Board of Health
Regular MeetingEasthampton, MA · April 13, 2021
Minutes
Easthampton Board of Health
Meeting Minutes
April 13, 2021
50 Payson Ave., Easthampton, MA 01027
PRESENT: Maggie Hebert (MH); Aimee Petrosky (AP); Bri Eichstaedt (BE), Health Director, Brian
Chapdelaine (BC), Health Inspector, Jackie Sienkiewicz (JS), Recorder. Also, present Mark O’Malley (MO)
and Sabrina Moreau (SM).
Meeting held on Zoom and recorded.
Motion to open A motion to open the meeting at 4:01 PM. was made by AP and seconded by
MH. All in favor – 2, Opposed – 0.
Public Speak Time: None
• Discuss and vote on the elimination of the easement requirement for the monitoring wells
in the BOH Private Well Regulations: BE requested the BOH remove the requirement for an
easement when a monitoring well is installed off city property. BE advised she could not think
of a reason why this would be necessary, and she also checked in with the DPW Director to
double check. The DPW Director did not see a reason to have this requirement either. The
BOH decided it was best to hold a public hearing on the matter. BE stated a public hearing
was only required for Title 5 regulations. BE and the BOH decided to update the well
regulations as a whole since the regulations are outdated and to avoid holding 2 separate
public hearings. BE advised the BOH that it may have to wait until the fall due to the current
inspection and COVID-19 demand.
A motion was made by AP and seconded by MH to open the hearing for well monitoring variances
for 317 Main St and 172-180 Pleasant St. All in favor: 2, opposed: 0.
O’Reilly, Talbot & Okun: 317 Main St., monitoring well variance request: BE explained that
updating well regulations had been planned prior to COVID making them more in line with state
models, but had not happened yet and a variance was needed for this project. MO described the
location and history of the property. MO was able to share his screen and show the blueprints of
the plan and placements of the proposed wells to the BOH. MO answered questions from the BOH
used in these situations. BE explained that she had been in contact with MA DEP and DEP stated
typically setback requirements are designed to protect drinking water wells and possible
contamination. Because monitoring wells are typically to check for contamination, the setback
requirements may not apply. BE stated that the existing regulations used “private well” verbiage
that cause unintended consequences.
A motion was made by MH and seconded by AP to approve the installation of a) One proposed
monitoring well within the 25’ setback from a property line (15’ provided), b) One proposed
monitoring well within the 15’ setback requirement from a dwelling/other structure (25 ft’ provided)
and c) Three monitoring wells withing the 150’ setback requirement from sub-surface fuel storage
tanks (6-10’ provided) at 317 Main St. All in favor: 2, opposed: 0.
● O’Reilly, Talbot & Okun: 172-180 Pleasant St monitoring well variance request: SM shared
her screen with the BOH to show the rear of this mill building and the adjacent bike path. SM
pointed out the special areas of concern about old utilities that may be unseen in this type of
building even with Dig Safe. SM explained the precautions that would be used to address this.
Precautions were also going to be used on the bike path to keep obstructions to a minimum
as well as the parking lot, stated SM. BE added that the city’s attorney drafted an agreement
that will need to be signed by the property owner to ensure any damages to city property
would be accounted for and the property owner would be liable to any damages caused by
the monitoring well installation. The setbacks that were not met did not appear to cause any
public health concern to the BOH.
● The BOH assured O’Reilly, Talbot & Okun, that if any further projects were submitted before
the updating of the regulations, that the BOH would arrange for hearings to address any
issues.
A motion was made by AP and seconded by MH to approve the variance request for a) Both proposed
monitoring wells are within the 25’setback requirement from a public way, road, and /or highway (3’
and 0’ provided), b) Both proposed monitoring wells are within the 25’setback requirement from a
sewer line (21’ and 6’ provided), c) Both monitoring wells are within the 25’ setback requirement from
a property line (11’ and 5’ provided), d) Both monitoring wells are within the 50’ setback requirement
form surface or subsurface drain (43’ and 7’ provided) for 172-180 Pleasant St. All in favor: 2,
opposed: 0.
A motion was made by AP and seconded by MH to waive the need to wait 30 days as stated in Section
6-16 of the regulations for these approved variances. All in favor: 2, opposed: 0.
● Meet new Health/COVID Compliance Inspector, Brian Chapdelaine: BE introduced BC to the
BOH. BC gave a brief overview of his job history. BE said that she and BC had already had a
variety of complaints, a condemnation, and inspections in his first few days. The BOH
welcomed BC to Easthampton.
A motion was made by MH and seconded by AP, to appoint Brian Chapdelaine, as an Agent of the
Board of Health. All in favor: 2, opposed: 0.
● Sherryla Diola, Ginger Love Café: Requesting the BOH add a seasonal temporary food
permit: BE said that Sherryla Diola, who was not present, had requested that the BOH grant
a seasonal temporary food permit in addition to the standard Temporary Food Permit since
she has so many events in the City and felt that the cost of these multiple permits was
prohibitive. BE said that this same request was brought to the BOH in the past. The BOH
discussed that the fees charged were in line with other communities and helped to cover the
administrative costs of issuing and inspecting of these events. In addition, the Food Code
defines a temporary food event as one event for 14 consecutive days in one location. The
BOH has already been lenient by allowing a permit to be issued for 14 non-consecutive days
in one location. The BOH decided to keep their decision of allowing one permit to cover 14
non-consecutive days in one location.
