Village Board
Regular MeetingEast Troy, WI · March 7, 2022
Minutes
EAST TROY
VILLAGE BOARD MINUTES
March 7, 2022
Page 1 of 5
Call Meeting to Order, Pledge of Allegiance
Clerk Alexander verified the meeting was posted according to law.
Roll Call:
President Seager called the meeting to order at 6:30 p.m.
Present: President Scott Seager, Trustees John Alexander, Matt Johnson, Forty Renucci, Jason
Smalley and Joe Wisnewski
Excused: Trustee Mary Nugent
Others: Chief Swendrowski, DPW Director Equitz, Administrator Suhm, Attorney Geary, Clerk
Alexander
Citizen Participation
No citizen participation.
Consent Agenda
1. Approval Minutes – 2/21/2022
2. Consider extending completion date for Conditional Use for Leon Davis, LD’s BBQ
3. Consider approval of Temporary Class B license for East Troy Railroad 2022 Special Dinner Trains
– per list – 17 dates for Beer and 2 dates for Beer/Wine
4. Consideration of lease renewal with SkyKnights for grass/parking areas
5. Consideration of the First Amendment to the vacant land purchase agreement with Quernemoen
East Troy, LLC
Motion by Trustee Alexander, second by Trustee Smalley, to approve the consent agenda. Motion
carried.
Miscellaneous Business
1. East Troy Area Chamber of Commerce Room Tax Report – Vanessa Lenz, Executive Director
Vanessa Lenz, Executive Director, discussed the success of the December 2021 month-long
celebration of East Troy Lights, the addition of new features and the New Year’s Eve Ball Drop.
She discussed the 2022 plans to bolster this momentum, bring back their events on the Village
Square, promote that there is always something to do in East Troy, continue to build on the
successful events they currently sponsor and develop new traditions. She stressed that they
promote the interaction with the community and businesses in their events and that this support
and access to resources helps make their events special and unique. She discussed the
improvements to the Village Square and commended the Village on maintaining a vision to the
future. Discussion included working to bring new people into the Village, plans to provide an
interactive map with information on activities in the area, building the Good Neighbors
publication, consideration of a billboard, bringing back the Visitor’s Guide, partnering with other
groups and highlighting winter activities to promote hotel stays. Other suggestions included
possible promotions during large Milwaukee events in the future and the possibility of working
with students to develop a mobile app to engage visitor. She ended by thanking the Village for
their support.
2. Consideration of support for East Troy Lions Club 4th of July fireworks
John Biersack, East Troy Lions Club, asked if the Village would consider again providing financial support for
the 4th of July fireworks this year for $10,000.
Motion by Trustee Johnson, second by Trustee Smalley, to use surplus funds and/or Village Board budgeted
funds to fund $10,000 for the 2022 4th of July fireworks. Motion carried.
EAST TROY
VILLAGE BOARD MINUTES
March 7, 2022
Page 2 of 5
3. Consideration and discussion regarding American Rescue Plan Act (ARPA) and Bipartisan
infrastructure funds and potential projects
DPW Equitz and Engineer Lynch explained that ARPA and bipartisan infrastructure funds have
become available to municipalities. Engineer Lynch explained the infrastructure funds plan and
that this is a still an evolving program. He presented suggestions based on the current information
to see if the Board would like to pursue application for these funds. He explained that there are
two pending deadlines – the first is FFY 2022 (Federal Fiscal Year) with a grant application deadline
of April 1, notification of award in May 2022, the DOT would need to process it by August 1 and
the project needs to be encumbered by the DOT by November 2022 (meaning let or bid by
November 2022) for 2023 construction. While there are no currently designed projects, he and
DPW Equitz have looked at several possible projects that would allow for engineering design to
be done in time to meet the application deadline. The risk to the Village is that engineering is not
able to be included in the funds awarded and would be the responsibility of the Village or that the
application may not be able to be reviewed by either the DOT or DNR in time. Should the project
not be awarded the funding the Village would be able to retain the engineering design for the
project until needed. DPW Equitz stated that these funds do have several steps required by the
DOT for the projects and is an 80/20 federal funding. They focused on less complex projects that
would be able to be done in the short timeframe, such as a pavement only project, and that would
be smart use of the funding to keep ahead of future roadwork needs. Discussion included the
prediction of higher costs in 2023 and the possibility of difficulty in finding contractors. One of the
considered projects would be Energy Drive, with no underground piping work needed although
this project is not in the current 5-Year plan. There are several questions on administration and
qualifications for this program that they are waiting for answers on (such as if streets can be
combined or must be contiguous) but feel confident that there are projects the Village could apply
for.
