City Council
Regular MeetingDanbury, CT · August 19, 2025
Minutes
Margerie Reservoir Trail Advisory Committee (Meeting #16)
August 19, 2025
Chair Robinson called the meeting to order at 6:37p.m. on Tuesday, August 19, 2025 in Danbury. Present
were Committee Members: David Day, City of Danbury; Peter Hearn, New Fairfield; Jeff Main, New
Fairfield. Absent was Ken Gucker, Alternate, City of Danbury and Ann Marie Mellas, Alternate, New
Fairfield. There is one Vacancy on the Committee. Also present was Joseph Mortelliti, Outside Counsel,
City of Danbury; and several members of the public.
Chair Robinson completed roll call.
A motion was made by Member Hearn, seconded by Member Main, to add Progress Reports regarding
the trail, progress reports #5 and #6 to the agenda. Motion carried unanimously.
Member Hearn spoke on the change to the format of the Progress Report and financial summary per the
request of New Fairfield and the State.
Chair Robinson identified these reports as Item 1B.
1. Minutes:
A motion was made by Member Hearn, seconded by Member Day, to approve the minutes from July
22nd. Motion carried unanimously.
1B. Progress Reports:
A motion was made by Member Hearn, seconded by Member Main, to approve progress reports 5 and
6. Motion carried unanimously.
2. Invoices:
Chair Robinson identified two additional invoices (11598, 11295) to be added to the agenda.
A motion was made by Member Hearn, seconded by Member Day, to add the invoices to the agenda.
Motion carried unanimously.
Member Hearn summarized the invoices pending committee approval and asked B&L to itemize the
invoices.
A motion was made by Member Main, seconded by Member Day, to approve the three invoices #12011,
11558 and 12195. Motion carried unanimously.
3. Communications to the Committee
Chair Robinson identified communications from 155 New Fairfield individuals, 7 property owners, and
54 Danbury residents supporting the trail. The Lakewood Condominium Association noted 84% of
residents are now in support of the trail; opposing communications were also received expressing
concerns with environmental impact, funding and maintenance, process and transparency. Chair
Robinson explained that most of these concerns have already been discussed and addressed by the
Committee
4. Recommendations:
Chair Robinson spoke on the completion of the Committee’s duties to this point; and that the
committee’s findings will now be provided to the Danbury City Council and New Fairifield Board of
Selectmen for review and action.
A motion was made by Member Day, seconded by Member Main, to conclude the work of the
Reservoir Trail Advisory Committee over the course of 15 plus meetings we have reviewed reports
from DEEP, gathered feedback from residents and neighbors, and identified a preferred trail route.
We recommend that project now be presented to the Danbury City Council and the New Fairfield
Board of Selectmen for further action. Remaining steps such as permitting, public presentation on
final design plans, issuing a construction RFP and construction itself should be coordinated by these
governing bodies. With this motion the Committee respectfully submitted its recommendation, and
suspends its advisory charges until and unless directed by City Council or the new Fairfield Board of
Selectmen. (Motion amended).
Member Hearn asked for further clarification of the recommendation. Chair Robinson confirmed that
B&L have presented a preliminary plan and design of the trail. Final handicap compliance can not be
done until materials are chosen which can not be done until the materials and costs are determined;
which will require the governing bodies vote on pursuing a construction RFP.
Member Hearn suggested amending the motion be clarified to explain that the committee is
recommending B&L’s design plan as presented. Mr. Mortelliti confirmed the motions that can be made
at this time.
A motion was made by Member Day, seconded by Member Hearn, to amend the language in the main
motion to include “the current B&L design plan”. Motion carried unanimously.
New Main Motion:
A motion was made by Member Day, seconded by Member Main, to conclude the work of the
Reservoir Trail Advisory Committee over the course of 15 plus meetings we have reviewed reports
from DEEP, gathered feedback from residents and neighbors, and identified a preferred trail route.
We recommend that the current B&L design plan now be presented to the Danbury City Council and
the New Fairfield Board of Selectmen for further action. Remaining steps such as permitting, public
presentation on final design plans, issuing a construction RFP and construction itself should be
coordinated by these governing bodies. With this motion the Committee respectfully submits the
current B&L design plan, and suspends its advisory charges until and unless directed by City Council
or the new Fairfield Board of Selectmen. Motion carried unanimously.
Member Day spoke on the need for addition needs to be identified including; adequate measures to
assure water quality of the reservoir, a way to limit public access to the reservoir, Constructions costs
and source of those funds, and a source for annual funds for operation and maintenance.
Mr. Mortelliti spoke on the purpose of advisory committees and ad hoc committees, and noted that this
recommendation is not binding. The committee is advising, and traditionally governing bodies will
make changes or amendments to plans. Member Main asked that this committee’s members stay
involved, specifically on the topic of materials.
Chair Robinson reiterated that this committee does not have jurisdiction over costs and the source of
funds.
5. Meeting Schedule:
A motion was made by Member Day, seconded by Member Main, to suspend any addition meetings of
this committee unless and until directed by the Town of New Fairfield or City of Danbury Motion
carried unanimously.
Member Hearn agreed that any further meetings are not necessary until next steps are established to
address items still needing to be finalized.
