
Page 6 of 70
Culpeper County
Courthouse Study
FINAL REPORT
PROJECT NUMBER 641337
April 24, 2025
Prepared by:
Moseley Architects
Trunk Branch Twig Bud
Timmons Group
Page 7 of 70
Executive Summary
CULPEPER COUNTY – COURTHOUSE STUDY
02 | EXECUTIVE SUMMARY | 1 OF 4
Page 8 of 70
In the summer of 2024, a team lead by Moseley Architects was engaged by Culpeper County to provide a
comprehensive facility study of the Culpeper County Courts reviewing current and future space needs planning for
the 20-year horizon and analysis of existing facilities. The following is a summary of the major findings of the study.
Current & Future Space Shortfall
A Space Needs Assessment was developed from which it was determined that the area of current facilities has a
short fall of 47,159 GSF and a short fall of 68,264 GSF for the space needs in 20 years in the year 2045.
Space for Future Growth
An analysis of caseloads was performed, and it was determined that the courthouse facility will need to provide an
additional two courtrooms to accommodate the anticipated growth in court cases by the year 2045.
CULPEPER COUNTY – COURTHOUSE STUDY
02 | EXECUTIVE SUMMARY | 2 OF 4
Page 9 of 70
Building Security - Circulation
The existing courthouse facility was assessed for
compliance with the Virginia Courthouse Facility
Guidelines and a security issue was identified. The
movement of in-custody detainees through public
spaces was identified in the guidelines to be strictly
prohibited.
Zoning
The team reviewed the existing zoning requirements
for the sites selected and identified the applicable parameters. Part way through the process of study’s development
it was determined that the Town of Culpeper was currently working on rewriting their zoning ordinance. The team
reviewed a draft of the proposed new zoning ordinance and discussed it with the town. It is anticipated that the new
zoning ordinance will be approved later in the year. The options advanced in the study are based on the parameters
of the new zoning ordinance and edits discussed in the meeting that occurred with the Town. Confirmation of the
zoning ordinance edits discussed is necessary for the advancement of the options proposed in this study.
Closing of Cameron Street
Two of the options reviewed require the closing of Camereon Street. This street closure was discussed in several
meetings with the Town of Culpeper.
CULPEPER COUNTY – COURTHOUSE STUDY
02 | EXECUTIVE SUMMARY | 3 OF 4
Page 10 of 70
Building Expansion
Based on the space needs short fall and circulation issues of the existing building, a new structure is required to
contain the majority of the courthouse functions. Three options were developed to accommodate all space needs
in a combined building, on two sites. Budgetary estimates were prepared for the Rough Order of Magnitude (ROM)
project cost for each option with costs ranging from $103 million to $115 million.
Parking
All courthouse options are located in an area of the Town of Culpeper that is identified as a Parking Overlay District,
exempting the courthouse from any zoning parking requirements. Through analysis of the parking utilization, it was
determined that the existing nearby surface parking could accommodate the short-term increase in parking. Long-
term parking increases could be accommodated by two proposed parking structure options which were developed
at different sites located near the courthouse. Budgetary estimates were prepared for the Rough Order of Magnitude
(ROM) project cost for each option with costs ranging from $18.2 million to $36.6 million.
CULPEPER COUNTY – COURTHOUSE STUDY
02 | EXECUTIVE SUMMARY | 4 OF 4
Page 11 of 70
March 3, 2026
Courts Study Update
Culpeper County
Page 12 of 70
Agenda
01 Study Recap 06
02 Space Needs Assessment Update 07
03 Parking Study 08
04 Project Design Variables 09
05 Next Steps 10
Page 13 of 70
Study Recap
Page 14 of 70
CLOSE PORTION OF
OPTION B CAMERON STREET
DEMO EXISTING
BUILDINGS
Existing
Historic Jail
Courthouse
Historic
Jail
Page 15 of 470
VEHICLE SALLYPORT ENTRY
& SECURE PARKING OFF ALLEY
OPTION B
PHASE 1 – NEW
4 LEVELS
CONSTRUCTION 104,000 GSF
PHASE 2 – 3 LEVELS
23,000 GSF
ADDITION
Existing
Historic Jail
Courthouse
COURTHOUSE Historic
ENTRY PLAZA Jail
Page 16 of 570
Space Needs
Assessment
March 2026 Update
Page 17 of 70
Program of Space Needs – First Round
Purpose of Exercise:
Courthouse Elements:120,117 GSF Other Elements:
• To maximize the possible space (2045)
needs (for site test purposes). Victim
• To allow for different Witness
configurations of elements to be
tested. Circuit Court Clerk Circuit
Magistrate Cust. Svc.
Court-
• Each element was programmed rooms
in isolation, with all required Magistrate
spaces included. CJ Services Admin.
• All elements were included in Culpeper
the courthouse. General District Court County Jail
Sheriff
• Total GSF of all elements was Clerk
• 104,410 (2025) Central Shared
• 120,117 (2045) Holding
General District Courtrooms
Decisions made:
J&DR Court Clerk Sheriff
• Option B was preferred.
Admin
J&DR Courtrooms Commonwealth's Attorney CSU
Page 18 of 770
Three-Dimensional
Adjacencies
(Stacking) Staff
Areas
Restricted
Access
Areas
Mixed
Access
Areas
Public
Areas
• Consideration for horizontal and vertical
adjacencies
• Three paths of circulation – public, secure,
mixed
Secure Access
Areas
Page 19 of 870
Program of Space Needs – Second Round
Purpose of Exercise - Efficiencies
• Public - Better defined waiting,
restrooms, and circulation. Courthouse Elements: 97,556 GSF Other Elements:
• Staff - Maximized sharing of (2045)
meeting rooms, break rooms, Victim
toilets, and circulation. Witness
• Courtrooms - Negotiated Commonwealth's
Circuit Court Clerk Circuit
sharing one courtroom between Attorney Magistrate
J&DR and GD. Court-
• Confirmed elements to include: rooms Cust. Svc.
• Elements to relocate inside
the new courthouse:
Shared
▪ Commonwealth's Attorney
▪ Court Service Unit
General District J&DR Courtrooms
▪ Criminal Justice Services Magistrate
• Elements to remain outside: Courtrooms Shared
Admin.
▪ Victim - witness
▪ Magistrate's Customer Culpeper
Sheriff
Service) County Jail
CJ Services Central CSU
• Total revised estimated GSF Holding
• 88,760 GSF (2025) General District Court Shared
• 97,556 (2045) Clerk Sheriff
• Program reduction of 15% (2025) J&DR Court Clerk 19%
Admin reduction
and 19% (2045).
Page 20 of 970
Footprint Reduction
The original footprint
filled all available site
area.
Next steps include
revising the original
Option B.
