East Orange Water Commission
Regular MeetingEast Orange, NJ · July 16, 2024
Minutes
CITY OF EAST ORANGE, NEW JERSEY
EAST ORANGE WATER COMMISSION
99 South Grove Street
East Orange, NJ 07018
TED R. GREEN, Mayor
REGULAR BOARD MEETING
July 16, 2024
MINUTES
Minutes of the Regular Meeting of the Board of Water Commissioners held at 99 South Grove
Street, East Orange, New Jersey on Tuesday, July 16, 2024.
I. CALL TO ORDER - 5:13 p.m.
ROLL CALL
PRESENT:
Commissioners
Alison Rolling
Shantel Harrison
Sherkera Lucas
Emmanuel O. Awe – approx. 5:25 pm
Lauren Shears – approx. 5:14 pm
Staff
Thomas Matich, Acting Executive Director
Joseph J. Tomashosky –Finance
Bianca Smith, Business Manager
Counsel
Denis Murphy, Esq. (Weiner Law)
Council Members
NONE
Public
NONE
The meeting was called to order, Commissioner Rolling determined that there was
a quorum and convened the Regular Meeting.
Commissioner Rolling read the Sunshine Law for the record.
Commissioner Rolling read the Rate Statement.
II. STATUS OF RESOLUTIONS
The Mayor has returned Resolutions #73 through #81. All resolutions are in full force and effect.
III. ADOPTION/CORRECTION OF MINUTES
7A: The Minutes of the June 18, 2024, Regular Board Meeting were approved on a
motion made by Commissioner Harrison seconded by Commissioner Lucas and
carried unanimously on the call for the Board to vote.
IV. PRESENTATION
NONE
V. STAFF REPORTS
ACTING DIRECTOR MATICH THANKED EVERYONE FOR THEIR KINDNESS AND
WORDS OF ENCOURAGMENT.
FINANCE – Joe advised the Board that the collection rate went down and that's because our
invoicing went up. We collected $1,834,000 for East Orange customers in the month, and we filled
$2,093,000 for the billing resulting in an 87.6% collection rate for June. April and May were both
above 105% and that goes to the efforts that we made after the state mandated no turn off period.
So, we had two great months in April and May. The collection rate for the year is 95.4% versus
last month we were at 97%. We increased our accounts receivable by $259,000. We did have
some good news, beginning in July, we would anticipate that we're going to have a bigger month
as one of our customers paid a large bill. In June, we didn't have any significant or unusual or
unplanned expenses. However, we did have a lot of cash that we paid out. We had $2,000,000 in
debt service that went out and we spent close to $1,000,000 in sending money for services and for
our medical benefit cost, the biggest piece being the medical benefits cost to the City and towards
the end of the year, in November, we'll send the balance of what we owe them. We should point
out that there have been years when we produced and billed customers when we had lower water
periods because it was a wet spring and you don't have a lot of water usage. With the weather that
we've all been experiencing lately, I would say that we have an unplanned upside in the collection
of future billings for additional water usage during this hot weather.
CUSTOMER SERVICE – Bianca advised the Board that they are continuing with the payment
arrangements and have continued with the asset management system. We do have a meeting with
them at the end of the month. Northstar and Paymentus are coming here at the end of the month
on the 30th. We're looking to move forward with those projects as well. We may have one person
that's on our customer log that comes in due to high usage. It was a building with about 103 units.
They may come in. We have also extended summer hours to 6:15 pm from Monday - Friday.
DIRECTOR’S REPORT - Director Matich advised the Board of the following:
He had a conference call with Boswell discussing the next phase of the lead service line. In light
of our meetings, it was brought up that we actually had to get approval from the Historical
Preservation Committee because some of the buildings that we're changing the lines on are
impacted by that. Fortunately, they understood that these are non-invasive since they're only
service lines and water. We're not doing anything with the actual structure itself. So that's just a
simple signature and hopefully we can get some final determination on when we are bidding that.