Adjournment:
A motion was made by Member Day, and seconded by Member Main, to adjourn. The
motion carried unanimously.
The meeting adjourned at 7:05pm.
Respectfully submitted,
Holly Robinson, Chair; David Day, Jeff Main, and Peter Hearn.
Agenda
CITY OF DANBURY Town of New Fairfield
155 DEER HILL AVENUE
DANBURY, CONNECTICUT 06810 4 Brush Hill Road
www.danbury-ct.gov New Fairfield, Connecticut 06812
ELISA ETCHETO Jean Green
LEGISLATIVE ASSISTANT
PHONE: 203-797-4514
Administrative Assistant to the First
FAX: 203-796-1529 Selectman
e.etcheto@danbury-ct.gov (203)312-5600
MEETING NOTICE
Who: Margerie Reservoir Trail Advisory Committee
When: Tuesday, August 19, 2025
6:30PM
Where: Danbury City Hall – 155 Deer Hill Avenue
3rd Floor
Purpose: Margerie Reservoir Trail Advisory Committee
Meeting #16
*Original agenda Item on file with the Danbury Legislative Assistant & with the Town of New
Fairfield
Committee Members & Representatives:
Holly Robinson, City Council Member, City of Danbury
David Day, Public Utilities Superintendent, City of Danbury
Corporation Counsel Representative, City of Danbury
Ken Gucker, Alternate, Danbury
Jeff Main, Conservation & Inland Wetland Commission, New Fairfield
Peter Hearn, New Fairfield
Ann Marie Mellas, Alternate, New Fairfield
Posted Notices: Town Clerk, City of Danbury & New Fairfield
Information Board, City of Danbury
City Website, City of Danbury & New Fairfield
Updated 8/20/25
Margerie Reservoir Trail Advisory Committee (Meeting #16)
AGENDA
When: 6:30 PM – Tuesday, August 19, 2025
Where: Danbury
City Hall – 3rd Fl – 3C
155 Deer Hill Avenue
______________________________________________________________________________
Call to Order
Roll Call
1. Minutes
July 22, 2025
1B. Progress Reports
#5 and #6
2. Invoices
Invoice # 12011
Invoice # 11558
Invoice # 12195
3. Communications to the Committee
4. Recommendations
Danbury City Council & New Fairfield Board of Selectmen
5. Meeting Schedule
6. Adjournment
*Note: This meeting will not include a public comment period.
1
Margerie Reservoir Trail Advisory Committee (Meeting #15)
July22, 2025
Chair Robinson called the meeting to order at 6:36p.m. on Tuesday, July 22, 2025 at the New Fairfield
Community Center. Present were Committee Members: David Day, City of Danbury; Peter Hearn, New
Fairfield; Jeff Main, New Fairfield; Ken Gucker, Alternate, City of Danbury. Absent was Ann Marie
Mellas, Alternate, New Fairfield. There is one Vacancy on the Committee. Also present was Joseph
Mortelliti, Outside Counsel, City of Danbury; and several members of the public.
Chair Robinson completed roll call.
1. Minutes:
Corrections were identified in the minutes from the June 17th meeting.
A motion was made by Member Hearn, seconded by Member Main, to amend the minutes. Motion
carried unanimously.
A motion was made by Member Hearn, seconded by Member Main, to approve the minutes as
amended. Motion carried unanimously.
Chair Robinson noted the resignation of Committee Member Antonio Iadarola.
Chair Robinson discussed the purpose of the committee, the process thus far, and the intent to present a
recommendation regarding the proposed trail to both the Danbury City Council and New Fairfield First
Selectmen once the design process is completed.
2. Public Speaking:
Chair Robinson identified a three-minute limit for each speaker.
Carl Anderson, New Fairfield Resident – Spoke against the trail and discussed his concerns with
congestion, and the need for greater transparency and access to information.
Jim Fandell, New Fairfield Resident – Spoke against the trail and expressed his concerns with the affect
of the trail on the town’s population.
Tom Perkins, New Fairfield Resident – Asked for a breakdown of committed funding for the project.
John Kreise, New Fairfield Resident – Asked about trail parking, security, and costs. He discussed
concerns with overcrowding and water pollution.
Jennifer Pappas, New Fairfield Resident – Spoke about concerns with a trail in Brookfield; identified noise
and car pollution, eagle nest, and safety concerns. Ms. Pappas identified a FOIA request regarding
communication about the project.
John McCartney, New Fairfield Resident – Spoke in favor of the trail as a safe place for children and
seniors. He discussed the online support for the project and the benefits of having a trail in your
community.
Chris Halloway, New Fairfield Resident – Spoke against the trail due to its impact on the environment.
Asked about safety and emergency response on the trail.
Kelly Linquist, New Fairfield Resident – Discussed concerns with the eagle’s nest.
Tom Hicks, New Fairfield Resident & Business Owner – Asked about the impact on businesses, discussed
concerns with safety and increased taxes.
Joseph (inaudible), New Fairfield Resident – Asked about the cost of the trail, maintenance, insurance,
parking, environmental impact, and safety needs.
Melanie Horn, New Fairfield Resident – Asked that a DEEP representative attend a meeting to address
public concerns.