Page 21 of1070
New Element – Intake and Local Lockup
A local lockup will: Questions:
• Provide a local intake for new arrests by the • Should Culpeper County pursue a stand -
Culpeper Police Department and Culpeper alone intake and local lockup?
County Sheriff's Office;
• Should this element be added to the
• Facilitate local screening for pre - trial courthouse?
alternative programs (Criminal Justice
Services);
• Allow for local release of individuals with
stays of <12 hours (bail, bond, OR releases).
• Stage local arrestees for transfer to either a
new local jail or an outside facility.
• Approximately 6,000 GSF of additional
space required if added to the courthouse.
Page 22 of1170
Parking Study
Findings
Page 23 of 70
PARKING LOT
SUMMARY
Page 24 of1370
ON-STREET PARKING SUMMARY
Page 25 of1470
EXISTING TOWN PARKING UTILIZATION ANALYSIS
Page 26 of1570
WEDNESDAY OBSERVATION
Page 27 of1670
MONDAY OBSERVATION
Page 28 of170
MONDAY OBSERVATION
Page 29 of1870
COMPILED OBSERVATIONS
Page 30 of1970
WEDNESDAY SUMMARY MONDAY SUMMARY
Page 31 of2070
Project Design
Variables
Page 32 of 70
CURRENT SPACE
AVAILABLE
DEMO EXISTING
MAINTAIN BUILDINGS
OPERATIONS AND
ENTRY TO
COURTHOUSE
Existing
Historic Jail
Courthouse
Historic MAINTAIN
MAINTAIN Jail ACCESS TO
OPERATIONS AND BUSINESS
ENTRY TO JAIL PARKING
Page 33 of2270
PROPOSED
CAMERON STREET IS
BUILDING
CLOSED
FOOTPRINT
DEMO EXISTING
BUILDINGS
MAINTAIN
OPERATIONS AND
ENTRY TO
COURTHOUSE
Existing
Historic Jail
Courthouse
Historic MAINTAIN
MAINTAIN Jail ACCESS TO
OPERATIONS AND BUSINESS
ENTRY TO JAIL PARKING
Page 34 of2370
MAINTAIN
OPERATIONS AND
ENTRY TO
COURTHOUSE
Existing
Historic Jail
Courthouse
Historic MAINTAIN
Jail ACCESS TO
BUSINESS
PARKING
Page 35 of2470
WEST STREET IS
TRANSITION FROM
COMMERICAL TO
RESIDENTIAL
Existing
Historic Jail
Courthouse
Historic
Jail
Page 36 of2570
• MAINTAIN WEST
STREET
RESIDENTIAL SET
BACKS
• CREATE PARKING
ALONG WEST
STREET
• CREATE
CENTERED ENTRY
OFF DAVIS STREET
COURTYARD
Existing
Historic Jail
Courthouse
Historic
Jail
Page 37 of2670
Next Steps
Page 38 of 70
Questions for
Next Steps
• The analysis indicates we don’t need a parking garage for
this project, what are the next steps for parking?
• In planning for the new courthouse, does the jail remain?
• Do we include the lockup in the in the space planning?
Page 39 of2870
Next Steps
• Develop Floor Plan Layouts
• Temporary Modifications for Phase 1
• Connection to Historic Courthouse
• Entry Courtyard
Page 40 of2970
Thank You.
QUESTIONS?
Page 41 of 70
Culpeper Courthouse Case Studies
Each case documents economic and redevelopment impacts and the social, symbolic, and
community identity roles that courthouses and civic anchors played in the decision. Each case
helps inform a framework of best practices and lessons learned that can be applied to the Culpeper
planning context.
Case 1: Montgomery County Courthouse – Existing Expansion
Retained downtown, rebuilt and expanded on original site
Case 2: Southampton County Courthouse
Retained downtown, expanded on original site
Case 3: Albemarle County Courthouse — Charlottesville, VA
Retained downtown, expanded adjacent.
Case 4: Augusta County / Staunton Courthouse — Relocated to Verona
Relocation outside the city
Page 42 of 70
Case 1: Montgomery County Courthouse
Town of Christiansburg, Virginia
Retained downtown, Rebuilt and expanded on existing site
The Montgomery County Courthouse is located within an incorporated town, Christiansburg, rather
than a standalone county seat. This town–county governance context closely parallels Culpeper,
where courthouse decisions intersect with downtown land use, civic identity, and shared local
infrastructure considerations.
Economic and Redevelopment Impacts
1. Courthouse siting in Courthouse Square anchors downtown
• The courthouse’s long-standing presence in the historic core has shaped surrounding land
use patterns, pedestrian activity, and the concentration of professional services in
downtown Christiansburg. Regular weekday visitation by county staff, legal professionals,
jurors, and residents conducting civic business continues to contribute to downtown
activity and supports nearby offices, services, and commercial uses.
2. Evolution through Redevelopment
• Each phase of courthouse redevelopment represented a deliberate decision to modernize
facilities while retaining the courthouse at its historic location. The replacement of earlier
courthouse buildings, including the demolition of the 1909 Edwardian courthouse and
construction of the modern facility in the 1970s, reflected changing functional, safety, and
space requirements, while preserving the courthouse’s role within Courthouse Square.
3. Public Safety and Civic Infrastructure
• Facility upgrades and related public safety improvements addressed modern service needs
while continuing to support the courthouse’s central role in local governance and civic life.
Page 43 of 70
Social, Symbolic, and Community Identity Roles
1. Courthouse Square as a Civic Core in Town Identity
• The retention of courthouse functions in the historic center reinforces Christiansburg’s
identity as the seat of county government and justice, even as the town has grown and
evolved since its chartering in 1792.
• The historic district’s listing on the Virginia Landmarks Register and National Register of
Historic Places underscores the communal value placed on downtown’s architectural and
historic resources, within which the courthouse plays a central symbolic role.
2. Preservation of Historic Courthouse Artifacts as Symbolic Memory
• Though the historic courthouse buildings themselves were replaced, the eagle sculpture
from the 1909 courthouse cupola was preserved and placed on the courthouse square as a
civic artifact. This eagle has become a symbol of continuity and heritage, anchoring
collective memory of earlier civic architecture and connecting present-day Christiansburg
with its judicial history.
Lessons for Culpeper
Christiansburg / Montgomery County
Dimension Transferable Lesson
Insight
Sustained courthouse siting in the historic Evaluate how courthouse siting contributes
Downtown
square supported downtown visitation and to downtown economic stability in
Anchoring
land use stability Culpeper
Balancing functional modernization with Consider heritage narrative and community
Evolution vs
preservation concerns shaped sentiment when modernizing historic civic
Preservation
redevelopment choices buildings
Use symbolic artifacts and interpretive
Symbolic Preservation of artifacts (eagle sculpture)
elements in downtown planning to maintain
Continuity reinforces civic memory
identity continuity
Investing in public safety and judicial
Integrated Plan courthouse modernization in
facilities can align with broader civic service
Infrastructure coordination with adjacent civic functions
delivery
Best-practice takeaways
• If the courthouse function changes, define a replacement “identity program” (arts, culture,
or community-serving uses) that preserves the building’s symbolic role while sustaining
downtown foot traffic.