I will let you know that the moment we get clearance on that, we are already preparing the next
phase, Phase 3A. Boswell is going to be submitting some paperwork on that so that we can submit
that. Since we split up the next phases into two parts, the state control review and approval process
should be more streamlined. If you look at the operational overview of the chart, you can see on
there that between curb boxes repaired and replaced and gate curb boxes located and operated we
are over 100 so triple digits on a regular basis on a regular month is what our norm has been, and
we continue with that as well. As far as sewers, we're still doing some in-house repairs some assets
between catch basins and superficial manhole repairs. We have a big project that will be taking
place or commencing in the next few weeks. I'm awaiting the traffic plan and the submittals for
the lining. That's the lining on Arlington. The further stretch that beyond what we have
encountered, the catastrophic failures, the last two over the course of the last few years and we'll
be engaged in that. Once I have the plan and traffic plan together, I'll submit it to you and also to
the City administration so they are aware of it and they can put out notifications as well as to how
much that area is going to be impacted traffic wise and how long the duration will be. So, although
this is a significant cost, it's far cheaper to line it now and give us some more structural integrity
in that area rather than just one small break. Continued in-house meter change outs, the numbers
aren't as aggressive as we anticipated. Now with people returning to work, we can realign people
into their divisions in order to make that happen. We haven't aggressively pursued the afterhours
that we had discussed. Once that kicks in, those numbers should increase, and we should start
being able to get back on track with that. WORPS, we had a meeting last week with H2M in
reference to the PFAS treatment facility. The original location that we wanted to put it had to be
adjusted a few feet because of encroachment to the highway, trees and things like that. This gives
us more seclusion from the golf course and from the roadway, almost an even split. They're looking
into now the obstacles that we encountered during the Air Stripper project with the migration
habitat of some local bat or bird. They're going to see if that will impact us as well. Plus, the
mandate to replace the trees that we're going to end up taking down, the area that they shifted over
to the diameter of the trees are smaller. So, that helps us out quite a bit. You know, the larger the
diameter of trees, they want more for those. So, these are smaller, and we should be able to stagger
them along the side. The key thing was that I told them I didn't want open access like we have with
the air strippers to the golf course. They become a target for people who can't swing very well.
So, once we have that determined and everything in the final footprint, they're going to provide
me with a drawing, and I'll submit that to all of you as well.
The emergency generator was put to the test last month with a failure of a power line. Trees went
down, two power lines down, both for all JCP&L customers and for us proper for one of our well
lines. With that being said, the emergency generator did exactly what it was supposed to do, it
engaged automatically, providing us with a full run production of energy for every single one of
our needed assets for a period of four days with no disruptions at all. So, the money we put in was
worthwhile. The system is fully operational except for one new piece and that is the transformer.
Right now, it's being run off the old transformer. The construction phase for that would just be to
shut down, tie into the new transformer and turn it back on. That should be taking place this fall.
September or October is still the anticipated delivery date for those. I mentioned the LSL program
that we're working on, the PFAS. Sewer rates, I think that's a discussion that we must have
internally. Collection Tower, coordinating the electrician and the two City agencies, the Fire
Department and Public Works for access to connect power. The GIS is ongoing. It's organic and
we're adding new and new layers to it regularly. QAA is still working on the asset management in
house. The I&I study, I believe that the eye trackers were purchased. On boarding for training,
how we can install them ourselves so that they can be mobile and move to different areas to do
continuous study in different areas of the town. Reservoir inspection and repair the finalizing of
valve exercising for the isolation of the two tanks. D4, the final design and submissions should be
taking place shortly. D3, was awarded and given to the contractor. Will be setting up a pre-
construction meeting for that in the coming weeks to start that evolution. Surge Tower Rehab,
waiting for the submittals of the prefab shroud design that we had discussed. Once that's in place,
there will be some landscape to be done, but then the deflection of water will be accomplished.
The baseline study for firm capacity, we finished Phase 1. We're ongoing with Phase 2 with final
plans on the priority listing of the wells involved. SCADA is ongoing integration with that.
WORPS pump system, pump 5 has been returned, completed and rehabbed. We have not returned
it to service. We anticipate doing that maybe at the end of July or beginning of August. Right
now, it's still being run on our master pump one and two. Conversion project, the final punch list
items are being addressed.
VI. COMMUNICATIONS
NONE
VII. UNFINISHED BUSINESS
Legal Matters to be discussed in Executive Session.
VIII. NEW BUSINESS
NONE
IX. APPROVAL OF RESOLUTIONS
The following resolutions 13A through 13G were presented to the Board for approval.
A Motion to omnibus Resolutions 13A through 13G was approved by Commissioner
Harrison, seconded by Commissioner Lucas, and carried unanimously on the call for the
Board to vote.
13A: Resolution ratifying the June 2024 recurring monthly bills in the amount of
$2,353,055.09
13B: Resolution authorizing the approval and payment of Operating Bills in the
amount of $1,374,475.16
13C: Resolution ratifying the June 2024 Payrolls in the amount of $399,167.44
13D: Resolution authorizing the payment of Capital Invoices in the amount of
$117,909.75
13E: Resolution adopting the 2024 Budget for the East Orange Water Commission
in the amount of $30,881,911.62
13F: Resolution authorizing the use of competitive contracting procedures and the
preparation of a request for proposals for the provision of accountant and
financial consultant services for the East Orange Board of Water Commission
13G: Resolution honoring John Liu, P.E., P.P. for his years of service
X. PUBLIC COMMENT
NONE
XI. EXECUTIVE SESSION
15A: Resolution for Closed Session
Resolution 15A was approved on a motion made by Commissioner Harrison, seconded by
Commissioner Lucas and carried unanimously on the call for the Board to vote.