3. Project updates:
Chair Robinson reiterated the purpose of the Committee; specifically, the task of reviewing the
feasibility of the trail so that the finding can be presented to the legislative bodies in Danbury and New
Fairfield.
Member Hearn spoke on the committee’s previous discussion of a new invoice approval process; he
confirmed that New Fairfield has specific approval requirements and all invoices will continue to be
approved by the committee at their regular meetings.
Member Hearn confirmed that he is working on a draft project report (#5) for DEEP that will include
financials in a format that New Fairfield has requested. The First Selectwoman will sign-off on these
reports. He confirmed that he will provide reports and invoices for the agenda moving forward. He
confirmed for Chair Robinson that DEEP project reports #5 and #6 are expected to be submitted in
August.
4. Invoices:
No invoices.
5. 2025 Meeting Schedule:
Chair Robinson suggested that the remaining meetings all take place in New Fairfield due to the
availability of a larger meeting room.
A motion was made by Member Hearn, seconded by Member Main, to approve the meeting schedule
dates; with the August 19th meeting taking place in Danbury. Motion carried unanimously.
Alt. Member Gucker expressed the need for both communities to be able to attend and be involved with
the process. Chair Robinson explained that the location of future meetings will be discussed at the
August meeting.
Member Hearn agreed that a larger space is needed for Danbury meetings.
6. New Business:
Member Hearn spoke on the need for the B&L website to be updated with a Frequently Asked Questions
section to address continues concerns. Chair Robinson noted that estimated costs will come as the
consultant finalizes the design of the trail and spoke on plans for sponsorships and grants to help cover
costs. Alt. Member Gucker began to comment on the public’s attendance of past meetings.
Adjournment:
A motion was made by Member Day, and seconded by Member Hearn, to adjourn. The
motion carried unanimously.
The meeting adjourned at 7:27pm.
Respectfully submitted,
Holly Robinson, Chair; David Day, Jeff Main, and Peter Hearn.
1B:
Progress Report #5
Grantee/Contractor Name: New Fairfield
Contract Value: $2,284,000 Contract End Date: 8/12/2027
Project Summary # 5. Reporting Period: August 13, 2024 through February 12, 2025
Supporting Narrative – Progress on Planned Activities – (2 pages plus attached spreadsheet)
1. Work Completed:
The Margerie Trail Advisory Committee (Committee) met In September, December of 2024 and in
January of 2025. Below is what was accomplished at each meeting. Included with the narration of this
report is a spreadsheet showing expenditures during that period.
September 24, 2024. The meeting began with public comments. Committee discussion turned to
the wetlands survey that had been authorized and was underway. The responses to the RFP for
a trail design were reviewed by the Committee. It was decided to send to the responders a list of
additional considerations to be included in their plan.
December 17, 2024. A public comment period was allowed. Mr. Villavicencio of Barton and
Loguidice (B&L), which had been chosen as contractor for the trail plan, presented the Margerie
Reservoir Trail design plans to the Committee. He provided a brief overview of the project’s
schedule, costs and objectives. He reviewed the previous Rt 37 corridor study and discussed trail
designs, outlined a proposed design and described the preliminary design process. He provided
details about the website launch. Members of the Committees stressed the importance of
addressing, in the trail design, any concerns that had been expressed by some members of the
public. These were: privacy buffering, pedestrian safety, proximity to residential areas, increased
noise, avoiding wetlands and protection of the eagle habitat.
January 28, 2025. The Committee approved the invoice # 10726 from B&L for $28,140 and
invoice # 10336 for $32,160. The invoices comprise the work done up to that date by B&L
including the Permit Review Process with CT DEEP and the creation of a project website with an
online survey and interactive map.
The Committee also authorized newspaper ads to inform the public of the online survey that
was designed by B&L to elicit public opinion with respect to the utility of a trail and design
preferences. Expenditures were allowed up to $1,100 for the Danbury News Times and for the
Town Tribune.
Member Ken Gucker had arranged the printing of flyers containing a QR link to the survey that
had been distributed in both municipalities.
1
It was reported that the FOIA requests had been answered by Danbury to the extent that the
requested information existed. It was decided that such communications be sent to Mr.
Mortelliti who could respond to them. Members of the public were invited to speak.