• Prioritize continuity of place where feasible. Modernization or redevelopment that retains
courthouse functions on or near the historic site helps maintain civic identity, access, and
downtown activity.
Page 44 of 70
Case 2: Southampton County Courthouse
Town of Courtland, Virginia
Retained Downtown, Expanded Existing Footprint
The Southampton County Courthouse is situated within the Town of Courtland. This town–county
relationship mirrors Culpeper’s context, in which courthouse investment decisions carry
implications for both county judicial operations and the vitality of a small-town downtown.
Economic and Redevelopment Impacts
1. Courthouse Investment as a Downtown Stabilizer
• The courthouse expansion and renovation represented one of the most significant public
capital investments in Southampton County in recent decades, reflecting a long-term
commitment to modernizing judicial infrastructure rather than a routine facilities upgrade.
• By retaining and expanding the courthouse at its historic downtown site, the County
sustained weekday judicial activity, county employment, and visitor traffic in Courtland.
Court functions, associated offices, and the nearby Sheriff’s Office continued to reinforce
downtown Courtland as the focal point of county governance and public services.
• Unlike the Christiansburg case, this investment followed visible public deliberation and
debate. Board of Supervisors meeting records document extended discussion of project
scope, cost, funding strategies, and preservation priorities, along with public comment
reflecting both concern and support prior to the final decision.
2. Modernization Without Relocation
• Rather than dispersing court operations to a new site, Southampton County chose to
modernize in place. The expanded courthouse integrates secure circulation, updated
courtrooms, administrative offices, and technology infrastructure within a design that
remains visually and spatial connected to Courtland’s historic core.
• This approach minimized disruption to existing land use patterns and preserved the
courthouse’s functional relationship with surrounding civic and governmental uses,
supporting a cohesive civic campus rather than fragmented facilities.
Page 45 of 70
Social, Symbolic, and Community Identity Roles
1. Courthouse as a Generational Civic Asset
• Public comments documented in Board of Supervisors meetings demonstrate that
residents view the courthouse as a symbol of county heritage, justice, and leadership.
Speakers emphasized the courthouse’s role as a generational institution and advocated for
recognizing local judges, public servants, and county history within the renovated facility
through naming, displays, and interpretive elements.
• These discussions reveal that the courthouse was understood not merely as a building, but
as a representation of Southampton County’s civic values and identity, reinforcing its
importance beyond functional considerations.
2. Preservation and Civic Continuity
• By keeping the courthouse in its historic location and preserving its visual prominence,
Southampton County reinforced continuity between past and present civic life,
strengthening community trust and attachment to place. The project’s receipt of a historic
preservation honor award further reflects its success in balancing modernization with
respect for architectural heritage.
Lessons for Culpeper
Dimension Southampton County Insight Transferable Lesson for Culpeper
The courthouse was modernized and Evaluate options that allow courthouse
Courthouse
expanded in place, preserving its historic functions to remain in or closely tied to
location
downtown site Culpeper’s historic core
Retaining the courthouse sustained Recognize courthouse presence as a
Downtown vitality weekday activity and reinforced Courtland’s stabilizing force for downtown activity and
role as the civic center civic use
Residents viewed the courthouse as a Treat courthouse decisions as identity-
Civic identity generational symbol of justice and county defining choices, not solely facilities
heritage decisions
Use transparent, ongoing public
Extensive public discussion reinforced
Public process engagement to build trust around major
legitimacy during a complex capital project
courthouse investments
Integrate preservation goals with
Preservation + Design balanced historic preservation with
operational upgrades rather than treating
modernization contemporary court requirements
them as competing priorities
Best-practice takeaways
• Acknowledge and reinforce the courthouse’s symbolic role. Incorporating heritage,
recognition of local leadership, and civic narratives strengthens public trust and long-term
community support.
Page 46 of 70
Case 3: Albemarle Courthouse Complex
Albemarle County / Charlottesville, VA
Retained downtown, Expanded adjacent
Economic and Redevelopment Impacts
1. Downtown Retention Preserved an Existing Economic Ecosystem
The National Center for State Courts (NCSC) found that maintaining a centralized downtown
courthouse campus produced significant operational and economic efficiencies:
• Attorneys, judges, clerks, court services, probation, treatment providers, and interpreters
benefited from co-location, which reduced continuances, delays, incarceration time, and
attorney fees.
• Early case resolution was facilitated by spontaneous interaction between defense attorneys
and prosecutors, reducing court time and public costs.
• Adjacent court services increased compliance with court-ordered rehabilitation and
reduced recidivism, producing downstream cost savings for law enforcement and
detention.
• The courthouse functioned as a weekday economic anchor, sustaining downtown foot
traffic and supporting professional services, food establishments, and support functions.
2. Relocation Offered Only Modest Development Potential
Stantec’s cost-benefit analysis concluded that:
• Keeping courts downtown was least expensive and economically neutral (it preserved value
rather than created new value)
• Relocating courts was more expensive and offered only modest development stimulus,
largely symbolic rather than market-driven.
• The courts themselves were not expected to generate enough spending to anchor
meaningful retail or restaurant development in a new location
• The primary redevelopment lever would be public parking infrastructure, not the courthouse
itself.
Page 47 of 70
Social, Symbolic, and Community Identity Role
1. Court Square as Albemarle’s Historic Civic Core
• The NCSC report explicitly documents the courthouse’s identity function. Courts have
operated in Court Square since 1762 with hosting figures such as Jefferson, Madison, and
Monroe. The courthouse provides a “significant historical community image” and “historic
court dignity”.
• Public and stakeholder surveys showed 83.3% opposed relocation and 63.5% strongly
supported staying downtown, citing centrality, access, and continuity
• The downtown courthouse represented stability, legitimacy of the justice system, continuity
of civic memory.
• Relocating risked eroding this identity capital. The County was advised that relocation
would require a public marketing campaign to rebuild legitimacy.
2. Civic Access and Equity Considerations
• Public transit was sufficient downtown but inadequate at the relocation site.
• Stakeholders emphasized that relocation would disadvantage residents without vehicles.
Lessons for Culpeper
Dimension Albemarle Insight Transferable Lesson
Courts sustain professional/service
Evaluate preservation value, not just catalytic
Economic ecosystems more than they create new
potential
markets
Pair relocation with a strong complementary
Courts alone rarely drive private
Redevelopment anchor (e.g., major employer, arts hub, or
development
parking investment)
Courthouse identity matters deeply to Treat courthouse decisions as identity planning,
Symbolic
public trust not just land use
Access Location affects equity of justice access Map transit, walkability, and user burden
Process Public legitimacy shapes success Measure and manage community acceptance
Best-practice takeaways
• Treat the courthouse decision as a campus strategy (phasing, adaptive reuse, and
adjacency) rather than a binary “move vs. stay.”