● Discuss and vote on either rescinding or updating BOH Order: “City of Easthampton Reverts
Back to Step 1 of Phase 3 of MA Re-Opening Plan”: The BOH discussed the existing BOH
orders and agreed that the order should be rescinded and to follow state orders but allowing
that if COVID metrics changed, new orders could be issued. The BOH also discussed The BOH
for “Construction Sites” and “All Essential Business Open to the Public” and agreed as well
that the orders should be rescinded and to follow state orders but allowing that if COVID
metrics changed, new orders could be issued.
● Discuss and vote on either rescinding or updating BOH Order: “Recreational Camps for
Children”: The BOH discussed the existing BOH orders and agreed to rescind current BOH
orders and to follow state guidelines.
● Discuss and vote to either rescinding or updating BOH Order: “Farmer’s Market”: BE
explained the manager of the Farmer’s Market had called and asked if changes could be made
in guidelines issued in 2020 for the 2021 season. BE said that the manager asked that wording
be changed from manager to committee member. The manager also asked that instead of a
hand wash sink at each booth at the market, that common ones be allowed instead. In
addition, the manager asked that cash would be able to be used at each booth and change
given if needed as opposed to last year when items had to be priced at an even dollar amount
so that no change was needed. The manager asked that a dedicated entrance and exit not be
ordered this year. BE also said there was a request that gloves not be mandatory and reusable
bags be allowed to be used again. The manager asked that customers be able to select their
own produce again using parchment paper, which was not allowed last year. BE stated that
she had no problems with these changes and were in line with what would happen if you
went shopping at a local grocery store. The BOH agreed with these changes. BE brought to
the BOH’s attention the last request from the manager. It is a request that vendors and
vendor employees not have to do a wellness check in. Be stated to the BOH, that she was
strongly against this due to the spread of COVID and its variants. The BOH agreed that this
guideline continue to be in place and adhered to.
A motion was made by AP and seconded by MH to rescind the BOH Order: “City of Easthampton
Reverts Back to Step 1 of Phase 3 of the MA Re-Opening Plan “and BOH Orders: “Recreational Camps
for Children”,” Construction Sites” and “All Essential Businesses” and update the BOH Order:
“Farmer’s Markets”. All in favor: 2, opposed: 0.
● Appoint Bri Eichstaedt as Health Director: BE explained to the BOH that according to
information from the City Clerk’s office, the BOH must appoint BE into the position of Health
Director for the City of Easthampton.
A motion was made by AP and seconded by MH to appoint Bri Eichstaedt as Health Director for the
City of Easthampton. All in favor: 2, opposed: 0.
A motion was made by AP to adjourn the meeting; seconded by MH. All in favor: 2, opposed: 0.
Meeting adjourned at 5:03 PM.
Agenda
NOTICE OF MEETING
OFFICE OF THE EASTHAMPTON CITY CLERK
TIME STAMP
By Office of the City Clerk at 8:37 am, Apr 08, 2021
BOARD/COMMITTEE: Board of Health
DATE: April 13, 2021 TIME: 4:00 p.m.
LOCATION
& ROOM: Topic: Board of Health
Time: Apr 13, 2021 04:00 PM Eastern Time (US and Canada)
Join Zoom Meeting
https://us02web.zoom.us/j/82694936626?pwd=cE1uRVM0K3p1WUFmdTlFd1c0czVZZz09
Meeting ID: 826 9493 6626
Passcode: 611183
One tap mobile
+16465588656,,82694936626#,,,,*611183# US (New York)
+13017158592,,82694936626#,,,,*611183# US (Washington DC)
Clerk or Bri Eichstaedt
board
member:
All meeting notices must be filed and time stamped in the City Clerk’s Office
no later than 3 p.m. on the Thursday prior to the week in which the meeting is scheduled.
BOARD OF HEALTH MEETING
AGENDA
April 13, 2021
4:00 P.M. Call meeting to order
Followed by:
1. Public speak time
2. Discuss and vote on the elimination of the easement requirement for monitoring wells in the BOH
Private Well Regulations
3. O’Reilly, Talbot & Okun: 317 Main St., monitoring well variance request:
a. One proposed monitoring well is within the 25’ setback requirement from a property line (15’
provided)
b. One proposed monitoring well is within the 25’ setback requirement from a dwelling/other
structure (25’ provided)
c. Three monitoring wells within the 150’ setback requirement from sub-surface fuel storage
tanks (6-10’ provided)
4. O’Reilly, Talbot & Okun: 172-180 Pleasant St. monitoring well variance request:
a. Both proposed monitoring wells are within the 25’ setback requirement from a public way,
road, and/or highway (3’ and 0’ provided)
b. Both proposed monitoring wells are within the 25’ setback requirement from a sewer line (21’
and 6’ provided)
c. Both monitoring wells are within the 25’ setback requirement from a property line (11’ and 5’
provided)
d. Both monitoring wells are within the 50’ setback requirement from surface or subsurface drain
(43’ and 7’ provided)
5. Meet new Health/COVID Compliance Inspector, Brian Chapdelaine
6. Sherryla Diola, Ginger Love Café: Requesting the BOH add a seasonal temporary food permit.
7. Discuss and vote on either rescinding or updating BOH Order: “City of Easthampton Reverts Back to
Step 1 of Phase 3 of the MA Re-Opening Plan”
8. Discuss and vote on either rescinding or updating BOH Order: “Recreational Camps for Children”
9. Discuss and vote on either rescinding or updating BOH Order: “Farmers Markets”
10. Appoint Bri Eichstaedt as Health Director
-Items not reasonably anticipated by the chair 48 hours in advance of the Board meeting
Next meeting: TBD
Get email alerts for Easthampton