2. Total Funds expended as of 2/12/2025: $ 130,135 (See attached spreadsheet.)
Signature _______________________________ 8/6/2025
Date ________
Melissa Lindsey, First Selectman
2
Margerie Reservoir Trail
Expenses to Date
Date Vendor Description/Reference Amount
10/19/23 Hearst Media 2796206-09072023 Legal No $ 313.45
04/11/24 Hearst Media 2834375-03162024 $ 271.80
11/22/24 Sydney A. Rapp Land Surveying Part 1 - Topographic Surv $ 54,000.00
11/22/24 Sydney A. Rapp Land Surveying Part 2 - Wetland Delineat $ 15,250.00
02/05/25 Barton & Loguidice Inv. 10726 $ 28,140.00
02/05/25 Barton & Loguidice Inv.10336 $ 32,160.00
TOTAL $ 130,135.25
Through 2/12/2025
POWERSCHOOL PAGE NUMBER: 1
DATE: 07/28/2025 TOWN OF NEW FAIRFIELD AUDIT21
TIME: 09:21:46 EXPENDITURE AUDIT TRAIL
SELECTION CRITERIA: orgn.fund='302' and orgn.orgn1 like '4110%' and expledgr.account='720.08'
ACCOUNTING PERIODS: 1/24 THRU 13/24
SORTED BY: FUND,DEPARTMENT,ACCOUNT
TOTALED ON:
PAGE BREAKS ON:
FUND - 302 - TOWN CAPITAL PROJECTS
BUDGET UNIT - 30241100000001 - MARGERIE RESERVOIR TRAIL
ACCOUNT CUMULATIVE
DATE T/C PURCHASE O REFERENCE VENDOR BUDGET EXPENDITURES ENCUMBRANCES DESCRIPTION BALANCE
302-4110-0000-001-30241100000001 - MARGERIE RESERVOIR TRAIL
720.08 IMPROVEMENTS .00 .00 .00 BEGINNING BALANCE
07/01/23 13-1 2,284,000.00 DEEP GRANT 2022-241
10/12/23 11-4 .00
10/17/23 17-4 24000536-01 00108 HEARST MEDIA SER 313.45 2796206-09072023 LEGAL NO
10/19/23 21-4 24000536-01 111979 00108 HEARST MEDIA SER 313.45 -313.45 2796206-09072023 LEGAL NO
02/15/24 17-8 24000656-01 91328 SYDNEY A. RAPP L 54,000.00 PART 1 - TOPOGRAPHIC SURV
02/15/24 17-8 24000656-02 91328 SYDNEY A. RAPP L 15,250.00 PART 2 - WETLAND DELINEAT
04/09/24 18-10 24000536-01 00108 HEARST MEDIA SER 272.00 CHANGE ORDER - 1
04/11/24 21-10 24000536-01 112980 00108 HEARST MEDIA SER 271.80 -271.80 2834375-03162024
09/04/24 21-13 24000536-01 00108 HEARST MEDIA SER .00 - .20 2796206-09072023 LEGAL NO
TOTAL IMPROVEMENTS 2,284,000.00 585.25 69,250.00 2,214,164.75
TOTAL REPORT 2,284,000.00 585.25 69,250.00 2,214,164.75
* THERE IS A NOTE ASSOCIATED WITH THIS TRANSACTION
1B:
Progress Report #6
DRAFT
Grantee/Contractor Name: New Fairfield Contract No: 2023-241
Project ID: DEPA00030202707 and DEPA00030202809
Contract Value: $2,284,000 Contract End Date: 8/12/2027
Project Summary # 6. Reporting Period: February 13, 2025 through August 12, 2025
Supporting Narrative – Progress on Planned Activities – (2 pages)
1. Work Completed:
The Margerie Trail Advisory Committee (Committee) met In September, December and January. Below
is what was accomplished at each meeting. Included with the narration of this report is a spreadsheet
showing project expenditures during that period.
• March 25,2025. The meeting began with public comment. Barton and Loguidice (B&L), the
design consultant for the project, reported that the inline survey received 514 responses, 177
map comments, mostly from New Fairfield residents age 45+. It was reported that B&L is in the
process of creating a proposed trail route alignment based on online data: Connection to other
activities and dog park, safety while walking the trail is a concern due to high traffic nearby,
privacy, connection from trail to sidewalks along Route 7, vegetation buffer to help with privacy.
There will also be an eagle nest buffer zone, existing stone walls will be avoided, grading and/or
boardwalk in wetland areas.
Committee member Day asked about DEEPs input on the eagle nest. Mr. Grindle of B&L
confirmed that the DEEP expert believes the trail will not make a significant impact in
comparison to the disruption Route 37 already has on the nest area. Mr. Grindle also confirmed
the water mitigation is on their radar. Member Iadarola asked about adding tags to the map; he
noted concerns with the flood line; and he asked about the grading plan that affected the
location of the path and the boardwalk plan; Mr. Grindle suggested PVC construction for
longevity. Member Iadarola also asked about addressing dead trees during the construction. Mr.
Grindle confirmed for Member Day that the length of the trail is 2 miles and the boardwalk
portion would be 1,300 linear ft.
B&L Invoice # 11079 ($8,040) – A motion was made by Member Gucker, seconded by Member
Iadarola, to approve the invoice from B&L Invoice #11079. Motion carried unanimously.
• On June 17. The meeting began with public comments. The Committee formally approved B&L
invoice #10763 for $8040 which had not been included in the minutes for previous meetings.
1
The Committee also approved B&L invoice # 11307 for $ 26,132. A discussion followed on how
to accelerate invoice payments, which have been slow.
Mr. Grindle of B&L showed a PowerPoint of the proposed trail route and features. He also
discussed the walk through that was conducted with Mr. Hess of the Department of Energy and
Environmental Protection. He said the PowerPoint will be added to the trail website. Mr. Day
asked about guaranteeing the safety of the reservoir.
Chair Robinson presented the schedule of future meetings. The committee then entered into
executive session to discuss the proposed trail plan.