The second funding program is for projects in 2023-2026 and will include such projects as bridges,
collectors and arterials, local roads and CMAQ (Congestion Mitigation & Air Quality) and
engineering funds will be eligible for reimbursement. The addition of CMAQ may be applicable
for the multi-use trail project on Hwy. 120. These projects have an application deadline of June
2022 offering a bit more time. These projects would need RFQ’s and the construction
bidding/award would be through the State. Should awards be granted the funds can be declined
without committing the Village to the project however with the offer of the 80/20 federal funding
this is a generous opportunity. Projects should be $200,000 or more to be of value for the
program.
They have also been informed of a possibility that some of these funds will be transferred into the
LRIP program which would allow access without going through the DOT process.
Engineer Lynch is working on the engineering cost estimates for these projects and will finalize
that should the Board choose a project to move forward with. He is working closely with the DOT
as they move forward in finalizing the details of the program. Projects at the Airport are through
the FAA and would not be included in this program.
The design and construction costs provided are estimates and do not consider the changing price
of oil or asphalt.
EAST TROY
VILLAGE BOARD MINUTES
March 7, 2022
Page 3 of 5
Discussion included projects planned for 2023, what streets could be considered if streets are able
to be combined, Townline Road and recent discussions with the Town of Troy regarding this multi-
jurisdictional road, the multi-use trail, if sidewalks would be included, that the PASER ratings for
streets were used in setting the priority of the project presented for 2022, that the proposed
design for Energy Drive would be from the Wastewater Treatment Plant east to Main Street, the
timeframe for the reconstruction of Hwy 20 is currently to be let in September 2023 with
construction in spring of 2024
None of these projects were budgeted for 2022 however there will be ARPA funds available.
Administrator Suhm stated that the Village can take the standard deduction and use ARPA funds
for these projects, that our expected disbursement of ARPA funds will be about $451,000 however
other projects have been considered using these funds include upgrading the Board Room
communications equipment and furnishings.
Motion by Trustee Johnson, second by Trustee Alexander, to have Lynch & Associates work with
DPW and begin design on Energy Drive and allocate funds from ARPA funds. Motion carried.
Direction was to confirm if a resolution is needed for submitting the application and DPW Equitz
will come back with 5-Year Plan for use in considering future funding opportunities.
4. Consideration of infrastructure design proposal from Lynch & Associates for utility work to be
done in conjunction with the state’s reconstruction of Highway 20
DPW Equitz discussed plans for improvements on Highway 20 and the proposal for the design of
sewer/water improvements to integrate those plans with the DOT plans from Thomas Drive east
to Sterling Oaks. Discussion included questions on what improvements may be planned by WE
Energies or Spectrum as the DOT plans do not include any street lighting so any additional street
lighting would be the responsibility of the Village and plans for additional fiber from Spectrum are
not known.
Direction was to proceed with this application as well as checking with WE Energies and Spectrum
while assessing needs for possible additional street lighting or fiber.
Motion by Trustee Johnson, second by Trustee Alexander, to approve $25,000 for Lynch &
Associates for design work of the water/sewer improvements related to the Highway 20
reconstruction. Motion carried.
