City Council
Regular MeetingElverson, PA · June 25, 2019
Minutes
MABE Meeting Minutes June 25, 2019
In Attendance: Absent: Others in Attendance:
Lori Sifford Dave Friedman, EEMA
Darrell Gibble John Dean, EEMA
Jose Colon Joe Margusity, Blue Rock Development
Steve Keech
Floyd Jennelle
Stephen Kalis, Fox Rothschild
Keith Showalter, Systems Design
Tom Unger, Systems Design
Charlotte Gehman
Meeting called to order at 7:00p
Meeting Minutes
Motion by Darrell to Approve Minutes of May 28, 2019 Board Meeting. Second by Floyd. Motion approved.
Public Comment
Joe Margusity – Developer of the Blue Rock project asked the Board for their opinion on the choice of a pump station
versus grinder pumps. He proposes 5 E-1 low pressure systems, with none of them being dedicated to the authority to
include an agreement that allows unfettered inspections and scheduled inspections by the authority engineer. He also
requests that the existing easement be used to take effluent to the Corbett pump station. This will reduce the lineal feet
of force main by 1000 and not require cutting into roads. He would also consider a fiduciary account to give MABE
access to the funds should any problems occur or dedicating the E-1 units to MABE. The Board agreed to give Mr.
Margusity a decision as soon as possible.
Correspondence/Communication
PMAA Region 1 Dinner 11/14/19 – Will reconsider at future meeting.
Operator’s Report
The plant is running well with no violations. Dave explains that all PA One Calls must be responded to even if multiple
contractors. There was an SSO at the manhole near 105 E. Main St due to disposable wipes. Berks Rooter was able to
unclog it and have the pump station cleaned. Review of the SSO report submitted to DEP. A bad float was repaired in
the sump pump in the DU building.
HVAC – The system is working well but must be flushed regularly. Well Water Plumbing Quote – Dave intends to
provide a quote for this work at the July meeting.
Influent Pump Station Repair and Pump Quote – The pump failed and was sent for repair. The second pump if repaired
can be used in any of 4 pump stations. Motion by Jose to approve cost of $2,160.00 to repair the spare pump. Second
by Darrell. Motion approved. Review of the Controlex and MGK quotes to repair PS1. Still waiting for a quote from
Pikeland.
Aeration Tank Painting Quote – Review of the painting quote presented. This would require taking down each tank
temporarily. Paint would extend 1 foot below the water line. Dave expects the painting project to take a week and
needs to be done when the weather is dry. Steve requested a second quote for painting.
Blower #2 Evaluation – Blower #2 is not working well and is about 15 years old. Dave will get Blower #2 evaluated and
feels it may need to be replaced.
Aeration Tank Improvements Quote -3 quotes presented. The first is all inclusive including labor. The second quote is
modified not including the drop legs. Valves may be able to be reused, but Dave prefers to replace them all.
Page 1 of 2
MABE Meeting Minutes June 25, 2019
Engineer’s Report
Blower Panel Project – Hydraterra is still managing this project, but Keith stays in contact with Eastern.
Blue Rock Project – Deferred to executive session.
Main St. Manholes, A-Series Manholes – Keith will complete the inspections with Allen Myers on Main St. S. Chestnut St
has one manhole and should not require any adjustments, but SDE will inspect. They have been in contact with Sewer
Specialties and are waiting for the Main St. project to be completed. Anticipate September/October timeframe. Waiting
on a certificate of insurance.
Penn Dot Authorized Agent – Keith has provided a blanket authorization form to allow SDE to submit Highway
Occupancy Permits on MABE’s behalf. Motion by Jose to approve SDE be the authorized PennDOT representative for
MABE. Second by Floyd. Motion approved.
Connection Inquiries – Based on a request from 51 W. Main St., Keith reviewed SDE’s procedures for handling
connection inquiries and securing funds to cover the engineering fees. Discussion of the process and review of the
sample Lateral Connection Procedures document SDE provides to customers. Motion by Jose to approve a $500.00
escrow fee for SDE to review connection requests. Second by Floyd. Motion approved.
Sewer Specifications - Review of a sample standards document for pump stations.
Lori asked Keith to look at the manhole metering data to help identify the next area of focus for sewer plumbing
inspections.
Solicitor’s Report
No report.
Old Business
HVAC Service Referrals – Charlotte shared conversations with Wheatly and Ressler & Mateer as options for service of
the Daikin unit at the plant. Steve will request rate sheet from Wheatley.
New Business
Lori shared that Borough Council is setting up an informational session to encourage participation in serving the
community. She would like to have MABE represented. More details to come as planning develops.
Treasurer’s Report
Sign Checks - Motion by Darrell to approve the June payables as presented. Second by Floyd. Motion approved.
Admin Update
Plumbing Inspections Future Schedule – Review of the inspections completed to date. Charlotte will follow up with
customer who refused entry with a copy the ordinance and notice that his inspection is not considered complete until
we are able to access the property.
Executive Session – entered 8:30p
Meeting reconvened. Board authorized SDE to send a letter to the developer outlining additional considerations for the
Blue Rock project.
Meeting Adjourned 9:09p
Next Scheduled MABE Meeting is Tuesday, July 30, 2019 at 7:00p.
Page 2 of 2