• Quantify and describe downtown continuity benefits (weekday activity and adjacent
civic/support uses) even when the main justification is security/ADA.
Page 48 of 70
Case 4: Verona Courthouse
Staunton/Verona, VA
Relocated outside the city
Economic and Redevelopment Impacts
1. Expanded Judicial Infrastructure with Operational Efficiencies
• The new Augusta County Courthouse, currently under construction, is a 124,000-square-
foot, four-story facility designed to house eight courtrooms, offices for more than 100 staff,
support spaces, and secured parking and circulation areas that the historic courthouse
could not accommodate.
2. Broader Economic and Access Footprint
• The Verona site was selected for its transportation accessibility. This location improves
countywide access for legal professionals, staff, and citizens from across the region,
potentially reducing travel times compared with downtown Staunton.
• Construction activity itself has created direct economic impacts through local contracting,
and is likely to continue to generate economic activity through project completion.
• However, relocating the courthouse outside of the downtown core also introduced the risk
that weekday foot traffic, and related support spending, could shift away from Staunton’s
historic business district.
Social, Symbolic, and Community Identity Roles
1. Historic Civic Identity Grounded in the Downtown
• The 1901 Staunton courthouse, situated on a site with court functions dating back to 1747
had long been a defining element of the historic downtown streetscape. Their presence
contributed to the downtown’s visual identity, civic continuity, and cultural memory for
residents.
• The decision to relocate was not made lightly. Opposition argued that court functions had
long served as a cornerstone of downtown activity, helping to sustain pedestrian flow,
Page 49 of 70
nearby commercial activity, and the presence of professional services. The relocation was
seen by some as a potential loss of a civic anchor and an important piece of the historic
identity that distinguished Staunton’s central business district.
2. Groundbreaking Ceremony and Symbolic Transition
• When construction began, a groundbreaking ceremony was scheduled to symbolize a
collective investment in the county’s judicial future and acknowledge the significance of the
courthouse as a civic institution.
• The architectural design reflects the civic architectural language of the historic courthouse.
3. Evolving Identity and Downtown Adaptation Conversations
Debates about the fate of the historic courthouse and adjacent properties have catalyzed broader
conversations about downtown Staunton’s identity. Preservation advocates have emphasized:
• Adaptive reuse strategies that keep historic buildings active, relevant, and integrated
• The importance of economic and cultural programming that can sustain or replace
traditional courthouse–driven activity, and
• Recognition that civic identity can evolve while preserving architectural heritage.
Lessons for Culpeper
Dimension Staunton Insight Transferable Lesson
Large, modern facilities can improve Conduct forecasting of courthouse–
Development courthouse operational capacity, but generated demand and develop backfill
impact relocation may shift economic activity away strategies for downtown if relocation
from historic cores occurs
Historic courthouses serve as anchors of place Embed identity preservation and design
Historic identity
memory and civic continuity continuity into redevelopment strategies
Ceremonies and design language can mediate
Community Use civic rituals and architectural cues to
transitions by reinforcing civic values even as
transitions signal continuity, not abandonment
functions relocate
Transportation access matters for equity and Evaluate relocation impacts on both
Access
regional connectivity downtown and broader community access
Best-practice takeaways
• If functions relocate, pair the decision with a downtown backfill plan so the community
does not experience “anchor removal” without a replacement.
• Use referendum/public process outcomes as impact data (not just politics): it is evidence
of community priorities and risk tolerance.
Page 50 of 70
Survey and Interview Analytical Synthesis
Key Stakeholder Group Takeaways
March 2026
This document analyzes key stakeholder feedback regarding the redevelopment of the
Culpeper Courthouse. Culpeper County engaged the Virginia Tech Center for Economic
and Community Engagement (VT CECE) to evaluate three potential scenarios: (1)
expanding and modernizing the existing courthouse in historic downtown, (2) constructing
a new courthouse within the Town of Culpeper but outside the historic downtown, and (3)
constructing a new courthouse elsewhere in Culpeper County.
To inform this effort, VT CECE partnered with Culpeper County to distribute a virtual
Culpeper Courthouse Community Impact Survey via QuestionPro to downtown residents
and merchant groups, receiving 62 responses (42 complete and 20 partial) between
February 19th and March 12th. In addition, 12 stakeholder interviews were conducted to
gather more in-depth perspectives from community, business, and government
representatives.
This analysis integrates findings from both survey responses and stakeholder interviews.
Survey data provides broad, quantitative insight into the perspectives of downtown
residents and merchant groups, while interviews offer deeper qualitative context from a
wider range of stakeholders, including organizations operating within, connected to, and
outside of the Town. The findings are intended to support decision-making by clarifying
considerations rather than recommending a specific outcome.
Question 1: How would you describe your relationship to Culpeper?
The survey respondent group includes a mix of town and county residents (27 and 26
responses, respectively), along with property owners (27) and business owners located in
both the town (26) and county (11). Additional responses came from employees (12),
government staff (10), and legal system employees (7). No respondents identified as
visitors, indicating the data reflects individuals with ongoing ties to Culpeper. In total, there
were 147 selections across categories, exceeding the number of individual respondents,
which confirms that respondents selected multiple categories and hold overlapping roles.
Notably, town-based stakeholders, including town residents and town business owners,
are slightly more represented than their county counterparts.
Page 51 of 70
Other, 1
Property owner, 27 Resident (Town), 27
Legal system employee, 7
Government employee, 10 Resident (County), 26
Employee in Culpeper, 12
Business owner (County), 11 Business owner (Town), 26
Figure 1: Respondent Relationship to Culpeper
Interview participants represent a diverse mix of backgrounds and connections to
Culpeper, including long-time residents, newcomers, and individuals who have returned
after careers elsewhere. They span a wide range of roles, including public safety, legal and
judicial services, local government, economic development and downtown revitalization,
and community-based services. Across interviews, participants often described “wearing
multiple hats,” reflecting involvement in various professional, civic, and volunteer roles
over time. This combination of personal ties and professional experience provides a well-
rounded perspective on Culpeper’s growth, community dynamics, and the potential
impacts of courthouse-related decisions.
Question 2: How frequently do you interact with the courthouse?
The largest share of survey respondents reported interacting with the courthouse on a
yearly basis (19), followed by those who never interact with it (14), and, in contrast, those
who engage on a monthly basis (12). This distribution may indicate that courthouse
interactions are often need-based rather than routine, while a smaller group relies on the
courthouse more consistently, likely due to professional or recurring obligations.