5. Consideration of proposal from Lynch & Associates for design of finishing elements for Village
Square project such as trees, benches, and greenspace
Engineer Lynch discussed the final improvements for the Square, including utilizing a landscape
architect, selecting items such as trees, planters, design of green space around the trees, benches,
trash receptacles, and bike racks. He will seek Board input once a design is ready and is hoping to
keep the work under the $25,000 bid mark to allow more flexibility in selecting local contractors
to allow more control with the project. Discussion included engaging the business community
from the Square with notifications and a possible Committee of the Whole meeting with the plan
options.
Motion by Trustee Johnson, second by Trustee Smalley, to approve the design proposal with
Lynch & Associates for the Village Square landscaping. Motion carried.
EAST TROY
VILLAGE BOARD MINUTES
March 7, 2022
Page 4 of 5
6. Consideration of 2021 street project financial update, consider amendment to engineering
contract and whether to pursue liquidated damages
Engineer Lynch discussed the financial position of the 2021 street project and informed the Board
that the project is about 4.6% over the bid amount of $2.38 million, from the $2.5 million
budgeted amount, which is very good for a project this size. Items that remain to be completed
include some landscaping, they are waiting for the cost of some of the winter concrete costs, and
there is a question on the amount of stone used for the storm sewer work vs the road work that
is outstanding. When these estimated costs are factored in the project will most likely be very
close to the original expectation. The complexity of the project did result in additional engineering
costs and there is a punch list of items for the contractor to complete including work on repairing
those sections of sidewalk that cracked (as was expected due to timing and weather) and the
center asphalt line around the Square. There are still meetings with the County as we continue to
work together on these final items, and they hope to shift some engineering inspection costs back
to the County.
The Board discussed that with a project of this size it is not unusual to be much more over budget
and acknowledged the work of both DPW Equitz and Engineer Lynch on keeping this project on
track.
DPW Equitz explained there are two street light poles that were added and still need to be
purchased and installed and there are a few outlying items that need to be completed. It is
recognized that the Village has incurred stress and disruption due to this project and there is the
possibility of pursuing liquidated damages for unfinished work. The contractor is also reminded
that by the first Friday in May the Village events will begin on the Square and work needs to be
completed.
Motion by Trustee Johnson, second by Trustee Smalley, to approve the engineering contract
amendment. Motion carried.
Ordinances & Resolutions
1. Ord. 2022-05 Revisions to the Comprehensive Plan relating to the downtown area
Motion by Trustee Johnson, second by Trustee Alexander, to approve Ordinance 2022-05.
Motion carried.
Reports
1. DRAFT Plan Commission Minutes – 2/14/2022
2. Municipal Court Report – February 2022
Closed session
Motion by President Seager, second by Trustee Johnson, to adjourn to closed session pursuant to Wis.
Stats. 19.85(1)(c) to consider employment, promotion, compensation, or performance evaluation data
of any public employee over which the governmental body has jurisdiction or exercises responsibility
(Department of Public Works), and 19.85(1)(g) to confer with legal counsel for the governmental body
who is rending oral or written advice concerning strategy to be adopted by the body with respect to
litigation in which it is or is likely to become involved (Dam and impoundment area), and 19.85(1)(e) to
conduct other specified public business, whenever competitive bargaining reasons require a closed
session (Potential development of residential properties that are part of the Crucible Materials
Environmental Response Trust)
EAST TROY
VILLAGE BOARD MINUTES
March 7, 2022
Page 5 of 5
Motion carried on a roll call vote:
President Seager Y
Trustee Alexander Y
Trustee Johnson Y
Trustee Renucci Y
Trustee Smalley Y
Trustee Wisniewski Y
Reconvene in Open Session
Possible action on closed session matters including possible action on an engineering design contract
related to the dam removal project.
Motion by Trustee Johnson, second by Trustee Smalley, to approve authorization of up to $80,000 for
Change Order 1 for construction contract related to the dam removal project and authorize President
Seager to sign it. Motion carried.
Direction to staff to proceed with initiating a wage study.
Adjourn
Motion by President Seager, second by Trustee Alexander, to adjourn. Motion carried at 9:46 pm.