2. Total Funds expended to date: $ 585.25
Funds expended in current reporting period $ 271.80 to Hearst Media.
Signature _______________________________ Date _________
2
2 (updated 8/19/25)
MARGERIE RESERVOIR TRAIL
FREQUENTLY ASKED QUESTIONS (FAQ)
(As of August 6, 2025)
1. PROJECT FUNDING & SUPPORT
Q. Who is paying for the current study of the reservoir’s suitability for a multiuse trail?
A. Neither the City of Danbury nor the Town of New Fairfield are paying for the current
study. The planning and design phase is funded by a $2.28 million State of Connecticut
grant dedicated solely to feasibility, permitting, and environmental review; these dollars
cannot be spent on unrelated city or town expenses. It is funded through a State of
Connecticut grant specifically for trail feasibility and planning (Urban Development Act
Grant).
Q. Which elected officials have supported the trail study?
A. Since the concept of a reservoir trail was first proposed, elected officials from both
political parties and multiple administrations have supported feasibility studies,
including:
● Former Danbury Mayor Mark Boughton
● Current Danbury Mayor Roberto Alves
● Former State Senator Michael McLachlan
● Former State Representative Stephen Smith
● Former State Representative Rachel Chaleski
● Current State Representatives Ken Gucker and Pat Callahan
● Former New Fairfield First Selectmen Susan Chapman and Pat Del Monico
● Former New Fairfield Selectman Khris Hall
● Former Danbury City Council President Vinny DiGilio
● Current Danbury Councilwoman Holly Robinson
In addition, the concept of regional trail connectivity is:
● Supported in both the Danbury and New Fairfield Plans of Conservation and
Development (POCD); and
● Endorsed by the Western Connecticut Council of Governments (WestCOG) (Danbury
POCD 2023, New Fairfield POCD 2021, WestCOG 2024).
Q. Is there business support for the trail?
A. In addition to individual business owners, the Greater Danbury Chamber of Commerce
confirms its support of the trail, stating “[f]rom an economic perspective, trails like this
can improve the performance and visibility of nearby businesses, particularly those in
retail, food service…..and generate sustained foot traffic, encourage “stop-in”
commerce, and create the kind of active, connected downtown that draws both
residents and visitors. In essence, they help convert pass-through activity into local
spending. In addition, connectivity and walkability are consistently ranked as top
community amenities, fostering a sense of place, encouraging investment, and
supporting workforce retention by enhancing the day-to-day experience of those living
and working in the community.”
2. THE MARGERIE RESERVOIR TRAIL ADVISORY COMMITTEE (MRTAC)
Q. What is the Margerie Reservoir Trail Advisory Committee (MRTAC)?
A. MRTAC is a joint committee formed by the City of Danbury and the Town of New
Fairfield. It serves in an advisory capacity only; it cannot approve or fund construction.
Its purpose is to evaluate engineering, environmental, and public-input data and then
issue a recommendation to elected officials.
3. PUBLIC INVOLVEMENT
Q. What public input has shaped the design?
A. Public engagement has included:
● 15+ committee meetings since 2022, each offering public comment.
● A six-week online interactive map for public feedback, which generated 500
responses and 177 geo-pinned comments.
● Adjustments to trail routing and design based on public input, including vegetative
screening near residences and sensitive environmental areas (Project Public
Engagement Summary 2025).
See Appendix A: Comprehensive Public Engagement Summary for more information
4. TRAIL COSTS & MAINTENANCE
Q. What will the trail cost to construct?
A. The exact cost depends on final design and materials. Preliminary estimates are
expected by the end of summer 2025. Funding sources include the $2.28 million Urban
Development Act grant, other state/federal grants, philanthropic donations, and
corporate sponsorships (CT DOT Trail Funding Program).
Q. How much will it cost taxpayers to maintain the trail?
A. Maintenance costs vary by design but are generally low. The trail will be on City of
Danbury property, and the City plans to pursue grant funding and partnerships for
upkeep. Trails similar in length and usage in Connecticut typically cost $2,000–$4,000
annually per mile for maintenance (Rails-to-Trails Conservancy, 2022). For the proposed
2-mile Margerie Reservoir Trail, a conservative estimate for annual maintenance is
approximately $10,000. Even if Danbury were to fund the full amount (without
considering any volunteer, sponsorships, grant funding, etc.), the cost would be around
11-22 cents per taxpayer per year.
5. ENVIRONMENTAL PROTECTION
Q. Will the trail endanger bald eagles?
A. No. The proposed trail alignment is outside the recommended federal buffer for nesting
eagles, except where it runs adjacent to Route 37, where over 11,000 vehicles per day
already travel without disturbing the nest (CTDOT traffic counts, CT DEEP Bald Eagle
Management Guidelines). The Connecticut Department of Energy and Environmental
Protection (CT DEEP) visited the site and has no objections to the alignment.
Construction will be timed to avoid the nesting period and will use low-impact methods
(no heavy equipment near the nest). Educational signage will also promote eagle
protection.
See Appendix B: Focus on Eagle Protection for more information
Q. What about other wildlife and wetlands?
A. The route was designed to avoid wetlands whenever possible. Where crossings are
necessary, elevated boardwalks will be used to maintain wetland function. The CT
Natural Diversity Database shows no endangered or threatened species within the
project area. If any are identified during permitting, additional protections will be
implemented as required by law (CT Natural Diversity Database 2024).