Page 52 of 70
Daily, 8
Never, 14
Monthly, 12
Yearly, 19 Quarterly, 7
Figure 2: Frequency of Courthouse Use
Interviewees described varying levels of interaction with the courthouse based on their
roles, ranging from regular and direct engagement to more periodic or indirect involvement.
Those in legal, public safety, and government-related roles indicated more consistent
interaction as part of their professional responsibilities, while others engage with the
courthouse less frequently, typically in relation to specific services, cases, or community
needs.
Question 3: How important is the courthouse in Culpeper beyond its judicial function?
The majority of survey respondents indicated that the courthouse is very important to
Culpeper beyond its judicial function (39), followed by those who view it as slightly
important (11), with few respondents indicating it is not important (4).
Interview findings present a more nuanced perspective. Stakeholders closely connected to
downtown and community development similarly describe the courthouse as central to
Culpeper’s identity, economic ecosystem, and sense of place. However, other
interviewees, particularly those focused on operational or government functions, view the
courthouse primarily as a functional facility with more limited broader community
influence. This variation suggests that perceptions differ based on stakeholder proximity to
downtown, professional role, and lived experience. This contrast in perspectives is
illustrated in the following stakeholder quotes:
“The courthouse is part of the ‘DNA’ of Culpeper… it is central to how the community sees
itself.”
“Primarily a functional building… not something people actively notice.”
Page 53 of 70
Question 4: In what ways does the courthouse contribute to Culpeper today? (select all
that apply)
When asked in what ways the courthouse contributes to Culpeper today, survey
respondents indicate that it is most commonly viewed as contributing through
employment (46), which may also reflect its role in supporting local government (40), as
well as serving as a civic landmark (45). A notable number of respondents also identified its
role in supporting downtown businesses (29) and attracting visitors (20).
50
45
Number of Responses
40
35
30
25
20
15
10
5
0
Supports Provides Serves as a Supports local Attracts Has minimal Other
downtown employment civic landmark government visitors broader
businesses impact
Figure 3: Ways the Courthouse Currently Contributes to Culpeper
Of the smaller number of “other” responses (3), several emphasized the courthouse’s
historical and architectural significance, noting its role as a contributing structure to the
town’s character.
Question 5: Please briefly describe the courthouse’s role in Culpeper today.
Survey participants were given the chance to briefly describe the role that the courthouse
plays in Culpeper today. Responses indicate that the courthouse serves as the central hub
for judicial and legal functions in Culpeper, including court proceedings, records
management, and access to government services. Beyond its functional role, many
respondents describe it as a historic landmark and civic anchor that contributes to the
town’s identity, character, and downtown environment. It is also frequently noted as
supporting local economic activity by bringing people into the area and maintaining
connections to surrounding businesses. These perspectives are illustrated in the following
stakeholder quotes:
“It is the most iconic and historically significant building in the Town of Culpeper and in
Culpeper County more generally, in my opinion. Something attractive about Culpeper is its
Page 54 of 70
historic 'core' which attracts people to this area and improves the quality of life for residents
and visitors.”
“It houses all local courts and related services, including the Clerk's Office for the Circuit
Court. The Clerk's Office also houses and records all land records and other governmental
records for public access.”
Interviewees similarly emphasized the courthouse’s dual role as both a functional
government facility and a defining community asset. Several noted its importance as an
anchor for downtown activity and its connection to surrounding businesses and services.
At the same time, some interviewees placed greater emphasis on operational limitations,
including space constraints, aging infrastructure, and challenges meeting modern security
and circulation needs. These perspectives are illustrated in the following stakeholder
quotes:
It’s not just a legal facility; it’s a symbol of community governance & civic pride.”
“It is the center of judicial processes, land records, and related functions for Culpeper
County.”
Question 6: Please rate the potential impact of expanding and modernizing the courthouse
at its current historic downtown location on impact on downtown businesses, accessibility
for residents, traffic and congestion, convenience, contribution to Culpeper’s identity, long-
term sustainability, and overall community benefit.
Survey responses indicate positive perceptions of expanding and modernizing the
courthouse at its current downtown location across most factors. The strongest positive
impacts are seen in contribution to Culpeper’s identity (25 very positive), accessibility (23
very positive), and impact on downtown businesses (22 very positive). Convenience (21
very positive) and overall community benefit (20 very positive) also received largely
favorable ratings.
However, responses are more mixed regarding traffic congestion, where 26 of respondents
indicated negative impacts.
Page 55 of 70
Community benefit
Sustainability
Identity
Convenience
Traffic
Accessibility
Downtown businesses
-30 -20 -10 0 10 20 30 40 50
Number of Responses
Very Negative Somewhat Negative Somewhat Positive Very Positive
Figure 4: Perceived Impacts of Expanding and Modernizing the Existing Courthouse in the
Town of Culpeper
Interviewees similarly highlighted the benefits of maintaining a downtown location,
particularly for supporting local businesses, preserving community identity, and
maintaining accessibility. However, interviews introduce more pronounced concerns about
feasibility than reflected in survey responses. These include physical space limitations,
construction disruption, parking constraints, and the ability of the current site to
accommodate long-term growth and modern facility needs. These perspectives are
illustrated in the following stakeholder quotes:
“Keeping the courthouse within the downtown district preserves the cultural and historical
integrity of Culpeper.”
“Expansion of the existing courthouse is suboptimal… a 50-year plan is needed.”
Question 7: Please rate the potential impact of building a new Courthouse within the Town
of Culpeper, outside the historic downtown on the impact on downtown businesses,
accessibility for residents, traffic and congestion, convenience, contribution to Culpeper’s
identity, long-term sustainability, and overall community benefit.
When asked about building a new Courthouse within the Town of Culpeper, survey
responses indicate more mixed perceptions. Accessibility (24 positive) and long-term
sustainability (23 positive) received more favorable ratings, along with overall community
benefit (23 positive). However, impacts on downtown businesses are evenly split between
positive (19) and negative (23) responses, and contribution to Culpeper’s identity is viewed
more negatively overall (25 somewhat or very negative).
Page 56 of 70
Community benefit
Sustainability
Identity
Convenience
Traffic
Accessibility
Downtown businesses
-30 -20 -10 0 10 20 30
Number of Responses
Very Negative Somewhat Negative Somewhat Positive Very Positive
Figure 5: Perceived Impacts of Building a New Courthouse Within the Town of Culpeper
Outside the Historic Downtown
Interview findings closely align with this balanced perspective and often frame this option
as a potential compromise. Stakeholders note that a well-selected site within Town limits
could preserve proximity to downtown, maintain economic connections, and allow for
improved design, parking, and expansion capacity. At the same time, interviews reinforce
concerns that moving away from the historic core could weaken the courthouse’s symbolic
connection to Culpeper’s identity if not carefully planned.