Respectfully Submitted,
Lorri Alexander
Clerk
Note: Recordings of the meeting may be found on our YouTube Channel - Link:
https://www.youtube.com/channel/UCGPfzVwLzE2Pqt4-g450Klg
Agenda
AGENDA
EAST TROY VILLAGE BOARD MEETING Packet materials associated with
2015 Energy Drive this meeting can be located at
www.easttroywi.gov
March 7, 2022
6:30 PM
In Person Meeting with Public Access for Viewing via Zoom and YouTube
Public Access is for viewing purposed only. No participation remotely for public.
Zoom Webinar ID: 876 0059 7791 Passcode: 118522
YouTube Channel Link: https://www.youtube.com/channel/UCGPfzVwLzE2Pqt4-g450Klg
Call Meeting to Order, Pledge of Allegiance
Verification of Open Meeting Notice
Roll Call
Citizen Participation
Per Village Resolution 2017-01, anyone wishing to address the Village Board during Citizen Participation will be allowed 5 minutes. Your subject
can be anything whether on the agenda or not. The Village Board should not engage in a discussion regarding comments because it was not
part of the publicly noticed agenda.
Upon conclusion of this Citizen Participation segment, members of the audience are not allowed further comment unless they are participating
in a public hearing or if specifically allowed by a majority vote of the Village Board due to involvement in an agenda item.
Consent Agenda
(One motion and second will approve all of the following items. Any item may be pulled from the list and voted on separately.)
1. Approval Minutes – 2/21/2022
2. Consider extending completion date for Conditional Use for Leon Davis, LD’s BBQ
3. Consider approval of Temporary Class B license for East Troy Railroad 2022 Special Dinner
Trains – per list – 17 dates for Beer and 2 dates for Beer/Wine
4. Consideration of lease renewal with SkyKnights for grass/parking areas
5. Consideration of the First Amendment to the vacant land purchase agreement with
Quernemoen East Troy, LLC
Miscellaneous Business
1. East Troy Area Chamber of Commerce Room Tax Report – Vanessa Lenz, Executive
Director
2. Consideration of support for East Troy Lions Club 4th of July fireworks (no packet materials)
3. Consideration and discussion regarding American Rescue Plan Act (ARPA) and Bipartisan
infrastructure funds and potential projects
4. Consideration of infrastructure design proposal from Lynch & Associates for utility work
to be done in conjunction with the state’s reconstruction of Highway 20
5. Consideration of proposal from Lynch & Associates for design of finishing elements for
Village Square project such as trees, benches and greenspace
6. Consideration of 2021 street project financial update, consider amendment to
engineering contract and whether to pursue liquidated damages
Ordinances & Resolutions
1. Ord. 2022-05 Revisions to the Comprehensive Plan relating to the downtown area
Reports
1. DRAFT Plan Commission Minutes – 2/14/2022
2. Municipal Court Report – February 2022
Closed session
Adjourn to closed session pursuant to Wis. Stats. 19.85(1)(c) to consider employment,
promotion, compensation, or performance evaluation data of any public employee over which
the governmental body has jurisdiction or exercises responsibility (Department of Public
Works), and 19.85(1)(g) to confer with legal counsel for the governmental body who is rending
oral or written advice concerning strategy to be adopted by the body with respect to litigation
in which it is or is likely to become involved (Dam and impoundment area), and 19.85(1)(e) to
conduct other specified public business, whenever competitive bargaining reasons require a
closed session (Potential development of residential properties that are part of the Crucible
Materials Environmental Response Trust)
Reconvene in Open Session
Possible action on closed session matters including possible action on an engineering design
contract related to the dam removal project.
Adjourn
Posted: 3/4/2022
Please note: The order of the items on this agenda is for the convenience of reference. These items may be taken out of order upon request of
the Village President or Village Board Members. Upon reasonable notice, efforts will be made to accommodate the needs of individuals with
disabilities through appropriate aids and services. For additional information or to request this service, contact the Clerk’s Office, 2015 Energy
Drive, (262) 642-6255.
Get email alerts for East Troy
A daily email when new agendas and minutes are posted.