6. PROPERTY & PRIVACY CONCERNS
Q. How close will the trail be to condominiums?
A. The trail alignment keeps at least 100 feet from the nearest condo building and
significantly more in most areas. Dense vegetative screening is included in the design for
privacy (Trail Concept Plans 2025).
Q. Will the trail bring strangers “into people’s backyards”?
A. The trail is on City of Danbury-owned land, not private property. Public access to
municipal land is a legal right and common practice statewide. Screening and fencing
options are being considered where necessary (CT General Statutes § 7-148).
7. SAFETY & SECURITY
Q. Will crime increase?
A. Studies consistently show that trails do not increase crime and, in some cases, reduce it
because more eyes are present (Rails-to-Trails Conservancy, 2022). Local trails in both
Danbury and New Fairfield have no significant crime incidents. National research shows
crime either decreases or remains unchanged after a trail opens; one multi-state study
found adjacent neighborhoods experienced a 10% drop in property crime.
Additionally:
● The trail is expected to have regular pedestrian activity, deterring crime.
● It is visible from Route 37.
● Mile markers and emergency access points are built into the design.
Q. How will medical emergencies be handled?
A. The entire route has cell coverage. Emergency vehicle access is available at two
locations: from the south via the Danbury Dog Park entrance on Bear Mountain Road
and from the north via the reservoir access road on Route 37 (North Street). Mile
markers will be installed along the trail to help emergency responders quickly identify
and access incident locations (PROJECT SAFETY PLAN 2025). Trail mile-markers and two gated
access points allow EMS to reach any location quickly.
8. PARKING & USE
Q. Where will people park?
A. Most anticipated users are local residents—including school cross-country teams and
Senior Center members—who can walk to the trail. Limited parking areas are being
studied for occasional visitors, but daily use is expected to be neighborhood-based (User
Demand Study 2025).
9. WATER QUALITY & RESERVOIR PROTECTION
Q. Will the trail pollute the reservoir?
A. The trail design follows best management practices (BMPs) for stormwater and erosion
control. The drainage plan may actually improve conditions by capturing and treating
runoff that currently flows from Route 37 directly toward the reservoir. In fact, it may
improve water quality by providing new drainage features to redirect roadway runoff
from Route 37, a current pollutant source (EPA Stormwater BMP Manual).
Q. Could the water supply be poisoned?
A. The trail will increase passive surveillance (more eyes on the area), reducing illegal
dumping risks. The Connecticut Department of Public Health encourages access trails
around reservoirs when properly designed and managed (CT DPH Drinking Water
Division Guidance).
10. COMMUNITY BENEFITS
Q. What are the benefits of the trail?
A. Numerous studies demonstrate benefits, including:
● Nearby homes typically gain 4–7% in value; Brookfield homes near the Still River
Greenway rose by up to $50,000.
● Public health: Trails promote exercise, reducing healthcare costs (CDC Healthy
Community Design Initiative).
● Education: Opportunities for environmental field trips and outdoor learning.
● Local economy: Trails typically boost nearby small businesses by 5–10% due to
increased foot traffic (Rails-to-Trails Conservancy Economic Impact Studies).
● Community connection: A safe space for social interaction and events.
11. CLARIFYING CONCERNS
Q. Why do some residents oppose the trail?
A. Community feedback has raised thoughtful concerns about privacy, wildlife protection,
potential safety issues, and long-term impacts—many of which are understandable
given the scale and visibility of the project. Some of these concerns stem from
uncertainty or incomplete information, which is common in the early stages of a public
planning process. The City of Danbury and the project team are committed to addressing
questions openly and respectfully. To support this, an active project website includes:
● Current plans
● Meeting notes
● Eagle protection information
● Project schedules
● Frequently Asked Questions (FAQ)
We encourage all residents to review the latest materials and submit feedback at:
(https://bartonloguidice.mysocialpinpoint.com/margerie-reservoir-trail/margerie-trail or
https://tinyurl.com/MargerieTrail).
REFERENCES
● USFWS Bald Eagle Management Guidelines (2007) -
https://www.fws.gov/sites/default/files/documents/national-bald-eagle-management-g
uidelines_0.pdf
● CT DEEP Bald Eagle Management Guidelines –
https://portal.ct.gov/DEEP/Wildlife/Fact-Sheets/Bald-Eagle
● Rails-to-Trails Conservancy (Crime, Economic, and Maintenance Studies) –
https://www.railstotrails.org/
● Connecticut DOT Traffic Counts for Route 37 –
https://portal.ct.gov/DOT/Performance/Traffic-Data
● Connecticut Natural Diversity Database (CT DEEP NDDB 2025)–
https://portal.ct.gov/DEEP/EndangeredSpecies/Natural-Diversity-Data-Base
● CDC Healthy Community Design Initiative – https://www.cdc.gov/healthyplaces/
● National Association of Realtors – https://www.nar.realtor/research-and-statistics
● CT DPH Drinking Water Division – https://portal.ct.gov/DPH/Drinking-Water
● EPA Stormwater BMP Manual – https://www.epa.gov/npdes/stormwater
AUTHORSHIP
Prepared collaboratively by the Margerie Reservoir Trail Advisory Committee (MRTAC), design
consultants from Barton & Loguidice, and other subject matter experts and stakeholders. It is
intended as a good-faith effort to inform the public and foster continued transparency.