Question 8: Please rate the potential impact of building a new Courthouse outside of Town,
within Culpeper County on the impact on downtown businesses, accessibility for
residents, traffic and congestion, convenience, contribution to Culpeper’s identity, long-
term sustainability, and overall community benefit.
Survey responses indicate more negative perceptions of building a new courthouse outside
of Town within Culpeper County. Impacts on downtown businesses (37 negative) and
contribution to Culpeper’s identity (28 negative) are viewed most negatively. Accessibility
(30 negative) and convenience (28 negative) also received predominantly negative ratings.
In contrast, traffic and congestion is viewed more positively (32 positive), and long-term
sustainability shows more favorable responses overall (26 positive).
Page 57 of 70
Community benefit
Sustainability
Identity
Convenience
Traffic
Accessibility
Downtown businesses
-50 -40 -30 -20 -10 0 10 20 30 40
Number of Responses
Very Negative Somewhat Negative Somewhat Positive Very Positive
Figure 6: Perceived Impacts of Building a New Courthouse Outside the Town of Culpeper,
within Culpeper County
Interview perspectives on the Courthouse locating to Culpeper County are more mixed.
Some stakeholders emphasize opportunities for improved efficiency, space for long-term
planning and expansion, and the ability to co-locate government services. Others express
strong concerns about loss of downtown economic activity, disruption on the existing
network of legal and supporting services, and transportation barriers for individuals without
reliable access to a vehicle.
At the same time, interviews introduce a more supportive perspective from operational and
government-focused stakeholders, who highlight the advantages of a county location for
long-term planning, security, expansion, and potential consolidation of government
services. These perspectives are illustrated in the following stakeholder quotes:
“If land is available to the county… it makes sense to design a courthouse complex that
meets modern needs.”
“Moving the courthouse away… would diminish the vibrancy of downtown Culpeper.”
Question 9: Are there any additional strengths or limitations that you would like to discuss?
Survey respondents who provided additional strengths or limitations highlighted the
importance of long-term, phased planning, coordination between courthouse decisions
and jail or broader government facility needs, and the potential to develop a consolidated
government complex. Survey participants also raised the opportunity for adaptive reuse of
the existing courthouse if relocated, suggesting uses such as public space, museum, retail,
or consolidated government offices. Additionally, some comments emphasized the need to
Page 58 of 70
carefully consider site selection, including parcel size, future expansion capacity, and
alignment with surrounding assets such as trails or adjacent civic spaces. These
perspectives are illustrated in the following stakeholder quotes:
“If a new courthouse is built outside the town the old building could be used to consolidate
county services/offices now spread among several buildings.”
“As a legal firm employee, the convenience and presence of the courthouse is crucial to
our daily dealings with all aspects of the law. No need to reinvent the wheel. Leave it where
it is!”
Interview findings reinforce several key themes identified in the survey, including the
importance of long-term planning, coordinated government services, and flexibility to
accommodate future growth. Many interviewees also identified opportunities to repurpose
the existing courthouse if relocated, suggesting uses such as a museum or heritage site,
public or civic space, consolidated government offices, or retail and mixed-use
development that continues to support downtown activity and preserve its historic
character.
Question 10: Using a rating of 1–5, how do you believe each courthouse location option
would affect the following groups or places? (1 = very positive, 2 = very negative)
Survey responses indicate that expanding and modernizing the courthouse at its current
downtown location is viewed most positively for downtown businesses, visitors, property
values, and legal professionals, with an average rating of 4, suggesting perceived benefits
tied to its central location and existing economic activity.
Building a new courthouse within the Town but outside the historic downtown reflects more
moderate perceptions across survey respondents, with average ratings of 3 across most
categories.
In contrast, building a new courthouse outside of Town is more frequently associated with
lower ratings for downtown businesses, visitors, and town-based stakeholders, averaging
2, while impacts related to traffic, county residents, and some operational considerations
remain more neutral, with average ratings of 3.
Page 59 of 70
Table 1: Average Ratings of Perceived Impacts to Groups by Courthouse Scenario
Group Downtown (Current Site) Town (Outside Downtown) County (Outside Town)
Downtown Business 4 3 2
County Business 3 3 3
Town Residents 4 3 2
County Residents 3 3 3
Gov. Employees 3 3 3
Legal Professionals 4 3 2
Visitors 4 3 2
Property Values 3 3 3
Traffic 3 3 3
Interviewees were not asked to rate impacts numerically; however, their responses provide
important context on how each scenario may affect different groups and systems.
Interview stakeholders consistently noted that maintaining the courthouse downtown
supports existing relationships with nearby businesses, particularly restaurants, law
offices, and retail, which benefit from steady weekday foot traffic. This option was also
seen as reinforcing accessibility for town residents, legal professionals, and those who rely
on proximity or walkability.
Relocating the courthouse within Town was generally viewed as a middle-ground option,
with more limited disruption to the local economy while potentially improving parking,
circulation, and space for expansion. However, interviewees noted that impacts would
depend heavily on the specific site and its connectivity to downtown.
In contrast, relocating the courthouse outside of Town was frequently associated with
reduced interaction with downtown businesses and potential declines in foot traffic,
particularly affecting small businesses and legal services clustered near the current site. At
the same time, some stakeholders identified potential benefits, including improved traffic
conditions, greater space for co-located government services, and more efficient
operations. These perspectives are illustrated in the following stakeholder quotes:
“Where the courthouse is located affects the steady weekday foot traffic that keeps nearby
small businesses… consistently busy.”
“If the new location is large enough… growth can occur in an anticipated, coherent, and
economical manner.”
Page 60 of 70
Question 11: Which groups would be most affected by courthouse relocation?
Survey responses indicate that the groups most affected by courthouse relocation are legal
professionals (30) and downtown businesses (29), followed by residents in Town (24).
Government employees were also identified by a notable number of respondents (18).
Fewer respondents identified residents in the County (8), property owners (8), or visitors (5)
as most affected. Overall, survey responses suggest that impacts are perceived to be most
concentrated among those directly tied to downtown economic activity and the legal
system.
Interview responses reinforce these findings while adding nuance around specific
populations. Many highlighted the need to consider elderly individuals, people with
disabilities, and those reliant on public transportation. These perspectives are illustrated in
the following stakeholder quotes:
“Travel beyond 10 minutes becomes significantly harder for some populations.”
“Law offices and services cluster near the courthouse.”
Question 12: How important are walkability, accessibility for elderly and disabled,
proximity to other government services, safety and security, and convenience when
selecting a courthouse location?
Survey participants were asked to indicate the importance of walkability, accessibility for
elderly and disabled, proximity to other government services, safety and security and
convenience were to the courthouse location. Survey responses indicate that accessibility
for elderly and disabled individuals (88.37% very important) and safety and security
(90.70% very important) are the most highly prioritized factors when selecting a courthouse
location. Convenience (60.47% very important) and walkability (58.14% very important) are
also viewed as important by the majority of respondents.