------------------
The Board went into Executive Session to discuss the following at approximately 5:42 pm:
1. Personnel Committee
2. Contracts and Litigation Matters
The Board came out of Executive Session at approximately 7:24 pm.
-------------------
There being no further business, the meeting was adjourned at 7:24 pm.
THESE MINUTES ARE OF NECESSITY CONDENSED AND ABRIGED AND DO
NOT PURPORT TO CONTAIN THE FULL CONTENTS OF THE MATTERS
DISCUSSED.
SONYA BUTLER
TRANSCRIBER
Agenda
EAST ORANGE
BOARD OF WATER COMMISSIONERS
AGENDA
TUESDAY, JULY 16, 2024
I. CALL TO ORDER @ 5:00 p.m.
II. PLEDGE OF ALLEGIANCE
III. ROLL CALL
IV. OPEN PUBLIC MEETING ACT STATEMENT
In accordance with the Open Public Meeting Act, this Regular East Orange Board
of Water Commissioners Monthly Meeting conforms to the notice requirements
of N.J.S.A. 10:4-8. This is the regular Monthly Meeting and Notice setting forth
the date, time and place thereof, was publicly posted on the bulletin board in the
public entry of the East Orange Board of Water Commissioners and sent to the
Newark Star-Ledger, the Record Transcript, filed with the City Clerk of the City
of East Orange and published in the Newark Star Ledger on February 16, 2024.
V. RATE STATEMENT
• This is the regular scheduled July Monthly Meeting of The East Orange Board of
Water Commissioners.
• The East Orange Board of Water Commissioners was established in July 1, 1909.
• The East Orange Board of Water Commissioners establishes water and sewer rates
for customers of the East Orange Board of Water Commission.
• The East Orange Board of Water Commissioners assumed responsibility for the
Operation, Management and Maintenance of the East Orange Sewer System on
December 1, 1995.
• The East Orange Board of Water Commissioners assumed responsibility for the East
Orange Storm Drainage System on May 1, 2004.
PAGE 2
VI. STATUS OF RESOLUTIONS
The Mayor has returned Resolutions #73 through #81 - All resolutions are in full
force and effect.
VII. APPROVAL OF MINUTES
A. Resolution to approve Minutes of the June 18, 2024 EOBWC Meeting
VIII. REPORT OF EXECUTIVE DIRECTOR
A. Presentations if any
B. Update on current capital projects
C. Customer Service
D. Mains Meters & Sewers
IX. EOBWC COMMITTEE REPORTS
A. Finance Committee
B. Capital Committee
C. Personnel & IT Committee
D. Employee Training and Development Committee
X. COMMUNICATIONS
XI. UNFINISHED BUSINESS
XII. NEW BUSINESS
XIII. RESOLUTIONS
A. RESOLUTION RATIFYING THE JUNE 2024 RECURRING MONTHLY
BILLS PAID IN THE AMOUNT OF $2,353,055.09
B. RESOLUTION AUTHORIZING THE APPROVAL AND PAYMENTS OF
OPERATING BILLS IN THE TOTAL AMOUNT OF $1,374,475.16 TO BE
PAID IN JULY 2024
C. RESOLUTION RATIFYING THE PAYMENT OF JUNE 2024 PAYROLLS
IN THE TOTAL AMOUNT OF $399,167.44
D. RESOLUTION AUTHORIZING THE PAYMENT OF CAPITAL
INVOICES - TO BE PAID IN JULY 2024 IN THE AMOUNT OF
$117,909.75
E. RESOLUTION ADOPTING THE 2024 BUDGET FOR THE EAST
ORANGE BOARD OF WATER COMMISSION IN THE AMOUNT OF
$30,881,911.62
PAGE 3
F. RESOLUTION AUTHORIZING THE USE OF COMPETITIVE
CONTRACTING PROCEDURES AND THE PREPARATION OF A
REQUEST FOR PROPOSALS, THE ADVERTISING SOLICTATION AND
RECEIPT OF SEALED PROPOSALS FOR THE PROVISION OF
ACCOUNTANT AND FINANCIAL CONSULTANT SERVICES FOR THE
EOBWC
G. RESOLUTION HONORING JOHN LIU, P.E., P.P. FOR HIS YEARS OF
SERVICE
XIV. PUBLIC COMMENT
XV. EXECUTIVE SESSION, IF NECESSARY
A. Resolution for Closed Session
XVI. ADJOURNMENT
Get email alerts for East Orange
A daily email when new agendas and minutes are posted.