APPENDIX A: COMPREHENSIVE PUBLIC ENGAGEMENT SUMMARY
This summary documents all public engagement, transparency efforts, and community
responsiveness by the Margerie Reservoir Trail Advisory Committee (MRTAC) during its advisory
review of a proposed multi-use trail along the Margerie Reservoir corridor between Danbury
and New Fairfield, Connecticut.
COMMITTEE STRUCTURE & TRANSPARENCY
● Advisory-only body created to assess trail feasibility; does not approve or fund construction
● 15 public meetings held (Dec 2022 – July 2025)
● Committee meetings noticed and recorded per FOIA and public meeting rules
● Rotating meeting locations between New Fairfield and Danbury to ensure accessibility for
both communities
● Minutes taken and posted for all meetings; several included audio/video recordings
● FOIA requests received and formally addressed in public session
● Corporation Counsel present at most meetings to ensure compliance with public records
and process obligations
PUBLIC COMMENT OPPORTUNITIES & PARTICIPATION
● Public comment offered at nearly every meeting, often at beginning
● Over 100 public comments across meetings (residents, town leaders, business owners,
stakeholders)
● Written comments submitted and read into the record at multiple meetings
● Committee members met with condo residents to hear property-specific concerns
● Chair and committee encouraged all speakers to raise new concerns while affirming respect
for repeated input
● Public speakers included senior citizens, cross-country coaches, parents, homeowners,
commissioners, and state/local officials
ONLINE PUBLIC ENGAGEMENT
● Project-specific website launched and maintained by consultant Barton & Loguidice (B&L)
● Website hosted trail maps, comment portal, survey, and updates
● Public Survey: 514 responses, 177 map-based comments
● Respondents were primarily New Fairfield residents, mostly aged 45+
● Strong majority (~80%) expressed support for the trail
MEDIA & PUBLIC NOTICE
● News-Times article (Jan 18, 2025): 'Planners Seek Feedback on Plan: Safe Link'
● Town Tribune article (Jan 23, 2025): 'MRTAC Seeks Your Input' with full-color trail map
● Newspaper ads: Town Tribune ($230), News-Times print+digital ($1,100)
● Public notice postings coordinated with both New Fairfield and Danbury municipalities
REVISIONS BASED ON PUBLIC INPUT
● Trail alignment adjusted to increase distance from Lakewood Condos
● Vegetative buffers and screening berms added for privacy
● Adjustments made to avoid stone walls and wetlands
● Safety, fencing, lighting, and water concerns reviewed and integrated into RFP
● Public input themes directly incorporated into consultant scope
WILDLIFE PROTECTION & ENVIRONMENTAL REVIEW
● April 25, 2025: Site walk conducted with CT DEEP Wildlife Biologist Brian Hess
● Nest observed; no distress noted; DEEP endorsed current trail alignment
● Construction to be phased to avoid nesting season
● Environmental Impact Assessment included in design scope
DESIGN CONSULTANT ENGAGEMENT
● Open RFP process conducted; B&L selected unanimously
● B&L attended public meetings, presented options, and revised plans based on input
● Committed to public updates
MEETINGS & MILESTONES
● Dec 2022 – Jul 2025: 15 public meetings held
● Jan–Feb 2024: Committee restructured with new chair
● Jan–Feb 2025: Public survey launched
● Apr 25, 2025: DEEP eagle nest walk
● Jul 22, 2025: Final major public meeting before recommendation
● Aug 19, 2025: Final report to be submitted
FINAL NOTES
● 2.5 years of structured public engagement
● Committee listened, documented, and responded to concerns
● Plans revised with expert and public input
● Process exceeded public input standards for feasibility studies
APPENDIX B: FOCUS ON EAGLE PROTECTION
Since early in the Margerie Reservoir Trail planning process, MRTAC has prioritized the
protection of wildlife, particularly the active bald eagle nest located near the proposed trail
corridor. To ensure responsible planning and regulatory compliance, the committee worked
closely with the Connecticut Department of Energy and Environmental Protection (CT DEEP),
specifically with Wildlife Biologist Brian Hess of CT DEEP’s Wildlife Division.
Brian Hess is a seasoned wildlife biologist with CT DEEP and is an expert on raptors, including
bald eagles. His role at CT DEEP includes overseeing eagle monitoring efforts, coordinating with
federal agencies such as the U.S. Fish and Wildlife Service, and advising municipalities and
developers on best practices for minimizing impacts to sensitive species and habitats. Mr. Hess
has conducted field research and public education around raptor conservation and has written
and spoken extensively about the post-DDT bald eagle recovery in Connecticut.