Question 13: Are there particular populations, communities, businesses, customers that
should be considered when evaluating these scenarios?
Several populations were identified for additional consideration, particularly those with
direct reliance on courthouse access and surrounding services. Frequently noted groups
include legal professionals, law enforcement, elderly individuals, people with disabilities,
and those with limited mobility or reliance on public transportation. Survey respondents
also identified broader community groups such as government employees, small business
owners, and individuals who regularly access court services, including lower-income or
vulnerable populations. Many noted that impacts extend to all residents and taxpayers,
underscoring the need to consider both town and county perspectives.
Page 61 of 70
These viewpoints are illustrated in the following stakeholder quotes:
“Ultimately all County taxpayers (which includes Town residents) should be fully aware of
the impacts - both financial and otherwise especially if a referendum is required.”
“Where the courthouse is located affects the steady weekday foot traffic that keeps nearby
small businesses, especially coffee shops and lunch spots, consistently busy. It also
impacts how easy it is for lower income and historically marginalized residents to access
court services without added transportation costs or logistical strain.”
Interview findings reinforce these perspectives, highlighting similar populations and
considerations related to access, community impact, and connections to surrounding
businesses and services.
Question 14: Which courthouse location would provide the best overall access to court
services?
The majority of survey responses indicate that remaining on the current site in historic
downtown and expanding and modernizing the courthouse would provide the best overall
access to court services (25).
New Courthouse in County, 9
Expand & Modernize, 25
New Courthouse in Town, 9
Figure 7: Preferred Courthouse Location for Access to Court Services
Page 62 of 70
Question 15: Please rank accessibility, cost to taxpayers, economic impact, community
identity, convenience, expansion space, long-term flexibility in order of importance when
deciding courthouse location.
Where 1 is most important and 7 is least important, survey responses indicate that
accessibility (average rank 3.33) and cost to taxpayers (3.20) are among the highest-priority
factors when deciding courthouse location. Economic impact (3.85) and convenience
(4.00) fall in the middle range of importance. Community identity (4.56), long-term
flexibility (4.24), and expansion space (4.81) are generally ranked lower on average, though
responses show some variation, with a portion of respondents still identifying these as
higher priorities.
Table 2: Average Rankings of Factors by Importance
Factor Average Rank
Accessibility 3.33
Cost to taxpayers 3.20
Economic impact 3.85
Community identity 4.56
Convenience 4.00
Expansion space 4.81
Question 16: Looking 20–30 years ahead, what should decision-makers be prioritizing
when planning the location of the next courthouse?
Survey respondents consistently emphasize growth, particularly increasing population, a
central consideration, along with the need to ensure sufficient space for expansion and the
ability to “grow in place.” Cost is also frequently noted, with survey respondents
highlighting the importance of making long-term investments that avoid the need for future
relocation or reinvestment.
Accessibility, including proximity to other government services and public transportation, is
also identified as critical. As well as emphasizing maintaining Culpeper’s historic identity
and supporting downtown vitality. These perspectives are illustrated in the following
stakeholder quotes:
“Community impact. Maintaining the historic identity of the town.”
“Account for room to further expand, renovate, and add additional government functions.”
Interview findings strongly align with these themes highlighting the importance of planning
for long-term growth, integrating courthouse decisions with broader government
infrastructure (including jail and administrative services), and ensuring flexibility to adapt
Page 63 of 70
to technological and operational changes over time. These perspectives are illustrated in
the following stakeholder quotes:
“Future demand will exceed the current footprint.”
“Continued reinvestment in old buildings becomes inefficient.”
Question 17: What is the most important factor decision-makers should consider when
determining the courthouse location?
When asked to discuss the most important factor decision-makers should consider survey
respondents stated accessibility, ensuring access for all residents, including those with
limited transportation options.
Cost to taxpayers is also a commonly cited priority, along with the need to plan for future
growth, expansion, and long-term flexibility. Survey respondents continue to emphasize
the importance of maintaining Culpeper’s historic identity and downtown presence, as well
as considering economic impacts on surrounding businesses and the broader community.
These perspectives are illustrated in the following stakeholder quotes:
“Keeping Culpeper identity as small town for people, tourists, citizens, small businesses.”
“The cost to taxpayers and the impacts on surrounding properties”
Interview responses reflect similar priorities with continued emphasis on accessibility,
cost, and planning for future growth. Interviewees more frequently frame these within a
long-term planning context, emphasizing the need to avoid short-term solutions that may
require reinvestment. Stakeholders also highlight the importance of site functionality, such
as space for expansion, co-location of government services, and operational efficiency.
While community identity and downtown connections remain important, interviewees
more often balance these considerations with practical constraints related to
infrastructure, capacity, and long-term viability. These perspectives are illustrated in the
following stakeholder quotes:
“The County will get only one chance to get this right.”
“Future needs, expansion availability, and current and future costs must be factored into
any decision.”
Question 18: Please share any additional thoughts or concerns about the courthouse
location decision.
Additional thoughts included at the end of the survey highlight the importance of balancing
preservation of community character with practical considerations such as growth, cost,
Page 64 of 70
and functionality, while recognizing the long-term implications of the decision. These
perspectives are illustrated in the following stakeholder quotes:
“Proximity to Town is important, but having a parcel large enough for a series of multiple
expansions in the coming decades is paramount. The County will get only one chance to
get this right. If it fails, our community will pay the price in perpetuity for waste of every
related resource.”
“The Town's reliance on tourism is significant. If the County makes decisions that cause the
charm and character of the Town to be erased or, at the very least compromised, visitors
will no longer flock to a Town that looks like what they are trying to escape in Arlington,
Fairfax or Manassas. The financial impact of that will put a larger tax burden on Town
residents.”
Interview responses reinforce these themes, with stakeholders emphasizing the
importance of long-term, forward-looking decision-making. Similar to survey respondents,
interviewees highlight the need to balance community identity and downtown vitality with
practical considerations such as space, infrastructure, and operational needs. Additional
emphasis is placed on thoughtful site selection, including adequate room for expansion,
parking, and coordination with related government facilities. Overall, interviewees stress
the importance of making a well-informed decision that considers both immediate needs
and long-term impacts on the community.
Page 65 of 70
Overall Stakeholder Insights
Several key themes emerge consistently across both survey responses and stakeholder
interviews.
Community Identity vs. Facility Capacity
Stakeholders widely recognize the courthouse as a defining feature of Culpeper’s historic
downtown, contributing to its character, tourism appeal, and sense of place. At the same
time, both survey respondents and interviewees acknowledge that the current facility may
not fully meet modern operational needs, including space, security, and circulation. This
creates a tension between preserving the courthouse’s symbolic and economic role in
downtown and ensuring it can effectively serve its core judicial functions.
While stakeholders frequently referenced “the courthouse” as a contributor to community
identity, there is an important distinction between the historic courthouse fronting W. Davis
Street and the later addition along W. Cameron Street. The historic courthouse is widely
understood to be a defining feature of downtown Culpeper’s character and is highly
unlikely to be removed under any scenario. As such, its contribution to sense of place,
tourism appeal, and community identity would remain intact regardless of future
operational decisions.
In contrast, the courthouse addition along W. Cameron Street is generally not perceived to
carry the same historic or aesthetic value, and its removal or redevelopment would likely
have minimal impact on how stakeholders perceive downtown character.
Accessibility vs. Court System Efficiency
Maintaining a central, walkable location is seen as critical for accessibility, particularly for
individuals who rely on proximity, public transportation, or have limited mobility. However,
alternative locations outside of downtown are often associated with opportunities for
improved traffic flow, parking, and the ability to co-locate government services.
Stakeholders consistently note that these benefits may come at the cost of reduced
accessibility for certain populations and decreased interaction with downtown businesses.
Immediate Needs vs. Long-Term Planning and Growth
Across both data sources, there is strong emphasis on the importance of long-term
planning. Stakeholders frequently express concern about making a decision that
addresses immediate needs but creates limitations in the future. Considerations such as
population growth, expansion capacity, and evolving service needs are viewed as critical,
with many emphasizing that the County has a limited opportunity to “get it right” and avoid
future reinvestment.
Page 66 of 70
Downtown Economic Support vs. Countywide Development Opportunities
The courthouse plays a key role in generating consistent daytime activity in downtown
Culpeper, supporting nearby restaurants, retail, and legal services. Relocating the
courthouse would likely shift, rather than eliminate, this activity, redistributing economic
impacts to other areas of the County. However, stakeholders note that this shift would not
be evenly experienced. Downtown businesses and town-based stakeholders are expected
to face more immediate and direct impacts, while potential benefits such as improved
infrastructure, expanded facilities, or new development opportunities may occur in other
parts of the County.
Page 67 of 70
Potential Economic Shifts from Courthouse Relocation
Important Disclaimer: The estimates below are based on a set of scenarios and are intended to
illustrate the potential scale and distribution of economic activity that could shift if the courthouse
is relocated. These figures do not represent a net loss to the regional economy, but rather a likely
redistribution of activity within Culpeper and surrounding areas. This analysis does not account for
potential redevelopment or longer-term market adjustments. The analysis relies on secondary data
sources, including business location data, estimated sales volumes and jobs, and industry
patterns. They should be interpreted as planning-level estimates. As such, these figures are not
intended to represent exact outcomes, but rather to provide a general sense of potential impacts.
Estimated Downtown Economic Snapshot
Using a refined dataset of downtown Culpeper businesses, focused on those most closely
associated with courthouse-related activity, estimated sales and employment data were compiled
to represent current economic conditions in downtown Culpeper.
• Total Estimated Downtown Sales Activity: $270 million
• Total Estimated Downtown Employment: 1,300 jobs
Together, these figures provide a baseline for understanding how changes in courthouse location
may influence downtown economic patterns.
Sectors Overview and Assumptions
Building on this baseline, downtown businesses were grouped into key sectors based on industry
type, estimated sales, and employment. This approach helps illustrate how different types of
businesses may respond to changes in courthouse location.
Table 1: Downtown Economic Activity by Sector, 2024 Data Estimates
Number of Estimated Estimated Assumed
Sector Embedded Industries Rationale
Businesses Sales Jobs Shift
Legal, Real Estate, High reliance on
Professional
Accounting, 70 $128 M 500 25%-40% courthouse
Services
Administrative Services proximity
Dependent on
Restaurants & Full-service
30 $89 M 580 10%-20% daytime foot
Food Services restaurants, cafes, bars
traffic
Indirect
Retail Trade Shops, specialty retail 35 $54 M 220 10%-15% dependence on
worker presence
*Data sources include Lightcast & DatabaseUSA business listings.
Page 68 of 70
Estimated Economic Activity Shift
Based on these sector characteristics, the following scenarios estimate the potential range of
economic activity that could shift under different conditions.
Table 2: Scenario-Based Direct Economic Activity Shift by Sector
Estimated Estimated
Sector Low Scenario Moderate Scenario High Scenario
Sales Jobs
Professional $32.0M / 125 jobs $41.6M / 163 jobs $51.2M / 200 jobs
$128M 500
Services (25%) (32.5%) (40%)
Restaurants & $8.9M / 58 jobs $13.4M / 87 jobs $17.8M / 116 jobs
$89M 580
Food Services (10%) (15%) (20%)
$5.4M / 22 jobs $6.8M / 28 jobs $8.1M / 33 jobs
Retail Trade $54M 220
(10%) (12.5%) (15%)
Total $271M 1,300 $46.3M/ 205 jobs $61.8M/ 278 jobs $77.1M/ 349 jobs
Total Economic Effects (Including Ripple Impacts)
In addition to direct changes in business activity, broader economic effects may occur
throughout the local economy. As a reminder, economic impacts occur in three ways:
Direct effects reflect initial Indirect effects capture the Indirect effects capture the
change in economic activity, resulting decrease in resulting decrease in
such as a decline or shift in business-to-business activity, business-to-business activity,
sales and jobs at businesses. as affected companies reduce as affected companies reduce
purchases from suppliers. purchases from suppliers.
• Indirect effects
Page 69 of 70
Using conservative industry multipliers (1.3–1.6, which estimate how changes in business
activity ripple through suppliers and household spending), the total regional economic
effect:
Total Estimated Impact
Low Scenario: $60M – $74M
Moderate Scenario: $80M – $99M
Higher Scenario: $100M – $123M
Additional Considerations
It is important to note that these estimates reflect a potential shift in economic activity
associated with courthouse relocation and do not represent an immediate or permanent
outcome. Changes in employment and business activity would likely occur over time. In
addition, this analysis does not account for potential redevelopment or reuse of vacated
spaces, which could offset or, in some cases, exceed current levels of jobs and sales. As
such, these estimates should be understood as illustrating a potential transition rather
than a final economic condition for downtown.
Key Takeaways
Overall, several key themes emerge from this analysis:
• Professional services represent a substantial share of downtown economic
activity, and are most closely tied to courthouse operations
• Restaurants and retail rely on consistent daytime activity, contributing
significantly to employment
• Potential impacts vary by sector, with some industries more directly tied to
courthouse proximity and others influenced more indirectly through changes in foot
traffic and activity levels
• The analysis suggests that a portion of downtown economic activity may shift
geographically depending on changes in courthouse location
• These estimates are intended to provide a general indication of potential changes
in economic patterns, and should be interpreted as planning-level insights rather
than precise forecasts
• These estimates reflect potential shifts in activity and do not account for longer-
term redevelopment or market adjustments
Page 70 of 70