On April 25, 2025, Mr. Hess conducted an in-person site walk with members of the Advisory
Committee and consultants from Barton & Loguidice (B&L). The walkthrough assessed the
location of the active eagle nest in relation to the proposed trail alignment. During the site visit,
an adult eagle and at least two eaglets were observed in the nest through a spotting scope. He
noted that while the nest is located within the 330-foot primary buffer zone recommended for
nesting bald eagles, the proposed trail alignment runs adjacent to Route 37 — a pre-existing
state highway that already introduces disturbance in the area that is tolerated by the eagles.
Mr. Hess stated that because the trail will be constructed along this corridor and because the
scope of the disturbance from the trail will be similar to the disturbance of the roadway, impact
on the nesting pair would be minimal. He expressed appreciation for the committee’s sensitivity
to wildlife concerns and stated he had no objection to the proposed alignment. Importantly, Mr.
Hess committed to providing technical assistance and coordination with both CT DEEP and the
U.S. Fish and Wildlife Service (USFWS).
Based on Mr. Hess’s observations and guidance, the committee and design consultant have
included the following protective measures into the trail planning and RFP scope:
- Phased construction schedule to avoid bald eagle nesting and fledging seasons (typically
January through July).
- Installation of physical barriers (e.g., fencing, natural screening) near the eagle nest area to
discourage off-trail wandering and provide additional visual screening between trail users and
the eagles.
- Use of educational signage about bald eagle conservation and federal protections.
- Monitoring of nesting activity in partnership with CT DEEP throughout the construction and
post-construction period.
- Avoidance of loud construction activities or mechanized equipment near the nest during
critical months.
- Routing adjustments made during design development to maximize distance from the nest
and minimize visibility.
These measures were designed in accordance with both CT DEEP and USFWS recommendations
for nest protection under the Bald and Golden Eagle Protection Act. The committee remains in
regular contact with DEEP and is committed to modifying any construction or operational plans
if eagle nesting behavior changes or if new nests are identified.
MRTAC would like to express its gratitude to Brian Hess and the Wildlife Division of CT DEEP for
their expertise, transparency, and collaboration in protecting this iconic species while
supporting thoughtful recreational development.
POWERSCHOOL PAGE NUMBER: 1
DATE: 07/28/2025 TOWN OF NEW FAIRFIELD AUDIT21
TIME: 09:23:01 EXPENDITURE AUDIT TRAIL
SELECTION CRITERIA: orgn.fund='302' and orgn.orgn1 like '4110%' and expledgr.account='720.08'
ACCOUNTING PERIODS: 1/25 THRU 8/25
SORTED BY: FUND,DEPARTMENT,ACCOUNT
TOTALED ON:
PAGE BREAKS ON:
FUND - 302 - TOWN CAPITAL PROJECTS
BUDGET UNIT - 30241100000001 - MARGERIE RESERVOIR TRAIL
ACCOUNT CUMULATIVE
DATE T/C PURCHASE O REFERENCE VENDOR BUDGET EXPENDITURES ENCUMBRANCES DESCRIPTION BALANCE
302-4110-0000-001-30241100000001 - MARGERIE RESERVOIR TRAIL
720.08 IMPROVEMENTS .00 .00 .00 BEGINNING BALANCE
07/01/24 13-1 2,214,164.75 FY24 AVAILABLE BUDGET
07/01/24 13-1 .00
07/22/24 11-1 .00 POSTED FROM BUDGET SYSTEM
09/04/24 13-1 54,000.00 PRIOR YR ENCUM-E4000656
09/04/24 13-1 15,250.00 PRIOR YR ENCUM-E4000656
09/04/24 17-1 24000656-01 91328 SYDNEY A. RAPP L 54,000.00 ENC CARRY FRWRD-E4000656
09/04/24 17-1 24000656-02 91328 SYDNEY A. RAPP L 15,250.00 ENC CARRY FRWRD-E4000656
11/22/24 21-5 24000656-01 113954 91328 SYDNEY A. RAPP L 54,000.00 -54,000.00 PART 1 - TOPOGRAPHIC SURV
11/22/24 21-5 24000656-02 113954 91328 SYDNEY A. RAPP L 15,250.00 -15,250.00 PART 2 - WETLAND DELINEAT
02/03/25 17-8 25000598-01 91689 BARTON & LOGUIDI 266,260.00 COMPREHENSIVE DESIGN SERV
02/03/25 17-8 25000599-01 19297 TOWN TRIBUNE 230.00 MARGERIE TRAIL SURVEY AD
02/03/25 17-8 25000600-01 00108 HEARST MEDIA SER 1,062.00 MARGERIE TRAIL ADVISORY S
02/05/25 21-8 25000598-01 114179 91689 BARTON & LOGUIDI 28,140.00 -28,140.00 INV. 10726
02/05/25 21-8 25000598-01 114179 91689 BARTON & LOGUIDI 32,160.00 -32,160.00 INV.10336 12/04/24
02/24/25 21-8 25000600-01 V1225 00108 HEARST MEDIA SER 500.00 -500.00 2898263-01312025
TOTAL IMPROVEMENTS 2,283,414.75 130,050.00 206,752.00 1,946,612.75
TOTAL REPORT 2,283,414.75 130,050.00 206,752.00 1,946,612.75
* THERE IS A NOTE ASSOCIATED WITH THIS TRANSACTION